Attachment 4 Specifications.pdf
PDF 1 MB Posted
- Attached to
- Amendment 0001 Puerto Rico-191 Water System Reconstruction Federal contract opportunity
- Solicitation number
- 12441923R0044
- Issued by
- Department of Agriculture Forest Service
About this file
This document provides specifications for a Puerto Rico-191 Water System Reconstruction project. The project includes cast-in-place concrete work such as gutters, a concrete storage tank, and other miscellaneous concrete items. It specifies formwork, reinforcement, concrete materials, mixture designs, placement procedures, and finishes. It also requires sediment, erosion and pollution control measures, waste material disposal, removal and disposal of existing structures, and other site works. Submittals such as concrete mix designs, test reports, and as-built drawings are required. Inspections and testing of concrete properties are specified.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Attachment 6 RFP Questions and Responses.pdf | ||
| SF 30 RFP 12441923R0044 Amendment 0001.pdf | ||
| Attachment 7 Site Visit Attendees 14-Aug-2023.pdf | ||
| Attachment 1 Schedule of Items.xlsx | XLSX spreadsheet | |
| Attachment 3 Drawings.pdf | ||
| SF 1442 RFP 12441923R0044.pdf | ||
| Attachment 5 Prior Experience Questionnaire.doc | DOC document | |
| Attachment 2 Statement of Work.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PR-191 WATERLINE
SPECIFICATIONS
A. The following specifications are considered incidental, and no additional compensation will be made.
Section 010250 - Construction Staking Section 011250 - Measurement And Payment Section 011500 - Archeological Protection Section 011700 - Accident Prevention Section 011900 - Mobilization Section 013300 - Submittal Procedures Section 014100 - Quality Control Section 015100 - Temporary Traffic Control Section 017320 - Selective Demolition Section 023701 – Sediment, Pollution, And Erosion Control Measures Section 024100 - Waste Material Disposal Section 024102 - Removal And Disposal Of Structures And Obstructions Section 033000 - Cast-In-Place Concrete Section 033020 - Concrete From Packaged Dry Mix For Minor Structures Section 033530 - Cast-In-Place Concrete Gutter Section 048600 - Stone Veneer Section 221100 - Water Distribution Systems Section 221102 - Curb Valves And Boxes Section 221103 – Plumbing Appurtenances Section 221105 - Water Hydrants Section 221219 - Aboveground Concrete Rectangular Potable-Water Storage Tanks Section 260500 - Common Work Results For Electrical Section 311000 - Clearing And Grubbing Section 312000 - Earthwork Section 321200 - Hot-Mix Asphalt Paving Section 321204 - Crushed Aggregate Base Or Surface Course Section 322705 - Pavement Sawing Section 323113 - Chain-Link Fences And Gates Section 330523 - Utility Horizontal Directional Drilling
CONSTRUCTION STAKING 010250-1
USDA FOREST SERVICE, R8
PR-191 WATER SYSTEM
SECTION 010250 - CONSTRUCTION STAKING
PART 1 - GENERAL
1.1 SUMMARY
A. This work shall consist of the construction staking of waterline in accordance with the Drawings and Specifications. The work includes the furnishing of all labor, equipment, instruments, materials, transportation and other incidentals necessary to complete the construction staking in accordance with these specifications and acceptable engineering practice. The construction staking is not a typical construction stakeout where X,Y, and Z coordinates are given. The stakeout is staking the location of the waterline as roughly indicated on the Drawings and then the CO agreeing to the waterline location. Specific waterline grades are generally not critical other than a need to go consistently downhill or uphill as depicted on the Drawings. Upon completion of the waterline installation the contractor shall survey in the location of waterline and appurtenances.
1.2 MEASUREMENT AND PAYMENT
A. Measurement shall be lump sum for staking the project through all phases of construction.
B. Measurement shall be lump sum for surveying in the entire waterline, above and below ground, and waterline appurtenances.
PART 2 - PRODUCTS
2.1 STAKES
A. Identification stakes shall be of sufficient length and width to provide a solid set in the ground and to provide space for marking above ground when applicable. Colors used on stakes or for flagging shall be as follows:
1. Waterlines, utilities, and culverts -Blue
PART 3 - EXECUTION
3.1 GENERAL
A. The design was accomplished using the best available information. This information included some survey data but also included GPS, digitizing in old plans/profiles, wheel logs, LiDAR, and use of Google Earth. With the uncertainty of the information and the inability to accurately tie the different sources of data together the locations and elevations are general in nature and exact locations shall be agreed upon in the field with the Contracting Officer (CO). If discrepancies are found from what is indicated on the Drawings notify the CO immediately and come to agreement on the best way to proceed.
CONSTRUCTION STAKING 010250-2
The CO will not provide stakeout points for the project. The contractor shall stake out waterlines based on the information provided in the Drawings.
3.2 ESTABLISHING AND REFERENCING IMPROVEMENT LOCATIONS
A. Waterline, Sewerline, & other Utilities
1. Waterline, Sewerline, & other Utilities shall be staked at the locations shown on the drawings with the specified minimum burial depth. Waterline elevations shall be accurately staked to provide for drainage as indicated on the drawings. Grade stakes shall be established as necessary to provide the control for the construction work.
3.3 DISCREPANCIES
A. The contractor shall compare the staked horizontal\vertical alignment with the Drawings.
3.4 MARKING STAKES
A. All stakes shall be legibly marked, in the format agreed upon with the Contracting Officer, with a stake pencil that leaves an imprinted or with waterproof ink. Marking shall conform to the nomenclature below;
RP Reference point
BM Benchmark
TBM Temporary benchmark
L Centerline
D Ditch
W Width
3.5 AS-BUILTS
A. Upon completion of the waterline the entire waterline shall be surveyed including above ground and below ground lines, and waterline appurtnenances. Survey shall be in accordance with the following:
1. Coordinate System: NAD83 Puerto Rico and Virgin Islands, US Survey Foot
2. Datum: NA83, 2011
3. Survey data shall include northing, easting, and elevations.
4. For final acceptance, all as-built data shall be on AutoCAD Civil 3D master drawing reflected on State plane coordinate system.
