This document is a Construction Statement of Work (SOW) for the repair and rehabilitation of the lantern of the Kilauea Point Lighthouse located at the Kilauea Point National Wildlife Refuge in Hawaii.
The key objectives of the SOW are to:
- Remove and reinstall the lantern curtain wall glass
- Replace all ferrous lantern sill cover plates and ventilation wall vents with stainless steel components
- Repaint and restore the interior and exterior metalwork of the lantern
- Coordinate construction activities to avoid interference with ongoing refuge operations The SOW includes detailed technical specifications, submittal requirements, quality control procedures, safety and environmental requirements, and closeout procedures. It requires the contractor to develop a Temporary Protection Plan to safeguard the historic lighthouse fabric during construction. Payment will be made on a lump sum and unit price basis. A mandatory pre-bid conference is required prior to submitting proposals.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Sol_140FHR24R0005_Amd_0002.pdf | ||
| Sol_140FHR24R0005_Amd_0001.pdf | ||
| Attachment_4-REVISED_Statement_of_Work(SOW)_KP_Lighthouse_Lantern_Repairs_072924.pdf | ||
| Attachment_10-Drawings.pdf | ||
| Attachment_2-Bid_Schedule_KP_Lighthouse_Lantern_Repairs.pdf | ||
| Attachment_3-DOL_Wage_Determination.pdf | ||
| Attachment_7-Specifications__KPLH_T4_LensCleaning_2023.pdf | ||
| Attachment_8-Specifications140505_LAMPIST_STANDARDS.pdf | ||
| Sol_140FHR24R0005.pdf | ||
| Attachment_1-Solicitation.pdf | ||
| Attachment_6-Specifications_KPLH_T1_FieldInspection_2023.pdf | ||
| Attachment_9-Specs_KPLH_Section_106_Compliance.pdf |
Show all 12
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
LIGHTHOUSE LANTERN REPAIR & TREATMENT PLAN USFWS – KILAUEA POINT NTL WILDLIFE REFUGE
LIGHTHOUSE LANTERN REPAIR / WEATHERPROOFING TREATMENT PLAN &
OPINION OF CONSTRUCTION COST
DANIEL K. INOUYE KILAUEA POINT LIGHTHOUSE
Kilauea Point National Wildlife Refuge
3500 Kilauea Road
Kilauea, HI 96754
TABLE OF CONTENTS
SECTION 1 INTRODUCTION
SECTION 2 SCOPE OF WORK
SECTION 2 CONSTRUCTION ROM BUDGET
ATTACHMENTS: SOW DRAWINGS
1. INTRODUCTION
ICC Commonwealth (ICC) is under contract by the USFWS to perform The Lighthouse Lantern
Weatherproofing and Isolation Design. Task 2
2. SCOPE OF WORK
1. Mobilize the Lighthouse and gain access to the Service Room and Lantern levels.
2. Remove First Order Fresnel Lens for safety during construction.
3. Remove and reinstall the Lantern curtain wall glass.
4. Access, review and clear the ventilator ball.
5. Replace all ferrous lantern sill cover plates and pinching strips with stainless steel (TYP 316-L)
6. Remove and replace Service Room wall vents with Stainless Steel (TYP 316-L)
7. Reinstall First Order Fresnel Lens
3. CONSTRUCTION ROM BUDGET
4. SPECIFICATIONS
Section 01 Page 1
DIVISION 1000
GENERAL REQUIREMENTS
3/10
1110 SUMMARY OF WORK
A. SUMMARY
1. Work: Includes all necessary materials, labor, labor superintendence, management, fees, assessments and costs to construct the project in accordance with the Contract Documents.
2. The Kilauea Point Lighthouse is listed on the National Register of
Historic Places. All Work will conform with the Secretary of the
Interior’s Standards for Treatment of Historic Places (CFR 38).
B. DESCRIPTION OF WORK
1. Location of Work is at the Kilauea Point National Wildlife Refuge, located just north of Kilauea, Hawaii. Kilauea Point National Wildlife
Refuge is a 203-acre property, under the ownership and management of the U.S. Fish and Wildlife Service. The refuge is known for its spectacular ocean headland, native seabirds, endangered animal species and its intact lighthouse station.
2. The Kilauea lighthouse was built in 1913 and operated until 1974 when its service was superseded by an automated beacon. The lighthouse stands as a monument to the duties that it once held. The Lighthouse is made up of a cast in place concrete tower and a lantern made of cast iron, bronze and brass. The lighthouse stands 53 feet tall. The
Kilauea Point Lighthouse was listed on the National Register of
Historic Places on October 18, 1979. The light station transferred to the U.S. Fish and Wildlife Service for inclusion in the 203-acre
Kilauea Point National Wildlife Refuge in 1985.
3. The Project is to rehabilitate the lantern of the Kilauea Point
Lighthouse with stainless steel replacement materials. This Work includes, but is not limited to, interior and exterior paint removal from metalwork; exterior replacement of cast iron; reglaze glass panels in bronze sash frames; fabrication of new lantern sill components in stainless steel and bronze screw replacements throughout the lantern.
ckreiser Highlight The Project is to rehabilitate the lantern of the Kilauea Point Lighthouse with stainless steel replacement materials. This Work includes, but is not limited to, interior and exterior paint removal from metalwork; exterior replacement of cast iron; reglaze glass panels in bronze sash frames; fabrication of new lantern sill components in stainless steel and bronze screw replacements throughout the lantern.
