Attachment 5 - Sample FAT Plan.pdf
PDF 294 KB Posted
- Attached to
- Mk 706 Mod 0 Shipping Containers Federal contract opportunity
- Solicitation number
- N0017424R0007
About this file
This First Article Test Plan outlines testing requirements for the MK 706 Mod 0 Shipping Container solicited under Request for Proposal N0017424R0007. The Navy seeks a contractor to manufacture and assemble the MK 706 Mod 0 Shipping Container, a rectangular aluminum container that holds four MK 66 Rocket Motors in individual tubes. The First Article Test Plan specifies visual and dimensional inspections, fit and compatibility testing with inert rocket motors, leak testing of the container and cover assembly, repetitive shock testing under vibration, and free fall drop testing of the loaded container per military standards. The contractor will conduct testing at its own facility while the Navy may witness, and will submit test data, materials certifications, and a final report for Navy review and approval. The sole award will go to the responsible offeror providing the best value to the government.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| N0017424R0007 Amendment 0002.pdf | ||
| N0017424R0007 Amendment 0001.pdf | ||
| N0017424R0007.pdf | ||
| Attachment 4 - GFP Attachment.xlsx | XLSX spreadsheet | |
| Attachment 3 - Past Performance Matrix.pdf | ||
| Attachment 2 - Past Performance Questionnaire.pdf | ||
| Attachment 1 - Order Period Stepladder Pricing.xlsx | XLSX spreadsheet | |
| Exhibit A - CDRLs A001 - A007.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
MK 706 Shipping Document FAT Plan i
01 Aug 2012
MK 706 MOD 0 SHIPPING CONTAINER
First Article Test Plan ii
CONTENTS
INTRODUCTION
1.1 DESCRIPTION
1.2 APPLICABLE DOCUMENTS
Standards Drawings
2.0 TEST OBJECTIVE
3.0 TEST ITEM CONFIGURATION
4.0 FIRST ARTICLE TEST MATRIX
5.0 TEST AND INSPECTION DESCRIPTION
5.1 VISUAL & DIMENSIONAL INSPECTION
5.2 FIT AND COMPATIBILITY TEST
5.3 LEAK TEST
5.4 REPETITIVE SHOCK TEST
5.5 FREE FALL DROP TEST
6.0 EXPECTED TEST RESULT
7.0 DATA COLLECTION, REDUCTION AND ANALYSIS
Introduction
1.1 Description
Roughly rectangular in shape, the MK 706 Container consists of four aluminum tubes with common end caps, each tube capable of holding a single MK 66 (2.75-inch) rocket motor. A single cover located in the top end cap allows access to all four tubes. The cover is secured with a combination quarter-turn/screw-type fastener, and features four circular rubber gaskets – one to seal each tube. The lateral surfaces of both end caps contain stacking lugs and matching recesses which allow stable horizontal tiering of like containers. Longitudinal restraint of the rocket motor in the tube is provided by polyethylene foam buffers (one each end) and acrylic disc spacers (on bottom, three top) which fit snugly against the end of the rocket motor, while two fiberboard strips taped about the circumference of the motor prevent contact with the tube wall.
The container measures 451/4” X 8” X 8” and weighs 20 pounds empty. This weight becomes 75 pounds when loaded with four 13 ½ pounds MK 66 Rocket Motors (including 4 acrylic spacers and 2 fiberboard strips per rocket motor).
1.2 Applicable Documents
Standards
MIL-STD-648D Department of Defense Design Criteria Standard Specialized Shipping Containers
Drawings
Number Revision Title
233AS601 J BODY ASSEMBLY
233AS602 E COVER ASSEMBLY
233AS603 D TOP
233AS604 G BASE
233AS605 C TUBE, BODY
233AS606 C SPIDER ASSEMBLY
233AS607 F BUFFER
233AS608 E SPACER
233AS609 F COVER PLATE
233AS610 F SHAFT ASSEMBLY
233AS611 E CLAMPING BAR ASSEMBLY
233AS612 D WASHER
233AS613 G WASHER
233AS614 D GASKET
233AS615 D SPIDER ASSEMBLY
233AS616 F RIVET
233AS617 F SHAFT
233AS618 F CLAMPING BAR
233AS619 E BUSHING
233AS620 D LUG
233AS621 C PIN
233AS622 D SHIPPING CONTAINER MARK 706 MOD 0
2.0 Test Objective
The objective of this test plan is to provide inspections and testing data to support First Article Testing (FAT) for the MK 706 MOD 0 Shipping Container in accordance with drawing 233AS622. The FAT is being performed to qualify the contractor for production of the MK 706 Mod 0 Shipping Container.
