Attachment 3 - Deliverable-Milestone Schedule 693JK326RA001.xlsx

XLSX spreadsheet 34 KB Posted

Attached to
Pipeline Safety Research and Development (R&D) - Research Announcement 12
Solicitation number
693JK326RA001
Issued by

About this file

This is a Deliverable-Milestone Schedule template in Excel format for the Pipeline Safety Research and Development (R&D) Research Announcement 12 (Solicitation Number 693JK326RA001), issued by the Department of Transportation's Pipeline and Hazardous Materials Safety Administration (PHMSA). The file serves as a required attachment for proposal submissions and is intended to be completed by applicants to outline the timing, sequencing, and completion dates of project deliverables and key milestones throughout the performance period of funded research projects.

As a template document, this file does not specify particular products or services but rather provides a standardized framework for proposers to demonstrate project planning and execution capability. Applicants must complete this Excel-based schedule as part of their full proposal package submission. The schedule is critical to proposal evaluation as it demonstrates the applicant's understanding of project scope, resource allocation, and ability to meet performance requirements within established timelines. Submission of this attachment in editable Excel format is mandatory; proposals missing this or other required appendices will not receive award consideration.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1

Technical and Deliverable Milestone Schedule
Item No.Task No.Activity/DeliverableQuarter No.Expected Completion Date/MosPayable MilestoneFederal PaymentResource-Share*Total
(per proposal)ACTIVITY/DELIVERABLETITLE
11Research, summarize, and document current in-field welding and coating practices13 monthsList of current in-field welding and coating practices and their level of interaction and overlap submitted16,984.000.0016,984.00
261st Quarterly Status Report13 monthsSubmit 1st quarterly report2,704.000.002,704.00
First Payable Milestone13 monthsSUBTOTAL19,688.000.0019,688.00
31Research, summarize, and document current in-field welding and coating practices26 monthsList of current in-field welding and coating practices and their level of interaction and overlap submitted9,844.000.009,844.00
42Develop protocols to improve communication and coordination between welding and coating26 monthsProtocol to improve communication and coordination between in-field welders and coating appliers submitted13,899.000.0013,899.00
562nd Quarterly Status Report26 monthsSubmit 2nd quarterly report2,704.000.002,704.00
Second Payable Milestone26 monthsSUBTOTAL26,447.000.0026,447.00
61Research, summarize, and document current in-field welding and coating practices39 monthsList of current in-field welding and coating practices and their level of interaction and overlap submitted9,952.000.009,952.00
72Develop protocols to improve communication and coordination between welding and coating39 monthsProtocol to improve communication and coordination between in-field welders and coating appliers submitted14,170.000.0014,170.00
863rd Quarterly Status Report39 monthsSubmit 3rd quarterly report2,704.000.002,704.00
Third Payable Milestone39 monthsSUBTOTAL26,826.000.0026,826.00
92Develop protocols to improve communication and coordination between welding and coating412 monthsProtocol to improve communication and coordination between in-field welders and coating appliers14,170.000.0014,170.00
103Fabricate in-field welded and coated test sections412 monthsSet of fabricated, in-field welded and coated test sections using the existing and improved protocols/procedures22,007.0042,500.0064,507.00
112Develop protocols to improve communication and coordination between welding and coating412 monthsProtocol to improve communication and coordination between in-field welders and coating appliers submitted14,170.000.0014,170.00
123Fabricate in-field welded and coated test sections412 monthsSet of fabricated, in-field welded and coated test sections using the existing and improved protocols/procedures submitted19,256.0042,500.0061,756.00
134Perform laboratory coating and accelerated corrosion testing412 monthsResults from laboratory coating and accelerated corrosion testing at GTI's analytical coating and corrosion laboratory submitted15,604.000.0015,604.00
144Perform laboratory coating and accelerated corrosion testing412 monthsResults from laboratory coating and accelerated corrosion testing at GTI's analytical coating and corrosion laboratory submitted15,467.0030,871.0046,338.00
154Perform laboratory coating and accelerated corrosion testing412 monthsResults from laboratory coating and accelerated corrosion testing at GTI's analytical coating and corrosion laboratory18,368.000.0018,368.00
165Draft a set of recommendations to be submitted to the appropriate standard development organizations412 monthsSet of clear, concise recommendations to be submitted to the appropriate standard development organizations (e.g., NACE/SSPC, AWS, API, AGA, etc.) for incorporation into the relevant consensus guides, standards, and recommended practices manuals10,798.000.0010,798.00
175Draft a set of recommendations to be submitted to the appropriate standard development organizations412 monthsSet of clear, concise recommendations to be submitted to the appropriate standard development organizations (e.g., NACE/SSPC, AWS, API, AGA, etc.) for incorporation into the relevant consensus guides, standards, and recommended practices manuals12,084.000.0012,084.00
185Draft a set of recommendations to be submitted to the appropriate standard development organizations412 monthsSet of clear, concise recommendations to be submitted to the appropriate standard development organizations (e.g., NACE/SSPC, AWS, API, AGA, etc.) for incorporation into the relevant consensus guides, standards, and recommended practices manuals10,798.000.0010,798.00
1964th Quarterly Status Report412 monthsSubmit 4th quarterly report2,704.000.002,704.00
Fourth Payable Milestone412 monthsSUBTOTAL155,426.00115,871.00271,297.00
20a6Prepare and Submit Draft Final Report512 monthsSubmit draft final report4,000.002,500.006,500.00
Draft Final Report Payable Milestone512 monthsSUBTOTAL4,000.002,500.006,500.00
21bN/APrepare & Present Paper at public event or publish paper in journal/magazineN/AN/APrepare & Present Paper at public event or publish paper in journal/magazine0.00TBD0.00
22cN/AFinal Virtually Held Info Dissemination MeetingN/AN/AFinal Virtually Held Info Dissemination Meeting0.00TBD0.00
23d6Address Comments and Submit Internal Final ReportN/AN/ASubmit final reportTBDTBD0.00
24e6Public Version of Final ReportN/AN/ASubmit public version of final reportTBDTBD0.00
25f6Public Research BriefN/AN/ASubmit Public Research BriefTBDTBD0.00
26gN/APeer Review 1N/AN/ASubmit Peer Review comments of Draft Report & how they were addressed0.00TBD0.00
27gN/APeer Review 2N/AN/ASubmit Peer Review comments of Draft Report & how they were addressed0.00TBD0.00
SUBTOTAL0.000.000.00

