This is a Statement of Work (SOW) specification document for the USCGC THETIS (WMEC-910) drydock repairs scheduled for FY2026. The specification encompasses 47 distinct work items totaling comprehensive vessel maintenance and modernization efforts spanning from June 15 to September 12, 2026. Work items include critical hull inspections and preservation (ultrasonic testing of underwater hull plating, 100% preservation of underwater body surfaces, partial freeboard preservation), propulsion system maintenance (shaft removal/inspection/reinstallation, bearing renewal, propeller system service), rudder and fin stabilizer overhaul, sea valve and strainer maintenance, and major equipment upgrades. Notably, the specification requires installation of a new MK 38 MOD 2 Machine Gun System with associated foundations, maintenance platforms, and ammunition handling equipment, along with replacement of anchor windlass systems, auxiliary seawater pumps, and emergency diesel generator raw water pumps. Several work items are designated as optional, allowing cost-plus flexibility for repairs identified during the availability.
The specification mandates compliance with multiple Surface Forces Logistics Center (SFLC) standards addressing general requirements, welding and allied processes, preservation systems, electrical installations, and temporary services. Government-furnished property includes propeller shafts, intermediate shafts, propeller blades, CPP hub assemblies, rudder assemblies, anchor windlass units, seawater pumps, transducers, and major weapons system components, with total estimated government-furnished equipment costs exceeding $4.5 million. The contractor must provide technical representatives for specialized systems (propulsion alignment, CPP hydraulics, rudder seals, fin stabilizers), submit quality assurance inspection forms for critical-coated surfaces, perform numerous operational tests and boundary integrity verifications, and deliver redlined as-built drawings. Environmental compliance and hazardous waste management are required throughout, with specific provisions for tank cleaning, fluid disposal, and preservation quality control inspections occurring within the first 25% of the contract period. Temporary services including office space, berthing for 17 personnel, electrical power, water supply, storage, and heavy lift equipment are included as separate work items.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| A0003.pdf | ||
| A0002.pdf | ||
| USCGC THETIS DDL FY26 Offerors Questions and Responses Rev1.pdf | ||
| USCGC THETIS DDL FY26 Offerors Questions and Responses.pdf | ||
| A0001.pdf | ||
| Attachment 1 - Schedule of Services - Blank Price Schedule Rev1.xlsx | XLSX spreadsheet | |
| STATEMENT OF WORK.docx | DOCX document | |
| 70Z08026QMECP0007.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
USCGC THETIS (WMEC 910)
SPECIFICATION FOR DRYDOCK REPAIRS
FY2026
Developed By: Allison J Waters
(Rev-0, 7 January 2026)
USCGC THETIS (WMEC-270B) DRYDOCK AVAILABILITY FY2026
ii (Rev-0)
TABLE OF CONTENTS
Revisions Record .......................................................................................................................................... iv Consolidated List of References .................................................................................................................... v Consolidated List of Government-furnished Property .............................................................................. xiii Consolidated List of Critical Inspection Items ......................................................................................... xvii Principal Characteristics .......................................................................................................................... xviii General Requirements ................................................................................................................................ xix WORK ITEM 1: Hull Plating, U/W Body, Ultrasonic Testing WORK ITEM 2: U/W Body, Preserve, 100 percent WORK ITEM 3: Hull Plating Freeboard, Preserve, Partial WORK ITEM 4: Propulsion Shaft Fairwaters and Rope Guards, Renew WORK ITEM 5: Appendages (U/W), Preserve (Internal) and Leak Test WORK ITEM 6: Voids (Non-Accessible), Preserve (Internal) and Leak Test WORK ITEM 7: Propulsion Shafting, Strain Gauge Alignment, Drydock, Check WORK ITEM 8: Propulsion Shafting; Remove, Inspect, and Reinstall WORK ITEM 9: Propulsion Intermediate Shafts; Remove, Inspect, and Reinstall WORK ITEM 10: Propulsion Shaft Coating, Renew (Optional) WORK ITEM 11: Propulsion Shafting, Straighten (Optional) WORK ITEM 12: Propulsion Shaft Seal (Mechanical And Inflatable) Assemblies, Inspect and Repair or
Renew WORK ITEM 13: Propeller Shaft Sleeves, Renew (Optional) WORK ITEM 14: Propulsion Shafting, Optical or Laser Alignment Check (Optional) WORK ITEM 15: Propulsion Shaft Bearings, External, Renew WORK ITEM 16: Stern Tube Interior Surfaces, Preserve, 100 Percent (Optional) WORK ITEM 17: Controllable Pitch Propellers, Clean and Inspect WORK ITEM 18: Controllable Pitch Propeller (CPP) System, Inspect and Service WORK ITEM 19: Controllable Pitch Propeller (CPP) Hubs, Renew (Optional) WORK ITEM 20: Controllable Pitch Propeller (CPP) Hubs, Inspect (Optional) WORK ITEM 21: Fathometer Transducer, Renew WORK ITEM 22: Doppler Speed Log Transducer, Clean and Inspect WORK ITEM 23: Sea Valves and Waster Pieces, Overhaul Or Renew WORK ITEM 24: Sea Strainers, Duplex, All Sizes, Overhaul WORK ITEM 25: Sea Strainers, Simplex, All Sizes, Clean and Inspect WORK ITEM 26: Rudder Assemblies; Remove, Inspect And Reinstall WORK ITEM 27: Fin Stabilizers (Bearings, Packing, Stock/Blade), Repair or Renew WORK ITEM 28: Superstructure, Preserve, Partial WORK ITEM 29: Cathodic Protection, Zinc Anodes, Renew, WORK ITEM 30: Drydock WORK ITEM 31: Temporary Services, Provide - Cutter WORK ITEM 32: Anchor Windlass, Replace WORK ITEM 33: Auxiliary Salt Water Pump, Replace WORK ITEM 34: Emergency Diesel Generator Raw Water Pump, Replace WORK ITEM 35: Shore Tie, Renew WORK ITEM 36: Shaft Seal Seawater Cooling System Configuration, Restore WORK ITEM 37: CPP Duplex Filter Assembly, Install WORK ITEM 38: Temporary Services, Heating and Cooling (Optional) WORK ITEM 39: Fan Space Deck Plating and Structure, Renew WORK ITEM 40: Bos’n Storeroom Deck Plating, Renew WORK ITEM 41: Sea Chest Piping, Renew iii (Rev-0)
WORK ITEM 42: Machinery Space Deck Plating, Renew WORK ITEM 43: Hull Plating, U/W Body, Renew WORK ITEM 44: Engine Room Fan Controllers, Renew WORK ITEM 45: Tanks, Ballast, Repair and Preserve 100 Percent WORK ITEM 46: Anchor Chain Components, Renew WORK ITEM 47: MK 38 MOD 2, Install iv (Rev-0)
REVISIONS RECORD
This page is used to record specification revisions, which may have occurred subsequent to a Revision 0 (Rev-0) package. Information listed is intended to provide contractors and field unit personnel a means to ensure all the current specification revision pages are present when reviewing or utilizing this specification package.
DATE REV# WORK
ITEM#
CHANGES MADE
NOTE : All work item and paragraph numbers listed above for a given revision correspond to same numbers in the previous revision. This revised specification is self-contained with all of the above listed changes incorporated.
v (Rev-0)
CONSOLIDATED LIST OF REFERENCES
The below-listed documents form a part of this specification to the extent specified herein. Approval/publication dates or revision dates/numbers are also identified, to ensure that same document versions are used at the time of specification writing and during contract execution.
All Coast Guard drawings, technical publications, and standard specifications will be provided to contractors by the Coast Guard at an appropriate time, or upon request, free of charge. Other Government documents may be accessed – free of charge – from links located on the SFLC website. Commercial sites provide access to their respective documents.
