Attachment 5-Risk Analysis.docx

DOCX document 26 KB Posted

Attached to
PEPFAR Small Grants Program U.S. Embassy Yaounde
Opportunity number
AFYDE-YCIF-GR-PEPFAR-2024
Issued by

About this file

This document is a Risk Analysis Attachment for a federal grant opportunity. The purpose of the risk analysis is to identify internal and external risks associated with the proposed project, rate the likelihood and potential impact of the risks, and outline risk mitigation plans and actions. The risk analysis should address risks affecting the realization of project objectives and outcomes, the organization, and the safety and security of personnel. Applicants are required to conduct thorough risk assessments and take necessary actions to mitigate risks. The federal grant opportunity is the PEPFAR Small Grants Program offered by the U.S. Embassy in Yaounde, Cameroon. This grant program aims to strengthen the operational and advocacy capacities of youth-led organizations enrolled in the Catalytic Youth Initiative program, provide direct resources to these organizations, and improve HIV prevention, care, and treatment services for youth in Cameroon by 2026. Grant awards are contingent on the receipt of funding.

Risk Analysis

View the file

Other files

File Type Posted
Attachment 1 - Budget Guidance and Template for New Awards (FY2021).xlsx XLSX spreadsheet
SF424A-V1.0.pdf PDF
Attachment 4- Logic Model.docx DOCX document
Attachment 3 - PMP Template.docx DOCX document
Attachment 2 - Budget Narrative Template.docx DOCX document
SF424B-V1.1.pdf PDF
SF424_4_0-V4.0.pdf PDF
Combined version NOFO Final 2.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Attachment 4: Risk Analysis

The purpose of the risk analysis is to identify the internal and external risks associated with the proposed project in the application, rate the likelihood of the risks, rate the potential impact of the risks on the project, and identify actions that could help mitigate the risks. The risk analysis should include gender-related risks, including, but not limited to, gender-based violence.

A risk analysis should not be considered a one-time exercise or a static document. Organizations should conduct adequate risk analysis and remediation for all its operations and advises that risk analysis and remediation occur throughout the life of a project and should result in revisions to risk analysis documents and processes as necessary.

A suggested format for a risk analysis document is below. Applicants should include all assumptions and external factors identified in the logic model in the risk analysis. Under “Description of Risk,” the risk analysis should address any risk of fraud and corruption, as well as assess the level of risk that the proposed program may inadvertently benefit terrorists or their supporters. Under “Likelihood of Risk” and “Potential Impact of Risk,” applicants should rate the as “High,” “Medium,” or “Low.” Additional lines can be included in the risk analysis table as necessary.

The safety and security of recipients and beneficiaries are of utmost importance. The Embassy requires all recipients to conduct thorough risk assessments and take all actions necessary in accordance with those assessments to mitigate those risks. The Embassy will not take responsibility for the risks incurred by any recipient.

Description of Risk
Likelihood of Risk
Potential Impact of Risk
Risk Mitigation Plans/Actions

Risks affecting realization of project objectives

Risks affecting realization of project outcomes/outputs

Risks affecting the organization

Risks affecting security and safety of personnel