This is a technical proposal drawing for an industrial compressed air system installation. The document presents a layout design prepared in accordance with NEC standards for a complete system configuration including two BSD 50 compressors, a 120-gallon wet receiver, a 240-gallon dry receiver, a KAD 260 air dryer with filter pack B, a KCF 200 cooling unit, and a 480V electrical panel with step-down transformer for single-point connection. The design incorporates thermostatically controlled inlet louvers and recirculating louvers with backflow prevention for cooling air management, wall heaters, access doors, and a service door. The system requires 4-foot clearance on all sides for service and ventilation, with additional clearance recommended for forklift and rear-access service operations. Total dimensions are 336 inches by 126 inches based on the layout specifications.

The proposal includes a detailed three-dimensional isometric view and multiple floor plan perspectives showing equipment placement and airflow management. Key specifications note that all site work, including site preparation and construction of system components, falls under the installer's responsibility. The document emphasizes compliance with occupational health and safety regulations and requires proper handling and treatment of condensate discharge in accordance with all local and state laws. A SAM 4.0 unit is recommended, and a 480V electrical disconnect is optional. The drawing was reviewed and released on 12/11/2019 and includes manufacturer information from Kaeser Kompressoren.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

1 2 3 4 5 6 7 8

1 2 3 4 5

A

B

C

D

E

F

A

B

C

D

E

Template Rev. 05.03.2019

12/11/2019

12/11/2019 refaia

Kemph

1 of 1Page

Layout Drawing Enclosure, (2) BSD 50, (2) KAD 260, SAM 4.0, KCF 200 / KCI-USA

12/11/2019 Manzke

Sketch

LYUS0193600Sketch

PI

Paper size

Project No.

Status

Rev. Modification Date Name Original Replaces Replaced by

Drawing Review

Released

Date Name

ANSI C / 1:50

Description

PROPOSAL

P&I Diagram

All site work, including but not limited to, site preparation, construction, system component assembly and installation, must be completed in accordance with all relevant local, state and national codes and regulations, including but not limited to, building, electrical and occupational safety. End-users and all sub-contractors responsible for this work may be provided with product information to initiate these tasks, however this is not a substitution for reading and understanding the appropriate Product Manuals prior to installation of the equipment. Since the compliance with the various federal, state and local laws and regulations concerning occupational health and safety and pollution are affected by the use, installation and operation of Equipment and other matters over which Kaeser has no control, Kaeser assumes no responsibility for compliance with those laws and regulations, whether by way of indemnity, warranty or otherwise.

Station Setup ID Station ID

Documents released by engineering are identified by these characteristics in the title block:

Date of review/ release and name of the reviewing/ releasing individual.

Layout Drawing 12/11/2019 refaia

All dimensions are in inches

Thermostatically controlled inlet louvers

This drawing was prepared in accordance with NEC standards

Thermostatically controlled recirculating louver with back flow prevention

Recommended clearance dimensions for service and proper ventilation are 4ft on all sides (additional clearance is recommended for forklift/service access on the rear)

Additional civil preparations at the site location are the responsibility of the user

Condensate discharge must be handled and treated in accordance with all local and state laws

Overview

BSD 50 BSD 50

KAD 260

w/Filter pack B

(2 Places)

120 Gallon Receiver (Wet)

240 Gallon Reciver (Dry)

KCF 200

480V Electrical Panel w/ step down transformer (single point connection)

120"336"

126"

Exhaust air via thermostatically controlled fan

Cooling Air Exhaust

Cooling Air Inlet

Enclosure base to include lifitng eyes, grounding lugs, and environmental barrier

Cooling air inlet via thermostatically controlled louvers (2 places)

Cooling air exhaust via duct with thermostatically controlled recirculation louvers

Wall Heater (2 Places)

1x BSD 50 Standby

SAM 4.0

(Recommended)

480V Electrical Disconnect (Optional)

Access Door Access Door

Service Door

Typical (May not reflect equipment being quoted)