Attachment 3 - 10 Jan 24 Paint Estimate FY24 through FY29.xlsx
XLSX spreadsheet 52 KB Posted
- Attached to
- Paint and Protective Coating IDIQ - Shaw AFB
- Solicitation number
- FA480324B0003
About this file
This document includes a paint estimate spreadsheet and statement of work for a protective coatings indefinite delivery indefinite quantity contract at Shaw Air Force Base. The contractor shall provide all labor, equipment, materials, supervision, and other services necessary to perform interior and exterior painting and protective coating services as defined in the statement of work. Work will include exterior and interior painting, pavement marking removal and application, drywall repair, wall covering removal, hydrant and structure painting, swimming pool painting, pressure washing, and sign fabrication. The base year and four option years are included, with a potential six month extension. Pricing will be awarded by individual task orders on an as-needed basis. The Department of the Air Force Air Combat Command is the contracting agency.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Base Year
| Project: | Protective Coatings | Project Engineer: | Mr. Patrick Holland |
| Location: | Shaw AFB | Department: | 20 CES |
| Contractor: | Date: | ||
| Address: | |||
| PR No.: |
Line No. Item Units Quantity Material Costs Labor Costs Direct Cost Line Total
| Unit Cost (Means) | Total | Labor Hours per Unit (Means) | Labor Cost per Unit (Means) | Labor Hours | Avg. Rate ($/hr) | Total | ||||
| 1 | Exterior Painting | SF | 54,075 | |||||||
| 2 | Partial Exterior and Trim | SF | 20,980 | |||||||
| 3 | Paint Interior | SF | 47,929 | |||||||
| 4 | Partial Interior and Trim | SF | 7,245 | |||||||
| 5 | Remove Pavement Markings | SF | 100 | |||||||
| 6 | Apply Pavement Markings | LF | 23,945 | |||||||
| 7 | Prime Interior / Exterior | SF | 17,746 | |||||||
| 8 | Repair Drywall Surfaces | SF | 1,723 | |||||||
| 9 | Remove Wall Coverings / Wallpaper | SF | 781 | |||||||
| 10 | Paint Hydrants | EA | 2 | |||||||
| 11 | Prepare / Paint Special Structures | SF | 3,122 | |||||||
| 12 | Prepare / Paint Swimming Pool | SF | 3,080 | |||||||
| 13 | Pressure Washing | SF | 75,055 | |||||||
| 14 | Fabrication of Sign Blanks | SF | 253 | |||||||
| 15 | Fabricate / Apply Letters & Numbers | EA | 2,539 | |||||||
| 16 | Glass Door Stenciling | SF | 41 |
Total: $0.00
Option Year 1
| Project: | Protective Coatings | Project Engineer: | Mr. Patrick Holland |
| Location: | Shaw AFB | Department: | 20 CES |
| Contractor: | Date: | ||
| Address: | |||
| PR No.: |
Line No. Item Units Quantity Material Costs Labor Costs Direct Cost Line Total
| Unit Cost (Means) | Total | Labor Hours per Unit (Means) | Labor Cost per Unit (Means) | Labor Hours | Avg. Rate ($/hr) | Total | ||||
| 1 | Exterior Painting | SF | 54,075 | |||||||
| 2 | Partial Exterior and Trim | SF | 20,980 | |||||||
| 3 | Paint Interior | SF | 47,929 | |||||||
| 4 | Partial Interior and Trim | SF | 7,245 | |||||||
| 5 | Remove Pavement Markings | Sf | 100 | |||||||