COAST GUARD DRAWINGS
Coast Guard Drawing 901 WMEC 245-013, Rev B, Pitch Actuator System Engagement Mechanisms, Links Shaft Clamps and Brackets
Coast Guard Drawing 901 WMEC 245-014, Rev A, CPP System Pitch Setters
Coast Guard Drawing 901 WMEC 245-015, Rev B, CPP System Pitch Setters Main Boards, Sub-Boards, Scales and Mechanical Stops
Coast Guard Drawing 901 WMEC 256-005, Rev A, Cooling Water Piping Mods Incidental to Stern Tube
Coast Guard Drawing 901 WMEC 256-012, Rev -, Shaft Seal Vent Line Modification
Coast Guard Drawing 901 WMEC 302-008, Rev A, 270 WMEC S&A Anchor Windlass Controls, Wiring
Diagram
Coast Guard Drawing 901 WMEC 320-035, Rev AV, As-Built Electrical One-Line Diagram
Coast Guard Drawing 901 WMEC 320-075, Rev B, Electrical One-Line Diagram (WMEC 901 Only)
Coast Guard Drawing 901 WMEC 401-007, Rev A, Arrangement Modifications – Misc Space
Coast Guard Drawing 901 WMEC 410-002, Rev E, Command & Control Sys Blk Wrg Diag & Details
Coast Guard Drawing 901 WMEC 410-009, Rev T, Seawatch Block Diagram & Installation Details
Coast Guard Drawing 901 WMEC 410-010, Rev M, Seawatch Wiring Data COED
Coast Guard Drawing 901 WMEC 424-004, Rev F, Doppler Speed Log System Replacement Ripout, Installation, Arrangement, Wiring and Details
Coast Guard Drawing 901 WMEC 431-003, Rev J, Main IC Switchboard Arrangements, Elementary
Wiring Diagram & Details
Coast Guard Drawing 901 WMEC 431-005, Rev G, Replacement Main IC Switchboard Wiring Data
COED
Coast Guard Drawing 901 WMEC 441-008, Rev D, Sea Tel 4010W-53 KU Band System Installation
Coast Guard Drawing 901 WMEC 451-010, Rev D, 1SG38-SINS2(V)45 Installation BWD & Details
Coast Guard Drawing 901 WMEC 562-003, Rev B, Rudderstock Seal
Coast Guard Drawing 901 WMEC 562-005, Rev K, Rudder Stock and Steering Gear A & D
Coast Guard Drawing 901 WMEC 565-005, Rev -, Fin Stabilizer Hydraulic System Diagram
Coast Guard Drawing 901 WMEC 565-031, Rev C, Fin Shaft Assembly, w/ Sleeve Fitted NSN 3040-01-
104-5121
Coast Guard Drawing 901 WMEC 565-034, Rev -, Fin Stabilizer Clevis Pin
Coast Guard Drawing 901 WMEC 581-007, Rev -, Anchor Windlass Upgrade Installation vi (Rev-0)
Coast Guard Drawing 901 WMEC 612-004, Rev A, NAVSEA Certified Flight Deck Net Installation
Coast Guard Drawing 901 WMEC 612-005, Rev B, Pilot Ladder Rail Mod
Coast Guard Drawing 901 WMEC 801-004, Rev L, General Arrangement 01 Level
Coast Guard Drawing 905 WMEC 111-001, Rev E, Shell Expansion Fwd 101
Coast Guard Drawing 905 WMEC 111-002, Rev F, Shell Exp Aft 182
Coast Guard Drawing 905 WMEC 111-003, Rev F, Shell Exp FR 101-182
Coast Guard Drawing 905 WMEC 114-001, Rev D, Skeg
Coast Guard Drawing 905 WMEC 114-002, Rev C, Bilge Keels
Coast Guard Drawing 905 WMEC 114-003, Rev B, Shaft Fairwaters & Rope Guards
Coast Guard Drawing 905 WMEC 121-001, Rev B, Long Tank Bhds Aft 182
Coast Guard Drawing 905 WMEC 123-002, Rev C, Chain Lkr Bhds & Details
Coast Guard Drawing 905 WMEC 131-002, Rev C, Main Deck Plating & Framing AFT 182
Coast Guard Drawing 905 WMEC 131-003, Rev H, Mn Dk Pl & Fr 101-182
Coast Guard Drawing 905 WMEC 136-001, Rev G, 01 Level Pl & Fr Fwd 101
Coast Guard Drawing 905 WMEC 141-001, Rev E, 1st Platf Pl & Fr Fwd 103
Coast Guard Drawing 905 WMEC 153-002, Rev -, SLEP MK38 MGS Temp Access Cut
Coast Guard Drawing 905 WMEC 162-001, Rev B, Stacks
Coast Guard Drawing 905 WMEC 179-001, Rev A, SLEP MKD 38 Maintenance Platform A&D
Coast Guard Drawing 905 WMEC 182-002, Rev D, Shaft Bearing Fdn
Coast Guard Drawing 905 WMEC 184-014, Rev C, Struct Mods Incidental to DS60 Doppler Install &
ODOM DWDS Rip-Out
Coast Guard Drawing 905 WMEC 184-015, Rev B, SLEP MK 38 MGS CSC 02-63-0-C Misc Fdns
Coast Guard Drawing 905 WMEC 184-016, Rev A, SLEP MK 92 Foundation Removal
Coast Guard Drawing 905 WMEC 185-001, Rev C, HVAC Fdns
Coast Guard Drawing 905 WMEC 185-004, Rev E, Anchor Windlass Fdn
Coast Guard Drawing 905 WMEC 185-009, Rev C, JP-5 Pump Room Fdns
Coast Guard Drawing 905 WMEC 185-015, Rev F, Aux Mchry Space No2 Fdn
Coast Guard Drawing 905 WMEC 185-022, Rev -, Anchor Windlass Foundation & Structural Mods
Coast Guard Drawing 905 WMEC 187-002, Rev A, SLEP MK 38 GWS Fdn Adapter
Coast Guard Drawing 905 WMEC 187-003, Rev 1, SLEP MK 38 MGS Ammo Hoist Fdn & Details
Coast Guard Drawing 905 WMEC 243-001, Rev B, Shafting Arrangement
Coast Guard Drawing 905 WMEC 243-002, Rev F, Stern Tubes Strut Brg and Seal – A & D
Coast Guard Drawing 905 WMEC 243-003, Rev -, Shaft Removal Arrangement
Coast Guard Drawing 905 WMEC 243-005, Rev C, Sftg Align Anal and Procs
Coast Guard Drawing 905 WMEC 243-006, Rev C, General Arrangement 12.125” Dia. Shaft Type MA
Water Lub., Inboard Stern Tube Seal
Coast Guard Drawing 905 WMEC 243-007, Rev A, Controllable Pitch Propeller Shaft Coupling
Assemblies
Coast Guard Drawing 905 WMEC 243-008, Rev B, Shaft & Rudder Removal Padeye A & D
Coast Guard Drawing 905 WMEC 243-010, Rev C, General Arrangement of 10.500” Dia. Bulkhead
Stuffing Box
Coast Guard Drawing 905 WMEC 243-012, Rev B, Controllable Pitch Propeller Shafting Details vii (Rev-0)
Coast Guard Drawing 905 WMEC 244-001, Rev A, Line Shaft Bearing
Coast Guard Drawing 905 WMEC 245-001, Rev H, CPCH Prop Hyd Sys Diagram
Coast Guard Drawing 905 WMEC 245-003, Rev C, Controllable Pitch Propeller Propeller Hub Assy
Coast Guard Drawing 905 WMEC 245-004, Rev A, Controllable Pitch Propeller Blade & Palm
Coast Guard Drawing 905 WMEC 245-005, Rev B, CPCH Prop Hyd Fill and Transfer Sys Diag
Coast Guard Drawing 905 WMEC 245-007, Rev C, Controllable Pitch Propeller Special Tools
Coast Guard Drawing 905 WMEC 245-008, Rev B, Controllable Pitch Propeller Actuating Unit 300.3GN
Coast Guard Drawing 905 WMEC 245-009, Rev C, CPCH Prop Hyd Sys Power Plant A & D
Coast Guard Drawing 905 WMEC 245-012, Rev B, CPCH Prop Hydraulic System Filter Replacement
Coast Guard Drawing 905 WMEC 256-002, Rev K, Eng Rm SW Cooling Sys A&D
Coast Guard Drawing 905 WMEC 256-003, Rev -, Orifice Install IWO EDG JW Heat Exchanger
Coast Guard Drawing 905 WMEC 256-004, Rev E, AMS SW Cooling Sys A+D
Coast Guard Drawing 905 WMEC 256-005, Rev D, Misc Equipment SW Cooling A~D
Coast Guard Drawing 905 WMEC 256-011, Rev E, Mn and Aux SW Cooling Sys Diag
Coast Guard Drawing 905 WMEC 256-014, Rev -, SLEP MK38 MGS ASW Removals
Coast Guard Drawing 905 WMEC 259-002, Rev D, Diesel Exhaust System Arr & Det
Coast Guard Drawing 905 WMEC 320-002, Rev H, Power System Feeders IWD
Coast Guard Drawing 905 WMEC 320-003, Rev K, Power System Hold
Coast Guard Drawing 905 WMEC 320-013, Rev BA, Electronic Power Distribution
Coast Guard Drawing 905 WMEC 320-014, Rev AR, Electrical One-Line Diagram
Coast Guard Drawing 905 WMEC 320-061, Rev -, Anchor Windlass Elec Arr & Wiring Det “B” Class
MEP.
