Attachment 5 - Schedule of Material Submittals NKAK 21-1076(1-4).xlsx
XLSX spreadsheet 36 KB Posted
- Attached to
- FY24 Civil Works IDIQ - Amendment 3
- Solicitation number
- FA446024R0005
About this file
This document outlines a fiscal year 2024 indefinite-delivery indefinite-quantity contract opportunity for civil works projects at Little Rock Air Force Base. The solicitation seeks a contractor to perform maintenance and repair services such as demolition, concrete work, asphalt maintenance, landscaping, utility and drainage installation, pavement markings, and traffic control devices and signage. Individual task orders may require projects to be completed in phases. Work may also include design-build services from initial concept through 100% design. The contractor must have in-house or readily available design capabilities. Responses are due under solicitation number FA446024R0005 issued by the Department of the Air Force Air Mobility Command. The contract type will be an IDIQ with task orders issued against it for individual projects.
View the file
Other files
Show all 26
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Material Submittals Schedule
| SCHEDULE OF MATERIAL SUBMITTALS | NKAK 21-1076(1-4) IDIQ CIVIL WORKS | Solicitation No.: FA446024R0005 | |||||||||||||||
| 9-Aug-2023 | |||||||||||||||||
| (To be completed by Project Engineer) | (To be completed by Contract Administrator) | ||||||||||||||||
| NUMBER OF COPIES REQUIRED | |||||||||||||||||
| LINE NUMBER | ITEM OR DESCRIPTION OF ITEM, CONTRACT REFERENCE, TYPE OF SUBMITTAL | CERTIFICATION OF COMPLIANCE | SHOP DRAWINGS | SAMPLES | COLOR SELECTION | MANUFACTURER'S RECOMMENDATION | MANUFACTURER'S WARRANTY | CATALOG DATA | OPERATING INSTRUCTIONS | SCHEDULES, LISTINGS, REPORTS, PLANS | TECHNICAL DATA | TEST REPORTS | FIELD REPORTS | REQUIRED SUBMISSION DATE |
fergusog: Enter the due date from the Contractor (MM/DD/YY)
DATE RECEIVED IN CONTRACTING
fergusog: Enter the date received from the Contractor. (MM/DD/YY)
DATE TO CIVIL ENGINEERING
fergusog: Enter the date submittal was given to CE for review. (MM/DD/YY)
RETURN SUSPENSE DATE
fergusog: Enter the date the submittal is due back from CE
(MM/DD/YY)
SUBMITTAL NUMBERS
fergusog: Enter the Submittal Number
DATE CONTRACTOR NOTIFIED CONTRACTOR RESUBMITTAL
fergusog: Enter Resubmittal Number
FINAL APPROVAL
fergusog: Enter the submittal final approval date
(MM/DD/YY)
REMARKS
fergusog: Enter any comments pertaining to the submittal
APPROVED
fergusog: Enter date the Contractor was notified of submittal approval
(MM/DD/YY)
fergusog: Enter Resubmittal Number
DISAPPROVED
fergusog: Enter date the Contractor was notified of submittal disapproval
(MM/DD/YY)
fergusog: Enter the submittal final approval date
(MM/DD/YY)
fergusog: Enter any comments pertaining to the submittal
| 1 | 01 14 19 Coordenation 1.15 Radioactive Material | X | X | X | |||||||||
| 2 | 01 45 00 Quality Control, Cultural Resource Management AND QC Plan | X | X | X | |||||||||
| 3 | 01 45 00 1.05 Temporary Erosion Control Measures | X | X | X | X | X | X | X | X | X | |||
| 4 | 01 33 00 1.03 GIS AND AS-BUILTS | X | X | X | |||||||||
| 5 | 01 57 23 Storm Water Pollution Prevention Plan | X | X | X | |||||||||
| 6 | 02 42 00 Construction & Demolition Wast Reports | X | X | ||||||||||
| 7 | 03 20 01 Concrete Reinforcement | X | X | X | |||||||||
| 8 | 03 31 00 Cast-In-Place Concrete | X | X | X | X | X | |||||||
| 9 | 04 21 13 Brick Masonry | X | X | X | X | X | X | ||||||
| 10 | 04 71 10 Cast Stone | X | X | X | X | X | X | ||||||
| 11 | 05 50 13 Metal Fabrications | X | X | X | |||||||||
| 12 | 05 50 90 Metal Screen Wall | X | X | X | X | X | X | ||||||
| 13 | 05 52 13 Handrails | X | X | X | |||||||||
| 14 | 26 05 19 Wire and Cables | X | X | X | |||||||||
| 15 | 26 05 43 Underground Electric Service | X | X | ||||||||||
| 16 | 26 05 48 Seismic Protection | X | X | X | X | ||||||||
| 17 | 26 05 53 Identification | X | X | X | |||||||||
| 18 | 26 05 74 Transient Voltage Surge Suppresor | X | X | X | X | ||||||||
| 19 | 26 09 13 Metering | X | X | X | X | ||||||||
| 20 | 26 23 05 Service Disconnects | X | X | ||||||||||
| 21 | 26 23 10 Equipment Disconnect | X | X | X | |||||||||
| 22 | 26 24 00 Panel Boards | X | X | X | |||||||||
| 23 | 26 27 26 Wiring Devices | X | X | ||||||||||
| 24 | 26 50 00 Lighting | X | X | X | X | X | |||||||
| 25 | 31 00 00 Civil Works Earthwork: Topsoil | X | X | X | X | ||||||||
| 26 | 32 01 17.63 Reflective Crack Pavement Membrane | X | X | X | |||||||||
| 27 | 32 01 19 Field Molded Sealant | X | X | X | X | X | X | X | |||||
| 28 | 32 01 20 Hot-Applied Sealant For Asphalt Crack Repair | X | X | X | X | X | X | X | |||||
| 29 | 32 01 22 Bituminous Rejuvenation | X | X | X | X | X | X | ||||||
| 30 | 32 12 10 Bituminous Prime and Tack Coat | X | X | X | X | X | |||||||
| 31 | 32 17 13 Bollards | X | X | X | X | X | X | X | |||||
| 32 | 32 17 26 Cast In Place Detectable Warning Surface Tiles | X | X | X | X | X | X | X | |||||
| 33 | 32 17 26.10 Retrofit Detectable Warning Surface Tiles | X | X | X | X | X | X | X | |||||
| 34 | 32 92 20 Hydroseeding | X | X | X | X | ||||||||
| 35 | 32 92 23 Sodding | X | X | X | X | ||||||||
| 36 | 32 93 01 Trees, Shrubs, & Groundcovers | X | X | X | X | ||||||||
| 37 | 33 31 00 Miscellaneous Construction | X | X | X | X | X | |||||||
| 38 | App. 303 & 306 3" Base | X | X | ||||||||||
| 39 | App. 214 Subgrade Preparation | X | X | ||||||||||
| 40 | App. 303, 306 Aggregate Base Course | X | X | ||||||||||
| 41 | App. 405 Asphalt Concrete Hot Mix Base Course | X | X | X | |||||||||
| 42 | App. m406 Asphalt Concrete Hot Mix Binder Course | X | X | X | |||||||||
| 43 | App. 407 Asphalt Concrete Hot Mix Surface Course | X | X | X | |||||||||
| 44 | App. 418 Slurry Seal | X | X | X | |||||||||
| 45 | App. 603 Maintenance of Traffic, Traffic Control Plan, Traffic Control Supervisor | X | X | X | |||||||||
| 46 | App. 604 Traffic Control Devices in Construction Zones | X | X | X | X | X | |||||||
| 47 | App. 606 Pipe Culverts | X | X | X | X | ||||||||
| 48 | App. 609 Drop Inlets and Junction Boxes | X | X | X | X | ||||||||
| 49 | App. 610 Manholes, Drop Inlets and Junction Boxes Adjusted to Grade | X | X | X | X | ||||||||
| 50 | App. 611 Pipe Underdrains, Outlet Protectors, and Covers | X | X | X | X | ||||||||
| 51 | App. 625 Geotextile Fabric | X | X | X | |||||||||
| 52 | App. 633 Concrete Walks and Concrete Steps | X | X | X | X | X | |||||||
| 53 | App. 634 Curbing | X | X | X | |||||||||
| 54 | App. 641 ABA Ramps | X | |||||||||||
| 55 | App. 705 Loop Wiring Duct | X | X | X | X | X | X | ||||||
| 56 | App. 718 Reflectorized Paint Pavement Marking | X | X | X | X | X | |||||||
| 57 | App. 719 Thermoplastic Pavement Marking | X | X | X | X | X | |||||||
| 58 | App. 722 Plowable Pavement Marking | X | X | X | X | ||||||||
| 59 | App. 726 Standard Signs | X | X | X | X | ||||||||
| 60 | 32 13 13 6" & 8" CONCRETE PAVING (4,000 PSI) | X | X | X | X | ||||||||
| 61 | 32 11 36 LOW COMPRESSION CONCRETE (2,500 PSI) | X | X | X | X | ||||||||
| 62 | Reflective Crack Pavement Membrane 32 01 17.63 | X | X | X | X | ||||||||
| 63 | Detectable Warning Safety Tiles 32 17 26 | X | X | X | X |