Attachment 3 - North Central Lagoon QASP 2025.docx
DOCX document 17 KB Posted
- Solicitation number
- 12444325Q0026
About this file
This document is a Quality Assurance Surveillance Plan (QASP) for the North Central Lagoon Wastewater System operated by the Allegheny National Forest. The plan details performance standards for the wastewater system operator, with five primary performance metrics (PM) focusing on task management, daily system inspections, annual startup/shutdown procedures, sampling and testing compliance, and operator qualifications. Each performance standard requires strict adherence with zero tolerance for deviations, to be monitored through periodic inspections by the Contracting Officer's Representative (COR).
The related federal contract opportunity (Solicitation 12444325Q0026) seeks a contractor to operate and maintain the North Central Lagoon Wastewater Plant at the Bradford Ranger Station in Pennsylvania. The contractor must provide all labor, materials, equipment, and supplies necessary for system operation, testing, record keeping, and reporting. Critically, the contract explicitly excludes system repairs. The solicitation is issued by the Department of Agriculture Forest Service's Eastern Region, with the contractor required to manage the system in compliance with all applicable Pennsylvania Department of Environmental Protection (PA DEP) permit requirements.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
QASP
Performance Measurables
Operator and Managerial Responsibility
The certified operator of this wastewater system is responsible for ensuring the proper operation of this lagoon and spray irrigation system that serves the Bradford Ranger District Office and many of the Recreational Facilities in the Allegheny National Forest. Specific responsibilities include:
· Ensure system is operated in accordance with all PA DEP permit requirements.
· Complete and document all required water quality testing.
· Ensure equipment is operating properly and receives required maintenance
· Perform annual startup and shutdown tasks
· Inform appropriate Allegheny National Forest personnel of problems and/or potential problems
· Keep current on procedures and permit requirements
· Perform DAILY inspections of all parts of the system to insure all are safe and in good working condition
| Perf Std # |
| Required Services |
| Performance Standards |
| Acceptable Quality Level |
(AQL)
Monitoring Method
| PM-1 |
| Manage task schedule and budget accurately and effectively. |
| Complete all tasks accurately, on-time and within budget. |
No more than two (2) of the deliverables may be completed and submitted beyond the due date.
No deviation.
COR/designee periodic inspection; review of Weekly Status Reports; notify COR once a week when going to be at lagoon.
| PM-2 |
| Daily inspection. |
| Perform DAILY inspections of all parts of the system to insure all are safe and in good working condition. Inform appropriate Allegheny National Forest personnel of problems and/or potential problems. |
| No deviation. |
COR/designee periodic inspection.
| PM-3 |
| Perform annual startup and shutdown tasks. |
| Compliance with the Operations Manual standards. |
| No deviation. |
COR/designee periodic inspection.
| PM-4 |
| Sampling, testing, and monitoring. |
| All required sampling, testing, and monitoring performed in compliance with all applicable laws and regulations. Submitted on time and to the proper authorities. |
| No deviation. |
| COR/designee periodic inspection. |
| PM-5 |
| Operator qualification and permitting. |
| Properly qualified operator shall be utilized, with all required licenses. All required permits will be kept up to date. |
| No deviation. |
| COR/designee periodic inspection. |