This is a Statement of Work (SOW) for RV pad improvements on the Kaibab National Forest in Northern Arizona. The project encompasses the rehabilitation of 11 RV camping pads across four administrative sites: six pads at Tanglefoot Work Center in Fredonia, five pads at Tusayan Ranger Station in Grand Canyon, and optional work involving eight pads at Jacob Lake Work Center and five pads at Big Springs Work Center. Rehabilitation work includes clearing overgrown pads, subgrade preparation, new gravel placement and compaction, replacement of water and sewer connections, limited replacement of water and sewer lines, and replacement of electrical components on existing service pedestals. Optional work items include subsurface utility locating, television inspection and flow testing of septic systems, septic tank and leach field replacement, and replacement or installation of propane lines and connections for 24 RV pads.
All work must comply with the latest adopted construction codes of Coconino County and applicable national and state codes, with specific construction specifications referenced for quality control, erosion and sediment control, concrete work, earthwork, water utilities, sanitary sewerage, on-site wastewater disposal, propane piping, and electrical utilities. Key deliverables include a quality control plan (due 14 days prior to pre-work meeting), proposed construction schedule (within 10 days of Notice to Proceed), equipment mobilization notification (10 days prior to mobilization), bi-weekly status reports (every Friday by 5:00 PM AZ time), manufacturers' literature prior to material procurement, material gradation documentation, concrete admixture designs (72 hours prior to placement), and as-built drawings upon contract completion. Contractor scheduling is restricted at Tanglefoot and Jacob Lake Work Centers between April 15 and October 31, and a minimum of four combined RV pads must remain operational during construction. No government-furnished materials are provided, though contractors may use electricity and limited water at all sites.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
US Department of Agriculture (USDA)
Region 3 Arizona Kaibab National Forest North Kaibab Ranger District & Tusayan Ranger District RV Pad Improvements Statement of Work
Contents
| Project | 3 |
| General Information | 3 |
| 1.0 Scope of Work | 3 |
| 2.0 Background | 3 |
| Contractor Requirements | 3 |
| 3.0 Technical Requirements / Tasks | 3 |
| 4.0 Government Furnished | 4 |
| 5.0 Deliverables / Schedule / Submittals | 4 |
| 6.0 Travel | 4 |
| 7.0 Contractor’s Key Personnel | 5 |
| 8.0 Security Requirements | 5 |
| 9.0 Data Rights | 5 |
| 10.0 Section 508 – Electronic and Information Technology Standards | 5 |
| Attachment | 5 |
Project Kaibab National Forest RV Pad Improvements
General Information
1.0 Scope of Work
This project will consist of the rehabilitation of 11 RV camping pads, six (6) at the Tanglefoot Work Center and five (5) at Tusayan Ranger Station. Pad rehabilitation consists of clearing overgrown pads; subgrade preparation, new gravel placement and compaction for parking pads; replacement of water and sewer connections; limited replacement of water and sewer lines; and replacement of electrical components on existing electrical service pedestals. This project also includes optional work items for the rehabilitation of an additional 13 RV pads, eight (8) at Jacob Lake Work Center and five (5) at Big Springs Work Center; subsurface utility locating; television inspection, and flow testing of an existing septic system; replacement of septic tank and leach field; replacement or installation of propane lines and connections for 24 RV pads; and additional water and sewer line replacement.
2.0 Background
The project will be located on the Kaibab National Forest at four different administrative sites. Tanglefoot Work Center, located in Fredonia, Arizona; Jacob Lake Work Center near Jacob Lake, Arizona; and Big Springs Work Center, approximately 15 miles south of Jacob Lake, are located on the North Kaibab Ranger District. The Tusayan Ranger Station, on the Tusayan Ranger District, is in Grand Canyon, Arizona. RV pads are existing at the Tanglefoot WC, Tusayan RD complex, and Jacob Lake WC and require utility upgrades. Big Springs WC has three existing pads with the need for two additional pads and utility extensions. Big Springs WC includes a rental cabin area that the public may be utilizing during the project.
Contractor Requirements
3.0 Technical Requirements / Tasks
All components included for rehabilitation shall meet standards of the latest adopted construction code of Coconino County and all applicable national and state codes. Specific tasks include the following:
A. RV Pad Rehabilitation/Construction B. Pad Layout C. Clearing D. Water Connection E. Sewer Connection F. Electrical Pedestal G. Carsonite Markers H. Water Line I. Sewer Line J. Electrical Line K. Existing Septic System – Locate – Optional L. Existing Septic System – Television Inspection – Optional M. Existing Septic System – Water Test – Optional N. Replace Septic Tank – Optional O. Replace Septic Drain Field – Optional P. Water Meters – Optional Q. Propane Line – Optional R. Propane Connection – Optional
Applicable Construction Specifications include:
A. Section 014500 – Quality Control B. Section 015713 – Temporary Erosion and Sediment Control C. Section 016600 – Product Storage and Handling Requirements D. Section 017113 – Mobilization E. Section 017400 – Cleaning and Waste Management F. Section 031100 – Concrete Forming G. Section 033000 – Cast-in-Place Concrete H. Section 033500 – Concrete Finishing I. Section 310000 – Earthwork J. Section 321500 – Aggregate Surfacing K. Section 331000 – Water Utilities L. Section 333000 – Sanitary Sewerage M. Section 333400 – On-Site Wastewater Disposal N. Section 335200 – Propane Piping O. Section 337000 – Electrical Utilities
4.0 Government Furnished
There are no government furnished items in this project. Contractor shall be allowed to use the electricity and limited water at all sites.
