Attachment 2 - Statement of Work.pdf

PDF 254 KB Posted

Attached to
Nez Perce-Clearwater NF Salmon River Seed Orchard Well Drilling (2026)
Solicitation number
1240LU26Q0065
Issued by

About this file

Statement of Work Summary: Salmon River Seed Orchard Well Drilling

This Statement of Work describes a groundwater well drilling project for the Nez Perce-Clearwater National Forests in Idaho County, Idaho. The project objective is to drill a well to provide potable water to the nursery located at the Salmon River Seed Orchard, with work to commence no earlier than June 1, 2026, and conclude no later than May 31, 2027. The estimated project magnitude is between $100,000 and $250,000. The well will be completed in accordance with Forest Service plans and specifications (referenced as Attachment 4 – Well Construction Plans_signed). The project location is in Section 23, Township 26N, Range 1E. Special Provisions 2100 Groundwater Well (Attachment 5 – SP 2100 Groundwater Well) are incorporated as part of the contract requirements.

The Statement of Work includes a contingency structure for well replacement if initial drilling does not meet specifications. If the first well fails to meet specifications, Option 1 authorizes decommissioning of that well and drilling of a second well. If the second well also fails to meet specifications, Option 2 authorizes decommissioning of the second well. While no official site visit is mandatory, contractors are highly encouraged and expected to visit the Salmon River Seed Orchard to familiarize themselves with site layout. A Contracting Officer's Representative (COR) will be designated in writing to provide on-the-ground administration, with certain contract authority reserved solely for the Contracting Officer.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK

SALMON RIVER SEED ORCHARD WELL DRILLING

NEZ PERCE-CLEARWATER NATIONAL FORESTS

IDAHO COUNTY, IDAHO

SCOPE OF CONTRACT

This project aims to provide potable water to the nursery located at the Salmon River Seed Orchard. The Forest Service plans to drill a well to provide potable water to the nursery. The well will be completed in accordance with the plans and specifications provided by the Forest. If the first well drilled does not meet specifications, then, additional alternative 1 (Option 1) will be utilized to decommission the first well drilled and then drill a second well. If well 2 does not meet specifications, then additional alternative 2 (Option 2) will be utilized to decommission the second well.

PROJECT LOCATION

This project is in the Salmon River Seed Orchard contained within the Nez Perce-Clearwater National Forests. The project is located in Section 23, Township 26N, Range 1E.

MAGNITUDE OF CONSTRUCTION PROJECT

Between $100,000 and $250,000.

SITE VISIT

No official Site Visit shall be performed. Contractors are highly encouraged to visit the Salmon River Seed Orchard to familiarize themselves with the layout of the site. Contractor is encouraged and expected to visit the site.

PERIOD OF PERFORMANCE

Work on the site shall commence no earlier than June 01, 2026, and proceed in accordance with the contractor’s approved work schedule and run continuously till the end of the project no later than May 31, 2027.

DRAWINGS (Entitled “Attachment 4 - Well Construction Plans_signed”) The following drawings are a part of this solicitation and any resulting contract:

TITLE OR NUMBER SHEETS

Title Sheet 1 Legend and Notes 2 Site Map 3 Drawings 4

SPECIAL PROVISIONS 2100 GROUNDWATER WELL (Attachment 5 - SP 2100 Groundwater Well)

SP2100 are a part of this solicitation and any resulting contract.

CONTRACTING OFFICER’S REPRESENTATIVE

The Contracting Officer (CO) will designate a representative, hereinafter referred to as the Contracting Officer’s Representative (COR) or, alternatively, as the Engineer, who will provide on-the-ground administration for the Government. The COR will be designated in writing, and a copy of the designation will be furnished to the Contractor.

The Contractor is cautioned to read the COR designation because certain authority under the contract is reserved solely for the Contracting Officer. The term “Contracting Officer” as used throughout the Specifications, shall be interpreted to include the Contracting Officer’s designated representative(s) acting within the limits of their delegation of authority.

STATEMENT OF WORK
DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK
PROJECT LOCATION
MAGNITUDE OF CONSTRUCTION PROJECT
SITE VISIT
PERIOD OF PERFORMANCE
DRAWINGS (Entitled “Attachment 4 - Well Construction Plans_signed”)
SPECIAL PROVISIONS 2100 GROUNDWATER WELL (Attachment 5 - SP 2100
Groundwater Well)
CONTRACTING OFFICER’S REPRESENTATIVE