Summary: Rock Creek Road Maintenance RFQ and Associated Documents
This file contains a Request for Quotation (RFQ) package issued by the U.S. Department of Agriculture Forest Service for the Rock Creek Road Maintenance project on the Tres Piedras Ranger District of the Carson National Forest in New Mexico. The solicitation number is 127EAX26Q0014, with a modification date of January 2, 2026. This is a Total Small Business Set-Aside contract with a NAICS code 237310 and small business size standard of $45 million. The contract type is Firm-Fixed-Price, and the government intends to make one award. All quotations are due by April 10, 2026, at 1:00 PM Central Daylight Time, with requests for information due by April 3, 2026. Contractors must commence work within 10 calendar days of receiving the notice to proceed and complete all work within 150 calendar days of NTP. The project includes base items totaling 10.9 miles and option items totaling 7.4 miles across multiple National Forest System Roads.
The Statement of Work specifies eight technical tasks including drain dip construction (approximately 180 cubic yards of native material), road widening (approximately 1,390 cubic yards of excavation resulting in 12-foot road widths), curve widening, road obliteration, new construction (0.6 miles of clearing and grubbing with approximately 600 cubic yards of excavation), rip rap placement, road reconditioning (ditch, shoulder, roadbed, and aggregate surface maintenance), and culvert installation (57" x 38" arched corrugated metal pipe, 30 feet long with approximately 30 cubic feet of bedding material). Quotations must include a completed SF 1442 form, price proposal using the Schedule of Items, technical proposal addressing capability and past performance, and a bid guarantee. Evaluation criteria consist of technical approach (40%), past performance (30%), and price (30%). The government incorporates the Standard Specifications for Construction of Roads and Bridges on Federal Highway Projects (FP-14) by reference along with Forest Service Supplemental Specifications. Nine deliverables are required including weekly status reports, construction schedules, traffic control plan, soil erosion and sediment control plan, hazardous spill plan, dewatering plan, and material tickets for bedding and pipe.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 127EAX26Q0014 0001.pdf | ||
| Attachment 5 - Schedule of Items.xlsx | XLSX spreadsheet | |
| 127EAX26Q0014 Rock Creek Road Maintenance.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PROJECT: ROCK CREEKROAD MAINTENANCE
SOLICITATION NO.: 127EAX26Q0014
Table of Contents Acquisition Description
Schedule of Items
Technical Data
Project Location
Solicitation Information
Quote Evaluation and Basis for Award
Evaluation Method
Required Quote Submission Documents
Acquisition Description
This is a combined synopsis/solicitation for commercial items prepared in accordance with the format in FAR Part 12. This announcement constitutes the only solicitation; offers are being requested, and a separate written solicitation will not be issued.
Solicitation number 127EAX26Q0014 is issued as a Request for Quotation (RFQ) for the Rock Creek Road Maintenance
This acquisition is set-aside for small business concerns. This solicitation incorporates provisions and clauses by reference. The full text of provisions and clauses may be accessed electronically at www.acquisition.gov.
The applicable North American Industry Classification Standard Code is 237310 The small business size standard is $45M This acquisition is a Total Small Business Set-Aside. All responsible sources may submit a quotation which will be considered by the agency.
Schedule of Items
See Attachment 5 for Schedule of Items. Attached Schedule of Items needs to be completed in full and submitted with quote.
Technical Data
Technical data and supporting documentation associated with this solicitation are available through the following sources:
Solicitation Attachments The following documents are included as attachments to this solicitation and can be accessed via the “Attachments/Links” section of the posting.
1. Statement of Work
2. Fire Plan
3. Drawing Set
4. Specifications
5. Schedule of Items
6. Wage Determination
Project Location
See solicitation attachment “1. Statement of Work” for project location.
Federal Acquisition Regulation (FAR) and United States Department of Aquiculture Acquisition Regulation (AGAR) Clauses and Provisions The clauses and provisions contained herein are applicable to any order awarded as a result of this solicitation. The terms and conditions set forth herein supersede all other terms and conditions.
Acceptance of the order in accordance with (IAW) FAR 12.201-1(b)(2) constitutes acceptance of all terms and conditions contained herein.
As part of the Revolutionary FAR Overhaul (RFO), system updates may lag policy updates. The System for Award Management (SAM) may continue to require entities to complete representations based on provisions that are not included in this solicitation. Contracting officers will rely on representations from offers based on provisions in the solicitation. Entities are not required to, nor are they able to, update their entity registration to remove these representations in SAM.
52.252-2 Clauses Incorporated by Reference Feb 1998 This solicitation incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also the full text of the clause may be accessed electronically at Internet address https://www.acquisition.gov/far-overhaul/far-part-deviation-guide/far-overhaul-part-52
The following clauses are mandatory in all solicitations and contracts - Do not delete these.
52.212-4 Terms and Conditions—Commercial Products and Commercial Services (Nov 2025)
This is a commercial construction acquisition. FAR 52.212-4 is amended as follows:
(b) Inspection/Acceptance. Inspection and Acceptance will be conducted in accordance with FAR 52.246-12, Inspection of Construction (Aug 1996).
(d) Changes. Changes will be handled in accordance with the following FAR clause(s):
☒ FAR 52.243-5, Changes and Changed Conditions (Nov 2025)
(o) FAR 52.246-21, Warranty of Construction is applicable to this contract.