Section 01 Page 2
4. Project is for the U. S. Fish and Wildlife Service (USFWS), referred to hereafter as Owner.
5. The Contracting Officer Representative (COR) is: Caroline Kreiser, USFWS
6. The Refuge Manager / Project Leader is: Heather Tonneson, USFWS
7. All prime Contractors interested in submitting a bid must attend the mandatory pre-bid meeting. Refer to the invitation to bid for the date and time of the mandatory pre-bid meeting.
8. Construction schedule: Contractor will not begin any demolition or construction, before required permits have been obtained, a proposed construction schedule is submitted along with required submittals and written approval has been given by the COR.
9. Required submittals will be provided to the COR 48 hours prior to the mandatory on-site pre- construction meeting. The pre-construction meeting will be scheduled after the Notice To Proceed letter has been issued.
01140 WORK RESTRICTIONS
A. Work Hours: For on-site construction Work, hours shall be Monday through
Saturday, 7:00 AM to 5:00 PM, except federal holidays, unless approved otherwise.
B. Housing for workers and campsites are not available on site unless explicitly indicated otherwise in the Task Order.
C. Government buildings and other facilities are not available for storage of Contractor’s materials, equipment and tools. Government owned equipment is not available for Contractor’s use to accomplish any Work.
D. Habitat Restrictions: Wildlife habitat issues may restrict building seasons. Coordinate with Refuge Manager for requirements.
E. All construction debris shall be disposed of in such a manner that it cannot enter the shoreline or ocean.
attend the are encouraged to ckreiser Typewritten Text Contracting Officer (CO).
ckreiser Typewritten Text unless explicitly agreed upon by the Project Leader.
ckreiser Typewritten Text optional ckreiser Highlight hours shall be Monday through Saturday, 7:00 AM to 5:00 PM ckreiser Callout per SOW ckreiser Line
Line
Section 01 Page 3
01250 BID ITEM MEASUREMENT
A. Measurement for Payment
See Bid Item List for breakdown of Payment Items
1. LUMP SUM:
Lump Sum Payment as indicated on Bid Item list shall include full compensation for items installed and completely in place and shall include costs connected with such items including, but not limited to labor, materials, transportation, services, equipment, scaffolding, taxes, overhead, profit, etc. for the Contractor and involved Subcontractors, (if any).
2 UNIT PRICES:
Unit Price Payment as indicated on Bid Item list shall refer to items installed and completely in place (including fasteners) and shall include costs connected with such items including, but not limited to labor, materials, transportation, services, equipment, scaffolding, taxes, overhead and profit for the Contractor and involved
Subcontractors, (if any).
01290 PAYMENT PROCEDURES
A. Payment: Payment will be made monthly for approved Work performed in accordance with the contract requirements based on the line items on the approved Schedule of Values.
B. Application for
Payment:
1. Schedule of Values:
a. Prepare a Schedule of Values in the format (or approved equivalent format) of the American Institute of Architects (AIA) form number
G702/703 Application and Certificate for Payment.
b. Submit a detailed Schedule-of-Values within 7 days prior to the start of on-site construction Work. Format the schedule-of-values to match the Schedule of Items and show sufficient additional detail to allow accurate calculation of monthly progress payments.
2. Updated Schedule: Submit updated schedule identifying actual Work complete with each application for payment.
3. Certified Payrolls: Certified payrolls current to within 1 week of payment application period shall be submitted to the COR with ckreiser Typewritten Text
CO
Section 01 Page 4 application for payment.
4. Items listed under the Unit Price method of payment must be approved through a signed Change Order before any payment will be made.
Quantities requested for payment must reflect the amount agreed upon in the change order.
5. Invoices: Submit an electronic Application and Certificate for Payment to the COR.
01310 PROJECT MANAGEMENT AND COORDINATION
A. The standard Government forms, specifications, associated plans, solicitation provisions, and contract clauses made a part of the contract are essential parts thereof, the requirements in one are as binding as though contained in all. They are intended to be mutually supplementary to describe and provide for a completed project.
B. In cases of conflict between specifications, contract provisions, supplemental agreements, and provisions of Standard Government Forms;
the provisions of Standard Government Forms shall govern. In all cases of dispute in respect to such conflict or as to what part or parts of the specifications apply to any given parts of the Work, decisions shall be made by the Contracting Officer (CO).
C. Coordination
1. Coordinate scheduling, submittals, and work of the various sections of specifications to ensure efficient and orderly sequence of installation of interdependent construction elements.
2. Verify and confirm all dimensions and conditions shown or implied on the Drawings and specifications as well as the physical conditions of the site. Notify COR of discrepancies prior to start of Work for resolution.
3. Verify that utility requirement characteristics of operating equipment are compatible with building utilities.
4. Provide field engineering to accurately establish the horizontal and vertical locations of the Work.
5. Government furnished drawings shall not be scaled to obtain missing or conflicting dimensions. The Contractor shall keep a check on dimensions and details as the Work progresses and any errors or discrepancies discovered shall be promptly reported to the COR.
D. Accomplish construction Work in a manner that does not interfere with ongoing station operations, nor allow any construction material or ckreiser Callout upload to IPP
Section 01 Page 5 debris to enter waters of the State.
01315 MODIFICATION PROCEDURES
A. SUMMARY
1. Section Includes: Administrative requirements for Requests for
Information and Proposal Requests.
