Attachment_5_Value_Bid_Schedule.xlsx
XLSX spreadsheet 16 KB Posted
- Attached to
- LA POSA & OXBOW TRASH COLLECTION SERVICES
- Solicitation number
- 140L6424Q0050
About this file
This document appears to be an attachment containing a Value Bid Schedule for a federal contract opportunity related to "LA POSA & OXBOW TRASH COLLECTION SERVICES". The contract has a base period of performance from 07/01/2024 to 06/30/2025 with four 1-year option periods. The document provides detailed pricing information for various trash collection locations and service levels during the winter and summer seasons. It includes items such as bin quantities, pick-up frequencies, and total costs for the base year and option years. The related federal contract opportunity is Solicitation Number 140L6424Q0050, issued by the Department of the Interior Bureau of Land Management Arizona Region.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1 La Posa and Oxbow Trash Collection
| Period of Performance | |
| Base Period: | 07/01/2024 - 06/30/2025 |
| Option Period 1: | 07/01/2025 - 06/30/2026 |
| Option Period 2: | 07/01/2026 - 06/30/2027 |
| Option Period 3: | 07/01/2027 - 06/30/2028 |
| Option Period 4: | 07/01/2028 - 06/30/2029 |
Base Period: 07/01/2024 - 06/30/2025
| Item No. | Description of Services | Bin Quantity | Pick-up Frequency | ||
| May 16th - August 31st | Pick-up Frequency | ||||
| September 1st - May 15th | Total Cost | ||||
| 00010 | La Posa North - Winter | 2 | 2 times per week | ||
| La Posa North - Summer | 0 | None |
| La Posa North Total | ||||
| 00020 | La Posa South - Winter | 4 | 2 times per week | |
| La Posa South - Summer | 1 | 1 time per month |
| La Posa South Total | ||||
| 00030 | La Posa Tyson Wash - Winter | 1 | 2 times per week | |
| La Posa Tyson Wash - Summer | 0 | None |
| La Posa Tyson Wash Total | ||||
| 00040 | La Posa West - Winter | 1 | 2 times per week | |
| La Posa West - Summer | 0 | None |
| La Posa West Total | ||||
| 00050 | Oxbow - Winter and Summer | 1 | 1 time per month | 1 time per month |
Oxbow Total
Total Base Year
Option Additional Pick-up 1 Additional Pick-up Total
Option Year 1: 07/01/2025 - 06/30/2026
| Item No. | Description of Services | Bin Quantity | Pick-up Frequency | ||
| May 16th - August 31st | Pick-up Frequency | ||||
| September 1st - May 15th | Total Cost | ||||
| 00010 | La Posa North - Winter | 2 | 2 times per week | ||
| La Posa North - Summer | 0 | None |
| La Posa North Total | ||||
| 00020 | La Posa South - Winter | 4 | 2 times per week | |
| La Posa South - Summer | 1 | 1 time per month |
| La Posa South Total | ||||
| 00030 | La Posa Tyson Wash - Winter | 1 | 2 times per week | |
| La Posa Tyson Wash - Summer | 0 | None |
| La Posa Tyson Wash Total | ||||
| 00040 | La Posa West - Winter | 1 | 2 times per week | |
| La Posa West - Summer | 0 | None |
| La Posa West Total | ||||
| 00050 | Oxbow - Winter and Summer | 1 | 1 time per month | 1 time per month |
Oxbow Total
Total Base Year
Option Additional Pick-up 1 Additional Pick-up Total
Option Year 2: 07/01/2026 - 06/30/2027
| Item No. | Description of Services | Bin Quantity | Pick-up Frequency | ||
| May 16th - August 31st | Pick-up Frequency | ||||
| September 1st - May 15th | Total Cost | ||||
| 00010 | La Posa North - Winter | 2 | 2 times per week | ||
| La Posa North - Summer | 0 | None |
| La Posa North Total | ||||
| 00020 | La Posa South - Winter | 4 | 2 times per week | |
| La Posa South - Summer | 1 | 1 time per month |
| La Posa South Total | ||||
| 00030 | La Posa Tyson Wash - Winter | 1 | 2 times per week | |
| La Posa Tyson Wash - Summer | 0 | None |
| La Posa Tyson Wash Total | ||||
| 00040 | La Posa West - Winter | 1 | 2 times per week | |
| La Posa West - Summer | 0 | None |
| La Posa West Total | ||||
| 00050 | Oxbow - Winter and Summer | 1 | 1 time per month | 1 time per month |
Oxbow Total
Total Base Year
Option Additional Pick-up 1 Additional Pick-up Total
Option Year 3: 07/01/2027 - 06/30/2028
| Item No. | Description of Services | Quantity | Pick-up Frequency | ||
| May 16th - August 31st | Pick-up Frequency | ||||
| September 1st - May 15th | Total Cost | ||||
| 00010 | La Posa North - Winter | 2 | 2 times per week | ||
| La Posa North - Summer | 0 | None |
| La Posa North Total | ||||
| 00020 | La Posa South - Winter | 4 | 2 times per week | |
| La Posa South - Summer | 1 | 1 time per month |
| La Posa South Total | ||||
| 00030 | La Posa Tyson Wash - Winter | 1 | 2 times per week | |
| La Posa Tyson Wash - Summer | 0 | None |
| La Posa Tyson Wash Total | ||||
| 00040 | La Posa West - Winter | 1 | 2 times per week | |
| La Posa West - Summer | 0 | None |
| La Posa West Total | ||||
| 00050 | Oxbow - Winter and Summer | 1 | 1 time per month | 1 time per month |
Oxbow Total
Total Base Year
Option Additional Pick-up 1 Additional Pick-up Total
Option Year 4: 07/01/2028 - 06/30/2029
| Item No. | Description of Services | Quantity | Pick-up Frequency | ||
| May 16th - August 31st | Pick-up Frequency | ||||
| September 1st - May 15th | Total Cost | ||||
| 00010 | La Posa North - Winter | 2 | 2 times per week | ||
| La Posa North - Summer | 0 | None |
| La Posa North Total | ||||
| 00020 | La Posa South - Winter | 4 | 2 times per week | |
| La Posa South - Summer | 1 | 1 time per month |
| La Posa South Total | ||||
| 00030 | La Posa Tyson Wash - Winter | 1 | 2 times per week | |
| La Posa Tyson Wash - Summer | 0 | None |
| La Posa Tyson Wash Total | ||||
| 00040 | La Posa West - Winter | 1 | 2 times per week | |
| La Posa West - Summer | 0 | None |
| La Posa West Total | ||||
| 00050 | Oxbow - Winter and Summer | 1 | 1 time per month | 1 time per month |
Oxbow Total
Total Base Year
Option Additional Pick-up 1 Additional Pick-up Total
Total Contract Value