Attachment 5 General Condition Breakdown.docx
DOCX document 13 KB Posted
- Solicitation number
- 36C24925R0040
About this file
The document is an Attachment 5 General Condition Breakdown detailing project management and site condition requirements for a VA medical facility renovation project. The breakdown includes comprehensive staffing categories such as Project Management (Superintendent, Safety Manager, CPM Scheduler, Project Manager), administrative support roles, and Field Office personnel.
The site conditions section outlines extensive temporary infrastructure requirements, including temporary power, water, electrical hookups, communication systems, fencing, fire protection, traffic control measures, security systems, and environmental protection measures like SWPPP (Stormwater Pollution Prevention Plan). These conditions are specifically for the VA Veterans Health Administration project (Solicitation Number: 36C24925R0040) to renovate B200 Ground for a Bronchoscopy Procedure Room in Veterans Integrated Service Network 9, indicating a detailed, comprehensive approach to preparing and managing the construction site's operational needs.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 36C24925R0040 0003.docx | DOCX document | |
| Attachment 1 Revised Specifications Amendment-0002 - 07-15-2025.pdf | ||
| LIST OF ATTACHMENTS.docx | DOCX document | |
| Attachment 2 Revised Drawings Amendment-0002 - 07-15-2025.pdf | ||
| Attachment 3 Sign-in Sheet - Renovate B200 Ground For Bronchoscopy.pdf | ||
| 36C24925R0040 0002.docx | DOCX document | |
| 36C24925R0040 0001.docx | DOCX document | |
| Attachment 8 Request For Information Form.docx | DOCX document | |
| Attachment 6 Past Performance Questionnaire.docx | DOCX document | |
| 36C24925R0040_1.docx | DOCX document | |
| Attachment 2 Drawings.pdf | ||
| Attachment 1 Specifications.pdf | ||
| Attachment 3 Pricing Schedule.xlsx | XLSX spreadsheet | |
| Attachment 7 Contractor EMR Certification.docx | DOCX document | |
| Attachment 9 Wage Determination TN20250160 - Modification 0 - 01-03-2025.pdf | ||
| Attachment 4 Calc. of Self Performed Work General Contractor.xlsx | XLSX spreadsheet |
Show all 16
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Project Management:
Superintendent(s)
Safety Manager
CPM Scheduler
Quality Assurance/Quality Control
Project Manager (s)
Project Executive
Field Office Engineer
Field Office Support Staff
Project Expeditor
Assistant Superintendent (s)
Project Manager Subtotal
Bonds and Insurance (excluding any for Subcontractors):
Builder’s Risk Insurance
General Liability Insurance
Security, Payment & Performance Bonds
Bonds and Insurance Subtotal:
Site Conditions:
Temporary Power Consumption (Offices)
Temporary Power Consumption (General Site Use)
Temporary Water and Sewer Consumption
Temporary Water Hookup, Distribution & Meters
Temporary Electrical Hookup, Distribution & Meters
Temporary Telephone & Network System Installation
Temporary Telephone & Internet Consumption Fees
Temporary Fire Protection
Temporary Heating & Cooling
Temporary Fencing
Temporary Covered Walkways
SWPPP Measures
Temporary Entries and Truck Washes
Street Cleaning (by G.C.)
Traffic Control Measures
Temporary Barricades & Signage
Temporary Roads & Walkways (install & maintenance)
Temporary Lighting
Temporary Partitions & Covered Floor Openings
Temporary Toilets/Sanitary Measures
Temporary Laydown (prep and restoration)
Security System/Watchman
Pre-construction Photo Documentation
Progress Photos
Temporary Protection (in place work/adjacent structures)