52.203-17 Contractor Employee Whistleblower Rights (Nov 2023) 52.203-19 Prohibition on Requiring Certain Internal Confidentiality Agreements or Statements (Jan 2017) 52.222-50 Combating Trafficking in Persons (Nov 2025) 52.226-8 Encouraging Contractor Policies to Ban Text Messaging While Driving (May 2024) 52.232-40 Providing Accelerated Payments to Small Business Subcontractors (Mar 2023) 52.233-3 Protest After Award (Sep 2025) 52.233-4 Applicable Law for Breach of Contract Claim (Sep 2025) 52.240-91 Security Prohibitions and Exclusions (Nov 2025) 52.244-6 Subcontracts for Commercial Products and Commercial Services (Nov 2025) 52.204-13 System for Award Management—Maintenance (Nov 2025) 52.209-6 Protecting the Government’s Interest When Subcontracting with Contractors Debarred, Suspended, or Proposed for Debarment (Sep 2025) 52.209-10 Prohibition on Contracting with Inverted Domestic Corporations (Sep 2025) 52.219-6 Notice of Total Small Business Aside (Nov 2025) 52.219-8 Utilization of Small Business Concerns (Nov 2025)
52.222-3 Convict Labor (June 2003) 52.222-35 Equal Opportunity for Veterans (Nov 2025) 52.222-36 Equal Opportunity for Workers with Disabilities (Nov 2025) 52.222-37 Employment Reports on Veterans (Nov 2025) 52.222-54 Employment Eligibility Verification (Nov 2025) 52.222-62 Paid Sick Leave Under Executive Order 13706 (Jan 2022) 52.223-23 Sustainable Products and Services 52.232-33 Payment by Electronic Funds Transfer— System for Award Management (Oct 2018) 52.222-6 Construction Wage Rate Requirements 52.222-7 Withholding of Funds 52.222-8 Payrolls and Basic Records 52.222-9 Apprentices and Trainees 52.222-10 Compliance with Copeland Act Requirements 52.222-11 Subcontracts (Labor Standards) 52.222-12 Contract Termination-Debarment 52.222-14 Disputes Concerning Labor Standards 52.222-15 Certificate of Eligibility 52.236-5 Material and Workmanship 52.222-32 Construction Wage Rate Requirements-Price Adjustment (Actual Method) (Nov 2025) 52.225-9 Buy American-Construction Materials (Nov 2025) 52.228-2 Additional Bond Security (Oct 1997) 52.228-14 Irrevocable Letter of Credit (Nov 2014) 52.228-15 Performance and Payment Bonds-Construction (Jun 2020) 52.228-17 Individual Surety-Pledge of Assets (Bid Guarantee) (Feb 2021) 52.236-2 Differing Site Conditions (Jul 2025) 52.236-3 Site Investigation and Conditions Affecting the Work (Jul 2025) 52.236-6 Superintendent by the Contractor (Jul 2025) 52.236-7 Permits and Responsibilities (Jul 2025) 52.236-8 Other Contracts (Jul 2025) 52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements (Jul 2025) 52.336-10 Operations and Storage Areas (Jul 2025) 52.236-11 Use and Possession Prior to Completion (Jul 2025) 52.236-12 Cleaning Up (Jul 2025) 52.236-13 Accident Prevention (Jul 2025) 52.236-14 Availability and Use of Utility Services (Jul 2025) 52.236-15 Schedules for Construction Contracts (Jul 2025) 52.236-16 Quantity Surveys (Jul 2025) 52.236-17 Layout of Work (Jul 2025) 52.236-21 Specifications and Drawings for Construction (Jul 2025) 52.242-14 Suspension of Work (Apr 1984)
AGAR Clauses
452.204–70 Modification for Contract Closeout (Nov 2025)
(a) If unliquidated funds in the amount of $1000 or less remain on the contract, the Contracting Officer (Contracting Officer) shall issue a unilateral modification for deobligation. The contractor will receive a copy of the modification but will not be required to provide a signature. The Contracting Officer shall immediately proceed with contract closeout upon completion of the period of performance, receipt and acceptance of supplies or services, and final payment.
(b) Upon contract closeout for contracts utilizing SAP: if unliquidated funds of more than $1000 remain on the contract, the Contracting Officer shall issue a bilateral modification for deobligation.
The contractor will receive a copy of the modification and will be required to provide a signature.
(The Contracting Officer may also request a “Contractor Release of Claims” be completed by the contractor, although not required for contracts and orders using SAP.) If the bilateral modification and Release of Claims are not returned to the Contracting Officer within 60 days, the Contracting Officer shall release the modification as unilateral and proceed with contract closeout upon completion of the period of performance, receipt and acceptance of supplies or services, and final payment.
(c) Upon contract closeout for contracts utilizing anything other than cost reimbursement, if unliquidated funds of more than $1000 remain on the contract, the Contracting Officer shall issue a bilateral modification for deobligation. The contractor will receive a copy of the modification and a ‘‘Contractor Release of Claims’’ and will be required to provide a signature on both forms. If the bilateral modification and Release of Claims are not returned to the Contracting Officer within 120 days, the Contracting Officer shall release the modification as unilateral and proceed with contract closeout upon completion of the period of performance, receipt and acceptance of supplies or services, and final payment.
(End of Clause)
452.203-71 Anti-Discrimination and Diversity, Equity, and Inclusion (DEI) Compliance (Dec 2025)
(a) By entering into this contract, the Contractor certifies that:
(1) It is compliant with all applicable Federal anti-discrimination laws and the Equal Protection principles of the U.S. Constitution, and it will remain compliant for the duration of the contract.