END OF SECTION 010250
SEPTEMBER 2022
MEASUREMENT AND PAYMENT 011250-1
USDA FOREST SERVICE, R8
PR-191 WATER SYSTEM
SECTION 011250 - MEASUREMENT AND PAYMENT
PART 1 - GENERAL
1.1 SUMMARY
A. Measurement and payment for contract work will be made only for and under those pay items included in the Schedule of Items. All other work, labor, materials, equipment, and incidentals necessary to successfully complete the project will be considered as included in the payment for items shown. This section defines the method of measurements and basis of payment for work items listed in the Schedule of Items.
B. When more than one class, size, type, thickness, etc. is specified in the Schedule of Items for any pay item, suffixes will be added to the item number to differentiate between the pay items.
1.2 DETERMINATION OF QUANTITIES
A. The following measurements and calculations shall be used to determine contract quantities for payment.
1. For individual construction items, longitudinal and lateral measurements for area computations shall be made horizontally or corrected to horizontal measurement unless otherwise specified. Measurements for geotextiles, netting and erosion control blankets shall be along slope lines.
2. For excavation or embankment volumes, the average end area method shall be used to compute volumes. However, if in the judgment of the Contracting Officer (CO), the average end area method is impractical, measurement shall be made by volume in hauling vehicles or by other three-dimensional methods.
3. For Structures, they shall be measured according to neat lines shown on the drawings or as altered by the CO, in writing, to fit field conditions.
4. For items that are measured by the linear foot, such as pipe culverts, fencing, guardrail, piping, utilities, and underdrains, measurements shall be made parallel to the base or foundation upon which the structures are placed.
5. For aggregates weighed for payment, the tonnage shall not be adjusted for moisture content, unless otherwise provided for.
6. For standard manufactured items (such as fence, wire, plates, rolled shapes, pipe conduits) identified by gauge, weight, section dimensions, and so forth, such identifications shall be considered the nominal weights or dimensions. Unless controlled by tolerances in cited specifications, manufacturer's tolerances shall be accepted.
7. For bituminous material, volumes will be measured at 60F or will be corrected to the volume at 60F by using ASTM D1250 for asphalts. Emulsified asphalt will be measured at 60F, or measured by converting the gallonage at another temperature to gallonage at 60F by means of the following formula:
MEASUREMENT AND PAYMENT 011250-2
Gallons at 60F = Gallons at AF
1+0.00025 (AF - 60F)
* AF is the temperature of the material at the time the gallonage is measured.
a. For vehicular shipments, net certified scale weights or weights based on certified volumes will be used as a basis of measurement. Measurements will be adjusted when bituminous material has been lost from the vehicle or the distributor, has been wasted, or has otherwise not been incorporated into this work. Determining true weights of hauling vehicles shall be made by weighing the empty vehicles at least once a day at the times the CO directs.
Each vehicle shall bear a plainly legible identification mark.
b. When bituminous materials are shipped, net certified weights, or volume corrected for loss of foaming, can be used for computing quantities.
1.3 UNITS OF MEASUREMENT
A. Payment shall be by units defined and determined according to U.S. Standard measure and by the following:
1. Cubic Yard (CY): A measurement computed by one of the following methods:
a. Excavation, Embankment, or Borrow. The measurement computed by the average end area method from measurements made longitudinally along a centerline or reference line.
b. Material in the Delivery Vehicle. The measurement computed using measurements of material in the hauling vehicles at the point of delivery.
Vehicles shall be loaded to at least their water level capacity. Leveling of the loads may be required when vehicles arrive at the delivery point.
2. Each (EA): One complete unit, which may consist of one or more parts.
3. Linear Foot (LF): Measurement of work along its length from point-to-point;
parallel to the base or foundation. Do not measure overlaps.
4. Lump Sum (LS): One complete unit.
5. Square Yard (SY): Measured on a plane parallel to the surface being measured.
6. Ton: Measured as a short ton consisting of 2,000 pounds.
1.4 METHOD OF MEASUREMENT
A. One of the following methods of measurement for determining final payment is designated on the Schedule of Items for each pay item:
1. ACTUAL QUANTITIES (AQ) - These quantities are determined from actual measurements of completed work.
2. LUMP SUM QUANTITIES (LSQ) - These quantities denote one complete unit of work as required by or described in the contract, including necessary materials, equipment, and labor to complete the job. They shall not be measured.
MEASUREMENT AND PAYMENT 011250-3
3. VEHICLE QUANTITIES (VQ) - These quantities are measured or weighed in hauling vehicles.
1.5 PRICE ADJUSTMENT (for Out-of-Specification Bituminous Materials)
A. Bituminous materials are defined as all types and grades of asphalt cement, liquid asphalt, emulsified asphalt, and dust oil.
B. If bituminous material fails one or more test requirements, and the Contracting Officer determines it is in the public interest to accept the material at a reduced price, the price reduction shall be based on the test results giving the largest percent price adjustment.
The contractor may remove and replace the defective material or accept the adjustment.
C. The price reduction shall apply to all pay items affected.
D. Price adjustment will be based on samples taken in duplicate in accordance with AASHTO T40 under the supervision of the Contracting Officer. Samples shall be sent to an authorized laboratory. The laboratory shall test one of each duplicate sample and retain the other. When any test result is not within the specification limits, the laboratory shall immediately notify the Contractor, the supplier, and the Contracting Officer. The Contractor, after notifying the Contracting Officer, may check test the retained sample.
