This document is a project specifications file for the High Sierra Demo - Admin and Rec Facilities Rehab project for the USDA Forest Service, located at the High Sierra Visitor Information Station on Kaiser Pass Road.
The specifications establish comprehensive requirements for demolition and construction waste management. Contractors must submit a waste management plan within 7 days of the Notice to Proceed, detailing waste identification, reduction strategies, and cost/revenue analysis using consistent units of measurement. Waste reduction progress reports using Form CWM-8 must accompany each Application for Payment, including generation points and total waste quantities in tons. The contractor must implement salvage and recycling operations for non-hazardous demolition waste, with demolition waste becoming contractor property unless otherwise specified. Historic items, relics, antiques, and similar objects discovered during demolition remain owner property and must be carefully salvaged and promptly returned. Landfill and incinerator disposal records with manifests, weight tickets, receipts, and invoices are required for verification.
Demolition procedures require compliance with applicable codes and EPA regulations, with hazardous materials discovery triggering work stoppage and COR notification. Contractors must perform demolition to maximize salvage and recycling, obtain required permits, prevent catastrophic collapses, and minimize dust production. Debris must be removed from Forest Service lands and disposed off-site. Below-grade construction within the footprint of new construction and 5 feet outside must be demolished to 12 inches below grade and filled with satisfactory soil materials. Site restoration includes filling voids with on-site subsoil free of lumps larger than 3 inches and rocks larger than 2 inches, with slopes grading away from buildings at minimum 2 inches per 10 feet.
View the file
Other files
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SECTION 000101
High Sierra Demo - Admin and Rec Facilities Rehab 000101 - 1 Project Title Page
PROJECT TITLE PAGE
PROJECT SPECIFICATIONS FOR
HIGH SIERRA DEMO - ADMIN AND REC FACILITIES REHAB USDA FOREST SERVICE
HIGH SIERRA VISITOR INFORMATION STATION, KAISER PASS RD
END OF SECTION
SECTION 000110
Rec Facilities Rehab 000110 - 1 Table of Contents
TABLE OF CONTENTS
PROCUREMENT AND CONTRACTING REQUIREMENTS
1.01 DIVISION 00 -- PROCUREMENT AND CONTRACTING REQUIREMENTS
A. 000101 - Project Title Page B. 000110 - Table of Contents
SPECIFICATIONS
2.01 DIVISION 01 -- GENERAL REQUIREMENTS
A. 017419 - Construction Waste Management and Disposal
2.02 DIVISION 02 –EXISTING CONDITIONS
A. 024100 - - Demolition B. 024116 - - Structure Demolition
2.03 DIVISION 03 -- CONCRETE
2.04 DIVISION 04 -- MASONRY
2.05 DIVISION 05 -- METALS
2.06 DIVISION 06 -- WOOD, PLASTICS, AND COMPOSITES
2.07 DIVISION 07 -- THERMAL AND MOISTURE PROTECTION
2.08 DIVISION 08 -- OPENINGS
2.09 DIVISION 09 -- FINISHES
2.10 DIVISION 10 -- SPECIALTIES
2.11 DIVISION 11 -- EQUIPMENT
2.12 DIVISION 12 -- FURNISHINGS
2.13 DIVISION 13 -- SPECIAL CONSTRUCTION
2.14 DIVISION 14 -- CONVEYING EQUIPMENT
2.15 DIVISION 21 -- FIRE SUPPRESSION
2.16 DIVISION 22 -- PLUMBING
2.17 DIVISION 23 -- HEATING, VENTILATING, AND AIR-CONDITIONING (HVAC)
2.18 DIVISION 25 -- INTEGRATED AUTOMATION
2.19 DIVISION 26 -- ELECTRICAL
2.20 DIVISION 27 -- COMMUNICATIONS
2.21 DIVISION 28 -- ELECTRONIC SAFETY AND SECURITY
2.22 DIVISION 31 -- EARTHWORK
A. 312323 -- Fill
2.23 DIVISION 32 -- EXTERIOR IMPROVEMENTS
2.24 DIVISION 33 -- UTILITIES
2.25 DIVISION 34 -- TRANSPORTATION
2.26 DIVISION 40 -- PROCESS INTEGRATION
2.27 DIVISION 46 -- WATER AND WASTEWATER EQUIPMENT
CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL 017419 - 1
Copyright © 2022 by the American Institute of Architects. Warning: This AIA MasterSpec based document is protected by U.S. Copyright Law and International Treaties. A valid, current MasterSpec license is required for editing or use of this document.