2. Prior to execution of a Change Order, the following documents shall be submitted as indicated.
B. REQUEST FOR INFORMATION (RFI)
1. General:
a. RFIs are requests for information originated, prepared and submitted by the Contractor to the COR only when the Contractor is unable to determine from the Contract Documents, the material, process, system or Work to be installed. The Contractor will endeavor to keep the number of RFIs to a minimum. For critical or emergency items, contact the COR at once.
b. In the event the Contractor believes that a clarification by the
COR results in additional cost or time, the Contractor shall not proceed with the Work indicated by the RFI until given approval to proceed by the CO.
c. Number RFIs sequentially; include date submitted.
d. Identify Project, pertinent Plan sheet, detail number, and
Specification Section.
e. Specifically identify time response information as required to avoid impact on Construction Schedule or Cost. COR shall endeavor to respond to proper RFIs within 7 Days, if possible.
2. RFIs shall include written and graphic solutions proposed by
Contractor. COR will determine if Contractor’s proposal is in accordance with Contract Documents and design intent of the Project.
a. Contractor's failure to make a reasonable effort to propose a realistic solution may result in RFIs being returned with no action.
b. RFIs that request information that is clearly shown in the
Contract Documents will be considered frivolous/improper and will be returned with no action.
Section 01 Page 6
3. Contractor to maintain current and accurate RFI Log.
01320 CONSTRUCTION PROGRESS DOCUMENTATION
A. Schedule:
1. Distribution: At pre-construction meeting, submit initial construction schedule.
2. Develop schedule on commercially available computer scheduling software
3. Provide schedule showing Work breakdown structure or precedence diagram.
4. Identify day, date, duration, and float for each Work activity.
5. Break down activities by task.
6. Identify all interfaces with government that may impact schedule.
Keep government interfaces from critical path to maximum extent practical.
7. Update schedule to reflect changes/delays in the Work.
8. Provide monthly updates with payment application.
B. Notification: Provide Refuge Manager 72 hours written notice prior to all service outages. Coordinate timing of outage to minimize conflicts with normal operations.
C. Project Meetings
1. Pre-construction Meeting: Attend a mandatory pre-construction meeting prior to start of project construction. Require attendance by all parties affected by the work including major subcontractors.
2. Progress Meetings: Attend progress meetings as required by the progress of the project. COR will coordinate and schedule progress job meetings.
3. Contractor will prepare and distribute Progress Meeting minutes within 72 hours of meeting.
01330 SUBMITTALS
A. Master Submittal List: Submit Master submittal list identifying all submittals required. Submit list at pre-construction meeting. Identify each submittal by appropriate specification section, item/description, required submittal date, date submitted, and action taken.
Sequentially number each submittal. This submittal list will be updated regularly and distributed at project progress meetings.
B. Transmit submittals with the Government-furnished Submittal Form R1-67 that will also be used as the document for approving or disapproving ckreiser Highlight Schedule:
ckreiser Highlight Project Meetings ckreiser Highlight Contractor will prepare and distribute Progress Meeting minutes within 72 hours of meeting.
Pre-construction Meeting:
ckreiser
Weekly
Section 01 Page 7 submittals. Obtain written approval before items are ordered. Use a separate R1-67 form for each broad category of material to avoid confusion should a re-submittal be necessary.
C. Submit all submittals to the COR signed by the Contractor indicating they comply with the contract requirements. Submittals without the
Contractor’s signature will be returned without action.
D. Submittal Completeness: Submittals which do not have all the information required to be reviewed are not acceptable and will be returned.
E. For each required submittal, the Contractor shall submit an electronic copy of all the required information not less than fourteen (10) Days prior to purchase and/or installation.
F. Submittals shall contain detailed product literature, shop drawings, material samples, and/or finish samples fully describing the items proposed for installation.
G. Conspicuously mark the item submitted to explicitly indicate the specific options, models, mechanical/electrical characteristics, trim styles, colors, sizes, etc. Annotate the submittal to cross reference to the mark numbers/group numbers shown on the drawings and/or specification.
H. Tab and index submittals containing more than (10) ten pages.
I. Explicitly and clearly indicate all features that differ from the contract requirements. Deviation from Contract: Submit a request for substitution for deviations from the Specifications or Drawings. Include the reason for the deviation and cost differential for the deviation.
Deviations from the contract shall be authorized by change order only.
J. Submittals will be returned to the Contractor within 10 working days of the date received by the COR.
K. See individual specification sections for submittal requirements.
L. Material Certifications:
1. Submit manufacturer’s certificate indicating material or product conforms or exceeds specified requirements. Submit supporting reference data, affidavits, and certifications as appropriate.
Rectangle
Section 01 Page 8
2. Certificates may be recent or previous test results on material or product but must be acceptable to COR.
M. Samples:
1. Submit exact product or material to be used.
2. Submit product sample of size specified and of sufficient size to clearly show the characteristics, integral parts, and attachment of the product or system.
3. Submit interior and exterior color and texture samples at one time for coordinated review by COR.
N. Additional Submittals:
1. Owner reserves the right to ask for additional SUBMITTALS that are not included on the above list. Review by the Owner shall not relieve the
Contractor from responsibility for error of omission. Obtain the Owner’s approval prior to beginning any fabrication or other work. No deviation from the reviewed drawings shall be allowed without approval from the
Owner.
O. REVIEW PROCEDURE
1. The COR will review the submittal and return it to the Contractor.
The returned submittal will indicate one of the following actions:
a. If the review indicates the material, equipment or Work method is in general conformance with the Plans/Specifications, the submittal copies shall be marked “Approved.” In this event, the Contractor may begin to incorporate the material/equipment/Work method covered in the submittal.
b. If the review indicates the submittal is insufficient or that limited corrections are required, the submittal copies may be marked “Approved as Noted.” The Contractor may begin to implement the Work method or incorporate materials/comments covered in the submittal in accordance with the corrections/comments noted.
ckreiser Text Box Some submittals may require review by the Hawaii Historical Foundation (HHF) and/or the State Historic Preservation Division (SHPD). Allow 30 days review time for review by HHF and SHPD.
