Attachment 2 - Statement of Work.pdf
PDF 134 KB Posted
- Attached to
- Stunner Bridge Repair Federal contract opportunity
- Solicitation number
- 1240LT22R0026
- Issued by
- Department of Agriculture Forest Service
About this file
This document contains a statement of work and related federal contract opportunity solicitation for bridge repair work. The U.S. Forest Service is soliciting offers for a sole source, firm-fixed price contract between $500,000 to $1,000,000 to perform repair work on the Stunner Bridge located in the Rio Grande National Forest in Colorado. The scope of work involves establishing traffic control, removing vegetation, excavating for footings, constructing footings and abutments, installing girders and decking, backfilling, paving approaches, installing guardrails, and seeding. Offerors must be certified as an 8(a) small business by the SBA to be eligible for award. The statement of work provides additional details on submittals, specifications, waste disposal locations, and plans.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Attachment 6 - Questions and Answers.pdf | ||
| 1240LT22R0026-0002.pdf | ||
| Attachment 1 - Schedule of Items.xls | XLS spreadsheet | |
| 1240LT22R0026-P0001.pdf | ||
| Attachment 1 - Schedule of Items.xls | XLS spreadsheet | |
| Attachment 3 - Stunner Bridge Plans.pdf | ||
| Attachment 4 - Stunner Bridge Specifications.pdf | ||
| RFP 1240LT22R0026 - Stunner Bridge Repair.pdf | ||
| Attachment 5 - WD CO20220012.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
- 1 -
SECTION C – SPECIAL CONTRACT REQUIREMENTS
GENERAL
Scope of Work:
The work shall consist of what is shown on the plans, stated in the specifications, and summarized below:
• Establish the traffic control signing as required.
• Remove trees and clear and grub as required.
• Excavate for footings.
• Construct the footings.
• Construct the abutments and wingwalls.
• Backfill the abutments.
• Grade portions of the channel banks under the new bridge.
• Install riprap adjacent to the new structure.
• Erect the steel girders.
• Place concrete deck.
• Construct the remaining backfill and a portion of the approach embankments.
• Install the bridge rails.
• Obliterate the old road and use the material to complete the new embankments.
• Install asphalt paving.
• Install the approach rails.
• Open the road new road to traffic.
• Close the road to existing bridge.
• Remove the existing bridge.
• Complete the grading at the location of the original bridge and road.
• Complete the riprap installation along the stream.
• Prepare the finished grading and apply seeding.
Project Location:
The bridge carries FSR 250 over the Alamosa River. The bridge is located southwest of
Monte Vista, Colorado and is just off of FSR 250 approximately 28 miles west of State
Highway 15 in the Rio Grande National Forest.
- 2 -
Work Procedure:
All work related to this project shall be done in accordance with all applicable OSHA and
State of Colorado regulations.
Final construction staging areas shall be designated by the CO. Security of the staging area shall be the responsibility of the Contractor.
If the contractor will be camping near the site, a permit must first be obtained. The permit request shall be made through the CO.
Waste Location:
Excess excavated material is to be wasted Lieutenant Creek Pit, approximately 12 miles away
(Latitude 37.392667, Longitude -106.398157). Excess material shall be graded to provide positive drainage. Coordinate grading and locations with the CO.