SECTION 017419
SECTION 017419 - CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section.
1.2 SUMMARY
A. Section includes administrative and procedural requirements for the following:
1. Salvaging non-hazardous demolition waste.
2. Recycling non-hazardous demolition waste.
3. Disposing of non-hazardous demolition waste.
1.3 DEFINITIONS
A. Construction Waste: Building, structure, and site improvement materials and other solid waste resulting from construction, remodeling, renovation, or repair operations. Construction waste includes packaging.
B. Demolition Waste: Building, structure, and site improvement materials resulting from demolition operations.
C. Disposal: Removal of demolition or construction waste and subsequent salvage, sale, recycling, or deposit in landfill, incinerator acceptable to authorities having jurisdiction, or designated spoil areas on Owner’s property.
D. Recycle: Recovery of demolition or construction waste for subsequent processing in preparation for reuse.
1.4 MATERIALS OWNERSHIP
A. Unless otherwise indicated, demolition and construction waste becomes property of Contractor.
B. Historic items, relics, antiques, and similar objects including, but not limited to, cornerstones and their contents, commemorative plaques and tablets, and other items of interest or value to Owner that may be uncovered during demolition remain the property of Owner.
1. Carefully salvage in a manner to prevent damage and promptly return to Owner.
CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL 017419 - 2
Copyright © 2022 by the American Institute of Architects. Warning: This AIA MasterSpec based document is protected by U.S. Copyright Law and International
1.5 ACTION SUBMITTALS
A. Waste Management Plan: Submit plan within 7 days of date established for the Notice to Proceed.
1.6 INFORMATIONAL SUBMITTALS
A. Waste Reduction Progress Reports: Concurrent with each Application for Payment, submit report.
Use Form CWM-8 for demolition waste. Include the following information:
1. Generation points of waste.
2. Total quantity of waste in tons (tonnes).
B. Landfill and Incinerator Disposal Records: Indicate receipt and acceptance of waste by landfills and incinerator facilities licensed to accept them. Include manifests, weight tickets, receipts, and invoices.
1.7 QUALITY ASSURANCE
A. Waste Management Conference(s): Conduct conference(s) at Project site to comply with requirements in Section 013100 "Project Management and Coordination." Review methods and procedures related to waste management including, but not limited to, the following:
1. Review procedures for periodic waste collection and transportation to recycling and disposal facilities.
1.8 WASTE MANAGEMENT PLAN
A. General: Develop a waste management plan according to requirements in this Section. Plan shall consist of waste identification, waste reduction work plan, and cost/revenue analysis. Indicate quantities by weight or volume but use same units of measure throughout waste management plan.
B. Waste Identification: Indicate anticipated types and quantities of demolition and site-clearing waste generated by the Work. Use Form CWM-2 for demolition waste. Include estimated quantities and assumptions for estimates.
PART 2 - PRODUCTS
PART 3 - EXECUTION
3.1 PLAN IMPLEMENTATION
A. General: Implement approved waste management plan. Provide handling, containers, storage, signage, transportation, and other items as required to implement waste management plan during the entire duration of the Contract.
1. Comply with operation, termination, and removal requirements in Section 015000 "Temporary Facilities and Controls."
CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL 017419 - 3
Copyright © 2022 by the American Institute of Architects. Warning: This AIA MasterSpec based document is protected by U.S. Copyright Law and International
3.2 DISPOSAL OF WASTE
A. General: Except for items or materials to be salvaged or recycled, remove waste materials from Project site and legally dispose of them in a landfill or incinerator acceptable to authorities having jurisdiction.