Section 01 Page 9
c. If the review reveals the submittal is insufficient or contains incorrect data and the comments require revision and resubmittal, the submittal copies shall be marked “Not Approved, Resubmit.” In this case, the Contractor shall not then undertake Work covered by this submittal until the submittal has been revised, resubmitted and returned to the Contractor with a marking of “Approved” or “Approved as Noted.”
d. If the review reveals the material, equipment, or Work does not require submittal, then the submitted copies shall be marked
“Review Not Required Per Contract Documents.” In this event, the Contractor may begin to incorporate the material/equipment/Work covered by the submittal and no further action is required.
P. EFFECT OF REVIEW OF CONTRACTOR’S SUBMITTALS
1. A mark of “Approved” or “Approved as Noted” shall mean the COR has no objection to the Contractor, upon the Contractor’s own responsibility, using the plan or method of Work proposed, or providing the materials or equipment proposed.
2. The Contractor shall furnish to the COR the following items for equipment, articles and materials incorporated in the Work:
a. Submittals for items identified in individual Specification sections.
b. Manufacturer’s special tools and special accessories normally furnished by the manufacturer and which, by their specific nature and special design, are suited for convenient and expeditious adjustment, maintenance and repair.
c. Two sets of installation instructions, parts lists; routine preventative maintenance and operation manuals; corrective maintenance instructions; Plans and other like data pertinent for maintenance and repair.
d. Manufacturer’s and dealer’s warranties and guarantees which are normally available to purchasers. Such warranties and guarantees shall be made effective to the Owner as the purchaser.
Rectangle
Section 01 Page 10
01340 SPECIAL HISTORIC PROCEDURES
A. TEMPORARY PROTECTION OF HISTORIC FABRIC
1. Important decorative and detailed interior and exterior elements may be exposed to potentially damaging conditions throughout the project.
Extra protection measures must be used by the contractor to ensure that the existing historic fabric is not damaged. No smoking is allowed at the project site, except at locations previously approved by the Refuge Manager.
2. Obtain COR approval before implementing temporary protection measures.
3. Temporary Protection Plan
a. The Contractor shall make a written plan, for the COR approval, describing in detail the method of protective measures they intend to use in working on, and providing temporary protection for the
Kilauea Point Lighthouse. Submit Temporary Protection Plan no later than 14 days after pre-construction meeting and before commencing any work on the lighthouse.
Include the following information:
I. Description of Work or procedures to be performed for the following:
i. Site and landscape including, but not limited to, Contractor’s staging area, historic walkways, native plants, and scaffold location and layout (if used).
ii. Building exterior including, but not limited to, bracing or anchorage of scaffolding to building and protection of historic materials not in this contract.
iii. Architectural features and finishes including, but not limited to, floors, walls, doorways, doors, hardware, windows, ceilings, and decorative moldings.
iv. Fire Protection
1) Reference National Fire Protection Association Document NFPA
241:
Safeguarding Building Construction and Demolition
Operations.
2) Reference National Fire Protection Association Document NFPA 914:
Rehabilitation and Adaptive Reuse of Historic Structures.
Section 01 Page 11
v. Method and equipment for use in cutting, welding, and soldering.
vi. The use of chemical or mechanical means to remove paint.
vii. Temporary removal and reinstallation of historic fabric and methods for documenting, removal, storage, and reinstallation.
II. What methods will be used.
III. Where temporary protection involves storage of historic material, submit location and details of storage environment.
b. The COR reserves the right to reject all or part of the
Contractor’s proposed plan, on the following basis:
I. Not conforming to the Plans and Specifications or the overall intent of this project.
II. Not conforming to the recommended treatments as outlined in the Secretary of the Interior’s Standards for the Treatment of Historic Properties.
III. Too intrusive or destructive to the remaining historic fabric.
IV. Proposed procedures are inherently unsafe.
V. Proposed procedures are unlikely to produce the high level of craftsmanship required.
VI. Contractor’s written proposal lacks sufficient detail to be properly evaluated.
c. Should the Contractor’s proposal be rejected by the COR, the Contractor shall resubmit a new or modified proposal, fully addressing the COR concerns. No Work shall proceed until the
Contractor’s proposed methods and procedures are fully agreed to and approved by the COR.
d. Submit proposed plan to the COR not less than five (5) working Days prior to the scheduled pre-construction conference.
B. MATERIALS
1. Use materials for temporary protection that will not mar, stain, and physically or chemically damage or alter historic features or finishes.
C. EXECUTION
1. SPECIAL PROJECT CONSIDERATIONS
a. Do not disturb sound, original material which is in place or is found at the site, unless specific agreements between the Owner and ckreiser Highlight Submit proposed plan to the COR not less than five (5) working Days prior to the scheduled pre-construction conference.
Section 01 Page 12
Contractor have been reached. Before beginning each area of Work, examine with the COR each area to determine which items, features and materials are to be retained and protected. Carefully remove, label, document, catalog and safely store original elements that are required to be retained, reinstalled, reused or be placed into long term archival storage.
2. PROTECTIVE MEASURES
a. Follow approved Temporary Protection Plan.
b. General Historic Fabric
I. Protect all historic fabric removed from the building or landscape. Consult with COR to determine disposition of material not scheduled for reuse or having been pre-identified for long-term storage.
