Attachment 5 DUVRI Ungulate Control.pdf
PDF 443 KB Posted
- Attached to
- Ungulate Control Service at DMC, Tirrenia, Pisa
- Solicitation number
- W912PF25QUNGU
About this file
This document is a Documento Unico di Valutazione dei Rischi di Interferenza (DUVRI), which is an Italian risk assessment document for a contract involving ungulate control services at the Darby Military Community (DMC) operated by USAG Italy. The document details potential workplace risks, safety precautions, and emergency management procedures for contractors performing wild boar and fallow deer population control within the military installation.
The contract involves three workers conducting ungulate control activities from 30 September 2025 to 29 September 2026, with potential extensions for four additional option years. Key safety considerations include risks from vehicular traffic, equipment operation, potential falling objects, noise exposure, and working in areas with military personnel and trained dogs. The document outlines specific preventive measures such as delimiting work areas, using appropriate personal protective equipment, following strict traffic and movement protocols, and coordinating with on-site military personnel for safe operations.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
[Type text]
CENTRALE COMMITTENZA / CONTRACTING OFFICE
COMANDO USA SETAF
DARBY MILITARY COMMUNITY
VIA AURELIA
56018 TIRRENIA (PI)
STRUTTURA ORGANIZZATIVA NELLA QUALE SARA’ SVOLTA L’ATTIVITA’ / ORGANIZATIONAL STRUCTURE WHERE ACTIVITY WILL TAKE PLACE
DATORE DI LAVORO / EMPLOYER
LPW-O - VIA AURELIA SS1
ZONA DEPOSITO
56018 TIRRENIA PISA
COMANDANTE / COMMANDER: Col. Scott W. Horrigan
DMC MANAGER: Timothy Andersen RSPP Ufficio SPP / Safety Officer ING. CHIARA CHELOSSI
DIRETTORATO /
DIRECTORATE
DIRECTORATE OF PUBLIC
WORKS (DPW)
Medico Competente / Occupational Health Doctor Dr. Peluso Raffaele Direttore del DPW /
Director of DPW
LORENZO MOLINA
RLS / Workers’ Safety Representative
Arianna Cappetti Michele Bastianelli Antonio Salsedo Luca Sbrana
Responsabile di area / Area Supervisor
Committente / Commissioning Employer Comando USA SETAF
Addetti al pronto soccorso / First Aid qualified Employees
DES – Fire Section
Addetti all’antincendio / Building Fire Wardens
DITTA APPALTATRICE / CONTRACTOR
INDIRIZZO / ADDRESS
DATORE DI LAVORO / EMPLOYER:
Responsabile di cantiere / Contractor’s on-site Representative
Medico competente / OH Doctor _______________ RSPP / Safety Officer _______________ Addetti al pronto soccorso (cantiere) / First Aid qualified Employees (Contractor)
Addetti all’antincendio (cantiere) / Fire Wardens (Contractor)
RLS / Employees’ Safety representative _______________
PWO MANAGER
VERIFICATO/REVIEWED
Safety Office
VERIFICATO/REVIEWED
LORENZO MOLINA Date: ___________
SIGNATURE _____________________________
Ing. Chiara Chelossi Date: _13 Jun 25__
SIGNATURE _____________________________
DUVRI
DOCUMENTO DI VALUTAZIONE DEI RISCHI DI INTERFERENZA
ART. 26 COMMA 3, D.LGS. 81/08
SINGLE DOCUMENT FOR THE ASSESSMENT OF INTERFERENTIAL RISKS
Article 26, paragraph 3, Legislative Decree 81/08
DESCRIZIONE ATTIVITÀ / DESCRIPTION OF ACTIVITY
Controllo degli ungulati, USAG-ITALY, Darby Military Community (Anno base + 4 anni opzionali, n. 3 operatori)
Ungulate Control, USAG-Italy, Darby Military Community (Base year, nr. 3 workers)
13 Jun 2025
MOLINA.LORENZO.1131037224 Digitally signed by MOLINA.LORENZO.1131037224 Date: 2025.06.26 10:42:28 +02'00' CHELOSSI.CHIARA.1462956963 Digitally signed by CHELOSSI.CHIARA.1462956963
Date: 2025.06.13 18:23:39 +02'00'
CENTRALE COMMITTENZA / COMMITTEE
COMANDO USA SETAF
DARBY MILITARY COMMUNITY
VIA AURELIA
56018 TIRRENIA (PI)
DOCUMENTO UNICO DI VALUTAZIONE DEI RISCHI Art. 26 comma 3, D.Lgs 81/08
Oggetto del contratto Controllo degli ungulati USAG-ITALY, DMC
Aree interessate USAG-ITALY, DMC - PASA Referente contratto/COR ___________________________________ Datore di lavoro richiedente DPW Numero di contratto ___________________________________ Appaltatore ___________________________________
Anagrafica dell'Appaltatore (una scheda per ciascun Appaltatore)
Ragione sociale
Legale rappresentante
Sede legale
Sede operativa
Telefono
Fax
Codice fiscale
Partita iva
Iscrizione alla C.C.I.A.A
Posizione assicurativa INAIL
Posizione INPS
C.C.N.L. applicato
Responsabile del Servizio di Prevenzione e Protezione (RSPP)
Rappresentante dei Lavoratori per la Sicurezza (RLS)
Medico Competente
Responsabile Prevenzione Incendi
Responsabile Pronto Soccorso
Referente della ditta appaltatrice per il coordinamento e la sicurezza
Periodo di lavoro PERIODO: 30/09/2025 – 29/09/2026 (Anno base) ORARIO: dalle 6.00 alle 17.00 dal Lunedi al Venerdi.