1. Except as otherwise specified, do not allow waste materials that are to be disposed of accumulate on-site.
2. Remove and transport debris in a manner that will prevent spillage on adjacent surfaces and areas.
B. General: Except for items or materials to be salvaged or recycled, remove waste materials and legally dispose of at designated spoil areas on Owner’s property.
C. Burning: Do not burn waste materials.
END OF SECTION 017419
STRUCTURE DEMOLITION 024116 - 1
Copyright © 2022 by the American Institute of Architects. Warning: This AIA MasterSpec based document is protected by U.S. Copyright Law and International
SECTION 024100
DEMOLITION
PART 2 PRODUCTS
1.01 MATERIALS
A. Fill Material: See Section 312323.
PART 3 EXECUTION
2.01 GENERAL PROCEDURES AND PROJECT CONDITIONS
A. Comply with applicable codes and regulations for demolition operations and safety of adjacent structures and the public.
1. Obtain required permits.
2. Take precautions to prevent catastrophic or uncontrolled collapse of structures to be removed; do not allow worker or public access within range of potential collapse of unstable structures.
3. Provide, erect, and maintain temporary barriers and security devices.
B. Do not begin removal until built elements to be salvaged or relocated have been removed.
C. Minimize production of dust due to demolition operations. Do not use water if that will result in ice, flooding, sedimentation of public waterways or storm sewers, or other pollution.
D. Hazardous Materials:
1. If hazardous materials are discovered during removal operations, stop work and notify COR; hazardous materials include regulated asbestos containing materials, lead, PCBs, and mercury.
2. Hazardous Materials: Comply with 29 CFR 1926 and state and local regulations.
E. Perform demolition in a manner that maximizes salvage and recycling of materials.
2.02 DEBRIS AND WASTE REMOVAL
A. Remove debris, junk, and trash from site. Dispose off of Forest Service lands
STRUCTURE DEMOLITION 024116 - 2
Copyright © 2022 by the American Institute of Architects. Warning: This AIA MasterSpec based document is protected by U.S. Copyright Law and International
SECTION 024116 - STRUCTURE DEMOLITION
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. Demolition and removal of buildings and site improvements.
2. Removing below-grade construction.
3. Disconnecting, capping or sealing, and removing site utilities.
4. Salvaging items for reuse by Owner.
B. Related Requirements:
1. Section 013200 "Construction Progress Documentation" for preconstruction photographs taken before building demolition.
2. Section 311000 "Site Clearing" for site clearing and removal of above- and below-grade site improvements not part of building demolition.
1.2 DEFINITIONS
A. Remove and Salvage: Detach items from existing construction, in a manner to prevent damage, and deliver to Owner ready for reuse.
1.3 MATERIALS OWNERSHIP
A. Unless otherwise indicated, demolition waste becomes property of Contractor.
B. Historic items, relics, antiques, and similar objects including, but not limited to, cornerstones and their contents, commemorative plaques and tablets, and other items of interest or value to Owner that may be uncovered during demolition remain the property of Owner.
1. Carefully salvage in a manner to prevent damage and promptly return to Owner.
1.4 PREINSTALLATION MEETINGS
A. Pre-demolition Conference: Conduct conference at Project site.
1. Inspect and discuss condition of construction to be demolished.
2. Review structural load limitations of existing structures.
3. Review and finalize building demolition schedule and verify availability of demolition personnel, equipment, and facilities needed to make progress and avoid delays.
4. Review and finalize protection requirements.
5. Review procedures for noise control and dust control.
6. Review procedures for protection of adjacent buildings.
7. Review items to be salvaged and returned to Owner.
STRUCTURE DEMOLITION 024116 - 3
Copyright © 2022 by the American Institute of Architects. Warning: This AIA MasterSpec based document is protected by U.S. Copyright Law and International
1.5 INFORMATIONAL SUBMITTALS
A. Proposed Protection Measures: Submit report, including Drawings, that indicates the measures proposed for protecting individuals and property, for environmental protection, for dust control and, for noise control. Indicate proposed locations and construction of barriers.
1. Adjacent Buildings: Detail special measures proposed to protect adjacent buildings to remain including means of egress from those buildings.