(2) Neither it nor any subcontractor or teaming partner operates or funds any program, policy, or initiative that promotes DEI in a manner that violates any applicable Federal anti-discrimination laws, including but not limited to Title VI and VII of the Civil Rights Act of 1964, or the Equal Protection principles of the U.S. Constitution, and the Contractor and any subcontractor or teaming partner will not do so for the duration of the contract.
(b) If the Contractor participates in, facilitates, or funds programs that implicate Title VI of the Civil Rights Act of 1964 or Title IX of the Education Amendments of 1972, as amended, including but not limited to grants to or for schools, colleges, universities, 4-H programs, non-governmental organization (NGO) programs, sports programs, and education-related grants to prisons or other detention facilities, the Contractor certifies that it will remain compliant with those laws, including the requirements set forth in Executive Order 14168, Defending Women from Gender Ideology Extremism and Restoring Biological Truth to the Federal Government, and Executive Order 14173, Ending Illegal Discrimination and Restoring Merit-Based Opportunity.
(c) The Contractor affirms that the above requirements are conditions of payment that go to the essence of the contract and are therefore material terms of the contract. Payments under the contract are predicated on compliance with the above requirements, and therefore the Contractor is not eligible for funding under the contract or to retain any funding under the contract absent compliance with the above requirements.
(d) This certification reflects a change in the Government’s position regarding the materiality of the foregoing requirements and therefore any prior payment of similar claims does not reflect the materiality of the foregoing requirements to this contract.
(e) Submission of a knowing false statement relating to Contractor’s compliance with the above requirements and/or eligibility for the contract may subject the Contractor to liability under the False Claims Act, 31 U.S.C. § 3729, and/or criminal liability, including under 18 U.S.C. §§ 287 and 1001.
(f) The Contractor must include the provisions of this clause in all subcontract solicitations.
(g) Failure on the part of the Contractor or its subcontractors to comply with the terms of this clause may be grounds for the Contracting Officer to terminate this contract for default.
(End of Clause)
452.232-71 Progress Payments for Commercial Construction Contracts (Dec 2025)
(a) Contractor entitlement to progress payments. The Contractor may request progress payments monthly as the work proceeds, or at more frequent intervals as determined by the Contracting Officer, on estimates of work accomplished that meets the standards of quality established under the contract, as approved by the Contracting Officer.
(b) Computation of amounts. Progress payments will be authorized when the payment requested is properly due in accordance with this contract; the work will be performed in accordance with the contract; and there has been no impairment or diminution of the Government’s security under this contract. The Contracting Officer may authorize consideration of:
(3) Materials delivered on site and preparatory work;
(4) Materials delivered to the Contractor at locations other than the site, if:
i. Specifically authorized by the contract; and
ii. The Contractor provides satisfactory evidence of title and intended use in the contract.
(c) Contractor request for progress payments. The Contractor’s request for progress payments shall include the following:
(1) An itemization of the amounts requested, related to the various elements of work required by the contract;
(2) A listing of the amount included for work performed by each subcontractor;
(3) A listing of the total amount of each subcontract;
(4) A listing of the amounts previously paid to each subcontractor; and
(5) Additional supporting data in a form and detail required by the Contracting Officer.
(d) Contractor Certification. Each request for progress payment shall be accompanied by the following certification:
I hereby certify, to the best of my knowledge and belief, that—
(1) The amounts requested are only for performance in accordance with the specifications, terms, and conditions of the contract;
(2) All payments due to subcontractors and suppliers from previous payments received under the contract have been made, and timely payments will be made from the proceeds of the payment covered by this certification, in accordance with subcontract agreements and the requirements of Chapter 39 of Title 31, United States Code;
(3) This request for progress payments does not include any amounts which the prime contractor intends to withhold or retain from a subcontractor or supplier in accordance with the terms and conditions of the subcontract; and
(4) This certification is not to be construed as final acceptance of a subcontractor’s performance.
________________________________________________(name) ________________________________________________(title) ________________________________________________(date)
(e) Access for verification of payment entitlement. To verify the Contractor’s entitlement to progress payments under this contract, the Contractor shall provide the Government, upon request and during normal business hours, access to the following:
(1) Records and Documentation:
(i) Certified progress payment requests and supporting documentation;
(ii) Subcontractor and supplier invoices, payment records, and lien waivers;
(iii)Updated schedule of values and progress schedules;
(iv) Quality assurance and inspection reports;
(v) Payroll records, if applicable under labor provisions.
(2) Facilities and Worksite Access:
(i) Physical access to the construction site for inspection of work progress;
(ii) Access to off-site storage locations for materials billed but not yet incorporated into the work; or (iii)Access to any fabrication facilities where contract-related work is being performed.
(3) Access to electronic invoicing or project management systems used to track progress and payments, if such systems are used in contract performance.
(f) Dates for payment. A progress payment under this clause is a contract progress payment under the Prompt Payment clause of this contract, and except as provided in paragraph (g) of this clause, approved requests shall be paid within 30 days of submittal of a proper request for payment.
(g) Liquidation of progress payments. Progress payments shall be liquidated by deducting from the payment of each item the total unliquidated amount of progress payments made for that separately priced unit of that line item. The liquidation amounts for each line item shall be clearly delineated in each request for progress payment submitted by the Contractor.
(h) Security for progress payments. In the event the Contractor fails to provide adequate security as required in this contract, no progress payment shall be made under this contract. Upon receipt of adequate security, progress payments shall be made, including all previous payments to which the Contractor is entitled, in accordance with the terms of the contract. If at any time the Contracting Officer determines that the security provided by the Contractor is insufficient, the Contractor shall promptly provide such additional security as the Contracting Officer determines necessary. In the event the Contractor fails to provide such additional security, the Contracting Officer may collect or liquidate such security that has been provided, and suspend further payments to the Contractor; the Contractor shall repay to the Government the amount of unliquidated progress payments as the Contracting Officer at his sole discretion deems repayable.