E. If the retained sample tests satisfactorily, the material will be accepted. If the retained sample also fails, the following schedule of price adjustments shall apply. The average of test values for the two samples will determine the basis for price adjustment, except when test results on the samples differ by more than the applicable AASHTO or ASTM Repeatability Unit; then, the test result numerically nearest the specification requirement will be used. (A repeatability unit is defined as D2S or D2S% limit for single operator precision described in ASTM C670.)
F. The schedule of price adjustments shall not apply to the following tests:
Test AASHTO Test Method
Spot Test T102
Particle Charge T59
Ductility T51
G. Bituminous materials failing to meet specifications for these tests shall be removed and replaced.
H. See Table 011250-1 for the schedule of price adjustments for bituminous materials that do not meet specifications.
MEASUREMENT AND PAYMENT 011250-4
Table 011250-1
Schedule of Price Adjustments for Out-of-Specification Bituminous Materials.
Application
Deviation from Specification Limit Measured in Reproducibility Units*.
Less than 1 1 but less than 2
2 but less than 3
3 or more
Price reduction applicable to bituminous base course and pavement mixture or to seal coat and bituminous material paid for as a separate item.
0% 5% 25% Remove & Replace
Price reduction applicable to bituminous material paid for as a separate item.
0% 10% 25% Remove & Replace
* A reproducibility unit is defined as D2S or D2S% limit for multi-laboratory precision described in ASTM recommended practice C670.
The Sieve Test (AASHTO T59) results may be exempt from the Schedule of Price Adjustments provided the contractor's quality assurance program includes checking the uniformity of bituminous spread rates in increments no greater than 1 foot over the width of the spray bar and variation between increments is no greater than 5 percent.
PART 2 - PRODUCTS (NOT APPLICABLE)
PART 3 - EXECUTION (NOT APPLICABLE)
END OF SECTION 011250
ARCHAEOLOGICAL PROTECTION 011500-1
USDA FOREST SERVICE, R8
PR-191 WATER SYSTEM
SECTION 011500 - ARCHAEOLOGICAL PROTECTION
PART 1 - GENERAL
1.1 SUMMARY
A. The work of this section consists of protecting archeological resources.
1.2 DEFINITIONS
A. Resources: Prehistoric, historic, and recent 20th century artifacts, including charcoal, human bones, rock-lined gutters/ditches, ash, fire rocks, and building materials that indicate the presence of past human occupation.
1.3 SUBMITTALS
A. As specific in Division 1, Section “Submittal Procedures.”
B. 30 days before start of ground-disturbing site work, submit a Daily Work Schedule.
Include the following information.
1. Starting and ending dates of ground-disturbing construction.
2. Locations of temporary facilities, such as barriers, field offices, staging areas, and sanitary facilities.
3. Types of construction, such as clearing, topsoil stripping, structure or trench excavation, and post construction clean up.
4. Methods and equipment used for each type of construction.
5. Plan for relocating work in the event of temporary work stoppages due to discovery of archaeological resource.
1.4 MEASUREMENT AND PAYMENT
A. No separate measurement or payment will be made for work specified in this section. All work will be included in other items listed in the Schedule of Items.
PART 2 - PRODUCTS
2.1 NA
PART 3 - EXECUTION
3.1 OBSERVATION
A. The government may have an Archaeological Monitor who may observe ground-disturbing site work, including construction of temporary facilities, from a safe location
ARCHAEOLOGICAL PROTECTION 011500-2
mutually agreed on by Contractor and Monitor. As new ground is broken, Monitor will examine excavated materials, using construction layout centerline staking as a reference point to record locations of findings.
3.2 DISCOVERY OF RESOURCES
A. If Contractor or Archaeological Monitor discover archaeological resources, immediate relocation of the work to a non-sensitive area may be required to allow Monitor to take soil samples and record resources. While Archeological Monitor is documenting resources in sensitive areas, Contractor shall relocate work to non-sensitive areas where monitoring is not normally required.
B. If resources are discovered while Archaeological Monitor is absent, stop work immediately and report the discovery to the Contracting Officer.
3.3 WORK STOPPAGE
A. The Contractor shall plan, schedule, and execute the work to prevent stoppage at one area from stopping all work at the construction site.
3.4 WORK
A. Depending on the nature of the archaeological finding the project may be modified to change trench location, or adjust trench depth. Any changes to location or depth shall be as agreed upon with the Contracting Officer.
END OF SECTION 011500
ACCIDENT PREVENTION 011700-1
USDA FOREST SERVICE, R8
PR-191 WATER SYSTEM
SECTION 011700 - ACCIDENT PREVENTION
PART 1 - GENERAL
1.1 DESCRIPTION
A. The work of this section consists of establishing an effective accident prevention program and providing a safe environment for all personnel and visitors.
1.2 SUBMITTALS
A. Accident Prevention Program: Before on-site work begins, submit for approval an accident prevention program. The Contracting Officer (CO) will review the proposed program for compliance with OSHA and project requirements. If the program requires any revisions or corrections, the Contractor shall resubmit the program within 10 days.
No progress payments will be processed until the program is approved. The program shall include:
1. Name of responsible supervisor to carry out the program.
2. Weekly and monthly safety meetings.
3. First aid procedures.
4. Outline of each phase of the work, the hazards associated with each major phase, and the methods proposed to ensure property protection and safety of the public, government personnel, and the Contractor's employees. Identify the work included under each phase by reference to specification section or division numbers.
5. Training, both initial and continuing.
6. Planning for possible emergency situations, such as floods, hurricanes, landslides, cave-ins, explosions, power outages, and wind storms. Such planning shall take into consideration the nature of construction, site conditions, and degree of exposure of persons and property.
B. Submit a brief report of safety meetings and of inspections.
1.3 QUALITY ASSURANCE
A. In case of conflicts between Federal, state, and local safety and health requirements, the most stringent shall apply. Equipment or tools not meeting OSHA requirements will not be allowed on the project sites. Failure to comply with the requirements of this section and related sections may result in suspension of work.
