Attachment 6 - EMIS Contractor Instruction Guide.pdf

PDF 695 KB Posted

Attached to
FY24 Civil Works IDIQ - Amendment 3
Solicitation number
FA446024R0005
Issued by

About this file

This document contains an attachment to a federal solicitation and the solicitation itself. The attachment provides guidance for contractors to track hazardous materials used on Little Rock Air Force Base, including filling out worksheets with details of materials, locations of use and storage, and certifications. The solicitation is for an indefinite-delivery/indefinite-quantity contract to perform various civil works construction and maintenance projects at Little Rock Air Force Base over the next fiscal year, including but not limited to demolition, concrete work, site work, electrical, asphalt, landscaping, utilities and traffic projects. Contractors must have in-house or ready design capabilities for potential design-build task orders. Individual task orders will specify individual project details and requirements.

View the file

Other files

File Type Posted
Solicitation Amendment FA446024R00050003 SF 30 signed.pdf PDF
Attachment 4 - General Wage Determination AR20240171 Pulaski.pdf PDF
Attachment 18 - NKAL 22-1067 6th Street Failure Drawing April 2022.pdf PDF
Attachment 20 - FY24 Civil Works Questions and Answers 2.6.24.pdf PDF
Attachment 2 - General Wage Determination AR20240152 White.pdf PDF
Solicitation Amendment FA446024R00050002 SF 30.pdf PDF
Attachment 3 - General Wage Determination AR20240168 Lonoke.pdf PDF
Attachment 17 - NKAK 22-1067 6th St Failure Description of Work 5.15.23.pdf PDF
Attachment 19 - FY24 Civil Works Site Visit Roster 1.30.24.pdf PDF
Solicitation Amendment FA446024R00050001 SF 30.pdf PDF
Attachment 11 - Sub-Contractor Consent Form.pdf PDF
Solicitation - FA446024R0005.pdf PDF
Attachment 14 - AF103 LRAFB Instructions.pdf PDF
Attachment 15 - LRAFB Information.pdf PDF
Attachment 1 - Civil Works IDIQ Schedule B.xlsx XLSX spreadsheet
Attachment 13 - Specifications NKAK 21-1076 IDIQ Civil Works 20231213.docx DOCX document
Attachment 4 - General Wage Determination AR20230171 Pulaski.pdf PDF
Attachment 2 - General Wage Determination AR20230152 White.pdf PDF
Attachment 16 - NKAK 22-1067 6th St Failure Package.pdf PDF
Attachment 10 - Past Performance Questionnaire.pdf PDF
Attachment 5 - Schedule of Material Submittals NKAK 21-1076(1-4).xlsx XLSX spreadsheet
Attachment 7 - Memo of Agreement Regarding Environmental Laws and Regulation.pdf PDF
Attachment 8 - Contractor Construction and Demolition Report.pdf PDF
Attachment 12 - IDIQ Civil Works Drawings NKAK 21-1076 (1 - 4).pdf PDF
Attachment 9 - Financial Institution Reference Sheet.pdf PDF
Attachment 3 - General Wage Determination AR20230168 Lonoke.pdf PDF
Show all 26

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Solicitation No.: FA446024R0005

LITTLE ROCK AFB AF-EMIS CONTRACTOR INSTRUCTION GUIDE

This information is required in order to help the base Hazardous Material Office (HAZMO) track all hazardous materials on-base. A worksheet must be filled out for each product containing a hazardous material. All blocks must be filled in.

1. Contractor Name: Fill in the name of the contracting company performing the work.

Contract Number: Fill in contract number or project number

Estimated Start Date: Fill in the date the project is projected to start.

Estimated Completion Date: Fill in the date the project is projected to end.

Shop Information: Fill in the AF-EMIS shop code that will be used to track the hazardous materials in the Air Force Environmental Management Information System. If you do not know this code, leave it blank. You will be assigned a shop code if you do not already have one.

2. Material Information: Information about the hazardous material that is going to be used.

National Stock Number, Local Stock Number, or Part Number: Fill in the identifying number of the product to be used.

Material Noun: Fill in the general term used to define the product. Example: Adhesive, Ni-cad Battery, etc.

