Attachment 6 - Delivery Schedule.pdf

PDF 691 KB Posted

Attached to
Marine Mammal Boats
Solicitation number
N6426725Q5007
Issued by

About this file

This document is a delivery schedule for a pre-solicitation notice for Marine Mammal Boats. The Naval Warfare Center Corona Division is seeking information from HUBZone small businesses that can provide these boats in accordance with the attached draft Statement of Work. The delivery schedule provides notional and proposed delivery timelines for Boat 1, 2, and subsequent boats, both with and without a break in production. Specifically, the notional delivery schedule shows Boat 1 being delivered 330 days after order, Boat 2 being delivered 60 days after the last boat, and subsequent boats being delivered 30 days after the last boat. The proposed delivery schedule shortens the timeline for Boat 1 to 300 days and maintains the 60 and 30 day intervals for subsequent boats. The document also defines "no break in production" as a new order being placed within 120 days of the last boat delivery, versus a "break in production" if the new order is placed after 120 days. Interested HUBZone small businesses are requested to submit capability statements by October 29, 2024 providing company details, pricing, lead times, and feedback on the draft SOW.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DRAFT

N6426725Q5007

Craft No. Destination OSR BP Notional Delivery Schedule OSR BP Proposed Delivery Schedule OSR UB Notional Delivery

Schedule OSR UB Proposed Delivery Schedule Boat 1 TBD 330 DAYS AFTER ORDER 300 DAYS AFTER ORDER Boat 2 TBD 60 DAYS AFTER LAST BOAT 60 DAYS AFTER LAST BOAT

Boat 3+ TBD 30 DAYS AFTER LAST BOAT 30 DAYS AFTER LAST BOAT

Craft No. Destination OSR BP Notional Delivery Schedule

NO BREAK in Production OSR BP Proposed Delivery Schedule

NO BREAK in Production

OSR UB Notional Delivery Schedule

NO BREAK in Production OSR UB Proposed Delivery Schedule

NO BREAK in Production Boat 1+ TBD 30 DAYS AFTER LAST BOAT 30 DAYS AFTER LAST BOAT

DELIVERY ORDER 2+ DELIVERY ORDER 2+

Craft No. Destination OSR BP Notional Delivery Schedule

BREAK in Production OSR BP Proposed Delivery Schedule

BREAK in Production

OSR UB Notional Delivery Schedule

BREAK in Production OSR UB Proposed Delivery Schedule

BREAK in Production Boat 1 TBD 330 DAYS AFTER ORDER 300 DAYS AFTER ORDER Boat 2 TBD 60 DAYS AFTER LAST BOAT 60 DAYS AFTER LAST BOAT

Boat 3+ TBD 30 DAYS AFTER LAST BOAT 30 DAYS AFTER LAST BOAT

Craft No. Destination OSR BP Notional Delivery Schedule

NO BREAK in Production OSR BP Proposed Delivery Schedule

NO BREAK in Production

OSR UB Notional Delivery Schedule

NO BREAK in Production OSR UB Proposed Delivery Schedule

NO BREAK in Production Boat 1+ TBD 30 DAYS AFTER LAST BOAT 30 DAYS AFTER LAST BOAT

Craft No. Destination OSR BP Notional Delivery Schedule

BREAK in Production OSR BP Proposed Delivery Schedule

BREAK in Production

OSR UB Notional Delivery Schedule

BREAK in Production OSR UB Proposed Delivery Schedule

BREAK in Production Boat 1 TBD 330 DAYS AFTER ORDER 300 DAYS AFTER ORDER Boat 2 TBD 60 DAYS AFTER LAST BOAT 60 DAYS AFTER LAST BOAT

Boat 3+ TBD 30 DAYS AFTER LAST BOAT 30 DAYS AFTER LAST BOAT

Craft No. Destination OSR BP Notional Delivery Schedule

NO BREAK in Production OSR BP Proposed Delivery Schedule

NO BREAK in Production

OSR UB Notional Delivery Schedule

NO BREAK in Production OSR UB Proposed Delivery Schedule

NO BREAK in Production Boat 1+ TBD 30 DAYS AFTER LAST BOAT 30 DAYS AFTER LAST BOAT