No restrictions are placed on weekend work. No restrictions are placed on Contractor’s schedule at Big Springs WC and Tusayan RS.
Contractor’s schedule shall be restricted at Tanglefoot Work Center and Jacob Lake Work Center between April 15 – October 31. A combined total of 4 RV pads must be available for full operation (either in existing conditions or fully rehabilitated; excluding T4 and T5 at Jacob Lake WC in existing condition) between Tanglefoot WC and Jacob Lake WC.
Weather normally starts impacting the road and ground conditions in mid-November, which can limit access to all sites. Road conditions generally improve mid-March.
5.0 Deliverables / Schedule / Submittals
5.1 Submittals
A. Interested bidders for this contract shall include in their bid submittal the contract Schedule of Items with a cost filled out for every bid item (including OPTION items), a list of previous projects (minimum 3) with similar qualities that the bidder had direct responsibility for, and a list of any technical experience and qualifications relevant to the work contained in this specification.
B. Contractor shall submit a digital copy of the proposed construction schedule within 10 days of receiving Notice to Proceed (NTP). Schedule shall indicate planned dates for site mobilization, construction start, and construction completion for each work site.
C. Contractor shall provide digital copies of manufacturers’ literature for all construction materials and equipment that indicate conformance with this specification document. Government is not responsible for costs incurred by Contractor for purchase of unapproved materials.
D. Contractor shall provide digital copies of reports and other deliverables as required by these specifications, in a timely manner.
E. As-Built Drawings shall be provided that show offset dimensions of all buried utility and service lines upon completion of work and prior to contract close out. As-Builts may be hand-drawn and schematic in nature but must accurately and clearly depict actual conditions found in field.
5.2 Key Deliverables
| Item No. |
| Deliverable |
| Applicable Specification |
| Due |
| 1 |
| Quality Control Plan |
| Section 014500 – Quality Control |
| 14-days prior to pre-work meeting |
| 2 |
| Proposed Construction Schedule |
| Section 011100 – Summary of Work |
| Within 10 days of receiving Notice to Proceed (NTP) |
| 3 |
| Equipment Mobilization Notification |
| Section 017113 – Mobilization |
| 10-days prior to mobilizing or delivering materials/equipment onto Kaibab NF |
| 4 |
| Bi-Weekly Status Report |
| See “Reporting Requirements” below |
| Bi-weekly, every Friday, by 5:00 PM AZ time until the contract expires |
| 5 |
| Manufacturers’ Literature/Product Information |
| Section 011100 – Summary of Work; Section 331000 – Water Utilities; Section 333400 – On-Site Wastewater Disposal; Section 335200 – Propane Piping; Section 337000 – Electrical Utilities |
| Prior to procurement of materials/equipment |
| 6 |
| Material Gradation |
| Section 310000 – Earthwork; Section 321500 – Aggregate Surfacing |
| Prior to procurement of materials |
| 7 |
| Admixture Design(s) |
| Section 033000 – Cast-in-Place Concrete |
| 72-hours prior to concrete placement |
| 8 |
| As-Built Drawings |
| Section 014500 – Quality Control |
| Upon completion of contract work |
5.3 Reporting Requirements: Contractor is required to provide written progress reports bi-weekly for duration of the project. Progress reports must be submitted in writing (i.e. email, text) to the COR. The progress report shall cover all work completed during the specified period and shall present the work to be accomplished during the subsequent period. This report shall also identify any problems that arose and a statement explaining how the problem was resolved. This report shall also identify any problems that have arisen but have not been completely resolved and provide an explanation.
6.0 Travel
Tanglefoot Work Center: From the North Kaibab Ranger District Office (430 S MAIN ST, FREDONIA, AZ 86022), head southeast on US-89A S/S MAIN ST toward MAURICE AVE. After 0.6 miles, Tanglefoot Work Center will be on the left. The complex is approximately 0.25 miles from the turnoff (LAT: 36.940778, LONG: -112.514777).
Tusayan Ranger Station: 176 LINCOLN LOG LOOP, GRAND CANYON, AZ 86023 (LAT: 35.989695, LONG: -112.120923).
Jacob Lake Work Center: From Jacob Lake, head south on AZ-87/GRAND CANYON HWY for 0.3 miles. Turn right onto NFSR 461. Jacob Lake Work Center will be on the left about 0.4 miles down NFSR 461 (LAT: 36.707778, LONG: -112.223783).
Big Springs Work Center: From Jacob Lake, head south on AZ-87/GRAND CANYON HWY and turn right after 0.3 miles. Follow NFSR 461 for 5.3 miles to the intersection with NFSR 462 and turn right. Continue west for 3.2 miles on NFSR 462. Turn left onto NFSR 22/WEST SIDE RD for 6.7 miles. Big Springs Work Center will be on the left (LAT: 36.601700, LONG: -112.350000).
7.0 Contractor’s Key Personnel
Contractor’s Representative.
8.0 Security Requirements
N/A
9.0 Data Rights
N/A
10.0 Section 508 – Electronic and Information Technology Standards N/A image1.png