| 6 | Apply Pavement Markings | LF | 23,945 | |||||||
| 7 | Prime Interior / Exterior | SF | 17,746 | |||||||
| 8 | Repair Drywall Surfaces | SF | 1,723 | |||||||
| 9 | Remove Wall Coverings / Wallpaper | SF | 781 | |||||||
| 10 | Paint Hydrants | EA | 3 | |||||||
| 11 | Prepare / Paint Special Structures | SF | 3,122 | |||||||
| 12 | Prepare / Paint Swimming Pool | SF | 3,080 | |||||||
| 13 | Pressure Washing | SF | 75,055 | |||||||
| 14 | Fabrication of Sign Blanks | SF | 253 | |||||||
| 15 | Fabricate / Apply Letters & Numbers | EA | 2,539 | |||||||
| 16 | Glass Door Stenciling | SF | 41 |
Total: $0.00
Option Year 2
| Project: | Protective Coatings | Project Engineer: | Mr. Patrick Holland |
| Location: | Shaw AFB | Department: | 20 CES |
| Contractor: | Date: | ||
| Address: | |||
| PR No.: |
Line No. Item Units Quantity Material Costs Labor Costs Direct Cost Line Total
| Unit Cost (Means) | Total | Labor Hours per Unit (Means) | Labor Cost per Unit (Means) | Labor Hours | Avg. Rate ($/hr) | Total | ||||
| 1 | Exterior Painting | SF | 54,075 | |||||||
| 2 | Partial Exterior and Trim | SF | 20,980 | |||||||
| 3 | Paint Interior | SF | 47,929 | |||||||
| 4 | Partial Interior and Trim | SF | 7,245 | |||||||
| 5 | Remove Pavement Markings | SF | 100 | |||||||
| 6 | Apply Pavement Markings | LF | 23,945 | |||||||
| 7 | Prime Interior / Exterior | SF | 17,746 | |||||||
| 8 | Repair Drywall Surfaces | SF | 1,723 | |||||||
| 9 | Remove Wall Coverings / Wallpaper | SF | 781 | |||||||
| 10 | Paint Hydrants | EA | 3 | |||||||
| 11 | Prepare / Paint Special Structures | SF | 3,122 | |||||||
| 12 | Prepare / Paint Swimming Pool | SF | 3,080 | |||||||
| 13 | Pressure Washing | SF | 75,055 | |||||||
| 14 | Fabrication of Sign Blanks | SF | 253 | |||||||
| 15 | Fabricate / Apply Letters & Numbers | EA | 2,539 | |||||||
| 16 | Glass Door Stenciling | SF | 41 |
Total: $0.00
Option Year 3
| Project: | Protective Coatings | Project Engineer: | Mr. Patrick Holland |
| Location: | Shaw AFB | Department: | 20 CES |
| Contractor: | Date: | ||
| Address: | |||
| PR No.: |
Line No. Item Units Quantity Material Costs Labor Costs Direct Cost Line Total
| Unit Cost (Means) | Total | Labor Hours per Unit (Means) | Labor Cost per Unit (Means) | Labor Hours | Avg. Rate ($/hr) | Total | ||||
| 1 | Exterior Painting | SF | 54,075 | |||||||
| 2 | Partial Exterior and Trim | SF | 20,980 | |||||||
| 3 | Paint Interior | SF | 47,929 | |||||||
| 4 | Partial Interior and Trim | SF | 7,245 | |||||||
| 5 | Remove Pavement Markings | SF | 100 | |||||||
| 6 | Apply Pavement Markings | LF | 23,945 | |||||||
| 7 | Prime Interior / Exterior | SF | 17,746 | |||||||
| 8 | Repair Drywall Surfaces | SF | 1,723 | |||||||
| 9 | Remove Wall Coverings / Wallpaper | SF | 781 | |||||||
| 10 | Paint Hydrants | EA | 3 | |||||||
| 11 | Prepare / Paint Special Structures | SF | 3,122 | |||||||
| 12 | Prepare / Paint Swimming Pool | SF | 3,080 | |||||||
| 13 | Pressure Washing | SF | 75,055 | |||||||
| 14 | Fabrication of Sign Blanks | SF | 253 | |||||||
| 15 | Fabricate / Apply Letters & Numbers | EA | 2,539 | |||||||
