This pre-solicitation notice seeks proposals for repairs to facilities at the Seward Military Resort in Alaska. The contractor will replace decks on lodging units, upgrade a bathroom to ADA accessibility standards, repair or replace rotten logs, and add attic insulation. The work must be completed between Labor Day and Memorial Day with possible additional work periods. The contract type will be firm-fixed price and awarded through sealed bidding to a small business. The estimated value is between $500,000 and $1,000,000. Interested parties should provide company and contact details along with capability statements by July 13, 2021 to the identified Army contracting contacts. The solicitation is expected to be released within 180 days for this 100% small business set-aside work for the Department of the Army Materiel Command Army Contracting Command.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| SUBMITTAL REGISTER | PROJECT NUMBER | PROJECT TITLE | CONTRACT NUMBER | ||||||||||||||||||||||||||
| SEW-20001-0J, SEW-00001-9J, SEW-00001-7J | Replace Decks to Lodging Units, Replace Rotten Logs, Install Wheelchair Access Shower | ||||||||||||||||||||||||||||
| TO BE COMPLETED BY PROJECT ENGINEER | CONTRACTOR SHEDULE DATES | CONTRACTOR ACTION | GOVERNMENT ACTION | REMARKS | |||||||||||||||||||||||||
| ACTIVITY NUMBER | TRANSMITTAL # | ITEM NUMBER | SPECIFICATION | PARAGRAPH | ITEMS OR DESCRIPTION OF ITEM | TYPE OF SUBMITTAL | CLASSIFI-CATIONS | REQUIRED SUBMISSION DATE (or prior to DFOW Preparatory) | |||||||||||||||||||||
| PRECONSTRUCTION | SHOP DRAWINGS | PRODUCT DATA | SAMPLES | DESIGN DATA | TEST REPORTS | CERTIFICATES | MANUFACTURER'S INSTRUCTIONS | MANUFACTURER'S FIELD REPORTS | OPERATION AND MAINTENANCE DATA | CLOSEOUT SUBMITTALS | FOR INFORMATION ONLY | GOVERNMENT APPROVAL | SUBMIT | APPROVAL NEEDED BY | MATERIAL NEEDED BY | CODE | DATE | SUBMITTED TO GOVERNMENT | Date Received by Govt | CODE | DATE of Actiton |
| 2.6 | Decking | X | X | ||||||
| 2.6 | Attic Insulation | X | X | ||||||
| 2.6 | Deck Paint | X | X | ||||||
| 2.6 | Metal Paint | X | X | ||||||
| 2.6 | Cold Galvanizing | X | X | ||||||
| 2.7 | Log Sealant | X | X | ||||||
| 2.7 | Log Oil | X | X | ||||||
| 2.8 | ADA Shower | X | X | ||||||
| 01 32 01 | 4 | Preliminary Schedule | X | X | With Proposal | ||||
| 01 32 01 | 4 | Initial Project Schedule | X | X | 10 Days after NTP | ||||
| 01 11 00 | 4 | Proof of Insurance & Bonding | X | X | |||||
| 01 45 04 | 2 | Quality Control Plan, DFOW | X | X | |||||
| 01 57 20 | 4 | Environmental Protection Plan | X | X | |||||
| 01 35 26 | 2 | Accident Prevention Plan (APP) | X | X | |||||
| 01 33 00 | 6 | Submittal Register | X | X | Precon & update monthly w/ Govt QA | ||||
| 01 32 01 | 2 | Schedule of Values | X | X | 10 Days after NTP | ||||
| 01 78 00 | 4 | O&M Data/Manuals | X | X | X | ||||
| 01 78 00 | 1 | As-Built Drawings and As built Record of Equipment and Materials | X | ||||||
| 01 50 00 | 3 | Site Plan to include temp storage/laydown/field office as applicable | X | X | |||||
| 01 78 00 | 3 | Contractor Warranty POC's | X | X | During duty and non duty | ||||
| 01 78 00 | 3 | Extended Warranties | X | X | |||||
| 01 19 30 | 9 | Solid Waste Disposal Reports | X | ||||||
| 01 78 00 | 2 | DD Form 1354 | X | X | |||||
| 01 11 00 | 2 | AT Level 1 Training | X | X | |||||
| 01 11 00 | 2 | Access List of Personnel/Subcontractor list | X | X | |||||
| 01 11 00 | 2 | iWatch Training | X | X | |||||
| 01 11 00 | 2 | OPSEC Training | X | X | |||||
| 01 11 00 | 2 | TARP Training | X | X |