Coast Guard Drawing 905 WMEC 321-006, Rev B, Wireway 02 Level and Above
Coast Guard Drawing 905 WMEC 331-005, Rev J, Lighting System – Main Deck
Coast Guard Drawing 905 WMEC 331-007, Rev F, Lighting System 02 Level and Above
Coast Guard Drawing 905 WMEC 400-008, Rev P, Command & Surveillance Wiring Data COED, Vol 4, IC Equipment
Coast Guard Drawing 905 WMEC 400-009, Rev AB, Command & Surveillance Wiring Data COED, Vol
5, Navigation System Cabling
Coast Guard Drawing 905 WMEC 400-010, Rev K, Command & Surveillance Wiring Data COED, Vol
6, Weapons & Fire Control Cabling
Coast Guard Drawing 905 WMEC 400-011, Rev AK, Command & Surveillance Wiring Data COED, Vol
7, Power Cabling
Coast Guard Drawing 905 WMEC 401-001, Rev AV, Arrangement Pilot House and Bridge Wings
Coast Guard Drawing 905 WMEC 401-002, Rev BR, Arrangement Sensor Room & Command Support
Center
Coast Guard Drawing 905 WMEC 401-004, Rev J, Arrangement IC Room
Coast Guard Drawing 905 WMEC 401-006, Rev AN, Arrangement Antenna and Wave Guide
Coast Guard Drawing 905 WMEC 406-003, Rev B, Topside Grounding, Bonding & RADHAZ, Warnings, Notes & Details
Coast Guard Drawing 905 WMEC 426-001, Rev AB, Gyro System Block & Isometric Wiring Diagram
Coast Guard Drawing 905 WMEC 432-001, Rev L, Sound Powered Telephone System Block & IWD
Coast Guard Drawing 905 WMEC 433-001, Rev N, Announcing System Blk & IWD viii (Rev-0)
Coast Guard Drawing 905 WMEC 436-003, Rev R, Fire & Smoke Detection & Quarterdeck Monitoring
System Blk & IWD
Coast Guard Drawing 905 WMEC 440-003, Rev BA, Radio Communication BWD & Details
Coast Guard Drawing 905 WMEC 441-001, Rev G, WG Dry Air System Diagram
Coast Guard Drawing 905 WMEC 441-006, Rev -, SLEP MK38 MGS Waveguide Dry Air System
Removals
Coast Guard Drawing 905 WMEC 455-001, Rev K, IFF System Block & IWD
Coast Guard Drawing 905 WMEC 472-001, Rev L, ESM System CKTS CI & CT Block & IWD
Coast Guard Drawing 905 WMEC 480-001, Rev P, MK 92 FCS Block & ISO Wiring Diagram
Coast Guard Drawing 905 WMEC 480-002, Rev B, SLEP MK-75 Gun / MK-92 FCS Rip-Out BWD, Arrangement & Waveguide Details
Coast Guard Drawing 905 WMEC 481-001, Rev A, SLEP MK-38 MGS Installation BWD & Details
Coast Guard Drawing 905 WMEC 481-003, Rev -, SLEP MK-38 MGS Wiring Data (COED)
Coast Guard Drawing 905 WMEC 501-004, Rev F, JP-5 Pump Room Arrangement
Coast Guard Drawing 905 WMEC 512-005, Rev E, Vent, Mn Dk Fwd 47 A&D
Coast Guard Drawing 905 WMEC 512-009, Rev C, Vent 01 Lvl and Above Fr 103-140 A & D
Coast Guard Drawing 905 WMEC 512-018, Rev -, SLEP MK 38 MGS Magazine 1-26-0-M Ventilation
Mods
Coast Guard Drawing 905 WMEC 514-005, Rev C, HVAC Fan Rooms Main Deck A&D
Coast Guard Drawing 905 WMEC 514-006, Rev D, HVAC Sensor Rm & CSC 02 Lvl A & D
Coast Guard Drawing 905 WMEC 514-017, Rev B, HVAC Snsr Rm & CSC 02 Lvl A & D
Coast Guard Drawing 905 WMEC 514-033, Rev A, SLEP MK38 MGS Magazine 1-26-0-M CW Mods
Coast Guard Drawing 905 WMEC 521-013, Rev –, Fire Main and Sprinkler System Diagram
Coast Guard Drawing 905 WMEC 522-004, Rev B, SLEP MK38 MGS Magazine 1-26-0-M Sprinkler
Mods
Coast Guard Drawing 905 WMEC 524-003, Rev C, Sea Conn, Sea Chest and Waster Piece A&D
Coast Guard Drawing 905 WMEC 528-002, Rev C, Plumbing Sys & Deck Drains
Coast Guard Drawing 905 WMEC 528-006, Rev C, Plumbing Sys & Deck Drains
Coast Guard Drawing 905 WMEC 529-006, Rev A, Ballasting & Emer Bilge Drainage Sys Diagram
Coast Guard Drawing 905 WMEC 533-010, Rev A, SLEP MK38 MGS Fresh Water Removals
Coast Guard Drawing 905 WMEC 551-009, Rev A, SLEP MK38 MGS Ammo Hoist Mods
Coast Guard Drawing 905 WMEC 562-001, Rev G, Rudder
Coast Guard Drawing 905 WMEC 565-007, Rev H, Fin Stabilizer Mchry Installation A&D
Coast Guard Drawing 905 WMEC 565-017, Rev -, Fin Stabilizer Variable Assembly (Sperry 1890934)
Coast Guard Drawing 905 WMEC 565-020, Rev -, Fin Stabilizer Tiller
Coast Guard Drawing 905 WMEC 581-001, Rev E, Anchor Handling A & D
Coast Guard Drawing 905 WMEC 581-004, Rev F, Anchor Windlass A & D
Coast Guard Drawing 905 WMEC 581-005, Rev -, Stbd Anchor Windlass, WMEC 270 B-Class, 1-1/2-inch Chain, Vertical, Model VAW-1.50-30E-36-B-S, General Arrangement
Coast Guard Drawing 905 WMEC 581-006, Rev -, Port Anchor Windlass, WMEC 270 B-Class, 1-1/2-inch Chain, Vertical, Model VAW-1.50-30E-36-B-P, General Arrangement
Coast Guard Drawing 905 WMEC 588-002, Rev H, Flight Deck & Hangar Markings Arr & Dets
Coast Guard Drawing 905 WMEC 593-004, Rev E, Sewage Transfer System- A&D ix (Rev-0)
Coast Guard Drawing 905 WMEC 602-002, Rev C, Distinguishing Figures
Coast Guard Drawing 905 WMEC 603-001, Rev A, Draft Marks
Coast Guard Drawing 905 WMEC 612-001, Rev G, Rails, Stans and Lifelines
Coast Guard Drawing 905 WMEC 633-001, Rev B, Cathodic Protection A & D
Coast Guard Drawing 905 WMEC 635-001, Rev F, Hull Thermal & Acoustic Insulation A/D
Coast Guard Drawing 905 WMEC 712-003, Rev -, SLEP MK 38, Ammo Hoist
Coast Guard Drawing 905 WMEC 713-004, Rev A, SLEP Magazine (1-26-0-M) Arr & Details
Coast Guard Drawing 905 WMEC 713-005, Rev 1, SLEP MK38 MGS Ready Service Locker A&D
Coast Guard Drawing 905 WMEC 801-003, Rev H, General Arrangement 02/Pilothouse and Above
Coast Guard Drawing 905 WMEC 801-004, Rev H, General Arrangement 01 Level
Coast Guard Drawing 905 WMEC 801-005, Rev F, General Arrangement Main Deck
Coast Guard Drawing 905 WMEC 801-006, Rev D, General Arrangement 1st Platform
Coast Guard Drawing 905 WMEC 801-007, Rev E, General Arrangement Hold
Coast Guard Drawing 905 WMEC 801-009, Rev K, Outboard Profile