B. Qualifications of Employees
1. Ensure that employees are physically qualified to perform their assigned duties in a safe manner.
ACCIDENT PREVENTION 011700-2
2. To as great an extent as possible, do not allow employees to work whose ability or alertness is impaired because of drugs, fatigue, illness, intoxication, or other conditions that may expose themselves or others to injury.
3. Operators of vehicles, mobile equipment, and hoisting equipment shall be able to understand signs, signals, and operating instructions, and be capable of operating such equipment. Provide operating instructions for all equipment. Newly hired operators shall be individually tested by an experienced operator or supervisor to determine if they are capable of safely operating equipment.
1.4 ACCIDENT REPORTING
A. Reportable Accidents: A reportable accident is defined as death, occupational disease, traumatic injury to employees or the public, property damage by accident in excess of $100. Within 24 hours or a death or traumatic injury and within 7 days for other reportable accidents, notify the CO.
B. All Other Accidents: The Contractor shall report all other accidents to the CO as soon as possible and assist the CO and other officials as required in the investigation of the accident.
1.5 MEASUREMENT AND PAYMENT
A. No separate measurement or payment will be made for work specified in this section. All work will be included in other items listed in the Schedule of Items.
PART 2 - PRODUCTS
2.1 FIRST AID FACILITIES: provide adequate facilities for the number of employees and the type of construction at the site.
2.2 PERSONNEL PROTECTIVE EQUIPMENT: meet requirements of NIOSH and MSHA, where applicable, as well as ANSI.
PART 3 - EXECUTION
3.1 EMERGENCY INSTRUCTIONS: post telephone numbers and reporting instructions for ambulance, physician, hospital, fire department, and police in conspicuous locations at the work site.
3.2 PROTECTIVE EQUIPMENT
A. Inspect personal protective equipment daily and maintain in a serviceable condition.
Clean, sanitize, and repair, as appropriate, personal items before issuing them to another individual.
B. Inspect and maintain other protective equipment and devices before use and on a periodic basis to ensure safe operation.
ACCIDENT PREVENTION 011700-3
3.3 SAFETY MEETINGS
A. As a minimum, conduct weekly 15-minute "toolbox" safety meetings. These meetings shall be conducted by a foreman and attended by all construction personnel at the worksite.
B. Conduct monthly safety meetings for all levels of supervision. Notify the CO so that they may attend. These meetings shall be used to review the effectiveness of the Contractor's safety effort, to resolve current health and safety problems, to provide a forum for planning safe construction activities, and for updating the accident prevention program.
3.4 TRAINING
A. First Aid: Provide adequate training to ensure prompt and efficient first aid.
END OF SECTION 011700
SEPTEMEBER 2022
MOBILIZATION 011900-1
USDA FOREST SERVICE, R8
PR-191 WATER SYSTEM
SECTION 011900 - MOBILIZATION
PART 1 - GENERAL
1.1 SUMMARY
A. This item is intended to compensate the Contractor for operations including, but not limited to, those necessary for the movement of personnel, equipment, supplies, and incidentals to the project site; for payment of premiums for bonds and insurance for the project; and for any other work and operations which must be performed or costs that must be incurred incident to the initiation of meaningful work at the site and for which payment is not otherwise provided for under the contract.
1.2 MEASUREMENT AND PAYMENT
A. The measurement shall be lump sum for mobilization. Payment shall be as follows:
1. Bond premiums will be reimbursed after receipt of the evidence of payment.
2. 50% of the lump sum, not to exceed 5% of the original contract amount, will be paid following completion of 5% of the original contract amount not including mobilization and bond premiums.
3. Payment of the remaining portion of the lump sum, up to 10% of the original contract amount, will be paid following completion of 10% of the original contract amount not including mobilization and bond premiums.
4. Any portion of the lump sum in excess of 10% of the original contract amount will be paid after final acceptance.
5. Progress payments for mobilization and preparatory work shall be subject to retainage.
PART 2 - PRODUCTS (NOT USED)
PART 3 - EXECUTION (NOT USED)
END OF SECTION 011900
July 2023
SUBMITTAL PROCEDURES 013300-1
USDA FOREST SERVICE, R8
PR-191 WATER SYSTEM
SECTION 013300 - SUBMITTAL PROCEDURES
PART 1 - GENERAL
1.1 SUMMARY
A. This Section includes administrative and procedural requirements for submitting Shop Drawings, Product Data, Samples, and other miscellaneous submittals. See Table 013300-1 for a summary of required submittals.
B. See other specification section within this package for additional requirements on submittal.
1.2 SUBMITTAL PROCEDURES
A. Coordination: Coordinate preparation and processing of submittals with performance of construction activities.
1. Coordinate transmittal of different types of submittals for related parts of the Work so processing will not be delayed because of need to review submittals concurrently for coordination.
a. The Contracting Officer (CO) reserves the right to withhold action on a submittal requiring coordination with other submittals until related submittals are received.
B. Processing Time: Allow enough time for submittal review, including time for re-submittals, as follows. Time for review shall commence on CO's receipt of submittal.
1. Initial Review: Allow 14 days for initial review of each submittal. Allow additional time if processing must be delayed to permit coordination with subsequent submittals. CO will advise Contractor when a submittal being processed must be delayed for coordination.
2. If intermediate submittal is necessary, process it in same manner as initial submittal.
3. Allow 14 days for processing each re-submittal.
4. No extension of the Contract Time will be authorized because of failure to transmit submittals enough in advance of the Work to permit processing.
C. Identification: Place a permanent label or title block on each submittal for identification.
1. Indicate name of firm or entity that prepared each submittal on label or title block.
2. Provide a space on label or beside title block to record Contractor's review and approval markings and action taken by CO.
3. Include the following information on label for processing and recording action taken:
a. Project name.
b. Date.