(i) Special terms regarding termination for cause. If this contract is terminated for cause, the Contractor shall, on demand, repay to the Government the amount of unliquidated progress payments. The Government shall be liable for no payment except as provided by the Termination for Cause paragraph of the clause at Federal Acquisition Regulation 52.212-4, Contract Terms and Conditions—Commercial Products and Commercial Services.
(j) Reservation of rights.
(1) No payment, vesting of title under this clause, or other action taken by the Government under this clause shall-
(i) Excuse the Contractor from performance of obligations under this contract; or
(ii) Constitute a waiver of any of the rights or remedies of the parties under the contract.
(2) The Government’s rights and remedies under this clause-
(i) Shall not be exclusive, but rather shall be in addition to any other rights and remedies provided by law or this contract; and
(ii) Shall not be affected by delayed, partial, or omitted exercise of any right, remedy, power, or privilege, nor shall such exercise or any single exercise preclude or impair any further exercise under this clause or the exercise of any other right, power, or privilege of the Government.
(k) Refund of unearned amounts. If the Contractor, after making a certified request for progress payments, discovers that a portion or all of such request constitutes a payment for performance by the Contractor that fails to conform to the specifications, terms, and conditions of this contract (hereinafter referred to as the "unearned amount"), the Contractor shall-
(1) Notify the Contracting Officer of such performance deficiency; and
(2) Be obligated to pay the Government an amount (computed by the Contracting Officer in the manner provided in paragraph (j) of this clause) equal to interest on the unearned amount from the 8th day after the date of receipt of the unearned amount until-
(i) The date the Contractor notifies the Contracting Officer that the performance deficiency has been corrected; or
(ii) The date the Contractor reduces the amount of any subsequent certified request for progress payments by an amount equal to the unearned amount.
(l) Retainage. If the Contracting Officer finds that satisfactory progress was achieved during any period for which a progress payment is to be made, the Contracting Officer shall authorize payment to be made in full. However, if satisfactory progress has not been made, the Contracting Officer may retain a maximum of 10 percent of the amount of the payment until satisfactory progress is achieved. When the work is substantially complete, the Contracting Officer may retain from previously withheld funds and future progress payments that amount the Contracting Officer considers adequate for protection of the Government and shall release to the Contractor all the remaining withheld funds. Also, on completion and acceptance of each separate building, public work, or other division of the contract, for which the price is stated separately in the contract, payment shall be made for the completed work without retention of a percentage.
(m) Title, liability, and reservation of rights. All material and work covered by progress payments made shall, at the time of payment, become the sole property of the Government, but this shall not be construed as-
(1) Relieving the Contractor from the sole responsibility for all material and work upon which payments have been made or the restoration of any damaged work; or
(2) Waiving the right of the Government to require the fulfillment of all the terms of the contract.
(3) The Government’s rights and remedies under this clause-
(i) Shall not be exclusive, but rather shall be in addition to any other rights and remedies provided by law or this contract; and
(ii) Shall not be affected by delayed, partial, or omitted exercise of any right, remedy, power, or privilege, nor shall such exercise or any single exercise preclude or impair any further exercise under this clause or the exercise of any other right, power, or privilege of the Government.
(n) Reimbursement for bond premiums. In making these progress payments, the Government shall, upon request, reimburse the Contractor for the amount of premiums paid for performance and payment bonds (including coinsurance and reinsurance agreements, when applicable) after the Contractor has furnished evidence of full payment to the surety. The retainage provisions in paragraph (l) of this clause shall not apply to that portion of progress payments attributable to bond premiums.
(o) Final payment. The Government shall pay the amount due the Contractor under this contract after-
(1) Completion and acceptance of all work;
(2) Presentation of a properly executed voucher; and
(3) Presentation of release of all claims against the Government arising by virtue of this contract, other than claims, in stated amounts, that the Contractor has specifically excepted from the operation of the release. A release may also be required of the assignee if the Contractor’s claim to amounts payable under this contract has been assigned under the Assignment of Claims Act of1940 ( 31 U.S.C.3727 and 41 U.S.C. 6305).
(p) Limitation because of undefinitized work. Notwithstanding any provision of this contract, progress payments shall not exceed 80 percent on work accomplished on undefinitized contract actions. A "contract action" is any action resulting in a contract, as defined in FAR subpart 2.1, including contract modifications for additional supplies or services, but not including contract modifications that are within the scope and under the terms of the contract, such as contract modifications issued pursuant to the Changes clause, or funding and other administrative changes.
(End of clause)
Solicitation Information
Award Type
It is anticipated that a Firm-Fixed-Price Contract will be awarded as a result of this synopsis/solicitation. The Government intends to make one award from this solicitation. Therefore, to be considered responsive, contractors must submit all required documents.
Period of Performance The Contractor shall be required to commence work under this contract within 10 calendar days after the date the Contractor receives the notice to proceed and the entire work ready for use not later than 150 calendar days after NTP. The time stated for completion shall include final cleanup of the premises.
Organized Site Visit Due to current weather conditions at project location, there will not be a scheduled site visit.
Contractors can visit the location on their own.
Requests For Information (RFI’s) Requests For Information (RFI’s) are required to be submitted on attachment “8. RFI Form” and are due to the Contracting Officer (troy.mccullough@usda.gov) via email no later than April 3rd, 2026, 1:00 PM Central Daylight Time. No questions will be accepted after this date and time.