Craft No. Destination OSR BP Notional Delivery Schedule

BREAK in Production OSR BP Proposed Delivery Schedule

BREAK in Production

OSR UB Notional Delivery Schedule

BREAK in Production OSR UB Proposed Delivery Schedule

BREAK in Production Boat 1 TBD 330 DAYS AFTER ORDER 300 DAYS AFTER ORDER Boat 2 TBD 60 DAYS AFTER LAST BOAT 60 DAYS AFTER LAST BOAT

Boat 3+ TBD 30 DAYS AFTER LAST BOAT 30 DAYS AFTER LAST BOAT

Craft No. Destination OSR BP Notional Delivery Schedule

NO BREAK in Production OSR BP Proposed Delivery Schedule

NO BREAK in Production

OSR UB Notional Delivery Schedule

NO BREAK in Production OSR UB Proposed Delivery Schedule

NO BREAK in Production Boat 1+ TBD 30 DAYS AFTER LAST BOAT 30 DAYS AFTER LAST BOAT

Craft No. Destination OSR BP Notional Delivery Schedule

BREAK in Production OSR BP Proposed Delivery Schedule

BREAK in Production

OSR UB Notional Delivery Schedule

BREAK in Production OSR UB Proposed Delivery Schedule

BREAK in Production Boat 1 TBD 330 DAYS AFTER ORDER 300 DAYS AFTER ORDER Boat 2 TBD 60 DAYS AFTER LAST BOAT 60 DAYS AFTER LAST BOAT

Boat 3+ TBD 30 DAYS AFTER LAST BOAT 30 DAYS AFTER LAST BOAT

Craft No. Destination OSR BP Notional Delivery Schedule

NO BREAK in Production OSR BP Proposed Delivery Schedule

NO BREAK in Production

OSR UB Notional Delivery Schedule

NO BREAK in Production OSR UB Proposed Delivery Schedule

NO BREAK in Production Boat 1+ TBD 30 DAYS AFTER LAST BOAT 30 DAYS AFTER LAST BOAT

Craft No. Destination OSR BP Notional Delivery Schedule

BREAK in Production OSR BP Proposed Delivery Schedule

BREAK in Production

OSR UB Notional Delivery Schedule

BREAK in Production OSR UB Proposed Delivery Schedule

BREAK in Production Boat 1 TBD 330 DAYS AFTER ORDER 300 DAYS AFTER ORDER Boat 2 TBD 60 DAYS AFTER LAST BOAT 60 DAYS AFTER LAST BOAT

Boat 3+ TBD 30 DAYS AFTER LAST BOAT 30 DAYS AFTER LAST BOAT

Craft No. Destination OSR BP Notional Delivery Schedule

NO BREAK in Production OSR BP Proposed Delivery Schedule

NO BREAK in Production

OSR UB Notional Delivery Schedule

NO BREAK in Production OSR UB Proposed Delivery Schedule

NO BREAK in Production Boat 1+ TBD 30 DAYS AFTER LAST BOAT 30 DAYS AFTER LAST BOAT

Craft No. Destination OSR BP Notional Delivery Schedule

BREAK in Production OSR BP Proposed Delivery Schedule

BREAK in Production

OSR UB Notional Delivery Schedule

BREAK in Production OSR UB Proposed Delivery Schedule

BREAK in Production Boat 1 TBD 330 DAYS AFTER ORDER 300 DAYS AFTER ORDER

ATTACHMENT 5

Proposed Delivery Schedule Form

ORDERING PERIOD 1

DELIVERY ORDER 1

DELIVERY ORDER 2+

ORDERING PERIOD 2

ORDERING PERIOD 6

ORDERING PERIOD 3

ORDERING PERIOD 4

ORDERING PERIOD 5

DRAFT

N6426725Q5007

Boat 2 TBD 60 DAYS AFTER LAST BOAT 60 DAYS AFTER LAST BOAT Boat 3+ TBD 30 DAYS AFTER LAST BOAT 30 DAYS AFTER LAST BOAT

DEFINITIONS:

NO BREAK in Production: If a Delivery Order is issued before 120 days from delivery of last boat on order.

(Example: Last boat on current order delivery date 15 July 2019, new order placed any time before 14 April 2019 would be defined as NO BREAK in production. Boat 1 on the new Delivery Order would have a delivery date of 15 August 2019)

BREAK in Production: If a Delivery Order is issued after 120 days from the date of delivery of the last boat on order. (Example: Last boat on current order delivery date: 15 July 2019, new order placed any time after 15 April 2019 would be defined as a BREAK in production. Boat 1 of the new Delivery Order would have a delivery date of 300 days after placement of new Delivery Order)