II. If damage occurs, such Work shall immediately cease.
Contractor shall immediately report damage to COR in writing
(describing who, what, when, where, why, how, etc.) and await further instructions.
III. Scaffolding shall not be attached to the building (exterior or interior).
3. SPECIAL DEMOLITION PROCEDURES
a. Exercise extreme care in removing historic elements and materials of any kind attached to historic elements that are indicated to remain. Proceed as follows:
I. Unbolt bolted connections.
II. Unscrew screw connections.
III. Do not pry apart members whose finish will be damaged by chipping, scratching, crazing or cracking, or whose structural and/or historic integrity will thereby be impaired.
IV. When prying cannot be avoided, protect finished surfaces and materials scheduled to remain or be reinstalled. Use sacrificial wood blocks, surface protection such as protective carpeting or other approved means agreed to by the COR
V. Throughout the facility, use non-invasive/non-destructive methods. The Owner realizes, however, that certain aggressive methods may need to be employed to complete the Work. All aggressive methods must be approved by the COR in advance. The
COR reserves the right to reject inappropriate methods not in
Section 01 Page 13 conformance with accepted and recognized historic preservation/rehabilitation standards.
VI. When invasive and aggressive methods are unavoidable and fully agreed to by the COR, the Contractor shall submit, for the COR’s approval, proposed methods for repairing and/or mitigating such damage.
VII. When conflicts arise regarding what may constitute appropriate methods, the Specifications shall prevail.
4. HISTORIC DISCOVERIES
a. In the event that features, materials or artifacts are uncovered or discovered during the execution of above-ground Work, notify the
CO immediately. The following procedures will be instituted:
I. CO will issue a verbal Work suspension directing the Contractor to cease all construction operations at the location of a potential historic discovery, to allow the COR to evaluate the significance of the find. A written Work suspension order will be issued within four hours of the verbal Work suspension order.
II. Such Work suspension will be effective until such time as the
COR and other qualified personnel can evaluate the potential historic discovery for their significance. Any Work suspension direction will contain the following:
i. A clear description of the Work to be suspended.
ii. Any instructions regarding issuance of further orders by the
Contractor for material services.
iii. Specific direction to the Contractor to minimize the Work suspension costs (i.e., Work elsewhere while find is being evaluated).
iv. Estimated duration of the temporary suspension.
III. If the COR determines the historic discovery requires further review and/or action, the CO may extend the duration of the
Work suspension order in writing.
IV. Equitable adjustment of the construction contract time will be made for temporarily suspended Work in accordance with the General Conditions.
Section 01 Page 14
5. INSPECTION FOR TEMPORARY PROTECTION OF HISTORIC FABRIC
a. Review all temporary protection Work on Site with COR prior to proceeding with restoration Work.
b. Hazardous Materials: The proposed Work areas are believed to contain hazardous materials. Should any unknown hazardous materials be encountered, stop Work immediately and notify COR in writing of condition.
01400 QUALITY REQUIREMENTS
A. Contractor Quality Control:
1. The Contractor is responsible for the overall quality of all his Work and the Work performed by his Subcontractors working under this contract.
2. The quality of any part of the Work installed must not be less than that required by the technical divisions of this specification.
3. If the Contracting Officer determines that the quality of Work does not conform to the applicable specifications and drawings, the
Contractor will be advised in writing of the areas of nonconformance, and within 7 days the Contractor must correct the deficiencies and advise the Contracting Officer in writing of the corrective action taken.
B. Noncompliance with Quality Control Requirements: Failure of the
Contractor to comply with the above requirements may be cause for termination for default.
C. Quality Control Procedures
1. Monitor quality control over Contractor staff, Subcontractors, suppliers, manufacturers, products, services, site conditions, and workmanship.
2. Comply fully with manufacturer's published instructions, including each step in sequence of installation.
3. Should manufacturer's published instructions conflict with
Contract Documents, request clarification from Contracting
Officer before proceeding.
4. Testing will be as required by regulation or permit or by individual specification sections.
5. Furnish copies of quality assurance documentation to the COR prior to end of job.
Contracting Officer determines that the quality of Work does not conform
Section 01 Page 15
D. Comply with specified standards as a minimum quality for Work, except where more stringent tolerances, codes, or specified requirements indicate higher standards or more precise workmanship.
E. Perform Work by persons who are thoroughly qualified and trained in their respective trade, to produce workmanship of specified quality.
F. Perform tests required by governing authorities having jurisdiction and utilities having jurisdiction.
G. Comply with qualification requirements within individual specification sections.
H. Testing and Inspection Laboratory Services
1. Selection and Payment:
a. The Contractor shall pay for services of an Independent Testing and
Inspection Laboratory to perform required specified testing and inspection.
b. Employment of Independent Testing and Inspection Laboratory in no way relieves Contractor of obligation to perform Work in accordance with requirements of Contract Documents.
2. Quality Assurance:
a. Comply with requirements of all applicable ASTM standards.
b. Laboratory: Authorized to operate in State in which Project is located.
c. Testing Equipment: Calibrated at reasonable intervals with devices of and accuracy traceable to either National Bureau of
Standards or accepted values of natural physical constraints.
3. Laboratory Responsibilities: Contractor should ensure the
Laboratory has the following responsibilities and limits on authority.
a. Test samples of mixes submitted by Contractor.
b. Provide qualified personnel at Project site. Cooperate with
Contracting Officer and Contractor in performance of services.
c. Perform specified sampling, testing, and inspection of Products in accordance with specified standards.
d. Determine compliance of materials and mixes with requirements of
Contract Documents.
ckreiser Highlight The Contractor shall pay for services of an Independent Testing and Inspection Laboratory to perform required specified testing and inspection.
ckreiser Highlight Laboratory: Authorized to operate in State in which Project is located
Section 01 Page 16
e. Promptly notify Contractor Quality Control Representative and
Contracting Officer of observed irregularities or non-conformance of Work or Products.
f. Perform additional tests as required by Contracting Officer.
g. Attend appropriate pre-construction meetings and progress meetings.
