This is a Statement of Work (SOW) for the Blackjack Campground Renovation project managed by the U.S. Forest Service Southwest Region 03, Apache-Sitgreaves National Forest, dated August 27, 2025.

The contractor shall furnish all supervision, materials, equipment, vehicles, tools, parts, labor, transportation, lodging, and miscellaneous items necessary to complete the campground renovation at Blackjack Campground located off AZ-78 in Clifton, Arizona (coordinates: 33° 3'22.65"N, 109° 4'52.28"W). Work scope includes removal of existing site features such as signs, trees, campfire rings, and grills, along with construction of roads, low-water crossings, parking areas, drainage channels, camping spurs, tent pads, trails, sidewalks, an overlook slab with railing, toilets, grills, gates, firepits, and a ramada structure. All work must be performed in accordance with detailed specifications and construction drawings provided in the scope attachments, which include a 100% Project Specifications document (40 pages), 100% Construction Drawings (59 pages), Septic System Design (10 pages), and Gates documentation (8 pages). The Contracting Officer's Representative is Chris Miller (928-651-1968; christopher.miller5@usda.gov). No modifications to specifications, terms, or conditions may be made without prior written approval from the Contracting Officer. Payment units include Actual Quantity, Lump Sum Quantity, and Estimated Quantity measurements using standard units such as cubic yards, each, linear feet, and tons.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

1 | P a g e

SOUTHWEST REGION 03

APACHE-SITGREAVES

NATIONAL FOREST

BLACKJACK CAMPGROUND

RENOVATION

STATEMENT OF WORK

U.S. FOREST SERVICE

08/27/2025

2 | P a g e

TABLE OF CONTENTS

1.0 GENERAL INFORMATION

1.1 WORK SUMMARY

1.2 PROJECT LOCATION

1.3 POINTS OF CONTACT

2.0 PROJECT SCOPE

2.1 SCOPE

2.2 SCOPE ATTACHMENTS

3.0 SCHEDULE OF ITEM DESCRIPTIONS

3.1 ABBREVIATIONS

3 | P a g e

1.0 GENERAL INFORMATION

1.1 WORK SUMMARY

Work includes removing site features, including signs, trees, campfire rings, grills, and other miscellaneous items. Constructing roads, low-water crossings, parking areas, drainage channel, camping spurs, tent pads, trails, sidewalks, overlook slab with railing, installing toilets, grills, installing gates, firepits and a ramada.

1.2 PROJECT LOCATION

From the Clifton Ranger District office head south toward AZ-75 s (0.2 mi), turn right onto AZ-75 n (486 ft), turn right onto AZ-78 E destination will be on the right (14.0 mi).

BlackJack Campground AZ-78, Clifton, AZ 85533

Latitude 33° 3'22.65"N, Longitude 109° 4'52.28"W

1.3 POINTS OF CONTACT

Contracting Officer’s Representative:

Chris Miller, 928-651-1968, christopher.miller5@usda.gov mailto:christopher.miller5@usda.gov

4 | P a g e

2.0 PROJECT SCOPE

2.1 SCOPE

The Contractor shall furnish all supervision, materials, equipment and vehicles, tools, parts, labor, transportation, lodging, and miscellaneous items for Blackjack campground renovation in accordance with the drawings, specifications, and other attachments referenced and contained herein.

No changes to the specifications, terms, or conditions of this statement of work shall be made without the prior approval of the Contracting Officer, in writing.

2.2 SCOPE ATTACHMENTS

Attachment 1 – Solicitation Terms and Conditions (41 Pages) Attachment 2 – Schedule of Items (1 Page) Attachment 3 – Statement of Work (6 Pages) Attachment 4 – 100% Project Specifications (40 Pages) Attachment 5 – 100% Construction Drawings (59 Pages) Attachment 6 – Septic System Design (10 Pages) Attachment 7 – Gates (8 Pages)

5 | P a g e

3.0 SCHEDULE OF ITEM DESCRIPTIONS

The following descriptions summarize the work for the Schedule of Items (SOI) listed below. They are not intended to be all-inclusive of the work needed to perform each item. Such work shall be considered incidental to the task and be included in the final costs to perform the work necessary.

3.1 ABBREVIATIONS

Method of Measurement

(MoM) Pay Units

AQ Actual Quantity CY Cubic Yards LSQ Lump Sum Quantity EA Each EQ Estimated Quantity LF Linear Feet EA Each LS Lump Sum

SF Square Feet TN Tons

6 | P a g e

Black Jack Campground Location Map

Located off AZ-78, Clifton AZ 85533

1.0 GENERAL INFORMATION
1.1 WORK SUMMARY
1.2 PROJECT LOCATION
1.3 POINTS OF CONTACT
2.0 PROJECT SCOPE
2.1 SCOPE
2.2 SCOPE ATTACHMENTS
3.0 SCHEDULE OF ITEM DESCRIPTIONS