DARBY MILITARY COMMUNITY
Datore di lavoro richiedente DPW
RISCHI AMBIENTALI PRESENTI ALL’INTERNO DELL’EDIFICIO OGGETTO DELL’INTERVENTO / POTENTIAL RISKS PRESENT INSIDE THE
BUILDING OBJECT OF THIS WORK CONTRACT
Edf Bldg
Direttorato-sezione/ Directorate-section
N. Addetti –Descrizione Generale / No. Employees - On site description
Attrezzature – Macchinari / Machinery - equipment
Rischi presenti / Risks
DMC
PASA
DPW Affollamento tot:
Popolazione di 1000 persone tra civili e militari – Controllo degli ungulati, USAG-ITALY, DMC - PASA
/Civilian and military popolation of 1005 persons – Ungulate control, USAG-ITALY, DMC - PASA
Macchinari ed attrezzature: camion, camion con gru, trattori, motoseghe, / Machines and equipment: Tucks, trucks with crane, tractors, chainsaws
Rischio di caduta nei canali,fosse di drenaggio.
Utilizzo di utensili e macchinari rumorosi.
Presenza di contenitori di liquidi facilmente combustibili.
Rischio di proiezione di schegge/materiali.
Movimentazione di materiali tramite carrelli elevatori.
Spostamento di veicoli e mezzi tattici.
Movimentazione di materiale esplosivo.
Movimentazione di veicoli su rotaia.
Rischio presenza di pozzetti per connessioni terre / Rischio di caduta di pine e rami.
Presenza di personale armato e cani addestrati per il pattugliamento.
Non fumare in prossimità (15 metri) delle entrate principali di ogni edificio.
Risk of falling into drainage canals and ditches.
Noisy equipments and mowers.
Combustible liquid present.
Risk of flying particles by using machines MHE movement on site.
Tactical vehicle traffic.
Explosive material movement.
Rail vehicle movement Risk of ground connection pits presence Risk of falling of pine cones and tree branches Presence of armed forces and trained dogs for patrolling.
No smoking within 50 feet.
DARBY MILITARY COMMUNITY
Datore di lavoro richiedente DPW
ALTRI RISCHI PRESENTI NELLE AREE / OTHER GENERAL HAZARDS PRESENT IN THE AREAS
1. Traffico veicolare; automezzi privati, muletti, (talvolta questi ultimi sprovvisti di segnalatori acustici e/o ottici), bus navetta, veicoli militari, cisterne rifornimento serbatoi di olio combustibile o GPL esterni agli edifici, veicoli per la raccolta dei rifiuti / Vehicular Traffic: POVs, forklifts, (sometimes with no regular yellow/orange blinking light and backward maneuvering beeper), shuttle bus, military vehicles, refueling tanks for combustible oil or LPG, trash collection dumpers
Rischi: collisione – schiacciamento – interferenza con operazioni di rifornimento/raccolta rifiuti / Risks: collision – crushing – interference with refueling/trash collection operations
2. Presenza di veicoli per emergenze dei Vigili del Fuoco in prossimita’ del Stazione dei Pompieri, edificio 918 e 5013 / Presence of Fire Department emergency response vehicles near Bldgs. 918 and 5013, Fire Departments
Rischi: investimento - interferenza con operazioni di intervento/salvataggio / Risks: crash - interference with response/rescue operations
3. Traffico pedonale / pedestrian traffic. Rischi: investimento / Risks: hitting a pedestrian
4. Segnaletica si sicurezza non sempre conforme alle vigenti norme di sicurezza e non sempre bilingue / Road signs / marking not always IAW traffic code and not always bilingual
Rischi: fraintendimento dei segnali / Risks: misinterpretation of road signs / marking
5. Presenza di personale di lingua non Italiana / Presence of non-Italian speaking personnel
Rischi: fraintendimento nelle comunicazioni verbali / Risks:
verbal communication misinterpretation
6. Possibile interazione con personale della sicurezza militare all’interno dell’area/edificio per esigenze di carattere operativo / Potential interaction with security personnel in the area/facility due to operational contingencies
Rischi: interferenza con operazioni di pubblica sicurezza -fraintendimento nelle comunicazioni verbali / Risks: interference with security forces operations - verbal communication misinterpretation
7. Possibile presenza di derivati dell’amianto in vecchie condutture, rivestimenti, guarnizioni;
(riferimento documento valutazione presenza amianto disponibile presso Environmental Office, edificio 5155) / Potential presence of asbestos containing materials on old pipelines, coverings, gaskets; (refer to specific evaluation document available at Environmental Office, Bldg. 5155)
Rischi: esposizione accidentale all’amianto / Risks: asbestos accidental exposure
8. Presenza deposito materiali tossici (pesticidi) all’edificio 5143. Possibile presenza di veicoli in ingresso o uscita dall’area / Presence of toxic materials, (pesticides), at Bldg.5143. Possible presence of transports accessing or exiting the area
Rischi: esposizione accidentale / Risks: accidental exposure
9. Gli edifici circondati da prato possono ospitare nelle adiacenze nidi di insetti, (vespe ad esempio), o altri animali / Green area surrounding facilities may hide insects or other animals’ nests
Rischi: biologico / Risks: biological
10. Presenza di alberi intorno i parcheggi e/o lungo le vie di passaggio / Trees surrounding parking areas and/or along cross ways