3.0 Test Item Configuration
There will be one (1) MK 706 MOD 0 Shipping Container, constructed in accordance with drawing 233AS622, being evaluated for FAT. Unless accompanied by a deviation, the one shipping container shall conform to the dimensional and material requirements of the MK 706 Mod 0 Shipping Container drawings specified in 1.2.
All Material Review Board (MRB) actions including Requests for Deviations (RFD’s) and Engineering Change Proposals (ECP’s) shall be completed prior to testing and documented in the final report. A detailed container pedigree including component serialization, quality control assessment, and inspection data and processing records shall be obtained and documented in the final test report.
4.0 First Article Test Matrix
Table 1. First Article Test Matrix
Inspection / Test Test Method Paragraph
Visual & Dimensional Inspection 5.1 A Fit and Compatibility Test 5.2 B Leak Test 5.3 C Repetitive Shock Test 5.4 D Free Fall Drop Test 5.5 E Leak Test 5.3 F
5.0 Test and Inspection Description
The tests and inspections to be performed are shown in the test matrix, section 4.0. The test and inspection specified are described in detail below:
5.1 Visual & Dimensional Inspection
The MK 706 container will be visually inspected for physical damage on the overall container and dimensionally inspected for conformance to drawing 233AS601 through 233AS622, as listed in 1.2. All
5.2 Fit and Compatibility Test
The container will be loaded with four inert MK 66 Rocket Motors, supplied by the Government, and evaluated for proper fit, compatibility, and ease of installation/removal.
5.3 Leak Test
The body assembly will be leak tested in accordance with note 9 of drawing 233AS601, Rev. J and the cover assembly will be leak tested in accordance with note 7 of drawing 233AS602, Rev. E. Each tube and the cover assembly will be submereged in water, pressurized to 5.00 psig for 15 seconds (minimum) and checked for leaks. No leakage is allowed.
5.4 Repetitive Shock Test
The container will be loaded with four inert MK 66 Rocket Motors, supplied by the Government, and subjected to the repetitive shock test of paragraph 5.5.2 of MIL-STD- 648D. The loaded container will be placed on a vibration platform and the platform vibrated with a 1 – inch double amplitude at a frequency of 4.1 Hz for a period of two hours. This input motion shall cause the container to leave the input platform by at least 1/16 inch on each cycle.
5.5 Free Fall Drop Test
The container will be loaded with four inert MK 66 Rocket Motors, supplied by the Government, and subjected to the free fall drop test of paragraph 5.2.3 of MIL-STD- 648D. Eight drops will be made from a height of 19 inches onto a concrete surface:
points of contact shall consist of two pairs of diagonally opposite corners, top, bottom, and two adjacent sides. The rocket motors and inert grains must remain undamaged and the container capable of continued use. Minor dents that do not affect stackability are acceptable.
6.0 Expected Test Result
The First Article Test Unit will not show any major physical damage and will not show any leakage.
Security
There are no security requirements for this validation as all activities are unclassified.
Location
First article testing will take place at the Contractor’s facility. No Government test facilities will be used in this validation.
Participation
Government and Contractor participation roles and responsibilities are identified in Table 2. The Government is invited to witness all test activities The Government shall be given a minimum of 7 business days notification, email is acceptable, prior to the scheduled FAT date which includes production of the FAT samples.
Table 2. FAT Roles and Responsibilities
Government Contractor Roles • Test team member
• Review/approve test plan
• Test conductor
• Submit formal test plan Responsibilities • Review test data
• Review/approve test report
• Collect test data
• Conduct data reduction/analysis
• Provide test report
7.0 Data Collection, Reduction and Analysis
Actual Test and Inspection data records (actual recorded data) used shall be included within the report. The data records shall be signed and dated by the inspector that performed the test or inspection at the time of the test. Actual signed data records may be supplemented with, but not replaced by, electronic spreadsheets to allow for data reduction. Transposed records should be avoided as a substitute for the original data sheet. All materials required by the drawings, 1.2, shall be validated by inclusion of a certificate of compliance (CoC) in the FAT report. Each CoC shall include any and all objective data necessary to evaluate material conformance to listed specifications and requirements.
| Introduction |
| 1.1 Description |
| 1.2 Applicable Documents |
| Standards |
| Drawings |
| 2.0 Test Objective |
| 3.0 Test Item Configuration |
| 4.0 First Article Test Matrix |
| 5.0 Test and Inspection Description |
| 5.1 Visual & Dimensional Inspection |
| 5.2 Fit and Compatibility Test |
| 5.3 Leak Test |
| 5.4 Repetitive Shock Test |
| 5.5 Free Fall Drop Test |
| 6.0 Expected Test Result |
| 7.0 Data Collection, Reduction and Analysis |