This is a Statement of Work (SOW) for the replacement of below-floor sanitary drain piping at the United States National Poultry Research Center (USNPRC) in Athens, Georgia, issued by the US Department of Agriculture (USDA).

The Contractor shall furnish all labor, supervision, materials, tools, equipment, and services necessary to demolish existing HDPE drain piping and install new 316L stainless steel drain piping. The scope includes approximately 2,668 linear feet of piping removal across three drain lines (BW3: 1,107 feet; BW3A: 1,320 feet; BW3AG: 241 feet), along with fabrication, installation, testing, and cleanup activities. Work must be performed in an occupied, operational facility while coordinating with USDA personnel to minimize disruption. The project must be completed within 180 days from the notice to proceed, with regular work hours of 8:00 am to 4:00 pm, Monday through Friday, excluding eleven federal holidays. The Contractor must obtain a site visit with a government representative before submitting a bid to confirm locations, dimensions, and existing conditions. Pre-construction submittals required include a project schedule, project design, Site Specific Safety Plan, and list of personnel. The Contractor is responsible for all safety measures, material protection, daily waste removal, daily work reports to the Contracting Officer's Representative, and weekly status updates. A Site Safety Specific Plan must be submitted within 14 days of contract award, and the drainage system must be tested for leaks per the May 2024 International Plumbing Code. The Contractor must provide a one-year guarantee against faulty materials and workmanship, with deficiencies corrected within 24 hours of notification. The work must comply with ARS 242.1M Facilities Design Standards and applicable federal, state, and local building codes, including ANSI, ASME, NEC, OSHA, and ADA standards. Security access requires government-issued identification with photo ID, visitor badges, facility orientation training, and compliance with all USDA biosecurity protocols relevant to the project, including containment access restrictions with 5:1 escort ratios where applicable.

View the file

Other files

Show all 16

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

US Department of Agriculture (USDA)

Statement of Work For

Replacement of B47 Sanitary Piping

Project Replacement of existing HDPE drain piping with welded 316L stainless steel drain piping at United States National Poultry Research Center (USNPRC) in Athens, GA.

General Information

1.0 Scope of Work

The United States National Poultry Research Center (USNPRC) is seeking a Contractor with extensive knowledge and expertise with design and facilities operations within animal agricultural research laboratories. USNPRC is designed to contain Bio-Safety Level (BSL) -2, BSL-3, ABSL-3, and BSL-3Ag animal agricultural research. Companies associated with services for the facility shall fully understand the construction types and maintenance methods associated with these facilities.

The United States Department of Agriculture (USDA) requires the replacement of existing below-floor sanitary drain piping systems within the facility located at 950 College Station Road, Athens, GA. The Contractor shall furnish all labor, supervision, materials, tools, equipment, and services necessary to demolish existing drain piping and install new 316L stainless steel drain piping in accordance with project requirements, drawings, and applicable codes.

All work shall be performed in occupied, operational facilities and coordinated with USDA personnel to minimize disruption.

Work includes, but is not limited to, demolition, fabrication, installation, coordination, and cleanup activities necessary to complete the drain piping replacement scope described herein. Drain vent and sanitary piping that extends above the floor decking will not be replaced and is excluded from this project.

Base Bid The Contractor shall provide a detailed proposal and cost breakdown for the entire project as specified in this statement of work.

Site Visit Contractors are required to visit the site and be escorted by a government representative to confirm locations, dimensions, and conditions of the project before a bid is submitted. The site visit shall be for the purpose of observing firsthand any conditions relevant to the completion of this project. No consideration will be given to claims based on lack of knowledge of existing conditions, except where contract documents make definite provisions for adjustment in cost or extension due to existing conditions not readily foreseeable.

Schedule Regular work hours for the site are 8:00 am to 4:00 pm, Monday through Friday, excluding Government holidays, unless otherwise approved by USDA.