| 16 | Glass Door Stenciling | SF | 41 |
Total: $0.00
Option Year 4
| Project: | Protective Coatings | Project Engineer: | Mr. Patrick Holland |
| Location: | Shaw AFB | Department: | 20 CES |
| Contractor: | Date: | ||
| Address: | |||
| PR No.: |
Line No. Item Units Quantity Material Costs Labor Costs Direct Cost Line Total
| Unit Cost (Means) | Total | Labor Hours per Unit (Means) | Labor Cost per Unit (Means) | Labor Hours | Avg. Rate ($/hr) | Total | ||||
| 1 | Exterior Painting | SF | 54,075 | |||||||
| 2 | Partial Exterior and Trim | SF | 20,983 | |||||||
| 3 | Paint Interior | SF | 47,932 | |||||||
| 4 | Partial Interior and Trim | SF | 7,249 | |||||||
| 5 | Remove Pavement Markings | SF | 100 | |||||||
| 6 | Apply Pavement Markings | LF | 23,945 | |||||||
| 7 | Prime Interior / Exterior | SF | 17,749 | |||||||
| 8 | Repair Drywall Surfaces | SF | 1,727 | |||||||
| 9 | Remove Wall Coverings / Wallpaper | SF | 785 | |||||||
| 10 | Paint Hydrants | EA | 3 | |||||||
| 11 | Prepare / Paint Special Structures | SF | 3,124 | |||||||
| 12 | Prepare / Paint Swimming Pool | SF | 3,080 | |||||||
| 13 | Pressure Washing | SF | 75,058 | |||||||
| 14 | Fabrication of Sign Blanks | SF | 254 | |||||||
| 15 | Fabricate / Apply Letters & Numbers | EA | 2,539 | |||||||
| 16 | Glass Door Stenciling | SF | 43 |
Total: $0.00
6 Month Extension
| Project: | Protective Coatings | Project Engineer: | Mr. Patrick Holland |
| Location: | Shaw AFB | Department: | 20 CES |
| Contractor: | Date: | ||
| Address: | |||
| PR No.: |
Line No. Item Units Quantity Material Costs Labor Costs Direct Cost Line Total
| Unit Cost (Means) | Total | Labor Hours per Unit (Means) | Labor Cost per Unit (Means) | Labor Hours | Avg. Rate ($/hr) | Total | ||||
| 1 | Exterior Painting | SF | 27,038 | |||||||
| 2 | Partial Exterior and Trim | SF | 10,490 | |||||||
| 3 | Paint Interior | SF | 23,965 | |||||||
| 4 | Partial Interior and Trim | SF | 3,623 | |||||||
| 5 | Remove Pavement Markings | SF | 50 | |||||||
| 6 | Apply Pavement Markings | LF | 11,973 | |||||||
| 7 | Prime Interior / Exterior | SF | 8,873 | |||||||
| 8 | Repair Drywall Surfaces | SF | 862 | |||||||
| 9 | Remove Wall Coverings / Wallpaper | SF | 391 | |||||||
| 10 | Paint Hydrants | EA | 2 | |||||||
| 11 | Prepare / Paint Special Structures | SF | 1,562 | |||||||
| 12 | Prepare / Paint Swimming Pool | SF | 1,540 | |||||||
| 13 | Pressure Washing | SF | 37,528 | |||||||
| 14 | Fabrication of Sign Blanks | SF | 127 | |||||||
| 15 | Fabricate / Apply Letters & Numbers | EA | 1,270 | |||||||
| 16 | Glass Door Stenciling | SF | 21 |
Total: $0.00
Totals
| Protective Coatings | |
| Base Year Line Total | $ - 0 |
| Option Year Line Total | $ - 0 |
| Option Year 2 Line Total | $ - 0 |
| Option Year 3 Line Total | $ - 0 |
| Option Year 4 Line Total | $ - 0 |
| 6 Month Extension Line Total | $ - 0 |
| Total Contract Cost | $ - 0 |
| Company Name |
| POC Name |
| POC Telephone Number |
| POC Signature |
File details come from the government source that posted it. Updated .