Coast Guard Drawing 905 WMEC 801-012, Rev C, Curves of Form
Coast Guard Drawing 905 WMEC 801-037, Rev H, Docking Plan
Coast Guard Drawing FL 184-002, Rev B, SS60 Transducer Install Adapter Assy
Coast Guard Drawing FL 711-037, Rev 3, Shipboard Installation, MK 38 MOD 3 Machine Gun System
(MGS)
Coast Guard Drawing FL 6713-203, Rev A, CRP-V850 Transducer (SS505) Adapter Assembly
Coast Guard Fleet Drawing FL 2804-12, Rev -, U.S.C.G. Emblem
Coast Guard Fleet Drawing FL 2804-22, Rev -, Consolidated Visual ID for Cutters
COAST GUARD PUBLICATIONS
Coast Guard Commandant Instruction (COMDTINST) M10360.3 (series), Coatings and Color Manual
Coast Guard Commandant Instruction (COMDTINST) M10360.3, Appendix B (Cutter and Boats Interior
Painting System)
Coast Guard Commandant Instruction (COMDTINST) M4500.5 (series), Property Management Manual
Coast Guard Commandant Instruction (COMDTINST) M5100.47 (series), Safety and Environmental
Health Manual
Coast Guard Commandant Instruction (COMDTINST) M9000.6F, Naval Engineering Manual
Coast Guard Commandant Instruction (COMDTINST) 9077.1 (series), Equipment Tag-Out Procedure
Manual
Coast Guard Technical Publication (TP) 10500, December 2019, Doppler Sonar, Model DS-60
Coast Guard Technical Publication (TP) 2721, May 2016, Manufacturer's Instruction Book - SWBS 581, Section A, Windlass, Anchor
Coast Guard Technical Publication (TP) 2815, Oct 2017, Reduction Gear
Coast Guard Technical Publication (TP) 2816, Mar 1986, Manufacturer’s Instruction Book-SWBS
Group(s) 242-244, SWBS 243, Section A, Bulkhead Seal Stuffing Box
Coast Guard Technical Publication (TP) 2816, Mar 1986, Manufacturer’s Instruction Book - SWBS
Group(s) 242-244, SWBS 244, Section A, 270’ WMEC “B” Class Cutters, Section 244, Technical
Manual for Cooper Split Roller Bearings
Coast Guard Technical Publication (TP) 2817, Jan 2023, Manufacturer’s Instruction Book-SWBS
Group(s) 245, Section A, Controllable Pitch Propeller System x (Rev-0)
Coast Guard Technical Publication (TP) 2819, SWBS 302, Feb 2009, Motor Controllers (270 WMEC)
Coast Guard Technical Publication (TP) 2835, Jan 2017, Manufacturer’s Instruction Book - SWBS
Group(s) 561-562, 270’ WMEC “B” Class Cutters
Coast Guard Technical Publication (TP) 2837, Jul 2016, Manufacturer’s Instruction Book, SWBS
Group(s) 565, 270’ WMEC “B” Class Cutters, SWBS 565, Section C, Fin Machinery and Hydraulics
Subsystems
Coast Guard Technical Publication (TP) 2837, Manufacturer's Instruction Book, SWBS Group 581, Section A, Jul 2016, Capstan-Windlass Model X-1836
Coast Guard Technical Publication (TP) 4432, 10 Oct 2024, Seawater Cooling Pump, Model- DURCO
MK 3 – Installation, Operation Maint & User Instructions
Coast Guard Technical Publication (TP) 5454, Nov 2013, Technical Manual for Type MA Mechanical
Stern Tube Seal
Coast Guard Technical Publication (TP) 5490, Apr 2018, Fin Stabilizer System
Coast Guard Technical Publication (TP) 9063, SWBS 252, Aug 2016, Coast Guard Machinery Control
System (CGMCS) – Pitch Control System & Throttle Control system – Vol 4
Coast Guard Technical Publication (TP) TBD, SWBS 581, Jun xxxx, Anchor Windlass (270 WMEC A-
Class)
Coast Guard Technical Publication (TP) TBD, SWBS 581, Jun xxxx, Anchor Windlass (270 WMEC B-
Class)
Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2022, General
Requirements
Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2022, Welding and
Allied Processes
Surface Forces Logistics Center Standard Specification 0850 (SFLC Std Spec 0850), 2022, General
Requirements for Drawing Preparation
Surface Forces Logistics Center Standard Specification 3041 (SFLC Std Spec 3041), 2022, Shipboard
Electric Cable Test
Surface Forces Logistics Center Standard Specification 3042 (SFLC Std Spec 3042), 2022, Shipboard
Electrical Cable Removal, Relocation, Splice, Repair, and Installation
Surface Forces Logistics Center Standard Specification 5000 (SFLC Std Spec 5000), 2022, Auxiliary
Machine Systems
Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2022, Requirements for Preservation of Ship Structures
Surface Forces Logistics Center Standard Specification 8634 (SFLC Std Spec 8634), 2022, Drydocking
Surface Forces Logistics Center Standard Specification 8635 (SFLC Std Spec 8635), 2022, Temporary
Services
OTHER REFERENCES
American Bureau of Shipping (ABS) Approved Chain, Accessory and Bar Manufacturing Facilities List, Oct 2016
American Society for Nondestructive Testing (ASNT) SNT-TC-1A, 2020, Recommended Practice for
Personal Qualification and Certification in Nondestructive Testing
American Society of Mechanical Engineers (ASME) B16.34, 2017, Valves-Flanged, Threaded, and
Welding End
ASTM D5162, 2021 Standard Practice for Discontinuity (Holiday) Testing of Nonconductive Protective
Coating on Metallic Substrates xi (Rev-0)
ASTM International (ASTM) D1330, 2015, Standard Specification for Rubber Sheet Gaskets
ASTM International (ASTM) D5363, 2016, Standard Specification for Anaerobic Single-Component
Adhesives (AN)
ASTM International (ASTM) F992, 2017, Standard Specification for Valve Label Plates
Code of Federal Regulations (CFR) Title 29, Part 1915, Occupational Safety and Health Standards for
Shipyard Employment
Commercial Item Description (CID) A-A-59313, Nov 2003, Thread Compound; Anti-seize, Zinc Dust-
Petrolatum
Commercial Item Descriptions (CID) A-A-59316, Nov 2016 Abrasive Materials for Blasting
Electrical Plant Installation Standard Methods for Surface Ships and Submarines, MIL-STD-2003B-2020.