Referenced Specifications:
Construction shall conform to the specifications in the “Standard Specifications for
Construction of Roads and Bridges on Federal Highway Projects, U.S. Customary Units” publication FP-14, 2014 Edition. This publication may be obtained from:
http://flh.fhwa.dot.gov/resources/specs/ http://flh.fhwa.dot.gov/resources/specs/
- 3 -
List of Required Submittals:
The required submittals shall include, but are not limited to, the following:
Submittal
Type
Plan Sheet
Reference
Specification
Reference
Description
Equipment Mobilization
Notification
NA Special Contract
Requirement 107
Equipment
Mobilization
Notification
Written Plan N/A Std. Specification
Section 153 and
Special Contract
Requirement 153
Quality Control Plan
Written Plan N/A Special Contract
Requirement 153
Proposal for Alternate
Test Methods (if applicable)
Written Plan Sheet C0.1, Note
N/A Hazardous Spill Plan
Written Plan N/A Special Contract
Requirement 107
Fire Prevention and
Suppression Plan
Written Plan N/A Special Contract
Requirement 157
Erosion Control Plan
Written Plan Sheet B1, Note
N/A Health and Safety
Plan for Working with Lead Paint
Written Plan N/A Standard
Specification
Section 203
Bridge Removal Plan
Written Plan Sheet B6 Special Contract
Requirement 208
Construction Plan for
Gap at Abutment 2
Written Plan N/A Special Contract
Requirement 208
Dewatering Plan
Written Plan N/A Special Contract
Requirement 155
Written Plan for
Construction
Schedule
Written Plan N/A Standard
Specification
Section 156
Written Plan for
Alternate Traffic
Control Plan
Written Plan N/A Standard
Specification
Section 555
Girder Erection Plan
Written Plan N/A Standard
Specification
Section 555
Quality Control Plan for Girder Fabrication
Written Notice N/A Standard
Specification
Section 555
Notice of Beginning
Shop Work for
Structural Steel
Fabrication
Certification/Documentation N/A Special Contract
Requirement 171
Noxious Weed
Certification
(Vehicles)
Certification/Documentation N/A Special Contract
Requirement 153
QC, Inspector, and
Testers Qualifications
Certification/Documentation N/A Special Contract
Requirement 153
Structural Backfill and Surface
- 4 -
Submittal
Type
Plan Sheet
Reference
Specification
Reference
Description
Aggregate Test
Reports
Certification/Documentation N/A Special Contract
Requirement 153
Testing Equipment
Calibration
Certification/Documentation N/A Special Contract
Requirement 208
Structural Backfill
Test Reports
Certification/Documentation N/A Special Contract
Requirement 208
Surface Aggreage
Test Reports
Certification/Documentation N/A Special Contract
Requirement 301
Roadbase Test
Reports
Certification/Documentation N/A Standard
Specification
Section 403
Asphalt Pavement
Job-Mix Formula
Certification/Documentation N/A Standard
Specification
Section 552
Concrete Mix Design
Certification/Documentation N/A Standard
Specification
Section 555
Certified Mill Test
Reports
Certification/Documentation N/A Standard
Specification
Section 564
Bear Device
Submittal
Certification/Documentation Sheet B10 NA Deck and Screed
Elevation Table
Documentation N/A Standard
Specification
109.01
Measurement Notes
Documentation N/A Standard
Specification
203.05 (a) and (d)
Disposal Agreements, Statements, and
Permits
Documentation N/A Special Contract
Requirement
208.06
Cofferdam fill source, construction and restoration method (if applicable)
Sample N/A Special Contract
Requirement 552
Water Repellent
Concrete Sealer
Drawings N/A Standard
Specification 208
Working Drawings &
Construction Details of Excavation
Support Systems (if applicable)
Drawings N/A Special Contract
Requirement 552
Stay-In-Place
Forms/Erection Shop
Drawings
Drawings N/A Standard
Specification
Section 555
Structural Steel Shop
Drawings
Drawings N/A Special Contract
Requirement 554
Rebar Shop Drawings
Drawings N/A Standards
Specification 562
Formliner Drawings
- 5 -
Submittal
Type
Plan Sheet
Reference
Specification
Reference
Description
Drawings N/A Standard
Specification 613
Falsework and
Shoring Drawings and Calculations
Drawings Sheet B18 N/A Bridge Rail Shop
Drawings
Drawings Sheet CD1.1 N/A Approach Rail Shop
Drawings
Drawings N/A Special Contract
Requirement 104
As-Built Drawings
File details come from the government source that posted it. Updated .