SUBMITTAL PROCEDURES 013300-2
c. Name and address of Contractor.
d. Name of manufacturer.
e. Unique identifier, including revision number.
f. Number and title of appropriate Specification Section.
g. Drawing number and detail references, as appropriate.
h. If more than one item is shown on submittal sheet, identify item.
D. Deviations: Highlight, encircle, or otherwise identify deviations from the Contract Documents on submittals.
E. Use for Construction: Use only final submittals with mark indicating action taken by CO in connection with construction.
1.3 MEASUREMENT AND PAYMENT
A. No separate measurement and/or payment will be made for this section. Payment shall be included with work shown in the schedule of items.
PART 2 - PRODUCTS
2.1 ACTION SUBMITTALS – (Submittals requiring CO approval)
A. General: Prepare and submit Action Submittals required by individual Specification Sections.
1. Number of Copies: Submit three copies of each submittal, unless otherwise indicated. CO will return two copies. Mark up and retain one returned copy as a Project Record Document. If allowed by the CO, some or all submittals may be allowed to be submitted electronically only.
B. Product Data: Collect information into a single submittal for each element of construction and type of product or equipment.
1. If information must be specially prepared for submittal because standard printed data are not suitable for use, submit as Shop Drawings, not as Product Data.
2. Mark each copy of each submittal to show which products and options are applicable.
3. Include the following information, as applicable:
a. Manufacturer's written recommendations.
b. Manufacturer's product specifications.
c. Manufacturer's installation instructions.
d. Manufacturer's catalog cuts.
e. Compliance with recognized trade association standards.
f. Compliance with recognized testing agency standards.
C. Shop Drawings: Prepare Project-specific information, drawn accurately to scale. Do not base Shop Drawings on reproductions of the Contract Documents or standard printed data.
SUBMITTAL PROCEDURES 013300-3
1. Preparation: Include the following information, as applicable:
a. Dimensions.
b. Identification of products.
c. Fabrication and installation drawings.
d. Roughing-in and setting diagrams.
e. Notation of dimensions established by field measurement.
D. Contractor's Construction Schedule: The contractor shall submit a Construction Schedule, for approval by CO, in accordance with the contract provisions within 5 days of commencement of work.
E. Samples: Prepare physical units of materials or products, including the following:
1. Samples for Initial Selection: Submit manufacturer's color charts consisting of units or sections of units showing the full range of colors, textures, and patterns available.
2.2 INFORMATIONAL SUBMITTALS – (Submittals NOT requiring CO approval)
A. General: Prepare and submit Informational Submittals required by other Specification Sections.
1. Number of Copies: Submit three copies of each submittal, unless otherwise indicated. CO will not return copies. If allowed by the CO, some or all submittals may be allowed to be submitted electronically only.
2. Certificates and Certifications: Certificates and certifications shall be signed by an officer or other individual authorized to sign documents on behalf of that entity.
3. Test and Inspection Reports: Comply with requirements in Section 014100 "Quality Control."
B. Material Test Reports: Prepare reports written by a qualified testing agency, on testing agency's standard form, indicating and interpreting test results of material for compliance with requirements.
C. Field Test Reports: Prepare reports written by a qualified testing agency, on testing agency's standard form, indicating and interpreting results of field tests performed either during installation of product or after product is installed in its final location, for compliance with requirements.
D. Maintenance Data: Prepare written and graphic instructions and procedures for operation and normal maintenance of products and equipment.
E. Manufacturer's Instructions: Prepare written or published information that documents manufacturer's recommendations, guidelines, and procedures for installing or operating a product or equipment. Include name of product and name, address, and telephone number of manufacturer.
PART 3 - EXECUTION
3.1 GENERAL
SUBMITTAL PROCEDURES 013300-4
A. Review each submittal and check for compliance with the Contract Documents. Note corrections and field dimensions. Mark with approval stamp before submitting to CO.
B. Approval Stamp: Stamp each submittal with a uniform, approval stamp. Include Project name and location, submittal number, Specification Section title and number, name of reviewer, date of Contractor's approval, and statement certifying that submittal has been reviewed, checked, and approved for compliance with the Contract Documents.
C. CO will not review submittals that do not bear Contractor's approval stamp and will return them without action.
D. Submittals not required by the Contract Documents will not be reviewed and may be discarded.
E. Substitutions – Whenever materials, products, and equipment are listed by name or brand in the specifications and/or on the drawings, it is used as a measure of quality, utility, or standard. If the Contractor prefers to use any other brand or manufacturer of same quality, appearance and utility to that specified, he shall request substitution as provided below, not less than 30 days before the planned installation of the item. The Contracting Officer will approve or disapprove the request for substitution.
F. Requests for substitutions will only be considered if contractor submits the following:
1. Complete technical data including drawings, complete performance specifications, test data, samples and performance tests of the article proposed for substitution.
Submit additional information if required by Contracting Officer. All items in the above information shall be circled, tagged, or marked in some way to indicate all deviations or differences which the proposed item differs from the originally specified item.
2. Similar data as above for item originally specified. All items shall be marked to identify where/how the proposed substitution will differ.
3. A statement by the Contractor that the proposed substitution is in full compliance with the contract documents, applicable codes, and laws.
4. The Contractor shall be responsible for any effect upon related work in the project for any substitution and shall pay any additional costs generated by any substitutions.
3.2 SUBMITTAL SCHEDULE – Submittals shall be made as required by and called for in the drawings and specifications. The following table is a summary of the required submittals for the project - the table is to assist the Contractor and may not be all inclusive
– additional submittals may be required by specific specifications:
TABLE 013000-1
Spec.
Section
Section Title Subsec tion Required Submittal
C General Specifications 1.3A Stream Protection Plan
C General Specifications 1.4A Traffic Control Plan
SUBMITTAL PROCEDURES 013300-5
Spec.
