About this file
This is a Schedule of Items pricing template for the Rock Creek Road Maintenance solicitation (127EAX26Q0014) issued by the Department of Agriculture Forest Service for work on the Tres Piedras Ranger District of the Carson National Forest. The document outlines line items with quantities and units for both base and optional work, though pricing has not yet been populated.
The base scope includes mobilization (1 lump sum), drain dip construction using native material (23 each), road widening incorporating native material with cut slope only (1,390 cubic yards), curve widening (70 cubic yards), road obliteration (0.4 miles), new construction with native material (0.6 miles), rip rap placement class 4 (20 tons), road reconditioning (10.8 miles), and culvert installation for a 57" x 38" arch corrugated metal pipe (30 linear feet). Option 1 includes additional drain dip construction (7 each), road widening (660 cubic yards), curve widening (110 cubic yards), and road reconditioning (7.4 miles). All unit prices and totals are currently blank, indicating this is a template for contractor proposals. The schedule does not include company name, point of contact information, SAM Unique Entity ID, or calculated totals, which are to be completed by responding contractors.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 127EAX26Q0014 External Documents.pdf | ||
| 127EAX26Q0014 0001.pdf | ||
| 127EAX26Q0014 Rock Creek Road Maintenance.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SOI
| SCHEDULE OF ITEMS - ROCK CREEK ROAD MAINTENANCE | |||||
| ITEM NO. | DESCRIPTION | QUANTITY | UNIT | UNIT PRICE | AMOUNT |
| BASE | |||||
| 15101 | Mobilization | 1 | LS | $ - 0 | $ - 0 |
| 20401A | Drain dip construction, native material, compaction using placement method 2 | 23 | EA | $ - 0 | $ - 0 |
| 20402A | Road widening, incorporate native material, cut slope only, compaction using placement method 2 | 1390 | CU YD | $ - 0 | $ - 0 |
| 20403A | Curve widening, incorporate native material, cut slope only, compaction using placement method 2 | 70 | CU YD | $ - 0 | $ - 0 |
| 21101 | Road obliteration, method 1 | 0.4 | MI | $ - 0 | $ - 0 |
| 21201 | New construction, incorporate native material, compaction using placement method 2 | 0.6 | MI | $ - 0 | $ - 0 |
| 25101 | Rip rap placement, machine placed, class 4 | 20 | TONS | $ - 0 | $ - 0 |
| 30301A | Road reconditioning | 10.8 | MI | $ - 0 | $ - 0 |
| 60201 | Culvert installation, furnish bedding material, 57" x 38" arch CMP | 30 | LN FT | $ - 0 | $ - 0 |
| OPTION 1 | |||||
| 20401B | Drain dip construction, native material, compaction using placement method 2 | 7 | EA | $ - 0 | $ - 0 |
| 20402B | Road widening, incorporate native material, cut slope only, compaction using placement method 2 | 660 | CU YD | $ - 0 | $ - 0 |
| 20403B | Curve widening, incorporate native material, cut slope only, compaction using placement method 2 | 110 | CU YD | $ - 0 | $ - 0 |
| 30301B | Road reconditioning | 7.4 | MI | $ - 0 | $ - 0 |
| Company Name: |
POC Name and Email:
| SAM UEI: | Base Total | $ - 0 | |
| Option 1 Total: | $ - 0 | ||
| Grand Total: | $ - 0 |