B. Schedule of Building Demolition Activities: Indicate the following:
1. Detailed sequence of demolition work, with starting and ending dates for each activity.
2. Shutoff and capping of utility services.
C. Pre-demolition Photographs or Video: Show existing conditions of adjoining construction and site improvements, including finish surfaces, that might be misconstrued as damage caused by salvage and demolition operations. Comply with Section 013233 "Photographic Documentation."
Submit before the Work begins.
D. According to the EPA (Environmental Protection Agency) Under the Lead Renovation, Repair, and Painting Rule, contractors who renovate or partially demolish pre-1978 residential buildings must be lead-safe certified by EPA and use lead-safe practices. This rule does not apply to total demolition of a structure. However, we recommend testing for lead base paints and using lead-safe practices during total demolition activities. Submit test results before work begins.
1.6 CLOSEOUT SUBMITTALS
A. Inventory: Submit a list of items that have been removed and salvaged.
1.7 QUALITY ASSURANCE
1.8 FIELD CONDITIONS
A. Buildings to be demolished will be vacated and their use discontinued before start of the Work.
B. Buildings immediately adjacent to demolition area will be occupied. Conduct building demolition so operations of occupied buildings will not be disrupted.
1. Provide not less than 72 hours' notice of activities that will affect operations of adjacent occupied buildings.
2. Maintain access to existing walkways, exits, and other facilities used by occupants of adjacent buildings.
C. Conditions existing at time of inspection for bidding purpose will be maintained by Owner as far as practical.
D. Hazardous Materials: It is not expected that hazardous materials will be encountered in the work.
1. If lead based paint is encountered, Certificates of training for the removal of lead base paints from all personnel who will be performing the work under this contract shall be
STRUCTURE DEMOLITION 024116 - 4
Copyright © 2022 by the American Institute of Architects. Warning: This AIA MasterSpec based document is protected by U.S. Copyright Law and International submitted to the U.S. Forest Service. A detailed plan for removal of lead paint and execution of proper protective equipment (PPE) is to be submitted. Contractors will adhere to OSHA regulation CFR 1910.1200 and 1910.1025.
2. If animal waste is encountered. Removing animal waste from a California demolition site requires strict adherence to OSHA worker safety regulations and state/local solid waste management codes. Because animal waste can carry zoonotic diseases (like Hantavirus or Salmonella) and release hazardous dust, proper site control and waste handling protocols are mandatory.
E. On-site storage or sale of removed items or materials is not permitted.
1.9 COORDINATION
A. Arrange demolition schedule so as not to interfere with Owner's on-site operations.
PART 2 - PRODUCTS
2.1 PERFORMANCE REQUIREMENTS
A. Regulatory Requirements: Comply with governing EPA notification regulations before beginning demolition. Comply with hauling and disposal regulations of authorities having jurisdiction.
B. Standards: Comply with ANSI/ASSP A10.6 and NFPA 241.
2.2
SOIL MATERIALS
A. Satisfactory Soils: Comply with requirements in Section 312000 "Earth Moving."
PART 3 - EXECUTION
3.2 EXAMINATION
A. Verify that utilities have been disconnected and capped before starting demolition operations.
B. Review Project Record Documents of existing construction or other existing condition and hazardous material information provided by Owner. Owner does not guarantee that existing conditions are same as those indicated in Project Record Documents.
C. Verify that hazardous materials have been remediated before proceeding with building demolition operations.
D. Inventory and record the condition of items to be removed and salvaged.
STRUCTURE DEMOLITION 024116 - 5
Copyright © 2022 by the American Institute of Architects. Warning: This AIA MasterSpec based document is protected by U.S. Copyright Law and International
3.3 PREPARATION
A. Salvaged Items: Comply with the following:
1. Store items in a secure area until delivery to Owner.
2. Transport items to storage area designated by Owner.
3. Protect items from damage during transport and storage.
3.4 UTILITY SERVICES AND MECHANICAL/ELECTRICAL SYSTEMS
A. Existing Utilities to Be Disconnected: Locate, identify, disconnect, and seal or cap off utilities serving buildings and structures to be demolished.