Rischi: esposizione alle pine che cadono dagli alberi / Risks:
exposure to pine cones falling
DARBY MILITARY COMMUNITY
Datore di lavoro richiedente DPW
11. Incrocio a 4 vie (STOP sui quattro lati – non conforme) / 4-Way stop crossroad (not European traffic code compliant)
Rischi: fraintendimento della precedenza – collisione / Risks:
yield misinterpretation - collision
12. Apertura di nuovi cantieri che puo’ comportare / New construction sites activation may imply the following:
a. Modifiche alla viabilita’ dell’area / Traffic flow changes
b. Scavi temporanei / Temporary open diggings
c. Incremento traffico veicoli pesanti / Increased number of heavy vehicles
d. Installazione opere provvisionali / Temporary work provisions on the installation
e. Rumore/vibrazioni / Noise/vibrations
Rischi: collisione – schiacciamento - interferenza con operazioni di cantiere / Risks: collision – crushing - interference with construction site operations Rischi: caduta / Risks: fall
Rischi: collisione – schiacciamento - interferenza con operazioni di cantiere / Risks: collision – crushing - interference with construction site operations Rischi: inciampo - interferenza con operazioni di cantiere / Risks:
trip & fall - interference with construction site operations
Rischi: esposizione / Risks: exposure
13. Armadi chiusi riportanti l’indicazione “Materiale Infiammabile – Flammable materials” / Closed cabinets/storage room with “Materiale Infiammabile – Flammable materials” signs
Rischi: incendi - esposizione accidentale / Risks: fire – accidental exposure
14. Presenza di depositi di materiali pericolosi segnalati con la scritta “HAZARDOUS WASTE” / Presence of dangerous materials with HAZARDOUS WASTE signs
Rischi: esposizione accidentale / Risks: accidental exposure
15. Presenza di cassoni porta rifiuti e relative operazioni periodiche di svuotamento con mezzi pesanti / Presence of trash collectors on related removal operations performed with dumpers
Rischi: collisione – schiacciamento – interferenza con operazioni di rimozione rifiuti / Risks: collision – crushing – interference with trash collection
16. Segnaletica stradale orizzontale non sempre chiaramente leggibile / Marking on the roads signs not always readable
Rischi: collisione / Risks: collision
ATIVITA’ SVOLTA DALL’APPALTATORE E FASI LAVORATIVE / CONTRACTOR WORK ACTIVITIES
CONTROLLO DEGLI UNGULATI, USAG-ITALY, DMC - PASA
UNGULATE CONTROL, USAG-ITALY, DMC - PASA
Periodo: Periodo: anno base / Period: base year Numero di addetti previsti: 3 persone / Personnel required: 3 contract workers
Fasi lavorative previste / Scheduled Work Phases:
a) Arrivo della ditta all’ingresso di un’area di competenza dell’USAG Italy DMC. Il personale della ditta dovra` gia` essere in possesso dell’autorizzazione e dei relativi pass, e si rechera` autonomamente presso le aree ove si deve svolgere il lavoro. Per recarsi presso le aree dovra` essere seguita la strada piu` breve procedendo ad una velocita` non superiore ai 40Km/h e rispettando tutte le regole del codice della strada incluso l’obbligo di indossare le cinture di sicurezza / Arrival of Contractor at one of USAG Italy DMC area entrance, the Contractor personnel shall be
DARBY MILITARY COMMUNITY
Datore di lavoro richiedente DPW already in possession of authorization and relative passes and it can proceed to the areas were the works should be done on its own. In order to reach these areas the Contractor must take the shortest route and travel at a speed not to exceed 40km/h and observe all traffic regulations including compulsory wearing of seat belts.
b) Al fine di evitare le interferenze le attivita’ saranno svolte adottando le seguenti precauzioni / In order to avoid interference work will be accomplished adopting the following precautions:
- La ditta incaricata dovra’ provvedere a delimitare con relativa segnaletica la zona oggetto dei lavori di controllo degli ungulati / The Contractor commissioned to perform the ungulate control will be responsible for delimitation, by specific warning signs, of the work area;
- Il responsabile di area dovra’ evitare l’esecuzione di attivita’ particolari che possano determinare rischi all’interno di ogna zona di lavoro / The person responsible for the area will prevent any particular activity that can put at risk anyone present in each work area;
- Sara’ vietato transitare all’interno dell’area delimitata durante la il controllo degli ungulati / Shall be forbidden to walk in the during the ungulate control
- Considerando i possibili rischi dovuti a caduta di pine e rami, collisione, schiacciamento e proiezione di schegge sara’ opportuno indossare scarponi antinfortunistici con puntale rinforzato , guanti antitaglio, elmetto protettivo e visiera / Considering the possible risks present in the work area associated with falling of pine cones and tree branches, collusion, crushing, and risk of flying particles by using machines it will be necessary to swear capped safety shoes, safety gloves, elmet and protective safety shield.