Section
Section Title Subsec tion Required Submittal
011500 Archaeological Protection 1.3B Ground Disturbing Work Schedule
011700 Accident Prevention 1.2A Accident Prevention Program
013300 Submittal Procedures 2.1D Construction Schedule
014100 Quality Control 1.3A Contractor Quality Control Plan
014100 Quality Control 1.3B Permits, Licenses, and Certificates
014100 Quality Control 1.3C Test and Inspection Reports
014100 Quality Control 1.3D As-Built Drawings
017320 Selective Demolition 1.4A Predemolition Photos or Video
017320 Selective Demolition 1.4B Landfill Records
023701 Sediment, Pollution, & Erosion Control Measures
1.2A Sediment & Erosion Control Plan
023701 Sediment, Pollution, & Erosion Control Measures
1.2B Concrete Mixing Plan
023701 Sediment, Pollution, & Erosion Control Measures
1.2C Spill Protection Plan
033000 Cast-in-Place Concrete 1.3A Product Data
033000 Cast-in-Place Concrete 1.3B Design Mix
033000 Cast-in-Place Concrete 1.3C Shop Drawings
033000 Cast-in-Place Concrete 1.3D Samples
048600 Stone Veneer 1.3A Product Data
047200 Stone Veneer 1.3B Stone Sample
047200 Stone Veneer 1.3C Colored Mortar Samples
047200 Stone Veneer 1.3D Qualification Data
221100 Water Distribution Systems 1.3A Product Data
221102 Curb Valves and Boxes 1.2A Product Data
221105 Water Hydrants
1.3A Manufacturer’s Literature and Maintenance Data
221105 Water Hydrants 1.3B Washed Rock Certification
SUBMITTAL PROCEDURES 013300-6
Spec.
Section
Section Title Subsec tion Required Submittal
221219 Aboveground Concrete Rectangular Potable Water Storage Tanks
1.3A Shop Drawings
221219 Aboveground Concrete Rectangular Potable Water Storage Tanks
1.3B Product Data
221219 Aboveground Concrete Rectangular Potable Water Storage Tanks
1.4A Qualification Data
221119 Domestic Water Piping Specialties 1.3C Operation and Maintenance Data
221142 Stream Crossings 1.2A Construction Plan for Stream Crossing
221200 Underground Water Storage Tank 1.3A Product Data and Shop Drawings
221200 Underground Water Storage Tank 1.3B Product Certificate
221200 Underground Water Storage Tank 1.3C Operation and Maintenance Data
260500 Common Work Results for Electrical 1.2A Product Data
312000 Earthwork 1.3A Bedding and Backfill Certification
312000 Earthwork 1.3A Sieve Analysis
312000 Earthwork 1.3B Product Data
321200 Hot Mix Asphalt Paving 1.2A Product Data
321200 Hot Mix Asphalt Paving 1.2B Job Mix Design
321200 Hot Mix Asphalt Paving 1.2C Material Certificate
321204 Crushed Aggregate Base or Surface Course
1.2A Aggregate Base – Source, Gradation, Material Properties
321204 Crushed Aggregate Base or Surface Course
1.2B Compaction Test Results and Proctor
321204 Crushed Aggregate Base or Surface Course
1.2C Material Properties
323113 Chain-Link Fences and Gates 1.4A Product Data
323113 Chain-Link Fences and Gates 1.4B Shop Drawings
323113 Chain-Link Fences and Gates 1.4C Product Certificates
SUBMITTAL PROCEDURES 013300-7
Spec.
Section
Section Title Subsec tion Required Submittal
323113 Chain-Link Fences and Gates 1.4D Qualification Data
330523 Utility Horizontal Directional Drilling 1.4A Drilling Plan
330523 Utility Horizontal Directional Drilling 1.4B Drilling Records
END OF SECTION 013300
QUALITY CONTROL 014100-1
USDA FOREST SERVICE, R8
PR-191 WATER SYSTEM
SECTION 014100 - QUALITY CONTROL
PART 1 - GENERAL
1.1 This work shall consist of providing quality control in conformance with the inspection, testing, and product certification requirements of this contract to ensure compliance with the drawings and specifications. The Contractor shall provide all personnel, equipment, tests, and reports necessary to meet the requirements of the contract.
1.2 QUALITY CONTROL
A. The Contractor shall provide and maintain a quality control system that will ensure all services, supplies, and construction work required under this contract conforms to the contract requirements. The Contractor shall perform, or cause to be performed, the sampling, inspection, and testing required to substantiate that all services, supplies, and construction conform to the contract requirements.
B. Special Tests and Inspections: Contractor will engage a testing agency to conduct required special tests and inspections. The Contractor shall authorize the testing agency to perform the required testing and inspections on the work completed. The authority shall include:
1. Testing agency will interpret tests and inspections and state in each report whether tested and inspected work complies with or deviates from the Contract Documents.
2. Testing agency will re-test and re-inspect corrected work.
C. Retesting/Reinspecting: Contractor shall provide quality-control services for retesting and reinspection for replaced construction work or for work that failed to comply with the requirements under the contract.
1.3 SUBMITTALS
A. Contractor Quality Control Plan
B. Permits, Licenses, and Certificates
C. Test and Inspection Reports
D. As-Built Drawings
1.4 MEASUREMENT AND PAYMENT
A. No separate payment will be made for the work included under this section; rather payment shall be considered to be included in the items of work listed in the Schedule of Items.
PART 2 - PRODUCTS (Not Applicable)
QUALITY CONTROL 014100-2
PART 3 - EXECUTION
3.1 QUALITY CONTROL SYSTEM
A. General: Perform required testing, inspections, sampling, and similar services per direction specified in the contract drawings and specifications and in accordance with established industry standards.
3.2 CONTRACTOR QUALITY CONTROL PLAN
A. At the time of the preconstruction conference, the Contractor shall submit for approval a written Contractor Quality Control Plan.
