Attachment 2 - Statement of Work.pdf

PDF 134 KB Posted

Attached to
Stunner Bridge Repair Federal contract opportunity
Solicitation number
1240LT22R0026
Issued by
Department of Agriculture Forest Service

About this file

This document contains a statement of work and related federal contract opportunity solicitation for bridge repair work. The U.S. Forest Service is soliciting offers for a sole source, firm-fixed price contract between $500,000 to $1,000,000 to perform repair work on the Stunner Bridge located in the Rio Grande National Forest in Colorado. The scope of work involves establishing traffic control, removing vegetation, excavating for footings, constructing footings and abutments, installing girders and decking, backfilling, paving approaches, installing guardrails, and seeding. Offerors must be certified as an 8(a) small business by the SBA to be eligible for award. The statement of work provides additional details on submittals, specifications, waste disposal locations, and plans.

View the file

Other files for this federal contract opportunity

Other files attached to Stunner Bridge Repair, newest first.
File Type Posted
Attachment 6 - Questions and Answers.pdf PDF
1240LT22R0026-0002.pdf PDF
Attachment 1 - Schedule of Items.xls XLS spreadsheet
1240LT22R0026-P0001.pdf PDF
Attachment 1 - Schedule of Items.xls XLS spreadsheet
Attachment 3 - Stunner Bridge Plans.pdf PDF
Attachment 4 - Stunner Bridge Specifications.pdf PDF
RFP 1240LT22R0026 - Stunner Bridge Repair.pdf PDF
Attachment 5 - WD CO20220012.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

- 1 -

SECTION C – SPECIAL CONTRACT REQUIREMENTS

GENERAL

Scope of Work:

The work shall consist of what is shown on the plans, stated in the specifications, and summarized below:

• Establish the traffic control signing as required.

• Remove trees and clear and grub as required.

• Excavate for footings.

• Construct the footings.

• Construct the abutments and wingwalls.

• Backfill the abutments.

• Grade portions of the channel banks under the new bridge.

• Install riprap adjacent to the new structure.

• Erect the steel girders.

• Place concrete deck.

• Construct the remaining backfill and a portion of the approach embankments.

• Install the bridge rails.

• Obliterate the old road and use the material to complete the new embankments.

• Install asphalt paving.

• Install the approach rails.

• Open the road new road to traffic.

• Close the road to existing bridge.

• Remove the existing bridge.

• Complete the grading at the location of the original bridge and road.

• Complete the riprap installation along the stream.

• Prepare the finished grading and apply seeding.

Project Location:

The bridge carries FSR 250 over the Alamosa River. The bridge is located southwest of

Monte Vista, Colorado and is just off of FSR 250 approximately 28 miles west of State

Highway 15 in the Rio Grande National Forest.

- 2 -

Work Procedure:

All work related to this project shall be done in accordance with all applicable OSHA and

State of Colorado regulations.

Final construction staging areas shall be designated by the CO. Security of the staging area shall be the responsibility of the Contractor.

If the contractor will be camping near the site, a permit must first be obtained. The permit request shall be made through the CO.

Waste Location:

Excess excavated material is to be wasted Lieutenant Creek Pit, approximately 12 miles away

(Latitude 37.392667, Longitude -106.398157). Excess material shall be graded to provide positive drainage. Coordinate grading and locations with the CO.

Referenced Specifications:

Construction shall conform to the specifications in the “Standard Specifications for

Construction of Roads and Bridges on Federal Highway Projects, U.S. Customary Units” publication FP-14, 2014 Edition. This publication may be obtained from:

http://flh.fhwa.dot.gov/resources/specs/ http://flh.fhwa.dot.gov/resources/specs/

- 3 -

List of Required Submittals:

The required submittals shall include, but are not limited to, the following:

Submittal

Type

Plan Sheet

Reference

Specification

Reference

Description

Equipment Mobilization

Notification

NA Special Contract

Requirement 107

Equipment

Mobilization

Notification

Written Plan N/A Std. Specification

Section 153 and

Special Contract

Requirement 153

Quality Control Plan

Written Plan N/A Special Contract

Requirement 153

Proposal for Alternate

Test Methods (if applicable)

Written Plan Sheet C0.1, Note

N/A Hazardous Spill Plan

Written Plan N/A Special Contract

Requirement 107

Fire Prevention and

Suppression Plan

Written Plan N/A Special Contract

Requirement 157

Erosion Control Plan

Written Plan Sheet B1, Note

N/A Health and Safety

Plan for Working with Lead Paint

Written Plan N/A Standard

Specification

Section 203

Bridge Removal Plan

Written Plan Sheet B6 Special Contract

Requirement 208

Construction Plan for

Gap at Abutment 2

Written Plan N/A Special Contract

Requirement 208

Dewatering Plan

Written Plan N/A Special Contract

Requirement 155

Written Plan for

Construction

Schedule

Written Plan N/A Standard

Specification

Section 156

Written Plan for

Alternate Traffic

Control Plan

Written Plan N/A Standard

Specification

Section 555

Girder Erection Plan

Written Plan N/A Standard

Specification

Section 555

Quality Control Plan for Girder Fabrication

Written Notice N/A Standard

Specification

Section 555

Notice of Beginning

Shop Work for

Structural Steel

Fabrication

Certification/Documentation N/A Special Contract

Requirement 171

Noxious Weed

Certification

(Vehicles)

Certification/Documentation N/A Special Contract

Requirement 153

QC, Inspector, and

Testers Qualifications

Certification/Documentation N/A Special Contract

Requirement 153

Structural Backfill and Surface

- 4 -

Submittal

Type

Plan Sheet

Reference

Specification

Reference

Description

Aggregate Test

Reports

Certification/Documentation N/A Special Contract

Requirement 153

Testing Equipment

Calibration

Certification/Documentation N/A Special Contract

Requirement 208

Structural Backfill

Test Reports

Certification/Documentation N/A Special Contract

Requirement 208

Surface Aggreage

Test Reports

Certification/Documentation N/A Special Contract

Requirement 301

Roadbase Test

Reports

Certification/Documentation N/A Standard

Specification

Section 403

Asphalt Pavement

Job-Mix Formula

Certification/Documentation N/A Standard

Specification

Section 552

Concrete Mix Design

Certification/Documentation N/A Standard

Specification

Section 555

Certified Mill Test

Reports

Certification/Documentation N/A Standard

Specification

Section 564

Bear Device

Submittal

Certification/Documentation Sheet B10 NA Deck and Screed

Elevation Table

Documentation N/A Standard

Specification

109.01

Measurement Notes

Documentation N/A Standard

Specification

203.05 (a) and (d)

Disposal Agreements, Statements, and

Permits

Documentation N/A Special Contract

Requirement

208.06

Cofferdam fill source, construction and restoration method (if applicable)

Sample N/A Special Contract

Requirement 552

Water Repellent

Concrete Sealer

Drawings N/A Standard

Specification 208

Working Drawings &

Construction Details of Excavation

Support Systems (if applicable)

Drawings N/A Special Contract

Requirement 552

Stay-In-Place

Forms/Erection Shop

Drawings

Drawings N/A Standard

Specification

Section 555

Structural Steel Shop

Drawings

Drawings N/A Special Contract

Requirement 554

Rebar Shop Drawings

Drawings N/A Standards

Specification 562

Formliner Drawings

- 5 -

Submittal

Type

Plan Sheet

Reference

Specification

Reference

Description

Drawings N/A Standard

Specification 613

Falsework and

Shoring Drawings and Calculations

Drawings Sheet B18 N/A Bridge Rail Shop

Drawings

Drawings Sheet CD1.1 N/A Approach Rail Shop

Drawings

Drawings N/A Special Contract

Requirement 104

As-Built Drawings