4. Limits on Authority:
a. Laboratory may not release, revoke, alter, or expand on requirements of Contract Documents.
b. Laboratory may not approve or accept any portion of Work.
c. Laboratory may not assume any duties of Contractors.
d. Laboratory has no authority to stop Work.
I. Maintain check-off list of Work that does not comply with Contract
Documents, stating specifically what is non-complying, date faulty Work was originally discovered, and date Work was corrected. No requirement to report deficiencies corrected same day it was discovered. Submit copy of
Non- Compliance Check-Off List of non-complying Work items to Contracting
Officer on a weekly basis.
J. Prior to final acceptance by Contracting Officer, submit a certification signed by Contractor to Contracting Officer stating that all Work has been inspected and all Work, except as specifically noted, is complete and in compliance with Contract Documents.
ckreiser
Prior to final acceptance by Contracting Officer, Section 01 Page 17
K. Project Safety:
1. The Contractor shall have the ultimate responsibility for safety on the project site at all times, from issuance of the Notice to
Proceed until final completion and acceptance of the project by the Contracting Officer.
2. The Contractor is responsible for ensuring that all onsite activities, equipment, and facilities constructed by the
Contractor, Subcontractor, or supplier conform fully to the standards of the Department of Labor, Occupational Safety and
Health Administration (OSHA) 29 CFR 1926 and 1910; and DOI and
FWS policies.
3. Adhere to all current Federal, State and local safety requirements. In the event where any safety standard referenced herein conflicts with another, the more stringent shall govern.
4. Initiate and maintain, throughout the performance of this contract, an effective safety program that provides adequate policies, procedures, and practices to protect their employees from, and allow them to recognize, job-related safety and health hazards.
5. Include in safety program, provisions for the identification, evaluation, prevention and control of general Work site hazards, specific job hazards, and potential hazards that may arise from foreseeable construction methods and conditions, as well as providing a competent person to conduct frequent and regular inspections.
6. Each employee must be instructed in the recognition and avoidance of unsafe conditions and the regulations applicable to the Work environment.
7. Provide barricades and warning devices as necessary to safeguard the public, workers, and government personnel.
8. Where project Work affects public roads, provide signage in accordance with the current edition of the Manual on Uniform Traffic
Control Devices (MUTCD) as published by the US Department of
Transportation, Federal Highway Administration.
01410 REGULATORY REQUIREMENTS
Section 01 Page 18
A. Regulatory Requirements:
1. Comply with all applicable federal, state, and local environmental laws and regulations. This condition applies to, but is not limited to, laws and regulations governing noise levels, air and water quality standards, and cultural resources.
2. Comply with the current edition of the National Fire Protection
Association (NFPA) 101 Life Safety Code, International Building
Code, Uniform Federal Accessibility Standard, National Electric
Code, International Plumbing Code, and International Mechanical Code
3. If the code provisions conflict, the more stringent code provision shall govern.
4. In any instances where the drawings and specifications do not specify explicit materials or methods, then perform the Work in accordance with the minimum requirements of the code applicable to the Work.
B. Permit Responsibility:
1. In general, customary building mechanical and electrical fees and permits are not required.
C. Clearances:
1. Contractor may be asked to perform studies and obtain permits as required by, but not limited to: the National Environmental
Protection Act (NEPA), Clean Air and Water Acts, U.S. Army Corp of
Engineers, Coastal Shorelines Act, U.S. Fish and Wildlife internal policies, and other State and local jurisdiction environmental regulations.
2. Coordinate scope of these requirements with COR.
01420 REFERENCES
A. Acronyms
1. USFWS, US FWS, US & FWS, FWS, Owner, Government, and Service, are all intended to mean
U.S Fish & Wildlife
Service, Region 1 911 NE
11th Avenue
Portland, OR 97232-4181
2. CO: Contracting Officer
Section 01 Page 19
3. COTR or COR: Contracting Officers Technical Representative
4. CGS: Division of Contracting and General Services, Region 1, U.S.
Fish & Wildlife Service.
5. DOI: Department of Interior
5. EN: Division of Engineering, Region 1, U.S. Fish & Wildlife Service.
6. D/B: Design Builder or Design Build entity
7. FF&E: Furnishings, Fixtures, and Equipment
8. NWR: National Wildlife Refuge
9. NWRC: National Wildlife Refuge Complex
10. NFH: National Fish Hatchery
11. NFHC: National Fish Hatchery Complex
B. Definitions
1. Allowance(s): A specific monetary sum included in the basic contract amount for a contract element that is undefined. Allowance includes all labor, materials, incidental expenses, taxes, and Contractor markups for incorporation of the element into the project. Allowances will be paid for on a time and materials basis after submittal and approval of a detailed cost break down and a contract modification has been issued. Should the allowance amount exceed the actual cost, savings will accrue to the Owner. Should the allowance not cover the cost an equitable contact modification will be issued.
2. Authority Having Jurisdiction: Division of Engineering, Region 1, U.S.
Fish & Wildlife Service
3. Industry Standard: A reference standard, that establishes a level of quality, performance or other characteristic of a material or system.
4. Local Authority Having Jurisdiction: Duly adopted local code authority, agency, or serving utility governing or serving the location of the project.
