Project Number: 1083977
Project Name: Repair Various Lift Stations
Project Location: DKGV - 1083977
Date: 2/3/2023
Activity Days
Submittal Process 75
Material Delivery 150
Mobilization 15
Sub-Total Pre-Construction Time 240
Construction Time
Sewer Lift Station 1389 Site Prep: 14
Demo: 14
Dewater 7
Construction: 30
Testing and Acceptance 3
Training 1
Sewer Lift Station 709
Site Prep: 14
Demo: 14
Dewater 7
Construction: 30
Testing and Acceptance 3
Training 1
Sewer Lift Station 730
Site Prep: 14
Demo: 14
Dewater 7
Construction: 30
Testing and Acceptance 3
Training 1
Completion
As Built Drawings 2
O&M Manuals 3
Final Cleanup and Demobilze 10
Final Acceptance 3
Sub Total Construction Time 225
Inclement Weather Days 53
Post Construction Close Out Days 45
Total Performance Time 563
Note: Days list are Calandar Days