- All’interno della zona delimitata la ditta potra’ eseguire l’intervento di manutenzione o riparazione previsto in autonomia utilizzando le proprie attrezzature / On the inside of the delimited area the Contractor can perform the maintenance or repairing work as scheduled in autonomy and with the use of its own tools;
- Il responsabile di cantiere della ditta incaricata dovra’ evitare l’esecuzione di attivita’ che possano comportare rischi per le aree di lavoro al di fuori dell’area delimitata di propria competenza / The Contractor responsible for the work site must avoid performing any activity which may be of risk for the work areas outside of the delimited area for which he/she is responsible.
c) Esecuzione degli interventi di manutenzione straordinaria o riparazioni degli equipaggiamenti utilizzando: scale, attrezzi manuali, Trapani/avvitatori, seghe a norma di sicurezza / Unscheduled maintenance or repair works of the equipment will be carried out using: ladders, hand tools, drills/powered screwdrivers, chainsaws meeting the safety rules
d) Terminato l’intervento di manutenzione o riaprazione e relativa pulizia il responsabile di cantiere comunichera’ la fine dei lavori al responsabile di area che provvedera’ a rimuovere le segnaletica usata per la delimitazione della zona / Once work has been completed the Contractor responsible for the work site will inform the person responsible for the area of work completion so that he may proceed to remove the signs to delimit the work area.
e) Terminati tutti gli interventi di manutenzione o riparazione e pulizia la ditta’ dovra’ provvedere a mettere in sicurezza le proprie attrezzature, a rimuovere tutti i residui delle lavorazioni eseguite, provvedendo eventualmente a smaltirli direttamente o a posizionarli all’interno degli appositi contenitori / Once all maintenance or repairing works and cleaning activities have ceased the Contractor is responsible for assuring that all his equipment is safely stowed out of harm way, he must remove all residue/rubbish created by his work, disposing of it himself or empting into the appropriate refuse containers.
ATTREZZATURE UTILIZZATE DALL’APPALTATORE / CONTRACTOR SPECIAL TOOLS
Camion, camion con gru, trattori, motoseghe / Tucks, trucks with crane, tractors, chainsaws L’utilizzo delle macchine ed attrezzature da parte dell’appaltatore non comporta rischi al di fuori dell’area delimitata dalla relativa segnaletica. Non sono previste ulteriori misure di prevenzione e protezione oltre alla perimetrazione delle aree / Use of machinery and equipment by the Contractor does not pose any risks outside of the delimited area with relative signs. No other preventive or protective measures apart from cordoning off the work area are prospected.
DARBY MILITARY COMMUNITY
Datore di lavoro richiedente DPW
MACCHINE OPERATRICI UTILIZZATI DALL’APPALTATORE/ MATERIAL HANDLING EQUIPMENT
TIPO DI MACCHINA / TYPE OF EQUIPMENT NOTE / REMARKS
Camion, camion con gru, trattori, motoseghe, / Tucks, trucks with crane, tractors, chainsaws
Gli operatori del Camion con altri equipaggiamenti utili a tale lavoro sono stati formati ed addestrati per la guida del mezzo ed è in possesso dei requisiti di idoneità psicofisica specifici per lo svolgimento di questo Contratto / Only trained, licenced and medically cleared employees will be allowed to operate the Truck with crane, welding machine, grinder and others equipments necessary to perform this contract.
SOSTANZE E PREPARATI UTILIZZI DALL’APPALTATORE / HAZARDOUS CHEMICALS
E’ previsto l’utilizzo di piccoli quantitativi di oli lubrificanti, prodotti per lo sbloccaggio in bomboletta nel caso di piccole riparazioni/regolazioni da eseguire sul posto del proprio macchinario e l’uso di contenitori con carburanti per il rifornimento / The use of small quantities of lubricant oil , “break-free” spray cans is expected in case of small repairs/adjustment of own machineries to be done on place and also the utilization of containers with fuel to fill up the equipments.
L’utilizzo delle sostanze chimiche da parte dell’appaltatore non comporta rischi al di fuori dell’area perimetrata / The use of chemical substances by the Contractor should not pose any risk outside of the cordoned off area.
Non sono previste ulteriori misure di prevenzione e protezione oltre alla perimetrazione delle aree / No other preventive or protective measures apart from cordoning off the work area are prospected.
RISCHI DI INTERFERENZA DELL’ATTIVITÀ OGGETTO DELL’APPALTO, SVOLTA ALL’INTERNO DELLA BASE, DERIVANTI DA UTENSILI/ATTREZZATURE/SOSTANZE/MEZZI UTILIZZATI / SUMMARY OF RISKS DUE TO USE OF TOOLS / EQUIPMENT / CHEMICALS /
VEHICLES
N. DESCRIZIONE / HAZARD DESCRIPTION RISCHIO / RISK MISURE DI PREVENZIONE-PROTEZIONE /
PREVENTIVE-PROTECTIVE MEASURES
MOVIMENTAZIONE MANUALE DEI CARICHI /
MANUAL HANDLING OF HEAVY LOADS
Assenti / Not applicable La movimentazione manuale dei carichi non comporta interferenza
Non necessarie / Not applicablabbattimento, AGENTI FISICI: Rischi utilizzo utensili/attrezzature RUMOROSI PHYSICAL AGENTS: use of tools / equipment producing high noise
Potenzialmente presenti di area / Potentially present in the area Possibili sorgenti di rumore dell’area (test di motori, particolare attrezzature) potrebbero determinare rischi di esposizione / Potential sources of noise (Engine testing, particular equipment) could pose a risk of exposure to noise.
Per eliminare tali rischi il responsabile di area evitera’ di eseguire lavorazioni rumorose durante gli interventi di controllo degli ungulati o quando appaltatori presenti in area/ To eliminate such risks the person responsible for the area will refrain from performing any work with high noise levels while the ungulate control is being performed or when contractors are present in the area.
Presenti appaltante / Present (contractor) La sorgenti di rumore dei mezzi per le il controllo degli ungulati e altri equipaggiamenti determinano rischi di esposizione / Sources of noise (tracks for ungulate control works and others equipment) pose a risk of exposure to noise.
Per eliminare tali rischi di interferenza dovra’ essere delimitata l’area dove viene effettuato il controllo degli ungulati in terra per mezzo di apposita segnaletica/ To avoid such risks of interference the area object of ungulate control will be delimited by proper warning signs.
AGENTI FISICI: Rischi utilizzo utensili/attrezzature VIBRANTI PHYSICAL AGENTS: use of vibrating tools / equipment
Gli interventi di controllo degli ungulati non prevedono l’utilizzo di attrezzature che comportano rischi di esposizione per i non addetti ai lavori / The ungulate control does not involve use of equipment which will but at risk those not directly involved with the work. Assenti / Not applicable
Non necessarie / Not applicable
AGENTI FISICI: Rischio di utilizzo attrezzature che emettono CAMPI ELETTROMAGNETICI
PERICOLOSI
PHYSICAL AGENTS: use of tools / equipment emitting dangerous electromagnetic fields
Assenti / Not applicable Non necessarie / Not applicable
DARBY MILITARY COMMUNITY
Datore di lavoro richiedente DPW
N. DESCRIZIONE / HAZARD DESCRIPTION RISCHIO / RISK MISURE DI PREVENZIONE-PROTEZIONE /
PREVENTIVE-PROTECTIVE MEASURES
AGENTI FISICI: Rischio di utilizzo attrezzature che emettono RADIAZIONI OTTICHE
PERICOLOSE
PHYSICAL AGENTS: use of tools / equipment emitting dangerous radiation / optic fields
Assenti / Not applicable Non necessarie / Not applicable
SOSTANZE PERICOLOSE: Rischi utilizzo sostanze/preparati chimici pericolosi CHEMICALS: use of hazardous chemicals
Assenti / Not applicable Non necessarie / Not applicable
SOSTANZE PERICOLOSE: Rischi utilizzo sostanze/preparati chimici cancerogeni/mutageni CHEMICALS: use of cancerous / mutagen chemicals
Assenti / Not applicable Non necessarie / Not applicable
AMIANTO: Rischi utilizzo sostanze contenenti amianto ASBESTOS: use of asbestos containing material
Assenti / Not applicable Non necessarie / Not applicable
AGENTI BIOLOGICI: Rischi di utilizzo agenti biologici pericolosi BIOLOGICAL AGENTS: use of hazardous biological agents
Assenti / Not applicable Non necessarie / Not applicable
ATMOSFERE ESPLOSIVE: Rischi di sviluppo di atmosfere esplosive durante svolgimento attività EXPLOSIVE ATMOSPHERES: Development of explosive atmospheres during operations
Assenti / Not applicable Non necessarie / Not applicable
ATMOSFERE ESPLOSIVE: Rischio utilizzo di utensili, attrezzature, mezzi che possono innescare atmosfere esplosive EXPLOSIVE ATMOSPHERES: use of tools, equipment, vehicles that could ignite explosive atmospheres
Presente / Present Nelle condizioni di lavoro previste non si rendono necessarie misure di sicurezza particolari / No particular safety measures are expected for this work
Rischi utilizzo sostanze infiammabili/facilmente combustibili Use of flammables / combustibles
Assenti / Not applicable Per eliminare tali rischi di interferenza dovra’ essere delimitata l’area dove viene effettuato il controllo degli ungulati per mezzo di apposita segnaletica/ To avoid such risks of interference the area object of ungulate control will be delimited by proper warning signs.
13 Rischi caduta materiale dall’alto Risk of falling objects
Presente / Present Le attivita’ lavorative svolte nell’area e dall’appaltante possono determinare il rischio di caduta di oggetti dall’alto / The work performed in the area and by the Contractor can pose a risk of falling objects from above.
Per eliminare tali rischi di interferenza dovra’ essere delimitata l’area dove viene effettuato il controllo degli ungulati per mezzo di apposita segnaletica/ To avoid such risks of interference the area object of ungulate control will be delimited by proper warning signs.
14 Rischi utilizzo corrente elettrica Electrical equipment
Assenti / Not applicable Non necessarie / Not applicable
Rischio utilizzo utensili/attrezzature che comportano la proiezione di schegge Use of tools / equipment that expose to flying particles
Presente / Present Le attivita’ lavorative svolte nell’area e dall’appaltante possono determinare il rischio di proiezioni di oggetti/schegge / The work performed in the area and by the contractor can pose risk of exposure to flying particles
Per eliminare tali rischi di interferenza dovra’ essere delimitata l’area dove viene effettuato il controllo degli ungulati per mezzo di apposita segnaletica/ To avoid such risks of interference the area object of ungulate control will be delimited by proper warning signs.
Rischio utilizzo/presenza di utensili/attrezzature che hanno parti mobili pericolose (urti, schiacciamenti, cesoiamenti, ecc.)
Use of tools/equipment with exposed moving parts
Presente / Present Le attivita’ lavorative svolte nell’area e dall’appaltante possono determinare il rischio di urti, schiacciamenti, cesoiamenti / The work performed in the area and by the Contractor can pose a risk of bumping, squashing, shearing.
Per eliminare tali rischi di interferenza dovra’ essere delimitata l’area dove viene effettuato il controllo degli ungulati per mezzo di apposita segnaletica/ To avoid such risks of interference the area object of ungulate control will be delimited by proper warning signs.
DARBY MILITARY COMMUNITY
Datore di lavoro richiedente DPW
N. DESCRIZIONE / HAZARD DESCRIPTION RISCHIO / RISK MISURE DI PREVENZIONE-PROTEZIONE /
PREVENTIVE-PROTECTIVE MEASURES
17 Rischio spostamento con automezzi Moving traffic
Presente / Present
Gli spostamenti all’interno della base devono essere preventivamente autorizzati dalla committente. Devono essere seguite scrupolosamente le regole di circolazione interna. In assenza di indicazioni particolari, procedere a passo d’uomo (5Km/ora). Vietato parcheggiare davanti a mezzi di salvataggio, soccorso, antincendio / All internal traffic needs to be previously authorized by the Commissioning Employer. All rules governing traffic will be observed. In the absense of signs, procede at walking pace (5 Km/h). Parking in front of emergency vehicles is prohibited
MISURE DI PREVENZIONE E PROTEZIONE ADOTTATE
Per rischi interferenti, in generale, si intendono:
rischi derivanti da sovrapposizioni di più attività svolte ad opera di appaltatori diversi;
rischi immessi nel luogo di lavoro del committente dalle lavorazioni dell’appaltatore;
rischi esistenti nel luogo di lavoro del committente, ove è previsto che debba operare l’appaltatore, ulteriori rispetto a quelli specifici dell’attività propria dell’appaltatore;
rischi derivanti da modalità di esecuzione particolari (che comportano rischi ulteriori rispetto a quelli specifici dell’attività appaltata), richieste esplicitamente dal committente.
Nelle misure di prevenzione e protezione adottate non sono riportate le misure per eliminare i rischi derivanti dall’attività delle singole imprese appaltatrici o dei singoli lavoratori autonomi, ma solo i rischi derivanti dalle interferenze presenti nell’effettuazione della prestazione.
L’impresa aggiudicataria, all’atto della comunicazione del rischi specifici connessi alla propria attività, può presentare proposte di integrazione, ove ritenga di poter meglio garantire la sicurezza del lavoro, sulla base della propria esperienza.
MISURE DI PREVENZIONE-PROTEZIONE AGGIUNTIVE / OTHER PREVENTIVE-PROTECTIVE MEASURES
1. Prima di accedere alle aree interessate dall’intervento, concordare con il COR dell’appalto le modalità di effettuazione delle attività e formalizzare le misure di prevenzione e protezione concordate / Before entering the premises subject to the contract work, coordination with Contract COR must be done in order to establish the procedures of performance activities and the agreed on preventive and protective measures
2. Esporre la tessera di riconoscimento corredata di fotografia contenente le generalità del lavoratore e l'indicazione del datore di lavoro per tutto il tempo di permanenza nell’azienda (ai sensi dell’art.26 c.8 del D.Lgs.81/08) / Wear a badge equipped with photograph, name and address of contractor during the entire permanence inside the premises (IAW art. 26 para 8 of Law 81/08)
3. Localizzare i percorsi di emergenza e le vie di uscita. / Locate emergency exits.
4. In caso di evacuazione attenersi alle procedure vigenti. / In case of evacuation of bldg follow emergency evacuation plan.
DARBY MILITARY COMMUNITY
Datore di lavoro richiedente DPW
5. Indossare i dispositivi di Protezione Individuale ove siano prescritti. / Wear personal Protective Equipment as prescribed.
6. Non ingombrare le vie di fuga con strumenti e attrezzature. / Do not block emergency exits with instruments and equipment.
7. Non operare su macchine, impianti e attrezzature se non autorizzati. / Do not operate machinery, equipment and tools if not authorized.
8. Evitare l’uso di cuffie o auricolari per l’ascolto della musica durante l’attività perché potrebbero impedire la corretta percezione dei segnali acustici di allarme in caso di emergenza (allarme incendio, allarme evacuazione, cicalini dei mezzi e delle macchine, ecc.). / Refrain from using headphones or earphones while working because they could prevent hearing emergency alarms (i.e. fire alarm, evacuation alarm, equipment and machinery buzzers, etc.).
9. Le attivita’ oggetto del contratto dovranno essere svolte perimetrando e isolando preventivamente la zona oggetto dell’intervento di manutenzione. / The activities object of the contract will be performed after having previously cordoned off the area object of the maintenance intervention.
10. E’ comunque vietato transitare all’interno dell’officine durante attivita’ di spostamento di mezzi o durante attivita’ di movimentazione eseguite con il carroponte. / In all cases it is forbidden to walk about the workshops when equipment/vehicles are being moved or the overhead crane is being operated.
11. Il responsabile di area dovra’ evitare l’esecuzione di attivita’ particolari che possano determinare rischi all’interno della zona di lavoro perimetrata. / The person responsible for the area will prevent any particular activity that can put at risk anyone present in the cordoned off work area.