5. Remove and Replace (RR): Remove existing component or assembly and replace in kind with new materials of same type, design, quality, and operating characteristics.
6. Remove and Salvage (RSALV): Remove component, equipment or assembly intact and turn over to government for their use.
7. Refurbish (RFR): Restore component, equipment, or assembly “as new”.
Refurbishing includes but is not limited to cleaning, restoring finishes, making inoperable items operable, rewiring, relamping, Section 01 Page 20 custom manufacturing unavailable parts, and replacing missing parts.
If necessary for refurbishment, remove component, equipment, or assembly intact, refurbish, and reincorporate it into the project.
8. Remove and Reinstall (RSR): Remove component, equipment, or assembly intact. Store and protect removed items, reincorporate into project in same condition prior to removal.
9. Unit Price: Establishment of a price based on a per unit basis or task basis for Work to be provided in the project. Unit prices will be good for the duration of the project. Quantities will be measured and only actual quantities installed will be paid for. Unit prices should include all costs including taxes and fee for furnishing and installing into the project. When unit prices are within 10% of estimated amounts the initial unit price will be valid. When unit price quantity exceeds
10% of estimated amounts unit price may be renegotiated.
C. REFERENCED STANDARDS:
1. All Work shall conform to the issue of following referenced standards which is current at date of receipt of bids. Whenever the following abbreviations are used in these Contract Documents, they are to be construed the same as follows:
AA Aluminum Association
AASHTO American Association of State Highway and
Transportation Officials ACI American Concrete Institute
ACM American Construction Manual
AISC American Institute of
Steel Construction APA American
Plywood Association
APWA American Public Works Association
ASTM American Society for Testing and Materials AWPA American Wood
Preservers' Association AWS American
Welding Society
AWWA American Water Works
Association BIA Brick Institute of
America
IBC International Building Code
NEC National Electric Code
Section 01 Page 21
OSHA Occupational Safety and Health Administration
SMACNA Sheet Metal and Air Conditioning Contractors
National Association, Inc. WCLIB West Coast Lumber
Inspection Bureau
01450 FIELD SAMPLES
A. Provide field samples as requested in specific specification sections or on the Drawings. Field samples will be physical examples of specific work constructed for review and approval of workmanship and quality. Field samples will be used for examples of specific products and techniques.
B. Work on field samples to be completed and approved by COR before commencing with remaining work of that construction type.
01460 MOCKUPS
A. Provide mockups as requested in specific specification sections or on the Drawings. Mockups will be used to establish a standard of quality by which the remainder of the work will be judged. They will be used to establish methods and techniques for work. Mockups will be used for examples of multiple products that establish the performance requirement of a system.
B. Work on Mockups to be completed and approved by COR before commencing with remaining work of that construction system type.
01510 TEMPORARY FACILITIES
A. Provide temporary facilities and utilities needed including heat, light, power, water, telephone, sanitary facilities, job offices, storage enclosures, safety devices, construction aids, and support equipment.
B. If suitable FWS power and water is present on the site, those utilities may be used for construction purposes at no cost to the
Contractor
1551 TRAFFIC CONTROLS:
A. Coordinate on site parking and access with Refuge Manager.
mockups
Section 01 Page 22
B. Maintain all fire access lanes and fire parking areas clear of all construction materials, vehicles, and equipment.
01560 ENVIRONMENTAL CONTROLS
A. Comply with all applicable federal, state, and local environmental laws and regulations. This condition applies to, but is not limited to, laws and regulations governing noise levels, air and water quality standards, and cultural resources.
B. Protect adjacent vegetation, property, structures, and improvements from damage.
C. Coordinate with the local FWS staff to select a construction staging area.
D. Provide safety equipment and methods as necessary to perform the Work in a safe manner in accordance with federal and state health and safety regulations. Provide temporary fencing, barricades, and warning devices as necessary to safeguard the public and government personnel.
01610 BASIC PRODUCT REQUIREMENTS
A. Definition: “Product” means new material, machinery, components, equipment, fixtures, and systems of current manufacturer included in the Work, and not including machinery and equipment used for preparation, fabrication, conveying and erection of the Work. Products may include existing materials or components required for reuse.
B. Provide Products that comply with Contract Documents, are undamaged and new at time of installation.
C. Provide Products complete with accessories, trim, finish, safety guards, and other devices and details needed for complete installation and intended use and effect.
D. Substitutions may be considered when Contractor becomes aware of a product or procedure that is more environmentally sensitive.
E. Provide interchangeable components of the same manufacturer, for similar components.
submit substitution request to FWS COR for approval
Section 01 Page 23
F. Use of asbestos or lead containing products is prohibited.
G. Product Selection
1. Comply with specified industry standards.
2. Provide products in size, type, and quantity indicated and specified, unless, variations are accepted by CO in writing.
3. Provide products with capacities, sizes, and performance ratings indicated and specified, unless, variations are accepted by CO in writing
4. Two or more products of the same kind shall be identical and by the same manufacturer
01630 PRODUCT SUBSTITUTION PROCEDURES
A. Product Options
1. For Products specified by Reference Standards or by description only, select any Product meeting those standards or description.
2. For Products specified by naming one or more manufacturers and allowing no options for substitutions, use products of manufacturers named and meeting specifications.
3. For Products specified by naming one or more manufacturer’s with a provision for substitutions, Contractor must submit a Request for
Substitution for any manufacturer not specifically named.
4. Use of the terms “or equal”, “approved”, or approved substitution”, means substitutions are allowed.
5. When a single product or material is identified and substitutions are allowed it is the intent of the specified product or material to provide a level of quality, design and performance for evaluation of substitutions.