Period of Performance The completion of this project shall not exceed 180 days from date of notice to proceed. A request for time extension must be submitted to the Contracting Specialist in writing. Each request must include specific and detailed reasons in support of the schedule alteration.

Federal Holidays The Contractor is hereby advised that Government personnel observe the following eleven (11) holidays:

• New Year's Day

• Birthday of Dr. Martin Luther King, Jr.

• Washington’s Birthday

• Memorial Day

• Juneteenth National Independence Day

• Independence Day

• Labor Day

• Columbus Day

• Veteran's Day

• Thanksgiving Day

• Christmas Day

In addition to the days designated as holidays, the government may observe the following days, any other days designated by Federal Statute; any other days designated by Executive Order; and any other days designated by the President's Proclamation. This includes Inauguration Day (Washington, D.C. metropolitan area only). Observance of such days by government personnel shall not be a reason for an additional period of performance, or entitlement of compensation. In the event of the Contractor's personnel work during the holiday, no form of holiday or other premium compensation will be reimbursed either as a direct or indirect cost.

2.0 Background

The objective is to award a contract for removal of all HDPE drain piping associated with the first floor drain system in B47 and replaced with welded stainless-steel piping. The USDA facility utilizes a Georg Fisher HDPE drain piping system that has proven to be unreliable for use inside our facility. This project will replace this system with a stainless-steel piping system to improve durability and long-term performance. The period of performance for this project will be 6 months.

The Contractor shall be an expert in mechanical and plumbing construction.

Contractor Requirements The Contractor shall provide a complete and functional installation, including all labor, supervision, tools, materials, equipment, apparatus, transportation, rigging and other equipment and services necessary to accomplish the work in accordance with the intent and meaning of this statement of work.

The project work shall be performed per the following guidelines:

1) Contractor will verify all dimensions and existing site conditions prior to beginning work.

2) The Contractor shall always be responsible for protecting his work and ensuring the safety of his crew and USDA employees.

3) Contractors shall remove and dispose of all construction related materials from all work areas daily and remove these waste materials from the site on a weekly basis.

4) Contractors are required to manage the project and consult with the Government prior to beginning all work phases.

5) Contractor shall perform work in a manner that minimizes the impact to daily operations of the facility and its workers. The building will be occupied during construction work.

6) Contractor will provide daily reports of work performed to the COR and weekly status updates to the TPOC.

7) Contractor must have a superintendent on the jobsite when crews are performing the installation work.

8) Contactors will provide their own restroom facility.

9) All Contractor personnel will be required to show a valid Federal or State ID to enter the property.

10) Contractors will abide by all USDA Biosecurity protocols relevant to this project.

11) Upon completion, the Contractor will test the drainage system for leaks in accordance with the May 2024 International Plumbing code (IPC), Chapter 3: General Regulations, section 312: Tests and Inspections, Sub-section 312.2: Drainage and vent water test.

The Contractor’s work meet ARS 242.1M P&P titled “ARS Facilities Design Standards” found at https://www.afm.ars.usda.gov/ppweb/pdf/242-01m.pdf and shall adhere to all applicable federal, state, and local building code requirements, established industry standards as well as health and safety codes in effect at the time of award, or as determined by the authority having jurisdiction.

Codes and Standards Applicable Codes and Standards apply and are not limited to the following:

ANSI - American National Standards Institute.

ASME - American Society of Mechanical Engineers.

NEC - National Electrical Code, NFPA 72.

OSHA - Occupational Safety and Health Administration ADA – Americans with Disabilities Act

All Contractor employees, including subcontractor employees, providing services for the USDA shall read, acknowledge, and follow all applicable USDA policies, SOPs, and guidelines. The Contractor shall work with USDA personnel to ensure all work is accomplished in a timely manner.

Safety The Contractor will submit a Site Safety Specific Plan (SSSP)/Accident Prevention Plan in industry recognizable format to the Contracting Officer within 14 days of contract award. The Government shall review the SSSP prior to the start of any construction activities.