Size: Fill in the quantity, circle the unit of measure, and circle the container type.

Unit of Issue: Fill in how the product is received. Example: box, case, pallet, each, etc.

Units Per Container: Identify how much comes in each unit of issue. Example: Twelve cans per box. Twelve being units per container and box being the unit of issue.

3. Location Information: Information about what the product will be used on, where it will be used, and where it will be stored when not in use.

Check all boxes that apply pertaining to where and on what the process of using the hazardous material will occur.

Location of Process: Identify in the physical location of where the product will be used. Example: Building number, intersection street names, etc.

Location of Stored Materials: Identify the physical location of where the material will be stored when not in use.

4. Additional Information: Information for the purpose of completing reports.

Hazardous Waste Generated: Does the process create any hazardous waste?

Site Diagram Available: Is a site diagram available for additional information on the site where the product will be used and stored?

Little Rock AFB SPCC Red Plan: This is part of the base Spill Prevention, Control, and Countermeasures Plan. The Red Plan lists base procedures for reporting spills.

5. Certifier Block: The certifier is the Government Representative for the project. This block must be completed and signed by both parties.

Notes:

A Manufacturer Material Safety Data Sheet (MSDS) for use by the Hazardous Materials Office is required to be turned in each time a worksheet is completed.

Each month a Contractor Hazardous Material Usage Data Sheet must be completed by the contractor and turned into the Government Representative for any project over six months. Projects less than six months are required to turn in a data sheet after completion of project. The Government Representative will be responsible for turning over this information to the HAZMO.

Attachment 6

LITTLE ROCK AFB AF-EMIS CONTRACTOR WORKSHEET

(Fill In All Information)

NOTE: Manufacturer’s Material Safety Data Sheet (MSDS) Required With Every Worksheet

1. CONTRACTOR INFORMATION

Contractor Name

Contract Number

Estimated Start Date

Estimated Completion Date

AF-EMIS Shop Code (Leave shop code blank if not known)

2. MATERIAL INFORMATION

National Stock Number (NSN), Local Stock Number (LSN), Or Part Number

Material Noun (Be Specific)

Size (Quantity) CIRCLE ONE Fluid Oz Troy Oz

Container Type Box Bottle Can Drum Bag Gram Pint Pound

Cartridge Other____________ Quart Kg Gallon

Unit of Issue Units Per Container Other _______________

3. LOCATION INFORMATION

Will The Process Be Performed On: (Check All That Apply)

Existing Facility Equipment New Structure Aircraft Outdoors Physical Location Of Process

Location Of Stored Materials

4. ADDITIONAL INFORMATION (Circle Answer That Applies)

Is A Hazardous Waste Generated? Yes No Additional Remarks:

Is A Site Diagram Available? Yes No

Is The SPCC Red Plan Posted? Yes No

5. CERTIFIER BLOCK

This Request Cannot Be Processed Without A Government Representative’s Signature Contractor Title: Phone: Date

Printed Name Signature

Gov’t Rep Title: Phone: Date

Printed Name Signature

CONTRACTOR HAZARDOUS MATERIAL USAGE DATA

Contractor: _______________________________AF-EMIS Shop Code: ____________________________

Contract Number___________________________Locations______________________________________

The following information is required for tracking of hazardous materials on-base. For contract times exceeding six months, this form is required to be filled out monthly and returned to the Government Representative, who will return it to the HAZMO office. This information is required in order to comply with Environmental Laws and Regulations. For purchase orders/contracts less than six months, this form is required at start and upon completion of work.

Material Name Manufacturer NSN/LSN or Part #

Quantity in Stock

Quantity Used

Printed name and Signature:

Contractor: __________________________________________________________________Date__________

Government Rep: _____________________________________________________________Date__________

CONTRACTOR INFORMATION
MATERIAL INFORMATION
CIRCLE ONE
LOCATION INFORMATION
ADDITIONAL INFORMATION (Circle Answer That Applies)
CERTIFIER BLOCK
This Request Cannot Be Processed Without A Government Representative’s Signature
Material Name
Manufacturer
Contractor: _______________________________AF-EMIS Shop Code: ____________________________
Contractor: __________________________________________________________________Date__________