Quote Due Date All quotes shall be emailed to the Contracting Officer (troy.mccullough@usda.gov) no later than April 10th, 2026, 1:00 PM Central Daylight Time.
Quote Evaluation and Basis for Award
The provision at FAR 52.212-2, Evaluation—Commercial Products and Commercial Services is not applicable to this solicitation. In lieu of this provision, quotes will be evaluated in accordance with FAR 12.203 based on the criteria listed below. Award will be made to the offeror representing the best value to the Government.
1. Technical Approach: The technical approach will evaluate the ability of the offeror to provide a sound, compliant approach offeror's ability to provide a sound and compliant approach that meets all requirements and shows a thorough understanding of them. It is the contractor's responsibility to ensure their quotation clearly demonstrates their capability to meet these requirements. All offerors must provide the following minimum information and documentation with their quotations to be considered responsive and have their offers evaluated:
Detailed explanation of your capability to accomplish this work. The offeror must address how they will accomplish all requirements of the SOW Description of the work you plan to subcontract.
Include any subcontractors and their experience and capabilities.
Planned sequencing of all work including the major tasks and timelines The resources (personnel and equipment) planned for use on the project and their availability.
2. Past Performance: Furnish a list of three (3) projects of similar magnitude completed by the firm within the last three (3) years. The list should include work similar in nature and complexity to that required by this solicitation. Include contracts with the Federal Government, agencies of state, local governments, and commercial customers. For each project cited, provide the following:
Name and location of the project;
Project Point of Contact’s name, phone, email address, and fax numbers; Total cost of the project;
A brief narrative of the project (include size, i.e. acres, square feet; date of start, and completion or anticipated completion date).
The Government may utilize any references provided by the Contractor, along with information available from past contracts/orders with the USDA and any information found using sources such as Federal Government sources or the Contractor Performance Assessment Reporting System (CPARS) to determine if the Contractor has acceptable or neutral Past Performance.
Past Performance will be evaluated using the following rating system:
Acceptable: The contractor shows a demonstrated ability to meet contract requirements in prior or current contracts, including quality of work, timeliness, cost control, business relations, and adherence to contract terms.
Neutral: Offeror does not have a past performance record.
Unacceptable: The contractor has a documented history of failing to meet contract requirements, including poor quality, missed deadlines, cost overruns, lack of responsiveness, or unethical behavior.
3. Price
The offeror shall provide pricing as requested in the Schedule of Items in attachment ” 2.
Schedule of Items” of this Request for Quote. Failure to propose pricing for all individual line items may result in a quotation being excluded from further consideration. The offeror’s quotation will be evaluated in accordance with FAR 12.204, to determine if it is fair and reasonable.
Evaluation Method
All quotations will be evaluated to identify the offeror presenting the most technically advantageous solution based on the stated evaluation criteria. Once the highest technically rated offeror is identified, their price will be evaluated to determine whether it is fair and reasonable. Past performance will also be assessed to ensure it is acceptable or neutral.
Award will be made to the offeror whose proposal is determined to be the highest technically rated, provided that:
1. The proposed price is fair and reasonable, and
2. Technical proposal is most advantageous to the Government
3. Past performance is assessed as acceptable or neutral.
Award will not necessarily be made to the lowest-priced offeror. Tradeoffs will not be conducted.
52.252-1 Solicitation Provisions Incorporated by Reference Feb 1998 This solicitation incorporates one or more solicitation provisions by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. The offeror is cautioned that the listed provisions may include blocks that must be completed by the offeror and submitted with its quotation or offer. In lieu of submitting the full text of those provisions, the offeror may identify the provision by paragraph identifier and provide the appropriate information with its quotation or offer. Also, the full text of a solicitation provision may be accessed electronically at this/these address(es): https://www.acquisition.gov/far-overhaul/far-part-deviation-guide/far-overhaul-part-52
52.212-1 Instructions to Offerors - Commercial Products and Commercial Services (Nov 2025)
FAR 52.212-1 is amended as follows:
Period for acceptance of offers: The Offeror agrees to hold the prices in its offer firm for 60 calendar days from the date specified for receipt of offers.
Offeror must have an active entity registration at https://www.sam.gov/ in order to submit a quote.
Required Quote Submission Documents
All quote submissions shall include:
1. Completed, Signed Offer SF1442 (Section A.): Complete blocks 10 Fill-ins, 14, 15, 16, 17, 20a, b, and c on the SF 1442. If amendment(s) are issued acknowledge amendments or complete blocks 19, 20a, 20b & 20c. Signed by authorized person to bind firm.
2. Price Proposal Section B, Attachment 5 - Schedule of Items: Complete fill ins Company Name, UEI #, POC Name and POC Email.
3. Technical Proposal: Technical approach and past performance
4. Bid Guarantees – See FAR 52.228-1: Scanned copy of fully executed Bid Guarantee emailed.
The four (4) documents detailed within “Required Quote Submission Documents” shall be submitted as separate Adobe PDF documents. It is the quoter’s responsibility to ensure delivery of all required documents by the date and time set for receipt of offers.
Contact the Contracting Officer by e-mail if you do not understand any part of these instructions.
