Material Submittals Schedule

Project Number:
MAHG22-1015Project Title:
RV Storage Aera at Oak ParkSolicitation / Contract Number:

FA301022R002

Line Number(To be completed by Project Engineer)(To be completed by Contract Administrator)
Number of Copies Required (if not electronically submitted)Remarks
Item or Description of Item, Contract Reference, Type of SubmittalCertificate of ComplianceShop DrawingsSamplesColor SelectionManufacturer's RecommendationWarranty-Manufacturer and/or WorkmanshipCatalog DataOperating InstructionsSchedules, Listings, Reports, PlansTechnical DataTest ReportsField ReportsRequired Submission DateDate Received in ContractingDate to Civil EngineeringReturn Suspense DateSubmittal NumbersDate Contractor
NotifiedContractor ResubmittalFinal Approval
ApprovedDisapproved
1HazMat Questionnaire15 Days Prior to Start DateProvide the documents as required per the Environmental packet provided by Keesler AFB.
2HazMat MSDS115 Days Prior to Start DateProvide the documents as required per the Environmental packet provided by Keesler AFB.
3Hazmat Reporting Entry Form1115 Days Prior to Start DateProvide the documents as required per the Environmental packet provided by Keesler AFB.
4Recycling and Landfill Report11End of ContractProvide the documents as required per the Environmental packet provided by Keesler AFB.
5Warranty (Manufacturer's)1End of Contract
61-Year Warranty (Contractor)1End of Contract
7Dust Control Plan15 Days Prior to Start Date
8Demolition Plan115 Days Prior to Need Date
9Existing Conditions115 Days Prior to Need Date
10Notification115 Days Prior to Need Date
11Safety Data Sheets115 Days Prior to Need Date
12Laboratory Accreditation115 Days Prior to Need Date
13Reinforcing Steel11115 Days Prior to Need Date
14Joint Sealant1115 Days Prior to Need Date
15Premolded Expansion Joint Filler115 Days Prior to Need Date
16Portland Cement115 Days Prior to Need Date
17Vapor Retarder and Vapor Barrier115 Days Prior to Need Date
18Concrete Curing Materials115 Days Prior to Need Date
19Admixtures1115 Days Prior to Need Date
20Bonding Agent1115 Days Prior to Need Date
21Ready-Mix Concrete1115 Days Prior to Need Date
22Form Release Agent115 Days Prior to Need Date
23Bonding Materials115 Days Prior to Need Date
24Mix Design115 Days Prior to Need Date
25Concrete Mix Design115 Days Prior to Need Date
26Pozzolan115 Days Prior to Need Date
27Aggregates115 Days Prior to Need Date
28Compressive Strength Tests11Immediately Follwing Install
29Air Content11Immediately Follwing Install
30Slump Tests11Immediately Follwing Install
31Concrete Curing Compound1115 Days Prior to Need Date
32Conduits and Raceways115 Days Prior to Need Date
33Wire and Cable115 Days Prior to Need Date
34Circuit Breakers115 Days Prior to Need Date
35Panelboards115 Days Prior to Need Date
36600-Volt Wiring Test1Immediately Follwing Install
37Continuity Test11Immediately Follwing Install
38Insulation Resistance Test11Immediately Follwing Install
39Manufacturer's Instructions115 Days Prior to Need Date
40Luminaires1115 Days Prior to Need Date
41Light Sources115 Days Prior to Need Date
42Photosensors115 Days Prior to Need Date
43Lighting Contactor115 Days Prior to Need Date
44Time Switch115 Days Prior to Need Date
45Luminaire Design Data115 Days Prior to Need Date
46ANSI/IES LM-79 Test Report1Immediately Follwing Install
47ANSI/IES LM-80 Test Report1Immediately Follwing Install
48ANSI/IES TM-21 Test Report1Immediately Follwing Install
49Aluminum Poles1115 Days Prior to Need Date
50Brackets And Supports1115 Days Prior to Need Date
51Anchor Bolts115 Days Prior to Need Date
52Lighting Standards115 Days Prior to Need Date
53Manufacturer's Color Charts and Chips115 Days Prior to Need Date
54Record Drawings115 Days Prior to Need Date
55Utilization of Excavated Materials115 Days Prior to Need Date
56Soil Testing11Immediately Follwing Install
57Fence Installation Drawings115 Days Prior to Need Date
58Posts115 Days Prior to Need Date
59Ornamental Fence Systems115 Days Prior to Need Date
60Swing Gates115 Days Prior to Need Date
61Gate Hardware and Accessories115 Days Prior to Need Date
62Wind Rating115 Days Prior to Need Date
63Fertilizer115 Days Prior to Need Date
64Topsoil composition tests1Immediately Follwing Install
65Sods115 Days Prior to Need Date

&"Verdana,Bold"&12Schedule of Material Submittals &12Print on Legal size paper ( 8 x 14 ).