Safety and health matters, as they relate to the work, are the exclusive responsibility of the Contractor. The Contractor shall furnish, erect, and maintain barricades, warning lights, signs, guards, or take other precautions that may be required by law or local authorities for the protection and security of the grounds, facilities, and personnel. Contractor shall coordinate with Lab Personnel and strictly always follow all Covid related precautions and procedures.

Guaranty The Contractor shall provide and submit a single guarantee stating that all portions of the work are in accordance with Contract requirements. Guarantee all work against faulty and improper material and workmanship for a period not less than one (1) year from date of final acceptance by the USDA, except where manufacturer guarantees or warranties are for longer terms. The Contractor shall correct any deficiencies which occur during the guarantee period within 24 hours after notification.

https://www.afm.ars.usda.gov/ppweb/pdf/242-01m.pdf

3.0 Technical Requirements / Tasks

3.1 Program Management

The Contractor shall provide on-site supervision and project management throughout the duration of the work.

Responsibilities include:

• Coordination with USDA personnel and other Contractors

• Schedule development and adherence

• Sequencing of demolition and installation activities

• Coordination of material deliveries and staging

• Daily oversight of field operations

Material Submittals The Contractor shall submit for approval all documents/samples necessary to ensure requirements of project will be satisfied. Electronic submittals on all equipment and materials used on this project shall be submitted to the TPOC noted in this document.

Pre-Construction Submittals Prior to construction activities beginning the following submittals must be provided to the CO and TPOC for approval.

1. Project Schedule (including daily work start/stop time)

2. Project Design

3. Site Specific Safety Plan (SSSP) / Accident Prevention Plan

4. List of contract personnel of the general and subcontractors

Inspection and Acceptance A government representative shall inspect and approve the work performed on this project. The Contractor shall schedule inspection a minimum of 2 days in advance with the TPOC.

4.0 Government Furnished Property and Services

The Contractor shall be responsible for safeguarding all Government property and using Government provided services responsibly. The Contractor shall conduct work so that Government property, personnel and work areas shall be always protected from inconvenience, damage or injury. In the event of loss or damage of any nature, caused by Contractor operations or employees, due to improper protection, precaution or safety measures, such damage shall be repaired, or such property shall be replaced by the Contractor at its expense. In the event the Contractor does not satisfactorily repair or replace such damages, the Government reserves the right to make necessary corrections, and the Contractor shall reimburse the Government for all labor and material costs associated with repairs or replacement.

4.1 Property

This section is not application to this requirement.

4.2 Services

Utilities: The Government will furnish electricity and water free of charge for the Contractor’s use incidental to contract performance at the location being serviced. The Contractor shall instruct employees in utility conservation practices and operate under conditions that preclude the waste of utilities.

Security and Fire Protection: In case of medical emergency, dial 911 from any phone. The Contractor may call the USDA Security at 706-546-3113 for Emergency assistance while performing services and requirements under this contract.

Emergency Medical Treatment: In the event of a severe emergency during hours of operation, call 911 for response and transport, if necessary, to an emergency medical facility. The Contractor shall be responsible for these services and all other associated services, as appropriate for their employees and subcontractors. Contractor personnel are responsible for preparing the necessary paperwork. All injuries will be promptly reported to the Contracting Officer (CO), Contracting Officer’s Representative (COR) and USDA’s Safety Office.

5.0 Deliverables

The following summarizes the deliverables associated with Section 3.0. All days are listed as business days. If a conflict exists between Section 3.0 and this table, Section 3.0 prevails. If a due date falls on a Federal holiday, Saturday, or Sunday, the deliverable due date shall be the next scheduled federal workday.

1. Review existing drawings, site conditions, and drainage routes.

2. Mobilize and obtain measurements for Shop Fabrication Drawings. Several trips may be required to complete all fabrication drawings.

