Attachment 2 Stanley Lake and Alturas Lake Specs.pdf

PDF 1 MB Posted

Attached to
Stanley Lake Road and Alturas Lake Road Pavement Maintenance Project, Sawtooth NF
Solicitation number
1240LT22R0054
Issued by

About this file

This solicitation posting includes plans and specifications for a pavement maintenance project on Stanley Lake Road and Alturas Lake Road located on the Sawtooth National Forest. The project involves asphalt concrete paving, full depth reclamation, chip sealing, and other roadwork. The Department of Agriculture Forest Service is the contracting agency. Products and services required include asphalt concrete, aggregate materials, emulsified asphalt, and equipment for pulverizing, mixing, placing, and compacting asphalt. The solicitation provides specifications for mix designs, material properties, construction methods, testing and acceptance criteria. The bid due date is not specified.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Table of Contents Preface

101 - Terms¸ Format¸ and Definitions

101.01 Meaning of Terms

101.03 Abbreviations

101.04 Definitions

102 - Bid¸ Award¸ and Execution of Contract

Delete Section 102

103 - Scope of Work

Delete Subsections 103.02, 103.03, 103.04, 103.05

104 - Control of Work

Delete Subsections 104.01, 104.02, 104.04

104.06 Use of Roads by Contractor

105 - Control of Material

105.05 Use of Material Found in the Work

106 - Acceptance of Work

106.01 Conformity with Contract Requirements

106.02 Visual Inspection

107 - Legal Relations and Responsibility to the Public

Delete Subsection 107.05

108 - Prosecution and Progress

Delete Section 108

109 - Measurement and Payment

Delete Subsections 109.06, 109.07, 109.08, 109.09

109.01 Measurement of Work

109.02 Measurement Terms and Definitions

155 - Schedules for Construction Contracts

Delete Section 155

156 - Public Traffic

Section 156. – PUBLIC TRAFFIC

403 – ASPHALT CONCRETE

Section 403. — ASPHALT CONCRETE

Table 403-2

407 - Chip Seal

Attachment #2-1240LT22R0054

407.01 Description

407.09 Asphalt Material/Cover Material Application

407.15 Payment

412 - Asphalt Tack Coat

412.05 Weather Limitations

Preface Preface_wo_02_16_2022

Delete all but the first paragraph and add the following:

The Forest Service, US Department of Agriculture has adopted FP-14 for construction of National Forest System Roads.

101 - Terms¸ Format¸ and Definitions 101.01_National_11_9_2016

Add the following paragraph to Subsection 101.01:

101.01 Meaning of Terms.

Delete all references to the TAR (Transportation Acquisition Regulations) in the specifications.

101.03_National_11_9_2016

Add the following to Subsection 101.03:

101.03 Abbreviations.

(a) Acronyms.

AGAR — Agriculture Acquisition Regulations

AFPA — American Forest and Paper Association

FSAR — Forest Service Acquisition Regulations

MSHA — Mine Safety and Health Administration

NESC — National Electrical Safety Code

WCLIB — West Coast Lumber Inspection Bureau

(f) Miscellaneous unit abbreviations.

MP — milepost location ppm — parts per million volume

STA station location

101.04_National_1_22_2020

Make the following changes to Subsection 101.04:

101.04 Definitions.

Delete these definitions and replace the following:

Bid Schedule — The Schedule of Items.

Bridge — A structure, including supports, erected over a depression or an obstruction such as water along a road, a trail, or a railway and having a deck for carrying traffic or other loads.

Contractor — The individual or legal entity contracting with the Government for performance of prescribed work. In a timber sale contract, the contractor is the “Purchaser”.

Culvert — Any structure with a bottom, regardless of fill depth, depth of invert burial, or presence of horizontal driving surface, or any bottomless (natural channel) structure with footings that will not have wheel loads in direct contact with the top of the structure.

Drawings — (Public Works Contracts) Design sheets or fabrication, erection, or construction details submitted to the CO by the Contractor according to FAR Clause 52.236-21 Specifications and Drawings for Construction. Also refers to submissions and submittals.

Notice to Proceed — (Public Works Contracts) Written notice to the Contractor to begin the contract work.

Right-of-Way — A general term denoting (1) the privilege to pass over land in some particular line (including easement, lease, permit, or license to occupy, use, or traverse public or private lands), or (2) Real property necessary for the project, including roadway, buffer areas, access, and drainage areas.

Solicitation—(Public Works Contracts) The complete assembly of documents (whether attached or incorporated by reference) furnished to prospective bidders.

Add the following definitions:

Adjustment in Contract Price — “Equitable adjustment,” as used in the Federal Acquisition Regulations, or “construction cost adjustment,” as used in the Timber Sale Contract, as applicable.

Change — “Change” means “change order” as used in the Federal Acquisition Regulations, or “design change” as used in the Timber Sale Contract.

Forest Service — The United States of America, acting through the Forest Service, U.S. Department of Agriculture.

Neat Line — A line defining the proposed or specified limits of an excavation or structure.

Pioneer Road — Temporary construction access built along the route of the project.

Purchaser — The individual, partnership, joint venture, or corporation contracting with the Government under the terms of a Timber Sale Contract and acting independently or through agents, employees, or subcontractors.

Protected Streamcourse — A drainage shown on the plans or timber sale area map that requires designated mitigation measures.

Road Order — An order affecting and controlling traffic on roads under Forest Service jurisdiction. Road Orders are issued by a designated Forest Officer under the authorities of 36 CFR, part 260.

Shop Drawings — (Timber and Stewardship Contracts) Referred to as “Drawings” in FP-14, include drawings, diagrams, layouts, schematics, descriptive literature, illustrations, lists or tables, performance and test data, and similar materials furnished by Purchaser to explain in detail specific portions of the work required by the contract.

Utilization Standards —

The minimum size and percent soundness of trees described in Public Works contract specifications or Timber Sale and IRTC contract provisions to determine merchantable timber.

Add Figure 101-1—Illustration of road structure terms:

Figure 101-1—Illustration of road structure terms.

102 - Bid¸ Award¸ and Execution of Contract 102.00_National_11_9_2016

Delete Section 102 in its entirety.

Delete Section 102.

103 - Scope of Work 103.00_National_11_9_2016

Delete all of Section 103 except Subsection 103.01 Intent of Contract.

Delete Subsections 103.02, 103.03, 103.04, 103.05.

104 - Control of Work 104.00_National_11_9_2016

Delete Subsections 104.01, 104.02, and 104.04.

Delete Subsections 104.01, 104.02, 104.04.

104.06_National_11_9_2016

Add the following to Subsection 104.06:

104.06 Use of Roads by Contractor.

The Contractor is authorized to use roads under the jurisdiction of the Forest Service for all activities necessary to complete this contract, subject to the limitations and authorizations designated in the Road Order(s) or described in the contract, when such use will not damage the roads or national forest resources, and when traffic can be accommodated safely.

105 - Control of Material 105.05_National_6_29_2020

105.05 Use of Material Found in the Work.

Delete 105.05 (a) and (b) and the last sentence of the second paragraph and substitute the following:

Materials produced or processed from Government lands in excess of the quantities required for performance of this contract are the property of the Government. Place excess material safely at government-approved location, at no additional cost to government.

106 - Acceptance of Work 106.01_National_7_18_2017

Delete Subsection 106.01 and replace with the following:

106.01 Conformity with Contract Requirements.

Follow the requirements of FAR Clause 52.246-12 Inspection of Construction.

References to standard test methods of AASHTO, ASTM, GSA, and other recognized standard authorities refer to the methods in effect on the date of solicitation for bids.

Perform all work to the lines, grades, cross-sections, dimensions, and processes or material requirements shown on the plans or specified in the contract.

Incorporate manufactured materials into the work according to the manufacturer’s recommendations or to these specifications, whichever is more strict.

Plan dimensions and contract specification values are the values to be strived for and complied with as the design values from which any deviations are allowed. Perform work and provide material that is uniform in character and reasonably close to the prescribed value or within the specified tolerance range. The purpose of a tolerance range is to accommodate occasional minor variations from the median zone that are unavoidable for practical reasons.

When standard manufactured items are specified (such as fence, wire, plates, rolled shapes, pipe conduits, etc., that are identified by gauge, unit mass, section dimensions, etc.), the identification will be considered to be nominal masses or dimensions. Unless specific contract tolerances are noted, established manufacturing tolerances will be accepted.

The Government may inspect, sample, or test all work at any time before final acceptance of the project. When the Government tests work, copies of test reports are furnished to the Contractor upon request. Government tests may or may not be performed at the work site. If Contractor testing and inspection is verified by the Government, the Contractor’s results may be used by the Government to evaluate work for acceptance. Do not rely on the availability of Government test results for process control.

Acceptable work conforming to the contract will be paid for at the contract unit bid price. Four methods of determining conformity and accepting work are described in Subsections 106.02 to 106.05 inclusive. The primary method of acceptance is specified in each Section of work. However, work may be rejected at any time it is found by any of the methods not to comply with the contract.

Remove, repair, or replace work that does not conform to the contract, or to prevailing industry standards where no specific contract requirements are noted. Removing, repairing, or replacing work; providing temporary traffic control; and any other related work to accomplish conformity will be at no cost to the Government.

(a) Disputing Government test results. If the accuracy of Government test results is disputed, promptly inform the CO. If the dispute is unresolved after reasonable steps are taken to resolve the dispute, further evaluation may be obtained by written request. Include a narrative describing the dispute and a proposed resolution protocol that addresses the following:

1. Sampling method;

2. Number of samples;

3. Sample transport;

4. Test procedures;

5. Testing laboratories;

6. Reporting;

7. Estimated time and costs; and

8. Validation process.

If the evaluation requires additional sampling or testing be performed, mutually agree with the Government on witnessing procedures and on sampling and testing by a third party laboratory. Use a third party laboratory accredited by the AASHTO accreditation program. Provide proof of the laboratory’s accreditation for the test procedures to be used. Do not use the same laboratory that produced the disputed Government test results or that produced the test results used as a basis for the dispute.

The CO will review the proposed resolution protocol and may modify it before final approval and execution.

The Government will use the approved resolution protocol test results to determine the validity of the disputed testing. If the Government test results are validated, the Contractor will be responsible for all costs associated with developing and performing the resolution protocol. If the Government test results are not validated, the Government will be responsible for all costs associated with developing and performing the resolution protocol.

If the validity of the Government test results cannot be determined, the Contractor and Government will equally share all costs associated with developing and carrying out the resolution protocol.

(b) Alternatives to removing and replacing non-conforming work. As an alternative to removal and replacement, the Contractor may submit a written request to:

1. Have the work accepted at a reduced price; or

2. Be given permission to perform corrective measures to bring the work into conformity.

The request must contain supporting rationale and documentation. Include references or data justifying the proposal based on an evaluation of test results, effect on service life, value of material or work, quality, aesthetics, and other tangible engineering basis. The CO will determine disposition of the nonconforming work.

106.02_National_11_9_2016

Delete Subsection 106.02 and replace with the following:

106.02 Visual Inspection.

Acceptance is based on visual inspection of the work for compliance with the specific contract requirements.

Use prevailing industry standards in the absence of specific contract requirements or tolerances.

107 - Legal Relations and Responsibility to the Public 107.05_National_7_18_2017

Delete Subsection 107.05.

Delete Subsection 107.05.

108 - Prosecution and Progress 108.00_National_11_9_2016

Delete Section 108 in its entirety.

Delete Section 108.

109 - Measurement and Payment 109.00_National_11_9_2016

Delete Subsections 109.06, 109.07, 109.08, and 109.09:

Delete Subsections 109.06, 109.07, 109.08, 109.09.

109.01_National_2_22_2019

Delete the third paragraph and Table 109-1 of Subsection 109.01 and replace with the following:

109.01 Measurement of Work.

Take measurements as described in Subsection 109.02 unless otherwise modified by the Measurement Subsection of the section controlling the work being performed. Table 109-1 indicates the accuracy required for quantities of the various pay units used in the Schedule of Items. Use this guide to determine the decimal placement in the final payment.

Table 109-1

Decimal Accuracy of Quantities for Final Payment

Pay Item Level of Precision Linear Foot 1

Exception--Timber, Steel, and concrete Piles 0.1 Station 0.1 Mile 0.01 Square Foot 0.1 Square Yard 0.1 Each 1 Acre 0.01 Gallon 1 M-Gals. 0.1 Cubic Yard 1

Exception--Structure Excavation; Sheathing Materials; Bedding, Bed Course, and Backfill Materials; Gabions;

0.1

Exception--Concrete; Masonry 0.01 Pound 1 Ton 0.1

Exception--Calcium Chloride;

Sodium Chloride; Hydrated Lime;

Bituminous Materials; Pavements;

Bed Course Materials

0.01

Hour 0.1

MFBM 0.01

Station Yard 1 Cubic Yard Mile 1 Ton Mile 1

109.02_National_11_9_2016

Add the following sentence to Subsection 109.02(b):

109.02 Measurement Terms and Definitions.

(b) Contract quantity.

Contract quantities will be adjusted only when there are errors in the original design of 15% or more.

155 - Schedules for Construction Contracts 155.00_National_11_9_2016

Delete Section 155 in its entirety.

Delete Section 155.

156 - Public Traffic 156.00_National_2_5_2019

Delete Section 156 in its entirety and replace with the following:

Section 156. – PUBLIC TRAFFIC Description

156.01 This work consists of controlling and protecting public traffic adjacent to and within the project.

Material

156.02 Conform to the MUTCD and the following Sections and Subsections:

Permanent Traffic Control 633

Traffic Signing and Marking Material 718

Concrete Barriers and Precast Guardwalls 618

Temporary plastic fence 710.11

Construction Requirements

156.03 General. Accommodate traffic according to MUTCD, approved traffic control plan and this section.

Perform work in a manner that ensures safety and convenience of the public. Unless otherwise provided for in Table 156-1, keep existing roads open to all traffic during road improvement work, and maintain them in a condition that will adequately accommodate traffic. Delays may not exceed 30 minutes at any one time followed by an open period of no less than 10 minutes. Accommodate public traffic on roads adjacent to and within the project until the project is accepted according to Subsection 106.07(b).

Submit traffic control plan at least 30 days prior to intended use. Perform no work that interferes or conflicts with traffic or existing access to the roadway surface until a traffic control plan has been approved.

Post construction signs and traffic control devices in conformance with MUTCD and Forest Service EM 7100-15.

All required signs will be in place and approved prior to beginning work on project.

If the Contractor agrees in writing to allow public traffic to use a new road being constructed prior to completion, it will be considered an existing road for traffic control purposes.

156.04 Temporary Traffic Control. Install and maintain temporary traffic control devices adjacent to and within the project as required by the approved traffic control plan and the MUTCD. Install and maintain traffic control devices as follows:

(a) Furnish and install traffic control devices before the start of construction operations.

(b) All detours outside of clearing limits will be approved in writing by the Contracting Officer as part of the traffic control plan.

(c) Install only those traffic control devices needed for each stage or phase.

(d) Relocate temporary traffic control devices as necessary.

(e) Remove devices that no longer apply to the existing conditions.

(f) Immediately replace any device that is lost, stolen, destroyed, or inoperative.

(g) Keep temporary traffic control devices clean.

(h) Remove all temporary traffic control devices upon contract completion or when approved.

(i) When required, use flaggers certified by the American Traffic Safety Services Association, the National Safety Council, the International Municipal Signal Association, a state agency, or other acceptable organization. Perform the work described under MUTCD Part 6. Use type III, VII, VIII, or IX retroreflective sheeting on flagger paddles. Do not use flags. Flaggers must wear high visibility safety apparel as required by MUTCD 6E.02.

156.05 Temporary Closures. Road segments may be closed as shown in Table 156-1. The maximum consecutive days of closure shall be followed by a minimum number of consecutive days open to traffic as shown. Maintain traffic control devices during closure period(s). Appropriate barricades and signs will be erected and maintained as shown in the traffic control plan or as otherwise designated.

Prior to closing roads during construction, give written notice to the Contracting Officer at least 10 days in advance.

During preliminary work no closures will be allowed on 674. Paving operations must not begin before Lick Creek or Johnson creek are open and not before July 11th. If there is a sports fishing opening for Chinook Salmon paving will not be allowed during that period. Otherwise during paving operations 674 may be closed from 0800 until 1700 Monday through Friday with COR approval.

Table 156-1 Temporary Road Closures

Road Number

From Terminus To Terminus

Maximum Consecutive Days of Closure

Minimum Consecutive Days Open

50674 0 (warm lake hwy)

30.9 (East Fork of South Fork) 5 2

156.06 Acceptance. Public traffic work will be evaluated under Subsection 106.02.

Measurement and Payment

156.07 Do not measure Public Traffic for payment. Payment for contract work is provided indirectly. See Subsection 109.05.

Section 304. — FULL DEPTH RECLAMATION

Description

304.01 This work consists of pulverizing an existing pavement and base in-place, adding crushed aggregate if required, mixing this material with water, and shaping and compacting the mix to produce a base.

Material

304.02 Conform to the following Subsections:

Crushed aggregate 703.06 Water 725.01(c)

Construction Requirements

304.03 General. Establish profile and cross slope control. Maintain the existing cross slope or crown if none is established.

Before pulverizing, remove and dispose of unsuitable material as directed by the CO. Replace unsuitable material with crushed aggregate according to Subsection 304.04.

Protect manholes, valve covers, and other buried facilities from damage.

304.04 Adding Crushed Aggregate. If required, add crushed aggregate to bring the finished surface to the established line, grade, and cross-section.

304.05 Pulverizing. Furnish a road reclaimer that is:

(a) Self-propelled;

(b) Specifically manufactured for in-place reclamation;

(c) Capable of reducing the existing material to the required size;

(d) Equipped with at least an 8-foot (2.4-meter) cutting width;

(e) Equipped with standard automatic depth controls adjustable in increments of ½ inch (13 millimeters); and

(f) Equipped with sufficient horsepower to constantly pulverize to the required depth in a single pass.

Use the reclaimer to pulverize the existing roadway material, in-place until 100 percent passes the 2-inch (50-millimeter) sieve. Reprocess or remove larger particles and dispose of them according to Subsection 203.05.

304.06 Mixing and Spreading. Add water as necessary to adjust the moisture content of the mixture to within 2 percent of the optimum for compaction. Mix to produce a homogenous full depth mixture. Spread the mixture uniformly across the existing roadbed to provide a final compacted shape according to the established line, grade, and cross-section.

304.07 Compacting. Compact using one of the following methods:

(a) Method 1. Compact material full width according to Subsection 204.11(a).

(b) Method 2. Compact material according to Subsection 301.05.

304.08 Surface Tolerance. See Subsection 301.06.

304.09 Maintenance. See Subsection 301.07. Overlay the base within 14 days after compacting.

304.10 Acceptance. See Table 304-1 for sampling, testing, and acceptance requirements.

Crushed aggregate will be evaluated under Subsection 106.03.

Construction of full depth reclamation will be evaluated under Subsections 106.02 and 106.04.

Measurement

304.11 Measure the Section 304 pay items listed in the bid schedule according to Subsection 109.02 and the following as applicable.

Measure crushed aggregate under Section 302.

Measure removal and disposal of unsuitable material under Sections 203 and 204.

Payment

304.12 The accepted quantities will be paid at the contract price per unit of measurement for the Section 304 pay items listed in the bid schedule. Payment will be full compensation for the work prescribed in this Section. See Subsection 109.05.

Table 304-1

Sampling, Testing, and Acceptance Requirements

Material or

Product

(Subsection)

Type of

Acceptance

(Subsection)

Characteristic Category Test Methods

Specifications

Sampling

Frequency

Point of

Sampling

Split

Sample

Reporting

Time

Remarks

Production

Pulverized material

Measured and tested for conformance

(106.04)

Moisture-density

– AASHTO

T 180, Method D (1)

1 per change in material

Behind reclaimer before compaction

Yes Before using in work

Density – AASHTO

T 310

1 per

2,000 yd2

(1,700 m2)

In-place after compaction

No End of shift

For

Method 2 compaction only

Process control

(153.03)

Moisture content

(in-place)

– AASHTO

T 255 or other approved methods

Minimum

1 per

3500 yd2

(3000 m2)

" " Upon completion of test

Gradation – AASHTO

T 27

" Behind reclaimer before

" " Minus

2-inch

(50-mm) compaction sieve requirement only

Finished Product

Finished pulverized material

Measured and tested for conformance

(106.04)

Surface tolerance

& grade

– Subsection

301.06

Determined by the CO

Completed

FDR

surface

No Before placement of next layer or as requested

(1) Minimum of 5 points per proctor.

403 – ASPHALT CONCRETE

Delete Section 403 in its entirety and replace with the following.

Section 403. — ASPHALT CONCRETE Description

403.01 This work consists of constructing asphalt concrete pavement using a hot or warm mix asphalt (HMA or WMA).

Asphalt concrete type is designated as Type I or Type II according to Subsection 403.02.

Construction Requirements

403.02 Composition of Mix (JMF). Conform to current state department of transportation material specifications for asphalt concrete.

(a) Type I. Submit a state department of transportation JMF approved within the past 12 months for approval at least 30 days before production. For each proposed JMF, submit a production certification conforming to state department of transportation specifications and conforming to design parameter (a), (b), or (c) for the type of mix submitted and conforming to design parameter (d) in Table 403-1.

Table 403-1 Asphalt Concrete Mix Requirements Design Parameters Specification

(a) Volumetric hot asphalt concrete pavement (AASHTO M 323, AASHTO R 35, and AASHTO T 312)

Gyratory compaction level 7, 75, 115 Volumetric properties at 0.3 to 3 million ESAL’s (AASHTO M 323) See Table 401-1

(b) Hveem (AASHTO T 246 and AASHTO T 247) Stabilometer, minimum 35 Percent air voids (1) 3.0 – 5.0

(c) Marshall (AASHTO T 245) Stability, pounds (kilonewtons), minimum 1500 (6.67) Flow, 0.01 inches (0.25 millimeters) 8 – 16 Percent air voids (1) 3.0 – 5.0 Compaction, number of blows each end of test specimen 50

(d) Moisture susceptibility (AASHTO T 283)

0.80 Tensile strength ratio, minimum

(1) The percent of air voids are based on AASHTO T 166, AASHTO T 209 and AASHTO T 269.

(b) Type II. Provide a mix composed of crushed stone or gravel and asphalt binder mixed in an approved plant.

Use an aggregate gradation and asphalt binder of a quality conforming to those normally used locally by either Federal, state or local agencies for the type of work being constructed.

Submit the strength, quality, and gradation specifications for the asphalt concrete mix. Include copies of laboratory test reports that demonstrate aggregate, asphalt binder, additive, and mix properties meet Federal, state or local government agency specifications.

For both Type I and Type II, submit the maximum specific gravity (density) of the mix as determined by AASHTO T 209.

403.03 Production Start-Up Procedures. See Subsection 153.04(b).

403.04 Mixing Plant. See Subsection 401.04.

403.05 Surface Preparation. See Subsection 401.06.

403.06 Weather Limitations. See Subsection 401.07.

403.07 Hauling. See Subsection 401.11.

403.08 Placing and Finishing. Do not use mixes produced from different plants unless the mixes are produced according to the same JMF, use material from the same sources, and are approved.

Place HMA at a temperature conforming to Table 401-2. Place WMA at temperatures conforming to Subsection 401.03. Measure temperature of the asphalt concrete mix in the hauling vehicle just before dumping into the spreader or measure it in the windrow immediately before pickup.

(a) Asphalt concrete for roadway construction. Place the mix with a paver conforming to Subsection 401.05. Control horizontal alignment using a reference line. Automatically control the grade and slope from reference lines, a ski and slope control device, or dual skis. Use skis having a minimum length of 20 feet (6 meters).

In areas where mechanical spreading and finishing is impractical; place and finish the asphalt concrete mix according to Subsection 403.08(b).

Offset the longitudinal joint according to Subsection 401.13.

(b) Asphalt concrete for non-roadway uses. Spread and finish each course by hand raking, screeding, or by other approved methods.

403.09 Compacting. Thoroughly and uniformly compact the asphalt surface by rolling. In places inaccessible to rollers, use alternate equipment approved by the CO. Do not cause cracking, shoving or undue displacement.

Monitor the compaction process with nuclear density gauges calibrate according to the ASTM D2950 calibration section within 6 months before use. Check the standard and reference on each day of use according to the ASTM D2950 standardization and reference check sections.

Compact to at least 91.0 percent of the maximum specific gravity (density) determined in Subsection 403.02.

No individual compaction test result shall have a density less than 89 percent of maximum specific gravity and the average of all the compaction tests results shall be greater than 91.0 percent of the maximum specific gravity.

Continue compaction until surface marks are eliminated and cracks are sealed.

403.10 Joints, Trimming Edges, and Cleanup. See Subsection 401.15.

403.11 Pavement Straightedge Measurement. Measure the pavement surface using a 10-foot (3-meter) metal straightedge at right angles and parallel to the centerline. Defective areas are deviations between the surface and the bottom of the straightedge in excess of ¼ inches (6 millimeters) measured between two contacts of the straightedge or deviations in excess of ¼ inches (6 millimeters) measured at the end of the straightedge.

Correct defective areas according to Subsection 401.16(g)(1) through (4). Obtain approval for the method of correction.

403.12 Acceptance. See Table 403-2 for sampling, testing, and acceptance requirements.

Asphalt concrete mix properties will be evaluated under Subsection 106.04.

Asphalt binder will be evaluated under Subsection 106.03.

Construction of asphalt concrete work will be evaluated under Subsections 106.02 and 106.04.

Pavement straightedge measurement will be evaluated under Subsection 106.04.

Quality assurance compaction tests must be taken at locations provided by the CO for acceptance.

Measurement

403.13 Measure the Section 403 pay items listed in the bid schedule according to Subsection 109.02.

Payment

403.14 The accepted quantities will be paid at the contract price per unit of measurement for the Section 403 pay items listed in the bid schedule. Payment will be full compensation for the work prescribed in this Section. See Subsection 109.05.

Table 403-2 Sampling, Testing, and Acceptance

Requirements

Material or Product

(Subsection)

Type of Acceptance (Subsection)

Characteristic Test Methods Specifications

Sampling Frequency

Point of Sampling

Split Sample

Reporting Time

Remarks

Production Asphalt concrete

Type I or II (403.02(a))

Measured and tested for conformance (106.04)

Density ASTM D2950 (Average of up to 4 measurements per test. Rotate gauge 90 degrees for each measurement.)

10 per day at specified locations

In-place after compacting

Yes 24 hours −

Surface Straightedge Continuously, Finished No " − tolerance measurement, after pavement Subsection compaction surface 403.11 Placement − First load Hauling vehicle " Upon − temperature and as before dumping, completion determined by or windrow of CO thereafter before pickup measurement Process control Gradation AASHTO Contractor Cold feed or " 24 − (153.03) at the plant T 27 & T 11 determined hot bins hours as applicable Moisture AASHTO " Stockpile " " − content of T 255 aggregates Density ASTM 1 per In-place after " " − D2950 500 feet compacting (150 meters)

407 - Chip Seal 407.01_National_7_18_2017

Delete the first sentence of Subsection 407.01 and replace with the following:

407.01 Description.

407.01 This work consists of applying a single, double, or triple course chip seal with emulsified asphalt.

Delete Subsection 407.09 and replace with the following:

407.09 Asphalt Material/Cover Material Application.

A. Apply asphalt material at a rate sufficient to obtain 50 percent chip embedment before the rolling operation, and 70 percent chip embedment after rolling operation.

1. Adjust application rates throughout the project depending on existing conditions.

B. Apply the asphalt emulsion at a minimum temperature of 145 degrees F.

C. Do not apply asphalt material if any of the following conditions apply:

1. Material does not meet the required viscosity.

2. Material does not spray through the distributor in a uniform way and remain in place on the roadway.

D. Place building paper adjacent to the transverse construction joint before starting each spraying operation.

1. Maintain the control valve to act instantaneously, both at start-up and cut- off.

E. Locate longitudinal joints within 6 inches of the traffic lane line location.

1. Construct meet lines with no skip or voids between adjacent passes.

2. Do not place a double thickness of cover material.

F. Calibrate the spreader at the beginning of each day and as often as necessary to comply with Table 407.09-1 or approved project application rate.

1. Maintain a distance of less than 150 ft between the distributor and the chip spreader.

2. Maintain the chip spreader speed such that chips do not bounce or roll upon application.

Table 407.09-1

Approximate Spread Rates Unit Weight lbs/ft3 Application Rate lbs/yd2 75 - 80 20.7 to 28 80 - 85 22.1 to 30

85 - 90 23.5 to 32

407.15_National_5_17_2017

Delete Subsection 407.15 and replace with the following:

407.15 Payment.

407.15 The accepted quantities will be paid at the contract price per unit of measurement for the Section 407 pay items listed in the bid schedule. See Subsection 109.05.

412 - Asphalt Tack Coat 412.05_National_11_4_2016

Delete Subsection 412.05(b) and replace with the following:

412.05 Weather Limitations.

(b) Ambient air temperature is above 40 °F (5 °C) and rising; and

Preface
101 - Terms¸ Format¸ and Definitions
101.01 Meaning of Terms.
101.03 Abbreviations.
101.04 Definitions.
102 - Bid¸ Award¸ and Execution of Contract
Delete Section 102.
103 - Scope of Work
Delete Subsections 103.02, 103.03, 103.04, 103.05.
104 - Control of Work
Delete Subsections 104.01, 104.02, 104.04.
104.06 Use of Roads by Contractor.
105 - Control of Material
105.05 Use of Material Found in the Work.
106 - Acceptance of Work
106.01 Conformity with Contract Requirements.
106.02 Visual Inspection.
107 - Legal Relations and Responsibility to the Public
Delete Subsection 107.05.
108 - Prosecution and Progress
Delete Section 108.
109 - Measurement and Payment
Delete Subsections 109.06, 109.07, 109.08, 109.09.
109.01 Measurement of Work.
109.02 Measurement Terms and Definitions.
155 - Schedules for Construction Contracts
Delete Section 155.
156 - Public Traffic
Section 156. – PUBLIC TRAFFIC
Section 304. — FULL DEPTH RECLAMATION
403 – ASPHALT CONCRETE
Section 403. — ASPHALT CONCRETE
Table 403-2
407 - Chip Seal
407.01 Description.
407.09 Asphalt Material/Cover Material Application.
407.15 Payment.
412 - Asphalt Tack Coat
412.05 Weather Limitations.