FAR Provisions
52.203-18 Prohibition on Contracting with Entities that Require Certain Internal Confidentiality Agreements or Statements-Representation (Jan 2017) 52.240-90 Security Prohibitions and Exclusions Representations and Certifications (Nov 2025) 52.203-11 Certification and Disclosure Regarding Payments to Influence Certain Federal Transactions (Sep 2024) 52.204-7 System for Award Management—Registration (Nov 2025) 52.223-4 Recovered Material Certification (May 2008) 52.225-2 Buy American Certificate (Oct 2022) 52.225-10 Notice of Buy American Requirement - Construction Materials (May 2014) 52.222-5 Construction Wage Requirements, Secondary Site of the Work (Nov 2025) 52.225-10 Notice of Buy American Requirement- Construction Materials (May 2014) 52.228-1 Bid Guarantee (Sep 1996)
AGAR Provisions
452.203-70 Anti-Discrimination and Diversity, Equity, and Inclusion (DEI) Certification (Dec 2025)
(a) By submission of its offer, the offeror certifies that:
(1) It is compliant with all applicable Federal anti-discrimination laws and the Equal Protection principles of the U.S. Constitution.
(2) Neither it nor any proposed subcontractor or teaming partner operates or funds any program, policy, or initiative that promotes DEI in a manner that violates any applicable Federal anti-discrimination laws, including but not limited to Title VI and VII of the Civil Rights Act of 1964, or the Equal Protection principles of the U.S. Constitution.
(b) If the offeror participates in, facilitates, or funds programs that implicate Title VI of the Civil Rights Act of 1964 or Title IX of the Education Amendments of 1972, as amended, including but not limited to grants to or for schools, colleges, universities, 4-H programs, non-governmental organization (NGO) programs, sports programs, and education-related grants to prisons or other detention facilities, by submission of its offer, the offeror certifies that it is compliant with those laws, including the requirements set forth in Executive Order 14168, Defending Women from Gender Ideology Extremism and Restoring Biological Truth to the Federal Government, and Executive Order 14173, Ending Illegal Discrimination and Restoring Merit-Based Opportunity.
(c) The offeror affirms that the above requirements are conditions of payment that go to the essence of the contract and are therefore material terms of the contract. Payments under the contract are predicated on compliance with the above requirements, and therefore the offeror will not be eligible for funding under the contract or to retain any funding under the contract absent compliance with the above requirements.
(d) This certification reflects a change in the Government’s position regarding the materiality of the foregoing requirements and therefore any prior payment of similar claims does not reflect the materiality of the foregoing requirements to this contract.
(e) Submission of a knowing false statement relating to offeror’s compliance with the above requirements and/or eligibility for the contract may subject the offeror to liability under the False Claims Act, 31 U.S.C. § 3729, and/or criminal liability, including under 18 U.S.C. §§ 287 and 1001.
(f) Failure on the part of the offeror or its subcontractors to comply with the terms of this clause may be grounds for the Contracting Officer to terminate the contract for default.
(End of Provision)
NOTICE FOR FILING AGENCY PROTESTS
United States Department of Agriculture (USDA) Ombudsman Program
The USDA is committed to issuing solicitations and awarding contracts in a fair and prompt manner.
The Ombudsman Program for Agency Protests (OPAP) was established to address protest issues within the agency, providing an alternative to costly and time-consuming litigation. Operating independently, OPAP offers relief comparable to that granted by the Government Accountability Office (GAO). Interested parties are encouraged to resolve concerns through USDA’s internal Alternative Dispute Resolution (ADR) process before pursuing external forums such as the GAO.
Concerns may be addressed informally or through a formal agency protest filed with either the Contracting Officer or the Ombudsman.
Informal Forum with the Ombudsman
1. Initial Point of Contact: Interested parties who believe a specific USDA procurement is unfair or otherwise defective should first direct their concerns to the applicable Contracting Officer.
2. Escalation: If the Contracting Officer is unable to address their concerns, interested parties are encouraged to contact the USDA Ombudsman for Agency Protests. Under this informal process, the agency is not required to suspend contract award performance. Utilization of the informal forum does not suspend any time requirement for filing a formal protest with the agency or other forums.
3. Required Information: To ensure a timely response, interested parties should provide the following information to the Ombudsman: solicitation/contract number, contracting office, Contracting Officer, and solicitation closing date (if applicable).
Formal Agency Protest with the Ombudsman
1. Effort to Resolve: Prior to submitting a formal agency protest, protesters must first use their best efforts to resolve their concerns with the Contracting Officer through open and frank discussions.
2. Independent Review: If the protester’s concerns remain unresolved, an Independent Review is available by the Ombudsman. The protester may file a formal agency protest with either the Contracting Officer or, alternatively, with the Ombudsman under the OPAP program. Contract awards or performance will be suspended during the protest period unless justified in writing for urgent and compelling reasons or determined in writing to be in the best interest of the Government.
3. Resolution Timeline: The agency’s goal is to resolve protests within 35 calendar days from the date of filing.
4. Required Information: Protests shall include the information set forth in FAR 33.104(a)(3).
Failure to submit the required information may result in a delay or dismissal of the protest.
5. Timeliness: Protests must be filed within the timeframes specified in FAR 33.104.
6. Submission: Formal protests under the OPAP program should be submitted electronically to SPE.inquiry@usda.gov and the Contracting Officer.
Election of Forum. By initiating a protest with the USDA, the protester agrees not to pursue the same matter with the Government Accountability Office (GAO) or any other external forum while the agency protest is pending. If a protest is filed externally, the agency protest will be dismissed.