3. Verify pipe sizes, slopes, elevations, and tie-in points.

4. Confirm stainless steel material type (e.g., 304 or 316), wall thickness, and welding method.

5. Identify shutoff points and schedule downtime with operations.

6. Develop safety plans (hot work, confined space, overhead work).

7. Obtain permits and hot-work authorization if required.

8. Protect surrounding equipment, finishes, and occupied areas.

9. Install temporary drainage or bypass system if required to maintain service.

10. Set up access (lifts, scaffolding, ladders) as needed.

11. Stage stainless steel piping, fittings, and welding equipment.

12. Isolate the existing HDPE drain system.

13. Drain and flush piping to remove liquids and debris.

14. Cap or temporarily seal open ends to control odors and spills.

15. Cut existing HDPE piping at the floor decking level as specified.

16. Remove drain lines that are Georg Fisher HDPE piping

a. BW3 (Approximately 1107’)

b. BW3A (Approximately 1320’)

c. BW3AG (Approximately241’)

17. Remove hangers, supports, and anchors associated with removed piping.

18. Carefully lower and remove HDPE sections to avoid structural or slab damage.

19. Dispose of removed HDPE piping and materials per local regulations.

20. Prepare cut HDPE pipe ends (square cut, cleaned).

21. Install approved HDPE-to-stainless transition coupling or flange adapter at the floor deck penetration.

22. Ensure transition is properly aligned, supported, and sealed.

23. Firestop or seal floor penetration as required by code.

24. Lay out new stainless-steel piping runs to match required slope and alignment.

25. Install stainless steel pipe supports and hangers (isolated from dissimilar metals).

26. Fit stainless steel pipe sections and fittings (elbows, tees, reducers).

27. Perform field welding (TIG or approved method) for all joints.

28. Allow for thermal expansion as required.

29. Perform welds in accordance with applicable standards and procedures.

30. Clean and passivate welds if specified.

31. Conduct visual weld inspection and any required NDT.

32. On-site weld scanning with BIM coordination

33. Repair or re-weld any defective joints.

34. Pressure test or leak test the stainless-steel drain system (per code/spec).

35. Inspect transition connections at floor decking for leaks.

36. Remove temporary bypasses.

37. Restore system to service and verify proper drainage and flow.

38. Provide as-built drawings if required.

39. Submit weld logs, test results, and inspection records.

40. Final walkthrough with owner/representative.

6.0 Travel

The Contractor shall include costs associated with onsite presence at USDA needed to meet the requirements of this statement of work in the FFP quote.

7.0 Contractor’s Key Personnel

8.0 Security Requirements

8.1 Site Security Access/Restrictions and Conditions

Access to the site is controlled by a security fence and visitor/Contractor check-in/check-out system. A current government-issued identification with a picture ID is required for entry. Contractor/subcontractor vehicles will be checked at the main entrance gate. A visitor badge will be issued/turned in daily at the security gate. The Contractor/visitor identification badge must always be worn while on the site.

Limited Contractor vehicles will be allowed access adjacent to the work; Contractor employees’ personal vehicles shall be parked in the facilities main parking lot unless approved otherwise.

Work shall be confined to the areas where the work is specified. Unless accompanied by a USDA employee, the Contractor, subcontractors, and their employees shall not enter buildings or facility spaces not specifically part of this project. Reasons included, but are not limited to, disease control and health requirements.

Failure to comply with access requirements shall be adequate grounds for removal of the Contractor/subcontractor employees from the site and barring further site access to individuals.

Personnel employed by the Contractor or any representative of, or agent of the Contractor, entering this facility shall conform to the facility security regulations and any site training requirements. The prime Contractor is required to provide onsite escort of Contractor employees or any representative of, or agent of the Contractor entering this facility.

All site visitors will be required to participate in facility orientation prior to being allowed to work onsite. The Contractor shall provide all information required for background checks to meet facility access requirements as performed by the facility security office.

