Attachment 3 - SOW Fernan lift station.pdf
PDF 2 MB Posted
- Solicitation number
- 1240LU26Q0125
About this file
This is a Statement of Work (SOW) for the Fernan Sewage Lift Station Electrical Repair project issued by the US Department of Agriculture (USDA). The project addresses critical safety hazards in an underground vault containing two Unimount electric motors that power lift station pumps at the Fernan Ranger Station, which serves as the Coeur d'Alene River Ranger District's main office.
The contractor must complete three primary tasks within thirty (30) business days of notice to proceed: (1) Replace the corroded disconnect switch, circuit breaker, and distribution block with corrosion-resistant, water-resistant replacements; (2) Protect exposed power cables by replacing worn or damaged cables, installing a waterproof covering at the point of penetration, and placing all exposed cables into waterproof conduit; and (3) Replace the existing A19 light fixture with a low-profile, hard-wired LED fixture and install an easily accessible switch at the vault entry point. All personnel must hold required licensing for their assigned tasks. Travel expenses must be included in the contractor's quote. The government will not furnish any materials or equipment. No security requirements, data rights considerations, or Section 508 accessibility standards apply to this contract. Reference photographs of the current conditions, including corroded distribution panels, exposed cables on the floor, and the existing light fixture, are included as attachments to illustrate the work scope.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
US Department of Agriculture (USDA)
Statement of Work
Contents Project General Information
1.0 Scope of Work
2.0 Background
Contractor Requirements
3.0 Technical Requirements / Tasks
4.0 Government Furnished
5.0 Deliverables / Schedule
6.0 Travel
7.0 Contractor’s Key Personnel
8.0 Security Requirements
9.0 Data Rights
10.0 Section 508 – Electronic and Information Technology Standards Attachment
Project Fernan Sewage Lift Station Electrical Repair
General Information
1.0 Scope of Work
The electrical infrastructure powering the two Unimount electric motors (see Pump Label 1 photo for specifications) that drive the lift station pumps presents several dangerous safety hazards to the service technicians who perform routine maintenance and monitoring. The hazards identified are as follows:
Corroded Disconnect and Breaker Components: The damp environment within the vault has corroded the connections and wires in the breaker box and disconnect switch. This presents several unsafe conditions and adds unnecessary wearing to the electrical motors that operate the pumps.
Exposed Power Cables on Floor: The unsecured power cables that come into the vault from the floor present a tripping hazard and are exposed to damage from foot traffic. To protect the cables and technicians, the point of penetration must be secured and the cables protected in a conduit rated for a damp environment.
Damaged light Fixture: The existing light fixture uses an A19 lightbulb that, due to the cramped conditions of the vault, presents a risk of being struck by a technician’s head while performing service on the lift station system. As a light source is necessary in the space to insure the safety of technicians, a low-profile light fixture is needed
To compound these hazards, the underground vault that they are contained in is cramped with machinery, minimal access to natural light, and often has standing water on the floor, increasing the chances of accidental electrocution. To mitigate these hazards, the exposed cable will need to be replaced and contained within waterproof conduit, the damaged light fixture will need to be replaced with a low-profile light fixture, and the corroded disconnect and circuit breaker box will need to be replaced with new equipment appropriate for the damp environment.
2.0 Background
The Fernan Ranger Station Serves as the Coeur d’Alene River Ranger Districts main office as well as houses a majority of the district’s specialist resource shops. During the busy summer season, the district supports approximately 90 employees and frequently has outside visiting crews utilizing the facilities.
Contractor Requirements
3.0 Technical Requirements / Tasks
-Replace Disconnect Switch and Breakers:
-Remove all components displaying signs of corrosion, including, but not limited, to the disconnect switch, circuit breaker, and distribution block.
-Install corrosion resistant replacements.
-Protect Exposed Cables:
-Replace any worn or damaged cables.
-Install a protective, waterproof covering at the point of penetration.
-Place all exposed cable into waterproof conduit.
-Replace Light Fixture:
-Remove current light fixture.
-Install low-profile, hard wired LED fixture.
-Install a switch in an easily accessible location from the entry point of the vault.
4.0 Government Furnished
NA
5.0 Deliverables / Schedule
Key Deliverables Item No. Deliverable Objective Due 1 Replace Disconnect
Switch and Breakers Remove corroded disconnect switch and components of the breaker box and install new water resist replacements
No later than thirty (30) business days after notice to proceed
2 Protect Exposed Cables Replace compromised cable, install junction box and metal conduit to protect cables.
No later than thirty (30) business days after notice to proceed
3 Replace Light Fixture Replace existing light fixture with a low profile, LED fixture.
No later than thirty (30) business days after notice to proceed
6.0 Travel
Any travel expenses should be included in the quote.
7.0 Contractor’s Key Personnel
All personnel working on this project must hold the required licensing for the tasks they are performing.
8.0 Security Requirements
NA
9.0 Data Rights
NA
10.0 Section 508 – Electronic and Information Technology Standards
NA
Attachments below are photos of existing conditions
Distribution panel and Breakers
Cables
Motor Label
Pump Label
Shutoff
Light Fixture
View from vault entry
| Project |
| General Information |
| 1.0 Scope of Work |
| 2.0 Background |
| Contractor Requirements |
| 3.0 Technical Requirements / Tasks |
| 4.0 Government Furnished |
| 5.0 Deliverables / Schedule |
| 6.0 Travel |
| 7.0 Contractor’s Key Personnel |
| 8.0 Security Requirements |
| 9.0 Data Rights |
| 10.0 Section 508 – Electronic and Information Technology Standards |
| Attachment |
File details come from the government source that posted it. Updated .