Statement of Work Summary: Salmon River Seed Orchard Well Drilling
This Statement of Work describes a groundwater well drilling project for the Nez Perce-Clearwater National Forests in Idaho County, Idaho. The project objective is to drill a well to provide potable water to the nursery located at the Salmon River Seed Orchard, with work to commence no earlier than June 1, 2026, and conclude no later than May 31, 2027. The estimated project magnitude is between $100,000 and $250,000. The well will be completed in accordance with Forest Service plans and specifications (referenced as Attachment 4 – Well Construction Plans_signed). The project location is in Section 23, Township 26N, Range 1E. Special Provisions 2100 Groundwater Well (Attachment 5 – SP 2100 Groundwater Well) are incorporated as part of the contract requirements.
The Statement of Work includes a contingency structure for well replacement if initial drilling does not meet specifications. If the first well fails to meet specifications, Option 1 authorizes decommissioning of that well and drilling of a second well. If the second well also fails to meet specifications, Option 2 authorizes decommissioning of the second well. While no official site visit is mandatory, contractors are highly encouraged and expected to visit the Salmon River Seed Orchard to familiarize themselves with site layout. A Contracting Officer's Representative (COR) will be designated in writing to provide on-the-ground administration, with certain contract authority reserved solely for the Contracting Officer.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK
SALMON RIVER SEED ORCHARD WELL DRILLING
NEZ PERCE-CLEARWATER NATIONAL FORESTS
IDAHO COUNTY, IDAHO
SCOPE OF CONTRACT
This project aims to provide potable water to the nursery located at the Salmon River Seed Orchard. The Forest Service plans to drill a well to provide potable water to the nursery. The well will be completed in accordance with the plans and specifications provided by the Forest. If the first well drilled does not meet specifications, then, additional alternative 1 (Option 1) will be utilized to decommission the first well drilled and then drill a second well. If well 2 does not meet specifications, then additional alternative 2 (Option 2) will be utilized to decommission the second well.
PROJECT LOCATION
This project is in the Salmon River Seed Orchard contained within the Nez Perce-Clearwater National Forests. The project is located in Section 23, Township 26N, Range 1E.
MAGNITUDE OF CONSTRUCTION PROJECT
Between $100,000 and $250,000.
SITE VISIT
No official Site Visit shall be performed. Contractors are highly encouraged to visit the Salmon River Seed Orchard to familiarize themselves with the layout of the site. Contractor is encouraged and expected to visit the site.
PERIOD OF PERFORMANCE
Work on the site shall commence no earlier than June 01, 2026, and proceed in accordance with the contractor’s approved work schedule and run continuously till the end of the project no later than May 31, 2027.
DRAWINGS (Entitled “Attachment 4 - Well Construction Plans_signed”) The following drawings are a part of this solicitation and any resulting contract:
TITLE OR NUMBER SHEETS
Title Sheet 1 Legend and Notes 2 Site Map 3 Drawings 4
SPECIAL PROVISIONS 2100 GROUNDWATER WELL (Attachment 5 - SP 2100 Groundwater Well)
SP2100 are a part of this solicitation and any resulting contract.
CONTRACTING OFFICER’S REPRESENTATIVE
The Contracting Officer (CO) will designate a representative, hereinafter referred to as the Contracting Officer’s Representative (COR) or, alternatively, as the Engineer, who will provide on-the-ground administration for the Government. The COR will be designated in writing, and a copy of the designation will be furnished to the Contractor.
The Contractor is cautioned to read the COR designation because certain authority under the contract is reserved solely for the Contracting Officer. The term “Contracting Officer” as used throughout the Specifications, shall be interpreted to include the Contracting Officer’s designated representative(s) acting within the limits of their delegation of authority.
| STATEMENT OF WORK |
| DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK |
| PROJECT LOCATION |
| MAGNITUDE OF CONSTRUCTION PROJECT |
| SITE VISIT |
| PERIOD OF PERFORMANCE |
| DRAWINGS (Entitled “Attachment 4 - Well Construction Plans_signed”) |
| SPECIAL PROVISIONS 2100 GROUNDWATER WELL (Attachment 5 - SP 2100 |
| Groundwater Well) |
| CONTRACTING OFFICER’S REPRESENTATIVE |