1. Owner will arrange to shut off utilities when requested by Contractor.
2. If removal, relocation, or abandonment of utility services affect adjacent occupied buildings, then provide temporary utilities that bypass buildings and structures to be demolished and that maintain continuity of service to other buildings and structures.
3. Cut off pipe or conduit a minimum of 24 inches (610 mm) below grade. Cap, valve, or plug and seal remaining portion of pipe or conduit after bypassing according to requirements of authorities having jurisdiction.
4. Do not start demolition work until utility disconnecting and sealing have been completed and verified in writing.
3.5 PROTECTION
A. Existing Facilities: Protect adjacent walkways, loading docks, building entries, and other building facilities during demolition operations. Maintain exits from existing buildings.
B. Temporary Shoring: Provide and maintain interior and exterior shoring, bracing, or structural support to preserve stability and prevent unexpected movement or collapse of construction being demolished.
1. Strengthen or add new support when required during progress of demolition.
2. Do not interrupt existing utilities serving adjacent occupied or operating facilities unless authorized in writing by Owner and authorities having jurisdiction.
3. Provide temporary services during interruptions to existing utilities, as acceptable to Owner and authorities having jurisdiction.
a. Provide at least 72 hours' notice to occupants of affected buildings if shutdown of service is required during changeover.
C. Temporary Protection: Erect temporary protection, such as walks, fences, railings, canopies, and covered passageways, where required by authorities having jurisdiction and as indicated. Comply with requirements in Section 015000 "Temporary Facilities and Controls."
1. Protect adjacent buildings and facilities from damage due to demolition activities.
2. Protect existing site improvements, appurtenances, and landscaping to remain.
3. Provide temporary barricades and other protection required to prevent injury to people and damage to adjacent buildings and facilities to remain.
STRUCTURE DEMOLITION 024116 - 6
Copyright © 2022 by the American Institute of Architects. Warning: This AIA MasterSpec based document is protected by U.S. Copyright Law and International
4. Provide protection to ensure safe passage of people around building demolition area and to and from occupied portions of adjacent buildings and structures.
D. Remove temporary barriers and protections where hazards no longer exist. Where open excavations or other hazardous conditions remain, leave temporary barriers and protections in place.
3.6 DEMOLITION, GENERAL
A. General: Demolish indicated buildings completely. Use methods required to complete the work within limitations of governing regulations and as follows:
1. Do not use cutting torches until work area is cleared of flammable materials. Maintain portable fire-suppression devices during flame-cutting operations.
2. Maintain fire watch during and for at least 2 hours after flame-cutting operations.
3. Maintain adequate ventilation when using cutting torches.
4. Locate building demolition equipment and remove debris and materials so as not to impose excessive loads on supporting walls, floors, or framing.
B. Site Access and Temporary Controls: Conduct building demolition and debris-removal operations to ensure minimum interference with roads, streets, walkways, and other adjacent occupied and used facilities.
1. Do not close or obstruct streets, walks, walkways, or other adjacent occupied or used facilities without permission from Owner and authorities having jurisdiction. Provide alternate routes around closed or obstructed trafficways if required by authorities having jurisdiction.
2. Use water mist and other suitable methods to limit spread of dust and dirt. Comply with governing environmental-protection regulations. Do not use water when it may damage adjacent construction or create hazardous or objectionable conditions, such as ice, flooding, and pollution.
3.7 DEMOLITION BY MECHANICAL MEANS
A. Proceed with demolition of structural framing members systematically, from higher to lower level. Complete building demolition operations above each floor or tier before disturbing supporting members on the next lower level.
B. Below-Grade Construction: Demolish foundation walls and other below-grade construction that are within footprint of new construction and extending 5 feet (1.5 m) outside footprint indicated for new construction. Abandon below-grade construction outside this area.
1. Remove below-grade construction, including basements, foundation walls, and footings, completely to at least 12 inches (300 mm) below grade.
C. Existing Utilities: Demolish existing utilities and below-grade utility structures that are within 5 feet (1.5 m) outside footprint indicated for new construction. Abandon utilities outside this area.