Federal Specification (Fed Spec) HH-P-151, Mar 1991, Packing; Rubber-Sheet, Cloth-Insert
Institute of Electrical and Electronics Engineers Standard, IEEE-45, Recommended Practice for Electrical
Installations on Shipboard
International Standard Organization (ISO) 4406, 2017, Hydraulic Fluid Power – Fluids – Method for
Coding the Level of Contamination by Solid Particles – Third Edition
Manufacturers Standardization Society of the Valve and Fittings Industry (MSS) SP-61, 2013 Edition, Pressure Testing Of Steel Valves
Manufacturers Standardization Society of the Valve and Fittings Industry (MSS) SP-67, 2017 Edition, Butterfly Valves
Manufacturers Standardization Society of the Valve and Fittings Industry (MSS) SP-72, 2018 Edition, Ball Valves with Flanged or Butt-Welding Ends for General Service
Manufacturers' Standardization Society of the Valve and Fittings Industry (MSS) SP-80, 2013 Edition, Bronze Gate, Globe, Angle and Check Valves
Manufacturers Standardization Society of the Valve and Fittings Industry (MSS), SP-58, 2018, Pipe
Hangers and Supports – Materials, Design, Manufacture, Selection, Application and Installation
MIL-C-24633, Oct 2014, Chain, Stud Link, Anchor, Low Alloy Steel, Flash Butt Welded
MIL-DTL-15024, General Specification for Plates, Tags, and Bands for Identification of Equipment
MIL-DTL-24643, General Specification for Low Smoke Electric Cables and Cords for Shipboard Use
MIL PRF-16173, Oct 2017, Corrosion Preventive Compound, Solvent Cutback, Cold-Application
MIL-A-18001, Dec 2015, Anodes, Sacrificial Zinc Alloy
MIL-A-22262, Mar 1996, Abrasive Blasting Media Ship Hull Blast Cleaning
MIL-PRF-17672E, Oct 2012, Hydraulic Fluid, Petroleum, Inhibited
MIL-PRF-24647, Jan 2018, Paint System, Anticorrosive and Antifouling, Ship Hull
MIL-S-45180, 1998, Sealing Compound, Gasket, Hydrocarbon Fluid and Water Resistant
MIL-STD-1687, Sep 1994, Thermal Spray Process for Naval Ship Machinery Application
MIL-STD-2191, Nov 1992, Repair Welding, Weld Cladding, Straightening, and Cold Rolling of Main
Propulsion Shafting
MIL-STD-2199B (SH), Jan 2020, Coverings for Waterborne Main Propulsion Shafting on U.S. Naval
Surface Ships and Submarines
Military Standard, MIL-STD-1310(SERIES), Shipboard Bonding, Grounding, & Other Techniques for
Electromagnetic Compatibility and Safety
NAVSEA Drawing 803-1385866, Rev E, Penetration, Bulkhead and Deck
NAVSEA Drawing 803-2145807, Rev C, Propulsion Shafting and Components
NAVSEA Drawing 803-5184097, Rev B, Safety Nets, Deck Edge GRP or Al Frame, Nylon Net xii (Rev-0)
NAVSEA Drawing 803-921865, Rev R, Cathodic Protection Hull Zinc Anodes
NAVSEA Drawing 804-5773931, Rev A, Acoustic & Thermal Insulation for Compartments Installation
Details
NAVSEA Technical Manual S9243-AW-TRS-011/SHAFT Rev 1, June 2015, Surface Ships Main
Propulsion Shafting Refurbishment Procedures
NAVSEA Technical Manual S9245-AR-TSM-010, December 2012, Marine Propeller Inspection, Repair, and Certification
NAVSEA Technical Publication T9074-AD-GIB-010/1688, (TP 1688), July 2012, Requirements for
Fabrication, Welding, and Inspection of Submarine Structure
ODOM Echotrac DF3200 MKII, Rev 2, Technical Manual
Raytheon V850 Color Echosounder, 2nd Edition, Mar 1993, Operation Manual
Recommended Practices for Electrical Installations on Shipboard IEEE STD-45 (Series)
Rules for Building and Classing Marine Vessels (ABS/MVR) – Part 4, Vessel Systems and Machinery
Society of Automotive Engineers (SAE) AMS-G-6032, August 2020, Grease, Plug Valve, Gasoline and
Oil Resistant, NATO Code Number G-363, Metric
Society of Automotive Engineers (SAE) Aerospace Material Specification AMS-C-6183, 2019, Cork and
Rubber Composition Sheet; For Aromatic Fuel and Oil Resistant Gaskets
The Society for Protective Coatings (SSPC) Surface Preparation Specification No. 1 (SSPC-SP 1), 2016, Solvent Cleaning
The Society for Protective Coatings (SSPC) Surface Preparation Specification No.11 (SSPC-SP 11), 2013, Power Tool Cleaning to Bare Metal
The Society for Protective Coatings (SSPC)/NACE International (NACE) Joint Surface Preparation
Standard SSPC-SP 10/NACE No. 2, 2007, Near-White Metal Blast Cleaning
The Society for Protective Coatings (SSPC)/NACE International (NACE) Joint Surface Preparation
Standard SSPC-SP 12/NACE No.5, 2002, Surface Preparation and Cleaning of Metals by
Waterjetting Prior to Recoating
The Society for Protective Coatings (SSPC)/NACE International (NACE) Joint Surface Preparation
Standard SSPC-SP 6/NACE No. 3, 2007, Commercial Blast Cleaning
The Society for Protective Coatings (SSPC)/NACE International (NACE) Joint Surface Preparation
Standard SSPC-SP WJ-2/NACE WJ-2, 2017, Water Jet Cleaning of Metals - Very Thorough
Cleaning
Title 46, Code of Federal Regulations (46CFR), Subchapter J, Electrical Engineering
USCGC DILIGENCE (WMEC-210A) DOCKSIDE AVAILABILITY FY2026
xiii (Rev-0)
CONSOLIDATED LIST OF GOVERNMENT-FURNISHED PROPERTY
The following is a list of property, which the Government will furnish. This list supersedes any other material obligations indicated or implied by referenced drawings.
WORK
ITEM
MTI ITEM DESCRIPTION NSN/PN QTY ESTIMATED
COST
($/UNIT)
8 Y **Propeller shaft NSN: 2010-01-135-7065 2 ea. 158,558.75
9 Y **Intermediate Shaft NSN: 2010-01-365-3908 2 ea. 8,449.00
12 N Stern tube seal major overhaul kit
NSN: 5330-01-527-0959 2 ea. 34,607.00
12 N **Stern tube seal split seat
NSN: 5330-01-359-5555 2 ea. 12,708.00
12 N Automatic Air Eliminator PN: AE36
NSN: 4820-01-690-3058
2 ea. 543.00
12 N **Drive clamp ring PN: H70146-7
NSN: 5330-01-733-9479
2 ea. 10,015.77
N
Stern Tube Sleeve
(Forward) NSN: 2010-01-340-6083 1 ea. 10,792.56
13 N Stern Tube Sleeve (Aft) NSN: 2010-01-345-2315 1 ea. 12,725.00
N
Propeller Strut Sleeve
(Forward) NSN: 2010-01-345-2314 1 ea. 13,180.16
N
Propeller Strut Sleeve
(Aft) NSN: 2010-01-340-5362 1 ea. 8,865.14
15 N Stern tube bearing NSN: 3120-01-189-1949 2 ea. 24,320.00
N
Intermediate Strut
Bearing NSN: 3120-01-189-1087 2 ea. 9,647.53
15 N Propeller Strut Bearing NSN: 3120-01-189-1088 2 ea. 12,752.00
18 N O.D. Box Inspection Kit NSN: 3010-01-470-3519 2 kt. 1,380.00
18 N **Oil Feed Bushing NSN: 3120-12-329-5287 2 ea. 14,760.00
18 N **Ball Bearing NSN: 3110-00-156-6745 2 pr. 121.00
18 N **Bearing Bushing NSN: 2010-01-469-8639 2 ea. 1,198.00
18 N **Bearing Bushing NSN: 3120-12-198-7607 8 ea. 1,255.00
18 N **Spool valve assembly NSN: 4820-01-513-2509 2 ay. 25,348.00
N
Strainer seal kit NSN: 5330-01-266-6513
PN: 909156
6 ea.