1. If the plan requires any revisions or corrections, the Contractor shall resubmit the plan within 10 days.
2. The Government reserves the right to require changes in the plan during the contract period as necessary.
3. No change in the approved plan may be made without written concurrence by the Contracting Officer.
4. At a minimum, the plan shall include the following:
a. A list of personnel responsible for quality control and assigned duties.
Include each person's qualifications.
b. A copy of a letter of direction to the Contractor's Quality Control Supervisor outlining assigned duties.
c. Names, qualifications, and descriptions of laboratories to perform sampling and testing, and samples of proposed report forms.
d. Methods of performing, documenting, and enforcing quality control of all work.
e. Methods of monitoring and controlling environmental pollution and contamination as required by all applicable regulations and laws.
3.3 TEST AND INSPECTION REPORTS
A. Submit three copies of complete test results no later than three calendar days after the test was performed. If allowed by the CO, some or all test results may be allowed to be submitted electronically only
B. Submit failing test results and proposed remedial actions within four hours of noted deficiency.
C. Testing and Inspection Reports shall include the following:
1. Date of issue.
2. Project title and number.
3. Name, address, and telephone number of testing agency.
4. Dates and locations of samples, tests, or inspections.
5. Names of individuals performing tests and inspections.
6. Reference Specification Section(s).
QUALITY CONTROL 014100-3
7. Complete test or inspection data.
8. Test and inspection results and an interpretation of test results.
9. Ambient conditions at time sample was taken, tested, or inspected.
10. Comments or professional opinion on whether tested or inspected work complies with the Contract Document requirements.
11. Name and signature of laboratory inspector.
12. Recommendations on retesting and reinspecting.
3.4 PERMITS, LICENSES, AND CERTIFICATES
A. For Contracting Officer’s records, submit copies of permits, licenses, certifications, inspection reports, releases, jurisdictional settlements, notices, receipts for fee payments, judgments, correspondence, records, and similar documents, established for compliance with standards and regulations relevant to the on performance of the work.
3.5 AS-BUILT DRAWINGS
A. The Contractor shall maintain a set of the contract drawings depicting as-built conditions.
These drawings shall be maintained in a current condition and shall be available for review. All variations from the original contract drawings shall be indicated in red on the drawings. Upon completion of the contract work, as-built drawings shall be submitted to the Contracting Officer.
3.6 SAMPLING, TESTING, AND CERTIFICATION REQUIREMENTS
A. Sampling, testing, and Certification requirements and frequency for specific items shall be as specified in the drawings and specification. The following table is a summary of the required sampling, testing, and certification for the project - the table is to assist the Contractor, but may not be all inclusive – additional submittals may be required by specific specification section:
TABLE 014100-1
Item
Subsection Certification or Test Required
Frequency
033000 2.12 Mixing and Delivery Each Truck
033000 3.13 Concrete – Slump, Air, Temperature 1 composite per truck load delivered
033000 3.13 Concrete - Compression Test Specimens at 7 days and 28 days (see spec)
221100 3.2N HDPE Pipe - Bent Strap Test Once Daily
221100 3.6A Hydrostatic Testing of Water System See Spec.
221100 3.6B Pressure and Leakage Test – Water Line
See Spec.
QUALITY CONTROL 014100-4
221100 3.7A Bacteriological Examination After disinfection, before use
221219 3.6 Tank Leak Test Until Passing
312000 3.14C Compaction Test – at Pipe Zone One per 600 Feet of Trench
312000 3.14C Compaction Test – at Pipe Zone One test – at each road or parking lot crossing
312000 3.14D Compaction Test – above Pipe Zone One per 600 Feet of Trench
312000 3.14D Compaction Test – above Pipe Zone One test every other lift – at each road or parking lot crossing
312000 3.14H Tracer Wire Conductivity Test Until Passing
312000 3.17A Compaction Test – Backfill/Fills under Structures
One test every 300 S.F. area per lift, and not less than 3
312000 3.19C Compaction Test – Gutters 1 per 2,000 sq ft
312000 3.19C Compaction Test – Tanks 1 per 300 sq ft and not less than 3
321200 3.10B Gradation and Asphalt Content One per 700 tons or Min. of 1 per Project
321200 3.10C Field Density Tests – Asphalt One test for every 300
sq. yd. of pavement or Min. of 1 per Project
321204 3.4A Compaction Tests – Road Base and Surface Course
One test for every 300
sq. yd. of aggregate or Min. of 1 per Project
321204 3.4A Compaction Tests – Aggregate Base for Concrete Gutters
1 per 2,000 sq ft
QUALITY CONTROL 014100-5
321204 3.4A Compaction Tests – Aggregate Base for Concrete Tanks
1 per 300 sq ft and not less than 3
END OF SECTION 014100
NOVEMBER 2022
TEMPORARY TRAFFIC CONTROL 015100-1
USDA FOREST SERVICE, R8
PR-191 WATER SYSTEM
SECTION 015100 - TEMPORARY TRAFFIC CONTROL
PART 1 - GENERAL
1.1 SUMMARY
A. This work consists of furnishing, maintaining, relocating, and removing temporary traffic control and safety devices and services for the control and protection of public traffic near the project site. Prior to beginning construction, the Contractor shall submit a traffic control and safety plan to the Contracting Officer for review and approval. As a minimum the traffic control and safety plan shall address signing in and near the project site and at all road and highway junctions that will be used as access to the project site, material sources, water sources and disposal sites as well as any other areas where the Contractor will be performing work under this contract.
1.2 MEASUREMENT AND PAYMENT
A. No separate measurement or payment will be made for work specified in this section. All work will be included in other items listed in the Schedule of Items.
