This document is a Price Schedule attachment for Solicitation No. 140P82425Q0062, related to replacing fire suppression and alarm systems at Pinnacles National Park in Paicines, California. The solicitation is a 100% small business set-aside for a firm fixed price contract, with a single contractor to be selected based on responsiveness and past performance. The scope of work involves comprehensive fire system upgrades, including removal and disposal of outdated systems, installation of new fire sprinkler and alarm/detection systems, ensuring compliance with NFPA standards and National Park Service Reference Manual 58, conducting hydrant flow testing, and performing system testing and commissioning. Contractors are required to submit a lump sum price that includes all labor, tools, equipment, materials, insurance, administration, project management, overhead, and profit, with a supporting price breakdown detailing job categories, hourly rates, and hours required.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Solicitation no. 140P82425Q0062– Attachment no. 5, Price Schedule to Submit with Quote (8/18/25) Replace Fire Suppression and Alarm Systems, Pinnacles National Park (PINN)

PRICE SCHEDULE

The quoter shall factor the lump sum price to include all labor, tools, equipment, materials, insurance, contract administration, project management, overhead and profit necessary for completing all work. All work shall be performed in accordance with the solicitation terms and clauses, including the attached Dept. of Labor Service wage rates and Statement of Work.

The Quoter shall submit a price for the line item below. Failure to do so may render the quote ineligible. The Government anticipates being able to evaluate solely based upon the price quoted. However, the Government is requesting as part of filling in price below to also submit a supporting price breakdown that includes labor, providing the job categories/titles, hourly rates, and number of hours. Award will be made to one contractor in accordance with Sections L and M.

Complete this page and the following pages and return with other documents described in Section L of the solicitation Terms, Provisions, Clauses.

Price Schedule Line Item Number
Description - Refer to Statement of Work (Solicitation Attachment 4)
Qty
Unit of Measure
Total Price
1
Removal and disposal of outdated fire suppression and alarm systems
1
Lump Sum
$

Installation of new fire sprinkler and fire alarm/detection systems

Ensuring compliance with NFPA standards, National Park Service (NPS) Reference Manual 58 (RM-58), and other relevant codes

Conducting hydrant flow testing and verification of water supply adequacy

Performing system testing and commissioning to ensure proper functionality

Providing final documentation, including compliance certifications and maintenance guidelines.

Quoter’s Business Name:

Business Address:

UEI Number from www.SAM.gov:

Are you proposing to use a sub-contractor? (Answer YES or NO):

If “YES”, list proposed sub-contractor:

Point of Contact Email/Phone Number:

Submitted by – Printed Name:

Submitted by – Signature:

Submitted Date: