Attachment 2 - Statement of Work 9-01-2023.pdf

PDF 222 KB Posted

Attached to
Grounds Maintenance Services - HTNF - Sparks, NV Federal contract opportunity
Solicitation number
1240LR23P0096
Issued by
Department of Agriculture Forest Service

About this file

This statement of work outlines the requirements for grounds maintenance services at the Supervisor's Office for the Humboldt-Toiyabe National Forest under solicitation number 1240LR23P0096. The contractor shall provide all tools, equipment, materials, and labor to perform biannual cleanups, commission and winterize the sprinkler system, maintain landscaping and lawns, trim shrubs, edge and fertilize the lawn, and aerate the soil. Work is required year-round with the majority performed between May and October. The contractor must submit chemical treatments for approval and keep weeds below 1% and grass below 5% coverage. Access is only permitted on weekdays during business hours. The contractor shall provide resumes for supervisory staff and may not substitute personnel for 90 days following award.

View the file

Other files for this federal contract opportunity

Other files attached to Grounds Maintenance Services - HTNF - Sparks, NV, newest first.
File Type Posted
Attachment 4 - MAP.pdf PDF
Attachment 3 - Wage Determination 2015-5595 Rev-20 7-27-23.pdf PDF
1240LR23P0096 Award signed by CO and KTR.pdf PDF
Attachment 1 - Schedule of Items 9-01-2023.xlsx XLSX spreadsheet
1240LR23P0096 AWARD signed by CO.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

US Department of Agriculture (USDA)

Statement of Work

Contents Project General Information

1.0 Scope of Work

2.0 Background ....................................................................................................................................... Error! Bookmark not defined.

Contractor Requirements

3.0 Technical Requirements / Tasks

4.0 Government Furnished

5.0 Deliverables / Schedule

6.0 Travel

7.0 Contractor’s Key Personnel

8.0 Security Requirements

9.0 Data Rights

10.0 Section 508 – Electronic and Information Technology Standards Attachment

Project HTNF SO Grounds Maintenance

General Information

1.0 Scope of Work

Grounds maintenance for the landscaping and lawns at the Supervisor’s Office for the Humboldt-Toiyabe National Forest. Work includes, but is not limited to, two annual cleanups, commissioning and winterizing sprinkler system, maintaining the sprinkler system during operational months, shrub maintenance, lawn trimming, lawn edging, weeding, weed treatment, fertilizing, thatching, and aerating of lawn.

Contractor Requirements

3.0 Technical Requirements / Tasks

Contractor shall provide all tools, equipment, materials, and labor to perform the work described above and in the Schedule of Items.

The majority of the work shall be performed between the months of May and October, however some work must also be performed in all four seasons throughout the year.

Contractor may only use fertilizer, weed treatment, and pre-emergent treatment after receiving written approval from the government for each product.

Weeds (including Lamb’s Ear and Dandilions) shall not be present in more than 1% of the lawn area.

Grass shall not be present in more than 5% of the rock landscaping from May 1 to October 30.

Unpruned branches shall not extend greater than 6” beyond the primary form of any shrub. (This does not apply to trees, the government will maintain responsibility for all tree maintenance, but the contractor shall take care not to cause damage to any existing trees.)

4.0 Government Furnished

There is an existing sprinkler system. The government shall be responsible for major repairs exceeding $150 in a given month. No other government furnished materials shall be provided.

5.0 Deliverables / Schedule

All written deliverables shall be phrased in layperson language.

• Herbicides and Fertilizers: Submit name and ingredients of any chemical treatments to the government no less than one week prior to treating lawn, weeds, or other.

Key Deliverables

See schedule of Items only

6.0 Travel

N/A

7.0 Contractor’s Key Personnel

The contractor shall provide a resume for work leaders/foreman. If multiple foremen are required each for a different scope of work, successful offeror must provide resumes for each of the foremen and the scope(s) for which they will be responsible. Contractor may not substitute any key personnel for 90 days after contract award.

8.0 Security Requirements

Contractor must only access our property to clear debris near two back entrances. This work shall be performed during normal business hours (0800-1630 Monday through Friday, and not on Federal Holidays). The government will permit access to our gate as needed.

9.0 Data Rights

N/A

10.0 Section 508 – Electronic and Information Technology Standards N/A

Attachment Successful offers must provide a cost for each item in the Schedule of Items and qualifications of key personnel described above in section 7.0.

Project
General Information
1.0 Scope of Work
Contractor Requirements
3.0 Technical Requirements / Tasks
4.0 Government Furnished
5.0 Deliverables / Schedule
6.0 Travel
7.0 Contractor’s Key Personnel
8.0 Security Requirements
9.0 Data Rights
10.0 Section 508 – Electronic and Information Technology Standards
Attachment

File details come from the government source that posted it. Updated .