12. Il responsabile di cantiere della ditta incaricata dovra’ evitare l’esecuzione di attivita’ che possano comportare rischi per le aree di lavoro al di fuori dell’area perimetrata di propria competenza. / The Contractor responsible for the work site must avoid performing any activity which may be of risk for the work areas outside of the cordoned off area for which he/she is responsible.
COSTI DELLA SICUREZZA
Sono quantificabili come costi della sicurezza tutte quelle misure preventive e protettive necessarie per l’eliminazione o la riduzione dei rischi interferenti individuate, così come indicativamente riportato di seguito:
gli apprestamenti previsti nel DUVRI (come ponteggi, trabattelli, etc.);
le misure preventive e protettive e dei dispositivi di protezione individuale eventualmente previsti nel DUVRI per lavorazioni interferenti;
gli eventuali impianti di terra e di protezione contro le scariche atmosferiche, degli impianti antincendio, degli impianti di evacuazione fumi previsti nel DUVRI;
i mezzi e servizi di protezione collettiva previsti nel DUVRI (come segnaletica di sicurezza, avvisatori acustici, etc.);
le procedure contenute nel DUVRI e previste per specifici motivi di sicurezza;
gli eventuali interventi finalizzati alla sicurezza e richiesti per lo sfasamento spaziale o temporale delle lavorazioni interferenti previsti nel DUVRI;
DARBY MILITARY COMMUNITY
Datore di lavoro richiedente DPW le misure di coordinamento previste nel DUVRI relative all'uso comune di apprestamenti, attrezzature, infrastrutture, mezzi e servizi di protezione collettiva.
La stima, analitica per voci singole, a corpo o a misura (quindi NON A PERCENTUALE), viene riferita ad elenchi prezzi standard o specializzati, oppure basata su prezziari o listini ufficiali vigenti nell'area interessata, o sull'elenco prezzi delle misure di sicurezza del committente; nel caso in cui un elenco prezzi non sia applicabile o non disponibile, si farà riferimento ad analisi costi complete e desunte da indagini di mercato.
GESTIONE DELLE EMERGENZE / EMERGENCY MANAGEMENT
In caso di emergenza e/o infortunio dovranno essere adottate le procedure specificate nel “Piano di pronto intervento per l’evacuazione delle persone infortunate per la comunita’ USAG-ITALY, DMC di Livorno” allegato al contratto di appalto. / In case of emergency and/or injury, follow the procedures contained in the Emergency plan for the evacuation of injured people for USAG-ITALY, DMC areas.
TIPO EMERGENZA
EMERGENCY TYPE
DESCRIZIONE
DESCRIPTION
RIFERIMENTI
REFERENCES
Sicurezza Security
La gestione della sicurezza è assicurata dal servizio interno di polizia militare.
Security services are the responsibility of the internal military police.
Servizi Interni/ Internal Services
MILITARY POLICE DSN 645-8202
Commercial 050-965-8202
CARABINIERI DSN 645-8823/8826
Commercial 050-965-8823/8826 Servizi esterni / External Services
CARABINIERI tel. 112 Incendio-
Esplosione Fire-Explosion
La gestione delle emergenze legate agli incendi/esplosioni è affidato agli addetti alla lotta antincendio designati dall’appaltatore ai quali saranno affiancati gli addetti alla lotta antincendio presenti nei repati e al dipartimento interno per la lotta antincendio.
Fire/explosion emergency management is the responsibility of the contractor’s qualified fire wardens, supported by the building fire wardens present in the area
Servizi Interni/ Internal Services Addetti di reparto / BFW:
FIRE DEPARTEMENT DSN 645-8296
Commercial 050-965-8296
Servizi esterni / External Services Vigili del Fuoco tel. 115
Infortunio – malore Accident – Illness
La gestione delle emergenze legate ad infortunio/malore è affidato agli addetti designati dall’appaltatore ai quali potranno essere affiancati gli addetti presenti nei repati.
Medical emergency management is the responsibility of the contractor’s first aid qualified employees, supported by the area firs aid qualified employees
Servizi Interni/ Internal Services Addetti al primo soccorso / First-Aiders Servizi esterni / External Services
Pronto Soccorto (esterno) First Aid (external)
Tel. Fisso/From fixed telephone: 99-118 Tel Cellulare /From Cell Phone:
800011800
DARBY MILITARY COMMUNITY
VIA AURELIA
56018 TIRRENIA (PI)
DOCUMENTO UNICO DI VALUTAZIONE DEI RISCHI Art. 26 comma 3, D.Lgs 81/08
Oggetto del contratto Controllo degli ungulati USAG-ITALY, DMC
Aree interessate USAG-ITALY, DMC - PASA Referente contratto/COR ___________________________________ Datore di lavoro richiedente DPW Numero di contratto ___________________________________ Appaltatore ___________________________________
Others general dispositions to eliminate interference / Disposizioni generali aggiuntive per l’eliminazione delle interferenze.
Utilizzare solo le area autorizzate Non accedere in altri locali o edifici
Non presentarsi sul luogo di lavoro sotto l’influenza di alcool, medicinali o sostanze psicotrope
Non manomettere e/o escludere protezioni, dispositivi di sicurezza o sistemi di segnalazione e controllo.
Non oltrepassare o disattivare le protezioni.
Non usare fiamme libere in azienda se non ESPRESSAMENTE AUTORIZZATI (tramite form MD 00 0277 “Richiesta permesso di lavoro”)
È vietato fumare in locali chiusi e all’esterno a 15 metri dalle porte.
