Attachment 4 - Performance Requirements Summary Table.pdf

PDF 300 KB Posted

Attached to
Payload Control System (PCS) Federal contract opportunity
Solicitation number
N6660426R0063
Issued by
Department of the Navy Naval Sea Systems Command

About this file

This Performance Requirements Summary Table details technical requirements for a complex software and hardware integration project, likely for a submarine or naval combat system. The document outlines multiple contract deliverable requirements (CDRLs) across seven main technical areas: Concept of Operations, Architecture Development, Software Development, Hardware/Software Integration and Testing, Capstone Demonstration, Shipboard Demonstration, and Cyberspace/Cyber Workforce.

Key technical objectives include developing Concepts of Operations (CONOPS), creating Top-Level Requirements (TLRs), designing software architecture, developing and testing software code, creating simulator/stimulator software, demonstrating end-to-end mission capabilities, and supporting shipboard installation and testing. Each requirement has specific performance standards, with most requiring 95% compliance, and involves detailed documentation, technical reviews, and government feedback. Monitoring methods include government project manager reviews and 100% receipt inspection of contract deliverable documentation (CDRLs). The document is dated January 2023 and appears to be part of a sophisticated naval systems integration contract.

View the file

Other files for this federal contract opportunity

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

3 v1.3_JANUARY2023

Performance Requirements Summary Table

Requirement (Task number and title from

SOW/PWS)

CDRL

(if applicable)

Performance Objective Performance

Standard

Acceptable Quality Level

(AQL)

Monitoring Method

4.1

CONCEPT OF

OPERATIONS (CONOPS)

AND TOP-LEVEL

REQUIREMENT (TLR)

DEVELOPMENT

CDRL A001

Existing payload mission CONOPS capture performance characteristics and limitations of the payload that is planned for integration. CONOPS include requirements for targeting, launch and post-launch, as well as potential impacts to safety and security on the representative combat system and platform.

Services provided are technically accurate, complete, and are provided in accordance with all approved schedules. Initial submission of Revised CONOPs is complete, accurate, and timely in accordance with Exhibit A; no revisions are required.

Standard is met 95% of the time.

Government feedback from Project Managers upon review and execution of services provided.

100% receipt inspection of CDRLs.

4.1

CONCEPT OF

OPERATIONS (CONOPS)

AND TOP LEVEL

REQUIREMENT (TLR)

DEVELOPMENT

CDRL A002

CDRL A003

TLRs identify capabilities of new payloads and submarine variants interfacing with CSA-PI Data Interface (CDI) software. TLRs include software interface requirements in terms of both objective and threshold requirements.

Analysis of potential impacts of the TLRs to existing systems and CDI software include recommended production combat system design changes, impacts to existing interfaces, and any new CDI software changes.

Services provided are technically accurate, complete, and are provided in accordance with all approved schedules. Initial submissions of TLRs and TLR Analysis are complete, accurate, and timely in accordance with Exhibit A; no revisions are required

Standard is met 95% of the time.

Government feedback from Project Managers upon review and execution of services provided.

100% receipt inspection of CDRLs.

4.2

ARCHITECTURE

DEVELOPMENT

CDRL A004

CDRL A005

Delivered CDI software architecture design package includes software components (identifying open source and proprietary components), abstraction layers, software development kits (SDKs), and application program interfaces (APIs). Combat system implementation approaches and software integration plans are included in the architecture design package.

Contractor presents the architecture design package and records meeting minutes and action items assigned during design reviews. Action items are tracked for closure.

Services provided are technically accurate, complete, and are provided in accordance with all approved schedules. Initial submissions of CDI Software Architecture Design Package and Report, Record of Meeting/Minutes are complete, accurate, and timely in accordance with Exhibit A; no revisions are required.

A read-ahead of the architecture design package is delivered one week in advance of scheduled design review.

Standard is met 95% of the time.

Government feedback from Project Managers upon review and execution of services provided.

100% receipt inspection of CDRLs.

4.3

SOFTWARE

DEVELOPMENT

CDRL A006

Software Development Plan (SDP) is delivered and includes changes, modifications, additions or substitutions for specific computer software throughout the life of the contract.

