Attachment_4_Submittals.pdf

PDF 71 KB Posted

Attached to
CO-ROCKY MTN ARSNL NWR-TRAIL PAVING PH 2
Solicitation number
140F0122R0081
Issued by

About this file

This document contains a projected submittal list and specifications for a federal construction contract opportunity with the Department of the Interior Fish and Wildlife Service. The contract is for the Lake Mary Trail Paving Phase 2 project located at the Rocky Mountain Arsenal National Wildlife Refuge. It involves paved concrete trail construction. The solicitation is set aside solely for small businesses and proposals are due no later than August 4th, 2022. The submittal list outlines requirements for items like schedules of values, construction plans, samples, test results, waste management documentation, and project closeout materials. It provides a template to indicate approval status for these submittals.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SHEET 1 OF 1

PROJECT NAME: LAKE MARY TRAIL PAVING - PHASE 2 ENGR. PROJECT NO.: 22-028

LOCATION: ROCKY MOUNTAIN ARSENAL NWR CONTRACT NO.:

CONTRACTOR:

Spec.

Section Number

Spec.

Paragraph No. Comments

011000 1.6.B.4 012900 1.2.A.1 013100 1.3 013200 1.4 013233 1.2 013300 1.3 014000 1.4 015000 1.3 017419 1.3 017419 1.4 017700 1.3 033000 1.2.B 033000 2.2 033000 2.7

321500.1 2.1 Gravel Surfacing

Waste records Closeout documents Concrete mix Steel Reinforcement Joint Filler Materials

Digital photos Submittal schedule Test agency information Erosion control plan Waste management plan

PROJECTED SUBMITTAL LIST

Description of item and submittal type (i.e. shop drawings, manufacture cut sheets, tests required, certifications, samples, operating and maintenance manuals, etc.)

Schedule of Values Subcontract list and information Construction schedule

Construction Access Plan

A - Approved as Submitted.

B - Approved, Except as Noted. No Resubmission Required.

C - Approved, Except as Noted. Resubmission Required.

D - No Action Taken. See Comments. Resubmission Required.

E - disapproved. See Comments. Resubmission Required.