31.00
N
Magnets NSN: 4330-01-258-2746
PN: 905904 WV
12 ea.
140.00
18 N Strainer Element, Sediment
NSN: 4730-01-456-6689 12 ea. 184.00
18 Y **Propeller Blade-RH
(Port) NSN: 2010-01-119-3972 1 se. 40,000.00
18 Y **Propeller Blade-LH
(Stbd) NSN: 2010-01-120-2871 1 se. 40,000.00
18 N O-Ring NSN: 5330-01-120-5229 8 ea. 9.00
18 N O-Ring NSN: 5330-01-118-8529 8 ea. 817.00
18 N Blade Washer NSN: 5310-01-335-4361 48 ea. 213.00
18 N **Shoulder bolt NSN: 5306-01-118-8337 8 ea. 2,139.00
18 N **Shoulder blade bolt NSN: 5306-01-119-3607 16 ea. 1,523.00
19 N Hub installation kit NSN: 2010-01-470-3258 1 kt. 2,565.00
19 Y Left hand hub assembly NSN: 2010-01-119-5469 1 ea. 897,576.00
19 Y Right hand hub assembly NSN: 2010-01-118-8538 1 ea. 920,016.00 xiv (Rev-0)
N
*Special tools (see 4.2
(Government-loaned installation tools))
N/A 1 se. 1,000.00
20 N Hub Installation kit NSN: 2010-01-470-3258 1 kt. 2,565.00
N
***Fathometer
Transducer, Shallow
Water
NSN: 5845-01-668-2181
PN: SS60
1 ea. 1,884.26
22 Y **FURUNO DS-630-30
Doppler Speed Log
Transducer with 30M
Cable
NSN: 5845-01-678-5056 1 ea. 7,097.35
24 N **Duplex 1” Strainer 4730-01-158-7998 3 ea. 1,280.39
24 N **Duplex 3” Strainer 4730-01-614-9064 2 ea. 6,694.99
24 N **Duplex 1 ½” Strainer 4730-01-600-9049 1 ea. 3,239.08
N
**Simplex 6” Strainer
(EDG)
4730-01-199-8099 2 ea. 4,000.00
25 N **Simplex 4” Strainer STP 135-YF 4IN 1 ea. 1,442.70
N
**Simplex 6” Strainer
(MSW)
DWG 1512A 2 ea. 4,000.00
25 N **Simplex 10” Strainer 4730-01-304-7347 2 ea. 21,600.00
26 Y **Rudder Assembly NSN: 2040-01-486-0550 2 ea. 182,000.00
26 N **Upper Bearing NSN: 3110-01-121-8032 2 ea. 3,910.00
26 N **Rudder Stock Sleeve NSN: 2040-01-F91-0187 2 ea. 4,269.00
26 N John Crane Seal kit NSN: 5330-01-527-0778 2 ea. 5,955.00
26 N **Thordon Lower
Bearing (SXL 20.7" X
17.5" X 14)
PN: F546150102 2 ea. 1,000.00
27 N Seal, Plain PN: 1856959-3 (Sperry Marine)
= 17855H1L5
NSN: 5330-01-625-6617
4 ea. 383.45
27 N O-Rings PN: MS9021-381
NSN: 5331-00-763-2637
4 ea. 9.21
27 N Packing Material NSN: 5330-00-902-5505 2 Roll 885.14
27 N Packing Material NSN: 5330-00-527-7496 16 ft. 16.30
27 N Thordon Bearing Set
Assembly
PN: TBFINSTABTG13886BRG
NSN: 3110-01-599-8155
2 ea. 11,916.00
27 N Inflatable Seal NSN: 5330-01-103-6518 2 ea. 1,031.62
27 Y **Roller Bearing NSN: 3110-00-155-9065 2 ea. 897.92
27 N O-ring NSN: 5331-01-306-4879 2 ea. 9.02
27 N O-ring PN: MS9021-359
NSN: 5331-00-435-0431
2 ea, 5.60
27 N O-ring PN: MS9021-377
NSN: 5331-01-129-0629
2 ea. 9.58
27 N Seal, Plain PN: 1856959-2 (Sperry Marine)
= 17444H1L5
NSN: 5331-01-625-4197
4 ea. 113.73
27 N **Seal Retainer NSN: 5330-01-382-7103 2 ea. 228.00
27 N Lantern Rings NSN: 4320-01-377-2106 2 ea. 720.33
27 N **Seal Housing NSN: 5330-01-382-9160 2 ea. 1,622.00
27 N **Tiller Ram Pin NSN: 5315-01-419-1523 4 ea. 829.00
27 N **Tiller Ram Clevis Pin NSN: 5315-01-685-7187 4 ea. 600.00
27 N **Hydraulic Cylinder NSN: 3040-01-103-6565 4 ea. 5,652.21
27 Y **Fin Stock with sleeves NSN: 3040-01-104-5121 2 ea. 17,849.79 xv (Rev-0)
27 Y *Fin Removal Tools NSN: 5180-01-F10-1826 1 set 15,000.00
30 Y *Transducer Cover Plate N/A 4 ea. 50.00
32 Y Anchor Windlass
Assembly
Port (B-Class)
NSN: 3950-01-F25-7138
PN: VAW-1.50-30E-36-B-P
1 ea. 222,000.00
32 Y Anchor Windlass
Assembly
Stbd (B-Class)
NSN: 3950-01-F25-7142
PN: VAW-1.50-30E-36-B-S
1 ea. 222,000.00
32 N Motor Controllers NSN: 6110-01-F25-7212
PN: ACS880-01-052A-5
2 ea. 5,000.00
32 N Junction box enclosure with pushbutton control pendant.
NSN: 0000-XF-C39-6480
PN: SCE-10086ELJSS6
2 ea. 2,000.00
32 N Cable, Electrical NSN: 6145-01-F25-7243
PN: 37-103-312VFD
1 ea. 4,798.08
33 N Auxiliary Salt Water
Pump
PN: Durco MK3 Pump 2K6X4V-
13RV-CD4
NSN: 4320-99-602-2262
2 ea 42,000.00
34 N Raw Water Pump*** NSN: 4320-01-705-5667
PN: MK3 1K3X1.5V M3V/1-
CD4
1 ea. 17,447.00
35 N Viking Industries Shore
Power Receptacle
Assembly, with 20ft
THDF-500 Cable***
PN: M24368/2-001 1 ea. 20,000.00
36 N Flow Switch NSN: 5930-01-043-0942 2 ea. 456.62
36 N Meter, Impeller Type, Liquid
NSN: 6680-01-727-4949
PN: G2P10NQ9GMA
2 ea. 800.00
37 N Parker HP In-Line
Duplex Filter
NSN: 4330-01-F25-7161
PN: 32PD-1-20Q-B-N-K-G20-1
6 ea. 4,252.11
37 N Parker Special Tube
Fitting NPS BSPP Male x
1-1/4” SAE Code 61 flange
NSN: 4730-01-F25-7162
PN: 20A4EQ1-S
12 ea. 178.59
37 N Parker Check Valve, Iron, 1-1/2” NPS, SAE Code
61 Flanges
NSN: 4820-01-693-4271
PN: C5V12-310B1
6 ea. 780.14
44 Y Intech Marine Services
Custom Engine Room
Fan Controller
NSN: 6110-01-721-8667
PN: IMS-23-1344
2 ea. 6,755.00
46 N Chain for Anchor Swivel
Shot, 11 links, 1-1/2”
Stud Link, ABS Grade 3
PN: 4620012FT
2 ea. 5,000.00
46 N Swivel, 1-3/8”-1-1/2”
Chain, USN 803-5959226
PN: 7200012F 1 ea. 2,000.00
47 Y MK 38 MOD 2 GWS 1005-01-527-2849/8180341 1 ea. 639,000.00
47 Y MAIN COMPUTER
UNIT (MCU)
6920-01-659-2303/8566238-1 1 ea. 105,336.00
47 Y MK 1 MOD 1 MULTI-
FUNCTION DISPLAY
(MFD)
1260-01-659-1331/8566235-3 1 ea. 68,334.00
47 Y MK 1 MOD 1 MAIN
CONTROL PANEL
6920-01-569-7066/8566238-2 1 ea. 65,167.00 xvi (Rev-0)
(MCP)
47 Y COMMANDER
SAFETY PANEL (CSP)
1005-01-566-2005/8180375
1 ea. 2,957.00
47 Y BATTERY CHARGER,
I/P 115VAC, 60HZ, 1PH,
O/P 24-28VDC
1005-01-606-3054/8566240-2 1 ea. 51,308.00
47 Y REMOTE OPERATION
CONSOLE (ROC)
NSN: N/A 1 ea. N/A
47 N MK38 MAINTENANCE
PLATFORM
NSN: N/A 1 ea. N/A
47 N MK38 FOUNDATION
ADAPTER
NSN: N/A 1 ea. N/A
*Government-loaned property, which shall be returned to the vessel upon completion of the availability.