PART 2 - PRODUCTS
2.1 TRAFFIC CONTROL
A. Traffic control and safety device (barricades, cones, tubular markers, vertical panels, drums, portable barriers and so forth) designs and configurations shall conform to the Manual of Uniform Traffic Control Devices (MUTCD). When interpreting the requirements in the applicable MUTCD sections, replace the word should with the word shall.
PART 3 - EXECUTION
3.1 GENERAL
A. All signs shall be constructed to comply with the requirements of MUTCD for the construction operations. Install and maintain temporary traffic control and safety devices adjacent to and within the project as shown on the approved traffic control and safety plan and MUTCD. Install and maintain traffic control and safety devices as follows:
1. Furnish and install traffic control and safety devices before the start of construction operations.
2. Install only those traffic control and safety devices needed for each stage or phase.
3. Relocate temporary traffic control devices as necessary.
4. Immediately replace any device that is lost, stolen, destroyed, or inoperative.
5. Keep temporary traffic control and safety devices clean.
TEMPORARY TRAFFIC CONTROL 015100-2
6. Remove all temporary traffic control devices upon contract completion or when approved.
B. Barricades
1. Perform the work described under MUTCD Part VI. Use type III or IV reflective sheeting. Use wood, metal, or plastic barricades. When type II barricades are used, use barricades that collapse when tipped over.
C. Construction Signs
1. Use type III or IV reflective sheeting. Use wood, metal, fiberglass, or other approved posts.
END OF SECTION 015100
SELECTIVE DEMOLITION 017320-1
USDA FOREST SERVICE, R8
PR-191 WATER SYSTEM
SECTION 017320 - SELECTIVE DEMOLITION
PART 1 - GENERAL
1.1 SUMMARY
A. This Section includes demolition and removal of the following:
1. Selected site elements.
2. Repair procedures for selective demolition operations.
1.2 DEFINITIONS
A. Remove: Detach items from existing construction and legally dispose of them off-site, unless indicated to be removed and salvaged or removed and reinstalled.
B. Remove and Salvage: Detach items from existing construction and deliver them to Government.
C. Remove and Reinstall: Detach items from existing construction, prepare them for reuse, and reinstall them where indicated.
D. Existing to Remain or Designated for Protection: Existing items of construction that are not to be removed and that are not otherwise indicated to be removed, removed and salvaged, or removed and reinstalled.
1.3 MATERIALS OWNERSHIP
A. Except for items or materials indicated to be reused, salvaged, reinstalled, or otherwise indicated to remain Government property, demolished materials shall become Contractor's property and shall be removed from Project site.
1.4 SUBMITTALS
A. Pre-demolition Photographs or Videotape: Show existing conditions of adjoining construction and site improvements that might be misconstrued as damage caused by selective demolition operations. Submit before Work begins.
B. Landfill Records: Indicate receipt and acceptance of wastes by a landfill facility licensed to accept waste.
1.5 PROJECT CONDITIONS
A. Storage or sale of removed items or materials on-site will not be permitted.
B. Utility Service: Maintain existing utilities indicated to remain in service and protect them against damage during selective demolition operations.
SELECTIVE DEMOLITION 017320-2
PART 2 - PRODUCTS
2.1 REPAIR MATERIALS
A. Use repair materials identical to existing materials.
1. If identical materials are unavailable or cannot be used for exposed surfaces, use materials that visually match existing adjacent surfaces to the fullest extent possible.
2. Use materials whose installed performance equals or surpasses that of existing materials.
PART 3 - EXECUTION
3.1 EXAMINATION
A. Survey existing conditions and correlate with requirements indicated to determine extent of selective demolition required.
B. Inventory and record the condition of items to be removed and reinstalled and items to be removed and salvaged.
C. When unanticipated mechanical, electrical, or structural elements that conflict with intended function or design are encountered, investigate and measure the nature and extent of conflict. Promptly submit a written report to CO.
3.2 UTILITY SERVICES
A. Existing Utilities: Maintain services indicated to remain and protect them against damage during selective demolition operations.
B. Do not interrupt existing utilities serving occupied or operating facilities unless authorized in writing by CO and authorities having jurisdiction. Provide temporary services during interruptions to existing utilities, as acceptable to CO and to authorities having jurisdiction.
1. Provide at least five working days’ notice to CO if shutdown of service is required during changeover.
3.3 PREPARATION
A. Site Access and Temporary Controls: Conduct selective demolition and debris-removal operations to ensure minimum interference with roads, streets, walks, walkways, and other adjacent occupied and used facilities.
1. Do not close or obstruct streets, walks, walkways, or other adjacent occupied or used facilities without permission from CO and authorities having jurisdiction.
Provide alternate routes around closed or obstructed traffic ways if required by governing regulations.
2. Protect existing site improvements, appurtenances, and landscaping to remain.
SELECTIVE DEMOLITION 017320-3
B. Temporary Facilities: Provide temporary barricades and other protection required to prevent injury to people and damage to adjacent buildings and facilities to remain.
3.4 SELECTIVE DEMOLITION
A. General: Demolish and remove existing construction only to the extent required by new construction and as indicated. Use methods required to complete the Work within limitations of governing regulations.
B. Existing Items to Remain: Protect construction indicated to remain against damage and soiling during selective demolition. When permitted by CO, items may be removed to a suitable, protected storage location during selective demolition and cleaned and reinstalled in their original locations after selective demolition operations are complete.
3.5 PATCHING AND REPAIRS
A. General: Promptly repair damage to adjacent construction caused by selective demolition operations.
B. Repairs: Where repairs to existing surfaces are required, patch to produce surfaces suitable for new materials.
C. Finishes: Restore exposed finishes of patched areas and extend restoration into adjoining construction in a manner that eliminates evidence of patching and refinishing.
3.6 DISPOSAL OF DEMOLISHED MATERIALS
A. General: Promptly dispose of demolished materials. Do not allow demolished materials to accumulate on-site.
B. Burning:…
This is the start of the file's text. The full file is on GovTribe.