Initial submission of the SDP is complete, accurate, and timely in accordance with Exhibit A; no revisions are required.

Standard is met 95% of the time.

100% receipt inspection of

CDRL.

4.3

SOFTWARE

DEVELOPMENT

CDRL A007

Existing CDI software code is functional and updated for compatibility with the existing payload control system, applicable variants, and launcher systems.

Status of software development is presented at working group meetings and software design reviews. Source code, software documentation, developer notes, and development environment are all delivered. Information assurance is implemented into the software design.

CDI software code is functional.

Services provided are technically accurate, complete, and are provided in accordance with all approved schedules

Information Assurance is implemented in accordance with Applicable Document 3.10.

CDI Source Code is complete, accurate, and timely in accordance with Exhibit A; no revisions are required.

Standard is met 95% of the time.

Government feedback from Project Managers upon review and execution of services provided.

100% receipt

CDRL.

CDRL A008

CDRL A009

Problems are tracked via Problem Trouble Report (PRT) tracker and adjudicated.

Problem Trouble Report (PTR) Adjudications is complete, accurate, and timely in accordance with Exhibit A; no revisions are required.

Standard is met 95% of the time.

Government feedback from Project Managers upon review and execution of services provided.

100% receipt inspection of

CDRL.

4.4

HARDWARE/SOFTWARE

INTEGRATION AND

TESTING

CDRL A00A

CDRL A00B

Simulator/stimulator software for validation of the CDI software is developed and software design and user documentation is delivered.

Simulator/Stimulator Software Code, Design and User Documentation are technically accurate complete, accurate, and timely in accordance with Exhibit A; no revisions are required.

Standard is met 95% of the time.

Government feedback from Project Managers upon review and execution of services provided. 100% receipt inspection of

CDRL.

4.4

HARDWARE/SOFTWARE

INTEGRATION AND

TESTING

CDRL A00C

Develop test plans and procedures using provided peripheral equipment to validate that the software meets the approved TRLs.

Services provided are technically accurate, complete, and are provided in accordance with all approved schedules. Initial submission of the Software Test Plans/Test Procedures is complete, accurate, and timely in accordance with Exhibit A; no revisions are required.

Standard is met 95% of the time.

Government feedback from Project Managers upon review and execution of services provided. 100% receipt inspection of

CDRL.

4.4

HARDWARE/SOFTWARE

INTEGRATION AND

TESTING

CDRL A00D

Test reports are delivered upon approval of the test plans and procedures. Approved test plans, procedures and reports will be used to develop, deliver, integrate, and install prototype software in an Engineering Development Module (EDM) laboratory to support formal evaluation of the new design to be performed by the Government.

Reports provided are technically accurate, complete, and are provided in accordance with all approved schedules.

Initial submission of the Software Test Report is complete, accurate, and timely in accordance with Exhibit A; no revisions are required.

Standard is met 95% of the time.

Government feedback from Project Managers upon review and execution of services provided. 100% receipt

4.5

CAPSTONE

DEMONSTRATION

CDRL A00E

Demonstrate the full end-to-end thread for mission areas of the payload defined in the CONOPs in a formal Concept of Operations Exercise (COOPEX). Document the results of the COOPEX and deliver a formal report detailing the results of all testing and post-test analysis.

Services provided are technically accurate, complete, and are provided in accordance with all approved schedules

Initial submission of the Software Capstone Report is complete, accurate, and timely in accordance with Exhibit A; no revisions are required

Standard is met 95% of the time.

Government feedback from Project Managers upon review and execution of services provided.

100% receipt inspection of

CDRL.

4.6

SHIPBOARD

DEMONSTRATION

(4.6.1 Alterations)

CDRL A00F

Updates to Alteration Technical Data Packages to support the approval and installation of systems required for full shipboard end-to-end testing.

Services provided are technically accurate, complete, and are provided in accordance with all approved schedules. Initial submission of Revised TDPs is complete, accurate, and timely in accordance with Exhibit A; no revisions are required.

Standard is met 95% of the time.

Government feedback from Project Managers upon review and execution of services provided.

100% receipt inspection of

CDRL.

4.6

SHIPBOARD

DEMONSTRATION

(4.6.1 Alterations)

CDRL A00G

System user/operator documentation for shipboard operation is delivered.