**New or refurbished equipment that the Government may provide for installation in place of existing equipment.
***Government-furnished property, which is to be supplied by either the vessel or the C4IT ServiceCenter xvii (Rev-0)
CONSOLIDATED LIST OF CRITICAL INSPECTION ITEMS
The following is a list of work items, which contain Critical Inspection reports, which the Contractor must complete within the first 25% of the availability contract period (see SFLC Std Spec 0000, paragraph 3.2.6.1.4
(Inspection report particulars)):
Work
Item Title
1 Hull Plating, U/W Body, Ultrasonic Testing
2 U/W Body, Preserve, 100 percent
5 Appendages (U/W), Preserve (Internal) and Leak Test
6 Voids (Non-Accessible), Preserve (Internal) and Leak Test
8 Propulsion Shafting; Remove, Inspect, and Reinstall
9 Propulsion Intermediate Shafts; Remove, Inspect, and Reinstall
Propulsion Shaft Seal (Mechanical And Inflatable) Assemblies, Inspect and Repair or
Renew
15 Propulsion Shaft Bearings, External, Renew
17 Controllable Pitch Propellers, Clean and Inspect
18 Controllable Pitch Propeller (CPP) System, Inspect and Service
24 Sea Strainers, Duplex, All Sizes, Overhaul
25 Sea Strainers, Simplex, All Sizes, Clean and Inspect
26 Rudder Assemblies; Remove, Inspect And Reinstall
27 Fin Stabilizers (Bearings, Packing, Stock/Blade), Repair or Renew
32 Anchor Windlass, Replace
33 Auxiliary Salt Water Pump, Replace
40 Bos’n Storeroom Deck Plating, Renew
42 Machinery Space Deck Plating, Renew
47 MK 38, MOD 2, Install xviii (Rev-0)
PRINCIPAL CHARACTERISTICS
270' WMEC (B-CLASS)
PHYSICAL
Length overall 270' 0"
Length between perpendiculars 255' 0"
Beam molded 38' 0"
Depth molded, main deck amidships, 01 level amidships
23' 7"
31' 4"
Full load displacement 1,886 long tons
Draft, full load to baseline amidships 14' 2"
Highest projection above baseline
*height approximated
≈ 110' 0"
Shore tie voltage requirements 2 cables, 400A / 450V, 3 phase
Frame spacing 1' 0"
MACHINERY
Main propulsion 2 ALCO Model 18-251-F Diesel Engines, 3,650 BHP each
Ship’s service generators 2 Caterpillar Model D-398-TA Diesel-driven KATO 6P6-1350 Generators. 475
KW each @ 0.8 power factor, 450VAC, 3 phase, 60 cycle
Emergency generators Caterpillar Model D-348-TA Diesel-driven KATO 4P4-1900. 475KW @ 0.8 power factor, 450VAC, 3 phase, 60 cycle
Number of propellers 2
Propeller diameter 9' 0"
Number of blades, each 4
Pitch Controllable
Shaft RPM 260
Shaft diameter 10.55" at exit of hull
Anchor & chain Two 4,000 lb Navy Stockless Anchors, 8 shots of chain each
TANK CAPACITIES
Diesel fuel total (95%) 79,950 gal.
JP-5 total (95%) 19,626 gal.
Potable water total (100%) 8,553 gal.
Hydraulic & lube oil total (95%) 2,561 gal.
xix (Rev-0)
00000_0725_FLT
REC_00000_FLT_Commercial Project @ Contractor’ Facility (0121)
General Requirements
1. SCOPE
1.1 Intent. This standard specification invokes general requirements for conducting vessel repairs performed at a commercial contractor’s facility for Coast Guard vessels.
1.2 Term interchangeability. The terms 'Contractor', 'CG Yard', 'NAVSTA EVERETT', 'shipyard', 'Base', and
'Coast Guard Industrial' are used interchangeably in this specification. Where the primary service provider is
Coast Guard personnel, references to contractor and other noted descriptors within this specification or within drawings, publications, SFLC Standard Specifications or other commercial and military references are deemed the same as prime service provider.
2. REFERENCES
COAST GUARD DRAWINGS
None
COAST GUARD PUBLICATIONS
Coast Guard Commandant Instruction (COMDTINST) M10360.3 (series), Coatings and Color Manual
Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2022, General
Requirements
Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2022, Welding and
Allied Processes
Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2022, Requirements for Preservation of Ship Structures
OTHER REFERENCES
Code of Federal Regulations (CFR) Title 29, Part 1915, Occupational Safety and Health Standards for
Shipyard Employment
NAVSEA Technical Publication T9074-AD-GIB-010/1688, (TP 1688), July 2012, Requirements for
Fabrication, Welding, and Inspection of Submarine Structure
3. REQUIREMENTS
3.1 General. The Contractor must conform to all requirements specified in SFLC Std Spec 0000 and in this item, as applicable, during the performance of this availability. The requirements in this WI applies to all work under the scope of this contract, whether explicitly stated in all following work items or not, and to all other work subsequently authorized by changes, modifications, or extensions to the contract.
xx (Rev-0)
NOTE
NAVSEA drawings listed will be available FOR INSPECTION ONLY from the Coast
Guard Port Engineer post-award. SFLC will not redistribute NAVSEA documents.
Contractors can apply to NAVSEA headquarters directly for copies.
3.2 Fire watch requirements. The Contractor must refer to 3.3.1.3 (Fire watch requirements) of SFLC Std Spec
0000, in accomplishing the following task:
• Provide portable fire extinguishers for Coast Guard fire watch personnel. Coast Guard fire watch is in lieu of contractor personnel during the hours of 0800-1600, Monday through Friday, and limited to two Coast Guard fire watch personnel.
• Provide fire watch personnel and fire extinguishers for the duration of the availability period, during and beyond noted Coast Guard fire watch support.
3.3 Preservation requirements. The Contractor must accomplish all preservation tasks, including touch-ups, in accordance with SFLC Std Spec 6310.
3.3.1 Brand name approval. Ensure that all contractor-furnished coatings are in accordance with SFLC Std Spec
6310, Appendix C (Authorized Coatings for Use on Cutters and Boats).
3.3.2 Coating colors and system color schemes. The Contractor must obtain a written KO authorization to deviate from any coatings required in SFLC Std Spec 6310 Appendix C before work.
3.3.3 In-process quality control measures. The Contractor must abide by all the safety, preservation, and quality control requirements specified in SFLC Std Spec 0000, paragraph 3.2.4.2 (In-process QC measures for “critical-coated surfaces”).
3.3.3.1 Quality control requirements. The Contractor must abide by the following when performing preservation related inspections. The following measurements must be randomly spaced throughout for the purposes of providing a representation of the entire prepared or coated surface.
3.3.3.1.1 Surface profile measurements. One surface profile measurement must be taken for every 200 square feet for the first 1000 square feet; for each additional 500 square feet or less, one profile measurement must be taken.
Profile measurements must be taken in accordance with SFLC Std Spec 6310, paragraph 3.1.8.3 (Surface profile measurements). A “measurement” for surface profile is defined as follows:
• ASTM D4417, Method B: One profile measurement is the average (mean) of 10 individual readings.
