Attachment 1 - Schedule of Items.xls

XLS spreadsheet 205 KB Posted

Attached to
Stunner Bridge Repair Federal contract opportunity
Solicitation number
1240LT22R0026
Issued by
Department of Agriculture Forest Service

About this file

This solicitation and schedule of items are for the repair of the Stunner Bridge located in the Rio Grande National Forest in Colorado. The U.S. Forest Service will award a single firm-fixed price contract between $500,000 to $1,000,000 to remove the existing bridge and construct a new bridge over the Alamosa River. The successful offeror must be an 8(a) certified small business. The scope of work includes traffic control, clearing and grubbing, road and bridge removal, excavation, structural work, concrete work, steel erection, railings, asphalt paving, erosion control, grading, seeding and other items. Pricing is provided for various pay items in the schedule of items attachment. The contract location is the bridge over the Alamosa River on FSR 250 southwest of Monte Vista, Colorado. The solicitation number is 1240LT22R0026.

View the file

Other files for this federal contract opportunity

Other files attached to Stunner Bridge Repair, newest first.
File Type Posted
Attachment 6 - Questions and Answers.pdf PDF
1240LT22R0026-0002.pdf PDF
Attachment 1 - Schedule of Items.xls XLS spreadsheet
1240LT22R0026-P0001.pdf PDF
RFP 1240LT22R0026 - Stunner Bridge Repair.pdf PDF
Attachment 5 - WD CO20220012.pdf PDF
Attachment 3 - Stunner Bridge Plans.pdf PDF
Attachment 4 - Stunner Bridge Specifications.pdf PDF
Attachment 2 - Statement of Work.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SOI

USDA Forest Service
SCHEDULE OF ITEMS
Rio Grande National Forest
Stunner Bridge Repair
PAY ITEMDESCRIPTIONUNITQTYUNIT PRICETOTAL
150 - Project Requirements
151(01)MobilizationLump Sum1$ 30,000.00$ 30,000.00
152(01)Construction survery and stakingLump Sum1$ 12,000.00$ 12,000.00
152(14)Bridge survey and stakingLump Sum1$ 5,000.00$ 5,000.00
154(01)Contractor testingLump Sum1$ 5,000.00$ 5,000.00
157(01)Soil erosion controlLump Sum1$ 10,000.00$ 10,000.00
200 - Earthworks
201(03)Clearing and grubbingAcre0.5$ 7,500.00$ 3,750.00
203(01)Removal of bridge (bridge and abutments)Each1$ 45,000.00$ 45,000.00
203(02)Removal of guardrailLinear Feet100$ 5.00$ 500.00
204(20)Embankment construction (permanent)Cubic Yard385$ 25.00$ 9,625.00
208(01)Structure excavationCubic Yard182$ 35.00$ 6,370.00
208(03)Structural backfillCubic Yard253$ 50.00$ 12,650.00
208(04)Structural backfill, existing screenedCubic Yard1,250$ 5.00$ 6,250.00
208(20)DewateringLump Sum1$ 25.00$ 25.00
211(02)Roadway obliteration, method 1Square Feet7,650$ 10.00$ 76,500.00
250 - Slope Reinforcement and Retaining Walls
251(05)Keyed Riprap, Method ACubic Yard264$ 100.00$ 26,400.00
300 - Aggregate and Base Courses
301(01)Aggregate base, class 6 (commercially furnished)Ton950$ 60.00$ 57,000.00
302(01)Roadway aggregate, 6-inch depthTon95$ 60.00$ 5,700.00
302(03)Roadway aggregate, reuse existing, 6-inch depthTon95$ 20.00$ 1,900.00
400 - Asphalt Pavements and Surface Treatments
418(01)Asphaltic concrete pavement, 7-inch depthTon66$ 240.00$ 15,840.00
550 - Bridge Construction
552(01)Structural concrete, class C (AE)Cubic Yard166$ 975.00$ 161,850.00
554(01)Reinforcing steelLB6,000$ 1.00$ 6,000.00
554(01)Reinforcing steel, epoxy coatedLB17,515$ 1.50$ 26,272.50
555(01)Structural steelLump Sum1$ 132,970.00$ 132,970.00
556(01)TXDOT T1W Bridge railingLinear Feet141$ 225.00$ 31,725.00
563(01)Painting, concrete structureLump Sum1$ 3,000.00$ 3,000.00
564(01)Bearing device, elastomericEach4$ 1,250.00$ 5,000.00
600 - Incidental Construction
613(01)Simulated stone masonry surface treatmentSquare Yard88$ 315.00$ 27,720.00
617(01)Guardrail system (Type 3, class A steel or woodLinear Feet175$ 200.00$ 35,000.00
617(02)Terminal sectionEach4$ 800.00$ 3,200.00
624(07)Placing conserved topsoil, 3-inch depthCubic Yard40$ 2.00$ 80.00
625(10)Seeding, dry methodSquare Yard485$ 2.48$ 1,202.80
625(15)Mulching, dry methodSquare Yard485$ 2.48$ 1,202.80
629(01)Rolled erosion control product, type 2.BSquare Yard18$ 15.00$ 270.00
633(01)Sign systemEach6$ 750.00$ 4,500.00
633(08)Object markerEach4$ 300.00$ 1,200.00
635(01)Temporary traffic controlLump Sum1$ 20,000.00$ 20,000.00
Project Total$ 790,703.10