Attachment 4 - PWS App D - Contractor s Submittals..pdf

PDF 182 KB Posted

Attached to
Maintenance and Repair of Gas Distribution System at Aviano AB, Italy
Solicitation number
FA568224Q8089
Issued by

About this file

This document is an Attachment 4 - PWS (Performance Work Statement) Appendix D that outlines the Contractor's Submittals required for the Maintenance and Repair of Gas Distribution System at Aviano AB, Italy contract opportunity.

The key details are as follows:

The PWS requires the contractor to submit various documents on specific timelines, including an updated ITM (Inspection, Testing, and Maintenance) service schedule, ITM service reports, Part History Summary, Work Order Tracker, and Metrics. These submittals are due within 5-10 working days after contract award, with weekly submittals of Metrics due by the second working day of each week. The contractor is also required to submit a Quality Control Plan, Operational Safety Plan, employee qualifications, and other documents either with the bid proposal or within 10 days of contract award. The contract opportunity, Solicitation Number FA568224Q8089, is a Request for Quotation (RFQ) issued by the U.S. Air Force United States Air Forces in Europe - Air Forces Africa for the maintenance and repair of the gas distribution system at Aviano Air Base, Italy. The quote submission deadline is September 18, 2024, at 16:00 Central European Time, and a site visit is scheduled for September 12, 2024.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

- Updated ITM service schedule (PWS paragraph 1.3.1.4)

- ITM service reports (PWS paragraph 1.3.1.5)

- Part History Summary (PWS paragraph 1.5.2.1)

- Work Order Tracker (PWS paragraph 1.5.2.2)

- Metrics (PWS paragraph 1.5.2.3)

PWS

paragraph

4.2.2

4.2.3

4.4

1.3.1.4

1.3.1.5

1.3.2.2

1.3.3.4

1.4.2

1.5.2.3

4.2.1

2.1

4.4.3.1 To be submitted at least ten (10) working days prior to the intended use of the hazardous material

ITM service schedule

Notification signs

Quality Control Plan (QCP)

Submittal type

SDS (safety Data sheet)

Operational Safety Plan

Contractor contact information

Organizational chart

Emergency request service report form

Extraordinary Maintenance request service report form

To be submitted right after the pre-performance meeting or within ten (10) working days after contract award, whichever is first

To be submitted no later than five (5) working days after contract award

To be submitted no later than five (5) working days after contract award

To be submitted with the Bid proposal

Employee Qualifications

APPENDIX D

Contractor's Submittals

ITM service report forms To be submitted no later than five (5) working days after contract award

Timing

To be submitted no later than five (5) working days after contract award

To be submitted no later than five (5) working days after contract award

To be submitted no later than five (5) working days after contract award

To be submitted no later than five (5) working days after contract award

To be submitted by Contractor awardee within ten (10) working days after contract award

To be submitted with the Bid proposal

MAINTENANCE AND REPAIR OF GAS DISTRIBUTION SYSTEM

AT AVIANO AB, ITALY

WEEKLY SUBMITTALS

(PWS paragraph 1.5.2) to be submitted by 16:00 on the second working day of each following week

OTHER SUBMITTALS

Metrics form

27 August 2024