• ASTM D4417, Method C: One profile measurement is the average (mean) of 2 individual readings.
3.3.3.1.2 Soluble salt conductivity measurements. 5 conductivity measurements must be taken every 1000 square feet. For submerged (immersed) applications conductivity measurements must not exceed 30 microsiemens/cm.
For non-submerged (non-immersed) applications conductivity measurements must not exceed 70 microsiemens/cm. If a conductivity check fails, clean the surface in accordance with SFLC Std Spec 6310, paragraph 3.1.8.5 (Soluble salt removal).
3.3.3.1.3 Coating thickness measurements. Three area measurements must be taken for the first 1000 square feet;
for each additional 1000 square feet, perform an additional area measurement. A “measurement” for coating thickness is defined as follows:
• SSPC-PA 2 defines an area measurement as 5 separate spot measurements randomly spaced throughout a 100 square foot area.
• SSPC-PA 2 defines a spot measurement as 3 gage readings and each new gage reading the probe must xxi (Rev-0) be moved to a new location within a 1.5-inch diameter circle defining the spot.
3.4 Welding and brazing requirements. The Contractor must perform all welding and allied processes, and NDE in accordance with SFLC Std Spec 0740.
3.4.1 HY-130 material substitution. The Contractor must be aware that HY-130 steel plating is no longer commercially available. For the purpose of performing flight deck repairs on US Coast Guard WMEC-270 “B-
Class” cutters, Strenx 900 steel plating has been approved as a replacement for HY-130. Due to the similarity in material properties and weldability of HY-130 and Strenx 900, all welding procedures and welder qualifications for welding Strenx 900 must be the same as those outlined in NAVSEA TP 1688 as applicable for welding HY-
130.
3.4.2 Standard spec modification. For any welding involving HY-130 on the flight deck of WMEC-270 “B-Class” cutters, perform all welding and allied processes, and non-destructive evaluation (NDE) in accordance with
NAVSEA TP 1688. The Contractor must be aware that the welding requirements specified in this document take precedence over paragraph 3.3.6 of SFLC Standard Spec 0000 for the purpose of welding involving HY-130.
3.4.3 Approval to weld HY-130. To obtain Coast Guard approval to weld on HY-130 steel for WMEC-270 “B-
Class” cutters, the Contractor must provide written Performance Qualification Records (PQR’s) for each process to be used. The PQR’s must be approved by one of the regulatory agencies affirming that the WPS meets the welding requirements of NAVSEA TP 1688. In addition, the Contractor must ensure that all subcontractors, prior to performing welding operations, have qualified procedures by meeting all the requirements set forth in this document.
NOTE
NAVSEA approval is NOT required for welding procedures submitted but the procedures must be reviewed and shown to satisfy the requirements set forth in
NAVSEA TP 1688, by a welding regulatory agency. The requirements for welding
Strenx 900 are considered the same as those for welding HY-130.
3.5 Environmental protection requirements. The Contractor must adhere to the following environmental protection requirements in accordance with the SFLC Stand Spec 0000:
3.5.1 Contractor operated (non USCG) facilities. The Contractor must provide and maintain environmental protection as defined in SFLC Std Spec 0000 Appendix A, Requirements for Environmental Protection at
Contractor Operated (Non USCG) Facilities, as applicable, during the performance of this availability. Contractor must plan for and provide environmental protective measures to control pollution that develops during normal practice, as well as plan for and provide environmental protective measures required to correct conditions that develop during the project. Contractor must comply with applicable Federal, state, and local laws, codes, ordinances, and regulations in their entirety. Any reference to a specific portion of a Federal, state, or local law, code, ordinance, or regulation in this or any other item must not be construed to mean that relief is provided from any other sections of the law, code, ordinance, or regulation.
3.5.2 Test and procedures. The Contractor is required to promptly conduct tests and procedures for the purpose of assessing whether operations are in compliance with applicable Environmental Laws. Analytical work must be done by qualified laboratories; and where required by law, the laboratories must be certified.
3.5.3 Regulatory notifications. The Contractor is responsible for all regulatory notification requirements in accordance with Federal, State and local regulations. In cases where the Coast Guard must also provide public notification, such as storm water permitting, the Contractor must coordinate with the Contracting Officer or COR, and if work is being performed at a USCG Facility, the local Facility Engineer or Engineering Officer. The xxii (Rev-0)
Contractor must submit copies of all regulatory notifications to the Contracting Officer and the local Facility
Engineer or Engineering Officer prior to commencement of work activities. Regulatory notifications must be provided for including but not limited to demolition, renovation, National Pollutant Discharge Elimination System
(NPDES) defined site work, and remediation of controlled substances such as asbestos, hazardous waste, and lead paint.
3.5.4 Environmental manager. The Contractor must appoint in writing an Environmental Manager for the project, who is responsible for coordinating Contractor compliance with Federal, State, local, and station environmental requirements. The Environmental Manager must ensure compliance with Hazardous Waste Program requirements, including hazardous waste handling, storage, manifesting, and disposal; implement the Contractors’
Environmental Management Plan; ensure that all environmental permits are obtained, maintained, and closed out;
ensure compliance with Storm Water Program Management requirements; ensure compliance with Hazardous
Materials including storage, handling, and reporting requirements; as well as coordinate any remediation of regulated substances such as lead, asbestos, and polychlorinated biphenyl (PCB). This may be a collateral position; however the individual must be trained to accomplish the following duties; ensure waste segregation and storage compatibility requirements are met; inspect and manage Satellite Accumulation areas; ensure only authorized personnel add wastes to containers; ensure all Contractor personnel are trained in 40 CFR requirements and individual position requirements; coordinate removal of waste containers; and maintain the Environmental
Records binder and required documentation, including environmental permits compliance and close-out.
3.5.5 HW disposal. Contractor must comply with SFLC Std Spec 0000 Appendix A, Requirements For
Environmental Protection At Contractor Operated (Non USCG) Facilities for HW disposal.
3.6 Local Policy. The Contractor must refer to site (e.g., Base) Regulations and Instructions for details regarding local policies (e.g., crane services, parking, or facility usage).
3.7 SFLC Standard Specification approved changes. Approved updates to the 2022 SFLC Standard Specifications will appear here.
3.7.1 Not applicable.
4. NOTES
4.1 QA inspection forms. QA inspection forms (QA-1 thru QA-5), required in SFLC Std Spec 6310 to be completed and submitted during preservation of “critical-coated surfaces”, are provided at the end of this document.
xxiii (Rev-0)
QA-1 - QUALITY ASSURANCE INSPECTION FORM
(PRESERVATION CHECKLIST)
VESSEL NAME HULL # WORK ITEM
WORK ITEM TITLE
LOCATION OF WORK (INCL. FRAME #’S) AREA (SQFT)
CHECKPOINT 1 – COATING SYSTEM COMPLIANCE
Ensure all coatings are in compliance with SFLC Std Spec 6310, Appendix C.
CHECKPOINT 2 - PAINT STORAGE
Ensure all coatings are kept at a temperature of 65 to 85°F at all times, unless otherwise specified by the coating mfg.
CHECKPOINT 3 - AMBIENT CONDITIONS
Ensure surface and surrounding temperatures are each between 50 and 90°F for water-containing coatings, and 35 and 95°F for other coatings, unless otherwise specified by the coating manufacturer(s).
Ensure maximum relative humidity (RH) is as follows, from surface preparations through final curing of topcoat: 50% for tanks, voids, and vent plenum; and 85% for all other areas, unless otherwise specified by manufacturer(s).
Ensure surface temperature is at least 5°F above the dew point, unless otherwise specified by the coating mfg.
CHECKPOINT 4 - PRE-SURFACE PREPARATION
Remove surface contaminants (soluble salts, loose rust, mud, and marine growth) with low pressure fresh water wash down (maximum 5,000 psi). If oil and grease are present, perform solvent cleaning, as per SSPC SP-1.
Verify equipment setup, blast media, and surface…