STRUCTURE DEMOLITION 024116 - 7
Copyright © 2022 by the American Institute of Architects. Warning: This AIA MasterSpec based document is protected by U.S. Copyright Law and International
1. Fill abandoned utility structures with satisfactory soil materials according to backfill requirements in Section 312000 "Earth Moving."
D. Existing Utilities: Demolish and remove existing utilities and below-grade utility structures.
3.8 SITE RESTORATION
A. Below-Grade Areas: Completely fill below-grade areas and voids resulting from building demolition operations with satisfactory soil materials according to backfill requirements in Section 312000 "Earth Moving."
B. Site Grading: Uniformly rough grade area of demolished construction to a smooth surface, free from irregular surface changes. Provide a smooth transition between adjacent existing grades and new grades.
3.9 REPAIRS
A. Promptly repair damage to adjacent buildings caused by demolition operations.
3.10 DISPOSAL OF DEMOLISHED MATERIALS
A. Remove waste of demolition materials from Project site [and dispose of them in an EPA-approved construction and demolition waste landfill acceptable to authorities having jurisdiction. and recycle or dispose of them according to Section 017419 "Construction Waste Management and Disposal."
1. Do not allow demolished materials to accumulate on-site.
2. Remove and transport debris in a manner that will prevent spillage on adjacent surfaces and areas.
B. Do not burn demolished materials.
3.11 CLEANING
A. Clean adjacent structures and improvements of dust, dirt, and debris caused by building demolition operations. Return adjacent areas to condition existing before building demolition operations began.
1. Clean roadways of debris caused by debris transport.
END OF SECTION 024116
SECTION 312323
Rec Facilities Rehab 312323 - 1 Fill
FILL
PART 2 PRODUCTS
1.01 FILL MATERIALS
A. General Fill: Subsoil excavated on-site.
1. Free of lumps larger than 3 inches, rocks larger than 2 inches, and debris.
PART 3 EXECUTION
2.01 FILLING
A. Fill to contours and elevations indicated using unfrozen materials.
B. Employ a placement method that does not disturb or damage other work.
C. Systematically fill to allow maximum time for natural settlement. Do not fill over porous, wet, frozen or spongy subgrade surfaces.
D. Maintain optimum moisture content of fill materials to attain required compaction density.
E. Slope grade away from building minimum 2 inches in 10 feet, unless noted otherwise. Make gradual grade changes. Blend slope into level areas.
F. Correct areas that are over-excavated.
G. Compaction Density Unless Otherwise Specified or Indicated:
H. Reshape and re-compact fills subjected to vehicular traffic.
I. Maintain temporary means and methods, as required, to remove all water while fill is being placed as required, or until directed by the COR. Remove and replace soils deemed unsuitable by classification and which are excessively moist due to lack of dewatering or surface water control.
| SECTION 017419 - CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL PART 1 - GENERAL |
| 1.2 SUMMARY |
| 1.3 DEFINITIONS |
| 1.4 MATERIALS OWNERSHIP |
| 1.5 ACTION SUBMITTALS |
| 1.6 INFORMATIONAL SUBMITTALS |
| 1.7 QUALITY ASSURANCE |
| 1.8 WASTE MANAGEMENT PLAN |
| PART 2 - PRODUCTS PART 3 - EXECUTION |
| 3.2 DISPOSAL OF WASTE |
| 1.2 DEFINITIONS |
| 1.3 MATERIALS OWNERSHIP |
| 1.4 PREINSTALLATION MEETINGS |
| 1.5 INFORMATIONAL SUBMITTALS |
| 1.6 CLOSEOUT SUBMITTALS |
| 1.7 QUALITY ASSURANCE |
| 1.9 COORDINATION |
| 3.3 PREPARATION |
| 3.4 UTILITY SERVICES AND MECHANICAL/ELECTRICAL SYSTEMS |
| 3.5 PROTECTION |
| 3.6 DEMOLITION, GENERAL |
| 3.7 DEMOLITION BY MECHANICAL MEANS |
| 3.8 SITE RESTORATION |
| 3.9 REPAIRS |
| 3.10 DISPOSAL OF DEMOLISHED MATERIALS |
| 3.11 CLEANING |
| END OF SECTION 024116 |