Project Number: 1083977

Project Name: Repair Various Lift Stations

Project Location: DKGV - 1083977

Date: 2/3/2023

Activity Days

Submittal Process 75

Material Delivery 150

Mobilization 15

Sub-Total Pre-Construction Time 240

Construction Time

Sewer Lift Station 1389 Site Prep: 14

Demo: 14

Dewater 7

Construction: 30

Testing and Acceptance 3

Training 1

Sewer Lift Station 709

Site Prep: 14

Demo: 14

Dewater 7

Construction: 30

Testing and Acceptance 3

Training 1

Sewer Lift Station 730

Site Prep: 14

Demo: 14

Dewater 7

Construction: 30

Testing and Acceptance 3

Training 1

Completion

As Built Drawings 2

O&M Manuals 3

Final Cleanup and Demobilze 10

Final Acceptance 3

Sub Total Construction Time 225

Inclement Weather Days 53

Post Construction Close Out Days 45

Total Performance Time 563

Note: Days list are Calandar Days

Statement of Performance Time