B. Substitution Representations
1. Changes in products, materials, equipment, and method of construction required by the Contract Documents proposed by the
Contractor after award of the Contract are considered to be requests for substitutions.
2. A substitution request constitutes a representation that the
Contractor has investigated the proposed product and determined that it meets or exceeds the quality level of the specified
Section 01 Page 24 product or system.
3. The Contractor will provide the same warranty for the substitution as for the specified product.
4. The Contractor will coordinate the installation and make changes to the Work, which may be required for the Work to be completed with no additional cost to the government.
5. Waive claims for additional costs or time extensions which may subsequently become apparent.
6. Reimburse the government for review or redesign services associated with re-approval.
C. Substitution Procedures
1. Submit substitution requests on a copy of the CSI Substitution Request
Form.
2. Submit a separate request for each product, supported with complete data, drawings, and samples as appropriate.
3. Substitution requests for a multiple list of mechanical and electrical components in one category of Work by one manufacturer may be listed on one Substitution Request Form.
4. COTR will notify Contractor, in writing, of decision to accept or reject substitution request.
5. Contractor will provide a statement indicating the substitution’s effect on the Contractor’s Construction Schedule compared to the schedule without approval of the substitution. Indicate the effect of the proposed substitution on overall Contract Time.
D. Substitution Conditions
1. After the contract has been executed, the Owner and Owner’s Representative will consider the Contractor’s request for substitution when one or more of the following conditions are satisfied, as determined by the Owner’s Representative. If the following conditions are not satisfied, the Owner’s Representative will return the requests without action except to record noncompliance with these requirements.
1. Extensive revisions to the Contract Documents are not required.
2. Proposed changes are in keeping with the general intent of the Contract Documents.
CSI Substitution Request Form.
Section 01 Page 25
3. The request is timely, fully documented, and properly submitted.
4. The requested substitution offer the Owner a substantial advantage, in cost, time, energy, conservation, or other considerations, after deducting additional responsibilities the
Owner must assume. The Owner’s additional responsibilities may include compensation to the Owner’s Representative for redesign and evaluation services, increased cost of other construction by the Owner, and similar considerations.
E. The Contractor’s submittal and the Owner’s Representative acceptance of Shop Drawings, Product Data, or Samples for construction activities not complying with the Contract Documents do not constitute an acceptable or valid request for substitutions, nor do they constitute approval.
01660 PRODUCT STORAGE AND HANDLING REQUIREMENTS
A. Transport and handle Products in accordance with manufacturer's instructions, using means and methods that will prevent damage, deterioration and loss, including theft.
/10
B. Schedule Product delivery to minimize long-term storage at Project site and prevent overcrowding of construction spaces.
C. Coordinate Product delivery with installation schedule to assure minimum holding time for items that are flammable, hazardous, easily damaged, or sensitive to deterioration, theft, and other losses.
D. Deliver Products to Project site in undamaged condition in manufacturer's original sealed container or other packaging system, complete with labels and instructions for handling, storing, unpacking, protecting, and installing.
E. Promptly inspect shipments to ensure that Products comply with project requirements, quantities are correct, Products are undamaged, and properly protected.
F. Store and protect Products in accordance with manufacturers' published instructions, with seals and labels intact and legible.
Section 01 Page 26
G. Store Products subject to damage by elements above ground, under cover in weather tight enclosure, with ventilation adequate to prevent condensation. Maintain temperature and humidity within range required by manufacturer's published instructions.
H. For exterior storage of fabricated Products, place on sloped supports, above ground.
I. Provide off-site storage and protection when Project site does not permit on-site storage or protection.
J. Cover Products subject to deterioration with impervious sheet covering. Provide ventilation to avoid condensation or potential degradation of Product.
K. Store loose granular materials on solid flat surfaces in a well-drained area. Prevent mixing with foreign matter.
01710 EXAMINATION
A. Verification of Conditions: Verify that field measurements, surfaces, substrates and conditions are as required, and ready to receive Work.
B. Report in writing to COR prevailing conditions that will adversely affect satisfactory execution of the Work. Do not proceed with Work until unsatisfactory conditions have been corrected.
C. By beginning Work, Contractor accepts conditions and assumes responsibility for correcting unsuitable conditions encountered at no additional cost to the US Fish and Wildlife Service.
01730 EXECUTION
A. Manufacturer’s Instructions
1. Handle Store, fabricate, erect, install, connect, apply, clean, condition and adjust products and systems in accordance with manufacturer’s printed instructions and in conformance with requirements specified herein.
3. Obtain and distribute copies of manufacturer’s printed fabrication, installation, and application instructions to parties involved in the construction.
4. Review and resolve conflicts between manufacturer’s instructions
Section 01 Page 27 and Contract Documents with COR prior to fabrication and installation of products and systems
D. Perform the Work in accordance with the technical specifications and other provisions of this contract.
E. Construct items plumb, true, and square.
F. Where dissimilar materials occur and are subject to degradation when in contact with each other, provide buffer materials to prevent degradation.
01735 CUTTING AND PATCHING
A. Comply with Section 01340.C.3 Special Demolition Procedures for work on historic materials.
B. Accomplish cutting and patching to:
1. Incorporate new Work into existing work.
2. Remove defective non complying Work.
3. Uncover defective Work or Work not installed in proper sequence.
4. Observe Work covered by Contractor prior to acceptance.
5. Provide openings in elements of Work for penetration of mechanical and electrical and other utility Work.
6. Remove…