US Department of Agriculture (USDA)
Statement of Work for
Rock Creek Road Maintenance
United States Forest Service
Carson National Forest
Tres Piedras Ranger District
June 18, 2025
Contents Project General Information
1.0 Scope of Work
2.0 Background
Contractor Requirements
3.0 Technical Requirements / Tasks
4.0 Deliverables / Schedule
Project Rock Creek Road Maintenance
General Information
1.0 Scope of Work
The Carson National Forest is pursuing road maintenance activities to be accomplished on the Tres Piedras Ranger District during Fiscal Year 2025. Base items include drain dip construction, road widening, curve widening, road obliteration, new construction, rip rap placement, road reconditioning, and culvert installation. Drain dip construction will involve excavation and compaction of approximately 180 cubic yards of native material. Road widening will involve approximately 1390 cubic yards of excavation and compaction and will result in total road widths of twelve (12) feet.
New construction will involve 0.6 miles of clearing and grubbing and approximately 600 cubic yards of excavation and compaction. Road reconditioning will involve ditch maintenance, shoulder maintenance, roadbed maintenance, and aggregate surface maintenance where applicable. Lastly, culvert installation will involve the placement of a 57” x 38” arched corrugated metal pipe thirty (30) feet in length on top of approximately 30 cubic feet of uncompacted bedding material.
Work is necessary to accommodate access and stabilize roads and drainages within the Rio Chama Collaborative Forest Landscape Restoration Project area. Road maintenance activities will accommodate future timber cutting operations and will be subject to the transport of heavy machinery and log hauling.
Base items are located along National Forest System Roads (NFSRs) 91, 91B, 178D, 187C, 187D, 1873, B3, and B6 for a total of 10.9 miles and option items are located along NFSRs 91B, 91C3, 9103, and B20 for a total of 7.4 miles. However, not all tasks are applicable to these total lengths.
2.0 Background
The project is located on the Tres Piedras Ranger District of the Carson National Forest near Tres Piedras, New Mexico.
The project area can be accessed using National Forest System Roads (NFSRs) 91B and/or 712. The project landscape is moderately steep and is generally located at the mid-to-high elevations of the area (~10,000 feet). Numerous trailheads for the Continental Divide National Scenic Trail are located within the project area and NFSR 91B is a major recreational corridor for hiking, dispersed camping, OHV use, and hunting opportunities. NFSRs 91, 91B, and 1873 are open to the public. The remainder of the roads included in this contract are closed to the public and will be temporarily open for administrative access only.
Contractor Requirements
3.0 Technical Requirements / Tasks
This contract contains eight different tasks, each of which are applicable to at least one of the twelve project road segments. Each road segment requires a different combination of such tasks as detailed in Table 3.1.
Table 3.1. Base Items and Option Items
NFSR Drain Dip Construction
Road Widening
Curve Widening
Road Obliteration
New Construction
Rip Rap Placement
Road Reconditioning
Culvert Installation
Base Items
91B
178D
187C
187D
B3
B6
Option Items
91B
91C3
B20
The Standard Specifications for Construction of Roads and Bridges on Federal Highway Projects (FP-14 U.S. Customary Units), 2014 are included by reference. The requirements contained in these specifications are hereby made a part of this solicitation and any resultant contract.
The 746-page book entitled “Standard Specifications for Construction of Roads and Bridges on Federal Highway Projects” (FP-14 U.S. Customary Units), is available from:
https://highways.dot.gov/federal-lands/specs
FOREST SERVICE SUPPLEMENTAL SPECIFICATIONS TO THE STANDARD SPECIFICATIONS FOR CONSTRUCTION OF ROADS AND BRIDGES ON FEDERAL HIGHWAY PROJECTS (FSSS) may add to, delete from, or modify the Forest Service Standard Specifications (FP-14).
Table 3.2 includes the primary specifications pertinent to this contract. However, this list is not comprehensive as these specifications may reference others not listed here.
Table 3.2. Included Standard Specifications
FP-14 Section Number FP-14 Section Title 151 Mobilization 204 Excavation and Embankment 211 Road Obliteration 212 Linear Grading 251 Riprap 303 Road Reconditioning 602 Culverts and Drains
4.0 Deliverables / Schedule
Table 4.1 details the nine deliverables the Contractor shall submit.
Table 4.1. Required Deliverables
No. Deliverable Description Frequency Reference(s) Due By
1 Status Reports Weekly reports documenting task progress and issues identified
Once per week SOW Section 3.0 Fridays by 3 PM MDST until contract expires
2 Initial Construction Schedule
Schedule of future tasks and time required to complete them
Once FAR 52.236-15 10 days following contract award
3 Construction Schedule Updates
Schedule of past and future tasks and time required to complete future tasks
Once per month FAR 52.236-15
Last Fridays by 3 PM MDST until contract expires
4 Traffic Control Plan Plan detailing preventative and mitigating measures promoting safety of public
Once FSSS 156 10 days following contract award https://highways.dot.gov/federal-lands/specs and administrative personnel necessary to maintain road access
Soil Erosion and Sediment Control Plan
Plan detailing preventative measures for avoiding mass erosion and mitigating movement of sediment
Once FSSS 157 10 days following contract award
6 Hazardous Spill Plan
Plan detailing preventative measures for avoiding spills of hazardous materials and contingency plans should such spills occur
Once FSSS 107, FAR 52.223-3
10 days following contract award
7 Dewatering Plan Plan detailing dewatering strategy for culvert installation
Once FP-14/FSSS 104, 5 days before beginning work on item 60201
8 Bedding Material Ticket
Ticket detailing source and specifications of culvert foundation material
Once FP-14/FSSS 209, 602, 704
5 days before beginning work on item 60201
9 CMP Material Ticket
Ticket detailing source and specifications of culvert pipe Once FP-14/FSSS 602, 5 days before beginning work on item 60201
The Contractor is required to provide written progress reports weekly for the entire duration of the contract. Progress reports shall cover all work completed during the specified period and shall present the work to be accomplished during the subsequent period. Progress reports shall identify any problems that arose and a statement explaining how the problems were resolved. Progress reports shall also identify any problems that have arisen but have not been completely resolved and provide an explanation. These are the same weekly reports as those referred to as Status Reports (Deliverable No. 1) in Table 4.1.