READ FOOTNOTES GRAND TOTALS 232,387.00 118,371.00 350,758.00

Notes:
a The Draft Final Report must be submitted prior to the period of performance end for the project.
b This requirement as described in the Research Announcement will be at ZERO gov costs but can have associated cost sharing.
c This requirement as described in the Research Announcement will be at ZERO gov costs but can have associated cost sharing.
d The Final Report shall be submitted by the project period of performance end.
e A Public Final Report is required when the Final submitted Report contains Intellectual Property or Trade Secret information. It should be submitted as
soon as possible after submittal of the Final Report.
f This requirement as described in the Research Announcement, template available in the PRIMIS system and will be a public posted document
don't include Intellectual Property or Trade Secret information.
g This requirement as describe in the Research Anouncement, will be at ZERO gov costs but can have associated cost sharing.
VERIFY Project Cost Calculations and Alignment with attachment 3, attachment 4 and proposal submittal form in MIS.
VERIFY correct version of Attachment 3

Project Title: 693JK326RA0001 Attachement #3

Project Team: SAMPLE SAMPLE SAMPLE 693JK3211RA0001 Attachement #3

Project Team: DTPH5617RA00002 Attachement #5

Project Title: 693JK322RA0001 Attachement #3

Project Title:

&"-,Bold"693JK326RA001&"-,Regular" Attachment #3

Page &P of &N

Page &P of &N

Page &P of &N

Page &P of &N

Page &P of &N

Sheet2

Sheet3

File details come from the government source that posted it. Updated .