8.2 Security Ingress/Egress for Contract Activities

Contractor Personnel, Small Tools & Equipment. The Main Entry serves as the initial screening point for vehicles and visitors. All Vehicles, equipment, and personnel will be confirmed for USDA access. Once cleared, visitors will be directed to park in the main lot and instructed to proceed to the specified work area.

Upon entry, visitors will be issued a short-term visitors badge for the day of their visit. Visitors will be required to present valid REAL ID Act complaint identification and sign in on a Daily Visitor Log during processing. All badges must be worn above the waist in such a manner that the photo and expiration date are always clearly visible from the front. No items may be attached to the card or affixed to the holder that would obscure the information on the card.

Upon successful screening, visitors will be escorted by either Contractor staff with a Contractor Service Provider Badge/PIV or an authorized USDA Escort to their designated work location. Escorts must always maintain line of sight of visitors and the site established escort ratio. Leaving the designated work areas, escorted visitors will turn their short-term visitor badges into the facility security guards at the end of each day. They will then exit through the Main Gate.

Vehicles, equipment, and personnel are subject to additional Security Screening and egress procedures pending campus status.

8.3 Security Ingress/Egress for Contract Activities Requiring Material Delivery or Work Vehicle Access Contractor Personnel, Vehicles, Tools, Equipment, Material Deliveries & Shipments. The Main Entry serves as the initial screening point for vehicles and visitors. All Vehicles, equipment, and personnel will be confirmed for USDA access. Once cleared, visitors may be screened by Security or will be directed to park in the parking lot. Visitors will be required to sign in on a Daily Visitor Log during processing.

8.4 Security Ingress/Egress for Contract Activities Requiring Material Delivery or Work Vehicles Access and Containment Access Access/Egress of containment loading areas and activities within containment are subject to additional limitations, requirements and restrictions that will be determined, evaluated, and approved on a case-by-case basis. All personnel, tools, equipment, and materials are subject to additional Security Screening and ingress/egress procedures pending campus status. At no time can a direct path from outside the facility into containment occur.

Within containment, the containment cafeteria is the only authorized place to eat and drink. All Contractor staff and visitors will be required to check their phones into a locker outside of containment prior to entering containment.

Escorts must always maintain line of sight of visitors and a 5:1 escort ratio.

All Contractor staff and visitors will follow the USDA Facility SOP for access into the Main Lab area. Access/Egress of containment areas and activities within containment are subject to additional limitations, requirements and restrictions that will be determined, evaluated, and approved on a case-by-case basis. All Contractor staff and visitors will be required to check their phones into a locker outside of containment. All Contractor staff and visitors will participate in all required training and sign a “No Off-Site Avian Contact” form before access into containment will be allowed. All personnel, tools, equipment, and materials are subject to additional Security Screening and ingress/egress procedures pending campus status. Escorts will have all Contractor staff and visitors sign the visitor log. All Contractor staff and visitors will be escorted into containment and throughout by an authorized USDA employee with containment access.

Upon leaving containment, all Contractor staff and visitors will sign out on the visitor log.

9.0 Data Rights

10.0 Section 508 – Electronic and Information Technology Standards

Project
General Information
1.0 Scope of Work
2.0 Background
Contractor Requirements
3.0 Technical Requirements / Tasks
3.1 Program Management
4.0 Government Furnished Property and Services
4.1 Property
4.2 Services
5.0 Deliverables
6.0 Travel
7.0 Contractor’s Key Personnel
8.0 Security Requirements
8.1 Site Security Access/Restrictions and Conditions
8.2 Security Ingress/Egress for Contract Activities
8.3 Security Ingress/Egress for Contract Activities Requiring Material Delivery or Work Vehicle Access
8.4 Security Ingress/Egress for Contract Activities Requiring Material Delivery or Work Vehicles Access and Containment Access
9.0 Data Rights
10.0 Section 508 – Electronic and Information Technology Standards