È vietato introdurre bevande alcoliche all’interno dell’azienda
È vietato arrampicarsi su scaffali, ripiani, macchinari e comunque su qualsiasi altra postazione sopraelevata; obbligatorio l’impiego di scale e/o trabattelli conformi alla normativa vigente, di proprietà.
È vietato toccare gli apparati elettrici alle persone non autorizzate e qualificate.
È obbligatorio:
farsi riconoscere all’ingresso presso il gate;
ricevere autorizzazione per l’ingresso di auto – furgoni – mezzi ed esporre il pass sul mezzo;
camminare percorrendo solo le aree pedonali segnalate;
rispettare la segnaletica orizzontale e verticale (percorsi pedonali e carrabili, aree di stoccaggio merci, vie di evacuazione, cartelli di divieto, d’obbligo, di segnalazione e di avvertimento, altro);
astenersi dall’utilizzare, manutenere, verificare, oliare, registrare, ingrassare, macchine e/o impianti di Ns. proprietà;
utilizzare esclusivamente Vs. macchine o attrezzature, previa Ns. autorizzazione scritta, conformi ai requisiti antinfortunistici;
rispettare le procedure di sicurezza aziendali;
mantenere ordinate e pulite le zone di passaggio, deposito e lavoro riprestinando le condizioni presenti prima dell’esecuzione degli interventi;
provvedere in proprio al trasporto e smaltimento dei rifiuti decadenti dallo svolgimento del/i Vs. incarico/i, salvo Ns.
diversa disposizione da comunicarvi per iscritto;
DARBY MILITARY COMMUNITY
Datore di lavoro richiedente DPW segnalare a Ns. addetto qualsiasi situazione ritenuta a rischio, oltre che di altre condizioni di pericolo di cui si è a conoscenza;
prendersi cura della propria sicurezza e della propria salute e di quella delle altre persone presenti, conformemente alla propria formazione ed alle istruzioni e ai mezzi forniti dal datore di lavoro.;
l’utilizzo degli idonei DPI forniti.
Rispettare tutte le procedure di sicurezza indicate dall’Ufficio Sicurezza della Committente
RISCHI INTRODOTTI DALL’APPALTATORE (DA COMPILARE UNA VOLTA SELEZIONATO L’APALTATORE):
N. DESCRIZIONE / HAZARD DESCRIPTION MISURE DI PREVENZIONE-PROTEZIONE ADOTTATE / PREVENTIVE-PROTECTIVE MEASURES
DARBY MILITARY COMMUNITY
Datore di lavoro richiedente DPW
CONSIDERAZIONI CONCLUSIVE / CONCLUSIONS:
Il Committente dichiara di aver fornito all’Appaltatore / The Commissioning Employer provided the Contractor with:
le informazioni tecniche relative allo stato dei luoghi sede dell’attività e dettagliate informazioni sui rischi specifici esistenti nell’ambiente dove dovrà operare e sulle misure di sicurezza e emergenza adottate; / all the technical info regarding the status of the work places and detailed information on the specific risks in the locations where the Contractor is going to work and the safety and emergency measures adopted;
le informazioni per evitare inutili rischi e per lavorare in sicurezza in relazione alla contemporanea presenza sul luogo di lavoro o nelle immediate vicinanze di altre imprese appaltatrici e sui rischi specifici relativi. / all the information to avoid unnecessary risks and to work in safety, in relation to the contemporary presence on the work-place, or in the immediate vicinities, of other contractors and relative specific risks.
Con la firma riportata in calce la ditta appaltatrice attesta / With the following signature the contractor states:
di aver preso atto delle dettagliate informazioni ricevute sui rischi specifici esistenti nell’ambiente in cui è chiamata ad operare e sulle misure di prevenzione e di emergenza adottate in relazione all’attività del committente; / understood the detailed information received regarding the specific risks in the workplace where is going to perform the activity and regarding the prevention measures and corrective actions adopted in relation to the Contractor’s activity.
dell’avvenuta cooperazione in merito all’attuazione delle misure di prevenzione e protezione dai rischi sul lavoro e incident i sull’attività lavorativa oggetto dell’appalto; / will cooperate for the implementation of the prevention and protection measusres regarding the on the job risks and injuries on the work activity subject of the contract.
dell’avvenuto scambio reciproco di informazioni, attraverso i documenti di cui si allega copia, al fine di eliminare i rischi dovuti alle eventuali interferenze tra i lavori svolti dalle parti; / the mutual exchange of information, through the attached documents, to avoid the risks/hazards due to potential interferences between works performed by the involved contractors and committing part.
che rimane a carico della ditta appaltatrice la valutazione e l’adozione di idonee misure di prevenzione e protezione inerent i i rischi della propria attività. / the contractor has the responsability for the evaluation and implemenatation of the required prevention and protection measusres for the own activity.
In corso d’opera, se dovessero venirsi a modificare le condizioni sopra esposte, sarà cura del committente promuovere una nuova iniziativa di coordinamento e cooperazione al fine dell’eliminazione dei rischi che tale nuova situazione potrebbe comportare. / During the contract activity, in case the conditions above axplained change, the Contractor has the responsability to implement action for the coordination and cooperation in order to eliminate the risks rised from the new condition.
Data / Date: ___________
FIRME / SIGNATURES:
Per la Commitenza (POC) / For the Commissioning Employer
Per l’Appaltatore / For the Contractor