Submittals shall include the following:
1. Date and revision date(s) if applicable.
2. Project name and contract number.
3. Name of Contractor and subcontractor, supplier, and/or manufacturer if applicable.
4. Contractor's stamp or signature certifying review of the submittal and compliance with all contract documents.
All submittals shall be sent via email to the Contracting Officer (CO) and the Contracting Officer’s Representative (COR).
Timely submission of deliverables is essential to successful completion of this requirement. Schedules for deliverables are specified in Table 4.1. All deliverables shall be prepared and submitted according to format, content, and schedule as described in Table 4.1. All “hard copy” deliverables will be submitted on recycled content paper and printed double-sided.
The CO shall fully accept, conditionally accept and provide comments, or fully deny submittals within five (5) business days of receipt from the Contractor.
FIRE PLAN
The Contractor shall be responsibile for the cost of suppressing all fires caused by his operation, and for all damage to any property of the USDA Forest Service or third parties The USDA Forest Service reserves the right to participate in extinguishing any fires caused by the contractor’s operations and the contractor reimburse the USDA Forest Service for the cost of all suppression activities ardered or directed by the USDA Forest Service. The following requirements are a part of this solicitation and any resulting contract.
(1) Fire Prevention: During periods of contract performance, fire requirements shall be met by the contractor.
(2) Execution of Fire Plan:
(a) Forest Service personnel involved will, in all cases, coordinate through the Contracting
Officer’s Representative (COR) except in cases of emergency of Forest closure.
(b) The contractor shall designate a fire plan representative who shall be responsible for executing and carrying out the fire requirements.
(c) The contractor shall include the fire requirements in all subcontracts
(d) The contractor shall assure that all contract employees are informed of the exsistence and conditions of the fire requirements.
(3) Compliance Inspection:
(a) Inspection by the Forest Service will be made to insure compliance with fire requirements.
(b) Should any deficiencies appear during the inspection, the contractor will be informed and the deficiencies shall be correctd within 24 hours. Activities with the potential to start fires shall be halted until the deficiencies are corrected and the corrections approved by the COR.
(4) Fire Presuppresssion Requirements:
(a) Fire Toolbox
(1) During fire season, the Contractor shall furnish and maintain, at the contractor’s expense, one fire toolbox at the campsite or some central location, as long as it is within ¼ mile of the location where the Contractor is currently performing work.
(2) The fire toolbox is to be maintained with tools in good condition in the following quantities for each five people in the Contractor’s workforce. The eqiupment is for the sole source of firefighting. Four shovels, two axes, one pulaski, and five each 1-gallon canteens. Where needed, brushhooks and McLeod tools may be substituted for shovels or axes.
(3) The fire toolbox shall be replenished by the Contractor after each incidence of fire use.
(a) Work-hours At all times during closed fire season period, as specified by State law, the Contractor shall comply with each of the following provisions to the extent applicable to his operation under the contract. Unless the COR waives the requirement in writing.
The fire plan shall also specify additional measures and/or special requirements, such as Mexican
Spotted Owl restrictions, necessary during periods of critical fire weather conditions.
When Mexican Spotted Owl restrictions are invoked, the Forest Service may curtail or shut down all or portions of a Contractor's operations. The following requirements may be imposed:
a. All high fire risk operations could be terminated at 1000 local time.
a. Patrolman may be required for a period of 2 hours after high fire risk operations and 1 hour after end of work shift. The Contractor shall provide the patrolman unless the contract is for equipment rental, in which case the Government will provide the patrolman.
Reference of Industrial Operations on last page of Fire Plan
Fire Extinguishers and Tools on Mobile or Stationary Equipment. Each unit of powered equipment used in connection with this contract, including automobiles, trucks, tractors, etc., shall be equipped with serviceable tools and fire extinguishers as follows:
a. One - fire extinguisher, dry chemical type of not less than 2-1/2 pound capacity with 4 BC or higher rating.
b. One - shovel, round point #0 lady or equal.
c. One - water container (at least 1-gallon capacity), not required with stationary equipment.
Spark Arresters. Each internal combustion engine shall be provided with a spark arrester or spark arresting device approved by the Forest Service. Exceptions where the Forest Service may approve mufflers, or other equipment in lieu of spark arresters qualified and rated under Forest Service Standard 5100-1a, are: (a) small multiposition engines, such as chain saws, shall meet Society of Automotive Engineers J335b standards; (b) passenger-carrying vehicles and light trucks may have baffle-type mufflers with tail pipe; (c) heavy-duty trucks may have a vertical stack exhaust system and muffler, provided the exhaust stack extends above the cab of the vehicle.
An exhaust-driven turbocharger is considered to be a satisfactory spark arrester. Internal combustion engine exhaust systems, arresters, and other devices must be properly installed and maintained.
Powersaws. For each powersaw used in connection with this contract, the following will be provided:
a. One - shovel, round point #0 lady or equal. Shovel must be immediately available for use.
b. One - Fire extinguisher, containing not less than 8 ounces of extinguisher fluid, or a dry chemical powder-type of not less than 1-pound capacity. The extinguisher must be immediately accessible to the saw operator at all times.
Any fueling or refueling of a powersaw shall only be done in an area which has first been cleared or is free of all material capable of carrying fire;…