Documentation will support the training and operation of prototype systems for shipboard demonstration.

User Documentation is technically accurate, complete, and timely in accordance with Exhibit the time.

Government feedback from Project Managers upon review and execution of services provided.

100% receipt inspection of

CDRL.

4.6

SHIPBOARD

DEMONSTRATION

(4.6.1 Alterations)

CDRL A00H

Develop test plans and procedures to demonstrate full software/ hardware capability on platform.

Approved test plans and procedures will be used to develop, deliver, integrate, and install prototype system on platform to support formal evaluation of the new design to be performed by the Government.

Services provided are technically accurate, complete, and are provided in accordance with all approved schedules. Initial submission of the Shipboard Plans/Test Procedures is complete, accurate, and timely in accordance with Exhibit A; no revisions are required.

Standard is met 95% of the time.

Government feedback from Project Managers upon review and execution of services provided.

100% receipt inspection of

CDRL.

4.6

SHIPBOARD

DEMONSTRATION

(4.6.2 Installation and Checkout)

CDRL A00J

Test reports are delivered upon approval of the test plans and procedures and final execution of the shipboard event.

Reports provided are technically accurate, complete, and are provided in accordance with all approved schedules.

Initial submission of the Shipboard Test Report is complete, accurate, and timely in accordance with Exhibit

Standard is met 95% of the time.

Government feedback from Project Managers upon review and execution of services provided.

100% receipt required.

4.6

SHIPBOARD

DEMONSTRATION

(4.6.2 Installation and Checkout, 4.6.3.

Demonstration of Software/Hardware)

CDRL A00K

Trip reports are delivered upon completion of installation and demonstration events. Reports will include major events, lessons learned, and follow-on actions as applicable.

Reports provided are technically accurate, complete, and timely in accordance with Exhibit A.

the time.

Government feedback from Project Managers upon review and execution of services provided.

100% receipt inspection of

CDRL.

4.7

CYBERSPACE/CYBER

WORKFORCE (CWF)

CDRL A00L

Submit a monthly CWF report status required certifications and fulfillment status and new hire information.

Reports provided are technically accurate, complete, and timely.

Standard is met 95% of the time.

Government feedback from Project Managers upon review and execution of services provided.

100% receipt inspection of

CDRL.

4.8

MEETING SUPPORT

CDRL A00M

Develop presentation material to support working group and technical discussions related to the development tasking assigned.

Material will support development discussion with technical stakeholders and progress status.

Presentation Documentation are technically accurate complete, and timely in accordance with Exhibit the time.

Government feedback from Project Managers upon review and execution of services provided.

100% receipt inspection of

CDRL.

4.8

MEETING SUPPORT

CDRL A005

Contractor presents the architecture design package and records meeting minutes and action items assigned during design reviews. Action items are tracked for closure.

Record of Meeting/Minutes are complete, accurate, and timely in accordance with Exhibit A; no revisions are required.

Standard is met 95% of the time.

Government feedback from Project Managers upon review and execution of services provided.

100% receipt inspection of

CDRL.

5.0

PROGRESS REPORTS

(5.1 Contract Status Report)

CDRL A00N

Submit a Monthly Report documenting technical progress and tracking program milestones.

Reports provided are technically accurate, complete, and timely

Standard is met 90% of the time.

Government feedback from Project Managers upon review and execution of services provided.

5.0

PROGRESS REPORTS

(5.2 Training)

CDRL A00P

Submit Training Completion Status Report and Limited Audience Training Applicability Lists.

Reports provided are technically accurate, complete, and timely

Standard is met 95% of the time.

Government feedback from Project Managers upon review and execution of services provided.

7.0

GOVERNMENT

FURNISHED PROPERTY

CDRL A00Q

The contractor shall adhere to DFARS Clause 252.245–7005 for the management and reporting of Government Property and shall use the GFP Module of the Procurement Integrated Enterprise Environment (PIEE) as specified in the clause. In addition, the Contractor shall prepare and submit a Government Property (GP) Inventory Report to capture GFP status.

Reports provided are technically accurate, complete, and timely.

Standard is met 95% of the time.

Government receipt and

CDRLs.