Attachment 14 - AF103 LRAFB Instructions.pdf

PDF 864 KB Posted

Attached to
FY24 Civil Works IDIQ - Amendment 3
Solicitation number
FA446024R0005
Issued by

About this file

This document provides instructions for contractors performing work at Little Rock Air Force Base regarding utility clearance requests. Contractors must submit an AF Form 103 to the base's Requirements and Optimization section at least 30 days prior to starting work to request utility clearance. The form initiates the process of having base utility shops locate and mark underground utilities within five working days. Contractors are responsible for verifying marked utilities by potholing or hand digging, notifying the R&O section once located, and submitting photos for record keeping. Any damaged utilities must be immediately reported. Clearance requests are valid for 30 days and may be extended for an additional 30 days if marks are maintained and photos provided. The related federal contract opportunity is a solicitation for an indefinite-delivery/indefinite-quantity multiple award contract for maintenance and repair projects at Little Rock AFB, such as demolition, concrete work, electrical, asphalt, landscaping, and utilities. Task orders will specify individual project requirements.

View the file

Other files

File Type Posted
Solicitation Amendment FA446024R00050003 SF 30 signed.pdf PDF
Attachment 4 - General Wage Determination AR20240171 Pulaski.pdf PDF
Attachment 18 - NKAL 22-1067 6th Street Failure Drawing April 2022.pdf PDF
Attachment 20 - FY24 Civil Works Questions and Answers 2.6.24.pdf PDF
Attachment 2 - General Wage Determination AR20240152 White.pdf PDF
Solicitation Amendment FA446024R00050002 SF 30.pdf PDF
Attachment 3 - General Wage Determination AR20240168 Lonoke.pdf PDF
Attachment 17 - NKAK 22-1067 6th St Failure Description of Work 5.15.23.pdf PDF
Attachment 19 - FY24 Civil Works Site Visit Roster 1.30.24.pdf PDF
Solicitation Amendment FA446024R00050001 SF 30.pdf PDF
Attachment 11 - Sub-Contractor Consent Form.pdf PDF
Solicitation - FA446024R0005.pdf PDF
Attachment 6 - EMIS Contractor Instruction Guide.pdf PDF
Attachment 15 - LRAFB Information.pdf PDF
Attachment 1 - Civil Works IDIQ Schedule B.xlsx XLSX spreadsheet
Attachment 13 - Specifications NKAK 21-1076 IDIQ Civil Works 20231213.docx DOCX document
Attachment 4 - General Wage Determination AR20230171 Pulaski.pdf PDF
Attachment 2 - General Wage Determination AR20230152 White.pdf PDF
Attachment 16 - NKAK 22-1067 6th St Failure Package.pdf PDF
Attachment 10 - Past Performance Questionnaire.pdf PDF
Attachment 5 - Schedule of Material Submittals NKAK 21-1076(1-4).xlsx XLSX spreadsheet
Attachment 7 - Memo of Agreement Regarding Environmental Laws and Regulation.pdf PDF
Attachment 8 - Contractor Construction and Demolition Report.pdf PDF
Attachment 12 - IDIQ Civil Works Drawings NKAK 21-1076 (1 - 4).pdf PDF
Attachment 9 - Financial Institution Reference Sheet.pdf PDF
Attachment 3 - General Wage Determination AR20230168 Lonoke.pdf PDF
Show all 26

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Little Rock AFB (LRAFB) AF Form 103, Base Civil Engineer Work Clearance Request Operating Instructions (30 days prior to start)

1. Customer/Contract Officer Representative (COR)/Construction Management Inspector/ will initiate AF Form 103, Base Civil Engineer Work Clearance Request (Blocks, 1 - 7) to the Requirements and Optimization (R&O) Section. R&O can/will provide a base utility map in coordination with the requester to properly identify the area to be worked. At this time a tracking number will be assigned specific to the task. Civil Engineering R&O section is located building 536.

2. Contract Officer Representative and Construction Management Inspector may immediately hand carry AF Form 103 Work Clearance Request to each shop for utility locates prior to digging on an emergency work clearance request only.

3. If a Ground Penetrating Radar test has been completed it must be submitted with the AF Form 103 during initial request.

4. 19CS / SCOI shall initiate all work clearances for their subcontractors including the phone company.

5. Hunt Properties shall initiate all work clearances for their subcontractors working within their area of responsibility (housing area).

6. R&O Electrical Engineer shall initiate all work clearances for Entergy, Suddenlink, Cable TV Company, CenturyLink, Windstream, Comcast, Strand, and any new electrical/communications contractors that are performing work on LRAFB in the industrial area.

7. Area requiring clearance request must be clearly marked with white paint, white whiskers, or white marker balls. If the contractor wants to have a different marking device, it is the contractor's responsibility to have that device approved by R&O. If the contractor will be using the trenching or boring operations the utilities will only be marked within 10 feet of the proposed path.

a. Contractor shall notify 811, so that all utilities can be marked. Contractor shall abide by all 811 requirements for the law. If the base requirements are more detailed than the 811 requirements, the Contractor shall follow the base requirements and 811 requirements.

b. Each CES shop foreman must schedule time to have utilities located and marked within five working days or sooner after receiving AF Form 103.

c. The CES shops are required to paint utilities markings on hard surfaces, concrete, and asphalt, and use plastic whiskers in field areas. The craftsman should paint a small dot on curb, concrete, and asphalt. Do not pound whiskers into a hard surface. Place whiskers between 5 and 10 feet apart.

e. If the digging Contractor believes that there should be primary power in the area and it is not marked, then the Contractor shall notify R&O section, so that this can be verified before digging can be started.

f. The verification of marked utility lines shall be done by pot holing (hydrovac) or hand digging by the Contractor. Once, the utility lines are located the Contractor shall notify the R&O section, so that an Engineering Technician (EA) that the lines can be verified, and GIS coordinates can be taken.

Contractor shall submit these photos to 19 CES/CEO, R&O section for record keeping.

d. The Contractor shall take clear photos showing that the utilities have been marked. The

Solicitation No.: FA446024R0005

Attachment 14

• Blue: Water Systems, Slurry Pipelines and Potable Water

• Green: Sewer Systems and drain lines

• Orange: Communications, alarm or Signal Lines, Cables, or Conduit

• Pink: General or Temporary survey Markings

• Red: Electric Power Lines, Cables, Conduit and Lighting Cables

• Yellow: Gas, Oil, Steam, Petroleum or Gaseous Materials

• White: Proposed Excavating

**NOTE** Marking accuracy is within 18 inches left and right of buried utility centerline.

Hand digging and/or Hydro Vac equipment shall be used within 18 inches to locate and expose buried utility during the process.

8. When AF Form 103 Work Clearance Request has been processed, the CES Operations Flight Commander or designated representative will sign for final clearance.

a. R&O will notify the requestor by email that the clearance request is complete and ready for pickup in R&O section.

b. The requestor will attach a copy of the contract specifications section pertaining to the work clearance request and provide the complete package to the contractor (if required).

a. At the time of the Approved AF Form 103 clearance being issued to the Contractor doing the work they will ensure that all utilities that are marked be maintained during the construction process.

b. Work will only be accomplished during the hours of 0700-1630 M-F.

9. Mishaps such as broken or damaged utilities must be reported immediately by calling 911 and then to CE Customer Service (501-987-6553/6554) and then the Contract Officer Representative or Construction Management Inspector.

a. Contractors will not call shop personnel directly. If the shop is contacted, they are to refer the contractor to the Contract Officer Representative (COR)/Construction Management Inspector.

b. Craftsmen responding to a mishap must isolate/shutdown utility to prevent further damage to property and brief CE Customer Service on what buildings are isolated. (Without water, gas, sewer, electricity).

c. Base Civil Engineer authority and contracting Officer will make final determination on who will repair utility. In most cases it will be the contractor making the repair with a licensed technician. If bench stock is loaned to the contractor to help expedite a record of the materials shall be provided to the Contract Officer Representative or Construction Management Inspector.

10. All AF Form 103 are valid for 30 days from the date signed by CES representative. A request can be extended for additional 30 days if the marks are maintained, and photos provided by the requester at time of extension.

Contractor Acknowledgment:

Signature/Date:

Print Name:

Attachment 14

Solicitation No.: FA446024R0005

Print Name: