Attachment 2 - SPECS.pdf

PDF 12 MB Posted

Attached to
UTES 2 BAY Addition: Pre-Engineered Metal Building with 30 Ton Crane
Solicitation number
W91364-23-B-0002
Issued by

About this file

This solicitation is for a firm fixed price construction contract to build a 6,480 square foot addition to an existing Unit Training Equipment Site vehicle maintenance facility at Camp James A. Garfield Joint Military Training Center in Ravenna, Ohio. The purpose of the project is to construct a pre-engineered metal building addition with two drive-through work bays to match the existing facility. The solicitation includes a base scope of work and nine options. Bids are due by the date and time specified in block 13 of the solicitation. The contract will be awarded to the responsible bidder whose conforming bid is the most advantageous to the Government, considering only price. The solicitation is being conducted by the Department of the Army Ohio Army National Guard. Interested contractors must be registered in the System for Award Management to be eligible to bid.

View the file

Other files

Show all 24

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

UTES TWO BAY ADDITION

BUILDING # C-0200

CAMP JAMES A. GARFIELD JOINT MILITARY TRAINING CENTER

BRACEVILLE TOWNSHIP, TRUMBULL COUNTY, OHIO

B-3 SUBMISSION

SPECIFICATIONS

FOR

THE NATIONAL GUARD BUREAU

CONTRACT: W9133L-16-D-0005

ORDER: W9136420F0093

AND THE

OHIO ARMY NATIONAL GUARD

PROJECT # 309321

BID OPENING: [DAY], [MONTH] [DAY #], 2022

CJAG JMTC UTES TWO BAY ADDITION

PN# 390321

TOC-1

TABLE OF CONTENTS

DIVISION SECTION TITLE

DIVISION 01 – GENERAL REQUIREMENTS

010000 (OHARNG) GENERAL REQUIREMENTS

010000.1 (OHARNG) AGOH PAM 210-1 (ARMY), SECTION 16 ANNEXE

011000 (OHARNG) SUMMARY

012200 (OHARNG) ENVIRONMENTAL PROCEDURES

012300 ADDITIONAL BID ITEMS (ABI)

012900 (OHARNG) PAYMENT PROCEDURES

013100 (OHARNG) PROJECT MANAGEMENT AND COORDINATION

013200 (OHARNG) CONSTRUCTION PROGRESS DOCUMENTATION

013300 (OHARNG) SUBMITTAL PROCEDURES

SUBMITTAL SCHEDULE

014000 (OHARNG) QUALITY REQUIREMENTS

014001 SPECIAL INSPECTIONS

SPECIAL INSPECTIONS SCHEDULE

014200 (OHARNG) REFERENCES

015000 (OHARNG) TEMPORARY FACILITIES AND CONTROLS

016000 PRODUCT REQUIREMENTS

017310 (OHARNG) CUTTING AND PATCHING

017419 CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL

017700 (OHARNG) CLOSEOUT PROCEDURES

017820 (OHARNG) OPERATION AND MAINTENANCE DATA

017839 (OHARNG) PROJECT RECORD DOCUMENTS

018200 (OHARNG) DEMONSTRATION AND TRAINING

DIVISION 02 – EXISTING CONDITIONS

024119 SELECTIVE DEMOLITION

DIVISION 03 – CONCRETE

030100 MAINTENANCE OF CONCRETE

031000 CONCRETE FORMING AND ACCESSORIES

032000 CONCRETE REINFORCING

033000 CAST IN PLACE CONCRETE

DIVISION 05 – METALS

051200 STRUCTURAL STEEL FRAMING

055000 METAL FABRICATIONS

DIVISION 06 - WOOD, PLASTICS, AND COMPOSITES

TOC-2

061053 MISCELLANEOUS ROUGH CARPENTRY

DIVISION 07 - THERMAL AND MOISTURE PROTECTION

071113 BITUMINOUS DAMPPROOFING

072100 THERMAL INSULATION

076200 SHEET METAL FLASHING AND TRIM

077253 SNOW GUARDS

078413 PENETRATION FIRESTOPPING

079200 JOINT SEALANTS

DIVISION 08 – OPENINGS

081113 HOLLOW METAL DOORS AND FRAMES

083613 INSULATED ROLLING SERVICE DOOR

084523 FIBERGLASS-SANDWICH-PANEL ASSEMBLIES

087100 DOOR HARDWARE

088000 GLAZING

089116 OPERABLE WALL LOUVERS

DIVISION 09 - FINISHES

099113 EXTERIOR PAINTING

099123 INTERIOR PAINTING

DIVISION 10 - SPECIALITIES

104416 FIRE EXTINGUISHERS

DIVISION 13 – SPECIAL CONSTRUCTION

133419 METAL BUILDING SYSTEMS

DIVISION 22 – PLUMBING

220516 EXPANSION FITTINGS AND LOOPS FOR PLUMBING PIPING

220517 SLEEVES AND SLEEVE SEALS FOR PLUMBING PIPING

220518 ESCUTCHEONS FOR PLUMBING PIPING

220519 METERS AND GAGES FOR PLUMBING PIPING

220523.12 BALL VALVES FOR PLUMBING PIPING

220529 HANGERS AND SUPPORTS FOR PLUMBING PIPING AND EQUIPMENT

220553 IDENTIFICATION FOR PLUMBING PIPING AND EQUIPMENT

220719 PLUMBING PIPING INSULATION

221116 DOMESTIC WATER PIPING

221119 DOMESTIC WATER PIPING SPECIALTIES

221316 SANITARY WASTE AND VENT PIPING

221319 SANITARY WASTE PIPING SPECIALTIES

TOC-3

221423 STORM DRAINAGE PIPING SPECIALTIES

221513 GENERAL SERVICE COMPRESSED AIR PIPING

223300 ELECTRIC, DOMESTIC-WATER HEATERS

224500 EMERGENCY PLUMBING FIXTURES

224716 PRESSURE WATER CODES

DIVISION 23 – HEATING, VENTILATING, AND AIR CONDITIONING (HVAC)

230513 COMMON MOTOR REQUIREMENTS FOR HVAC EQUIPMENT

230517 SLEEVES AND SLEEVE SEALS FOR HVAC PIPING

230518 ESCUTCHEONS FOR HVAC PIPING

230519 METERS AND GAGES FOR HVAC PIPING

230523.12 BALL VALVES FOR HVAC PIPING

230523.14 CHECK VALVES FOR HVAC PIPING

230593 TESTING, ADJUSTING, AND BALANCING FOR HVAC

230713 DUCT INSULATION

230716 HVAC EQUIPMENT INSULATION

230719 HVAC PIPING INSULATION

230923 DIRECT DIGITAL CONTROL (DDC) SYSTEM FOR HVAC

230923.11 CONTROL VALVES

230923.27 TEMPERATURE INSTRUMENTS

231123 FACILITY NATURAL-GAS PIPING

232113 HYDRONIC PIPING

232116 HYDRONIC PIPING SPECIALTIES

232123 HYDRONIC PUMPS

232513 WATER TREATMENT FOR CLOSED-LOOP HYDRONIC SYSTEMS

233113 METAL DUCTS

233300 AIR DUCT ACCESSORIES

233416 CENTRIFUGAL HVAC FANS

233713.13 AIR DIFFUSERS

233713.23 REGISTERS AND GRILLES

235216 CONDENSING BOILERS

237223 AIR TO AIR ENERGY RECOVERY EQUIPMENET

DIVISION 26 - ELECTRICAL

260500 COMMON WORK RESULTS FOR ELECTRICAL

260519 LOW-VOLTAGE ELECTRICAL POWER CONDUCTORS AND CABLES

260523 CONTROL-VOLTAGE ELECTRICAL POWER CABLES

260526 GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS

260529 HANGERS AND SUPPORTS FOR ELECTRICAL SYSTEMS

260533 RACEWAYS AND BOXES FOR ELECTRICAL SYSTEMS

260553 IDENTIFICATION FOR ELECTRICAL SYSTEMS

262200 LOW-VOLTAGE TRANSFORMERS

262416 PANELBOARDS

262726 WIRING DEVICES

262813 FUSES

262816 ENCLOSED SWITCHES AND CIRCUIT BREAKERS

TOC-4

264113 LIGHTNING PROTECTION FOR STRUCTURES

265119 LED INTERIOR LIGHTING

265213 EMERGENCY AND EXIT LIGHTING

DIVISION 31 – EARTHWORK

312001 EARTHWORK FOR STRUCTURES

DIVISION 41 – MATERIAL PROCESSING AND HANDLING EQUIPMENT

412213 .13 BRIDGE CRANE

APPENDICIES

APPENDIX A – GEOTECHNICAL MEMORANDUM

END OF TABLE OF CONTENTS

GENERAL REQUIREMENTS 010000 - 1

CJAG JMTC UTES TWO-BAY ADDITION

OHIO ARMY NATIONAL GUARD

PN# 390321

SECTION 010000-GENERAL REQUIREMENTS

PART 1 - GENERAL

1.1 SCOPE

A. Project provides for furnishing all permits, except for wetland permits which will be provided by the OHARNG. Also furnished shall be all plant, labor, material, equipment, and appliances to construct the building as described herein and shown on the construction Drawings.

B. The CONTRACTOR will be held responsible for all requirements described in the Contract Documents. All work, including that of subcontractors, shall be completed in accordance with the Contract Documents. Failure to be familiar with the requirements of the Contract will not relieve the CONTRACTOR of responsibility to comply.

C. The organization of the Specifications into divisions, sections, and articles, and the arrangement of the Drawings shall not control the CONTRACTOR in dividing the work among subcontractors or in establishing the extent of the work to be performed by any trade.

1.2 WORK SCHEDULING

A. Normal base work hours for the CONTRACTOR will be between the hours of 7:30 am through 4:30 pm, excluding Saturdays, Sundays, and Federal Holidays. The normal work hours for National Guard personnel are 7:00 am to 5:00 pm, Monday through Friday. If the CONTRACTOR desires to work during periods other than above, CONTRACTOR must notify the CONTRACTING OFFICER 5 working days in advance of CONTRACTOR's intention to work during other periods to allow assignment of additional inspection forces and for notification of fire, security, and safety. When the CONTRACTING OFFICER determines that they are reasonably available, CONTRACTING OFFICER may authorize the CONTRACTOR to perform work during periods other than normal duty hours/days. However, if inspectors are required to perform in excess of their normal duty hours/days solely for the benefit of the CONTRACTOR, the actual cost of the inspection, at overtime rates, will be charged to the CONTRACTOR and will be deducted from the final payment of the Contract amount. (Note: If applicable, at time of award this paragraph will be modified to the negotiated schedule for this Project.)

B. The following Federal Legal Holidays are observed by this base:

1. New Year’s Day 1 January

2. Martin Luther’s King’s Birthday Third Monday of January

3. President’s Day Third Monday of February

4. Memorial Day Last Monday of May

GENERAL REQUIREMENTS 010000 - 2

OHIO ARMY NATIONAL GUARD

PN# 390321

5. Independence Day 4 July

6. Labor Day First Monday in September

7. Columbus Day Second Monday in October

8. Veteran’s Day 11 November

9. Thanksgiving Day Fourth Thursday in November

10. Christmas Day 25 December.

C. NOTE: Any of the above holidays falling on a Saturday will be observed the preceding Friday, holidays falling on a Sunday will be observed on the following Monday.

D. Prior to commencing work on the job initially, resumption of work after prolonged interruption (7 calendar days or more) commencement of any warranty work, and upon completion of warranty work, the CONTRACTOR must notify the CONTRACTING OFFICER or the CONTRACTING OFFICER Representative (COR). When relocating to new sites, returning to sites for follow-up work on a phased work plan, notification to the COR is sufficient. Notification should be by personal contact; however, advance notification may be by telephone, or in writing, and should be accomplished sufficiently in advance to allow scheduling of inspection forces. The above precautions are to ensure construction inspection and recording of work proceedings.

E. The organization of the Specifications into divisions, sections, and articles, and the arrangement of the Drawings shall not control the CONTRACTOR in dividing the work among subcontractors or in establishing the extent of the work to be performed by any trade.

1.3 UNAUTHORIZED PERSONNEL

A. The CONTRACTOR shall inform all personnel (including subcontractor and visiting supplier personnel) that access to areas outside of the immediate work area excluding, direct haul and access routes, and point of supply and storage, is prohibited. Circulation of said personnel will be limited to official business only.

Persons in violation of the above will be apprehended and appropriately disciplined.

1.4 INSPECTION OF SITE

A. The CONTRACTOR shall be responsible for the complete coordination and proper relation of the work of all trades. Reference Contract Clauses FAR 52.236-3, "Site Investigation and Conditions Affecting the Work," and FAR 52.236-8, "Other Contracts."

GENERAL REQUIREMENTS 010000 - 3

OHIO ARMY NATIONAL GUARD

PN# 390321

B. It is recommended that prospective offerors visit the premises and thoroughly familiarize themselves with the details of the work and working conditions. It is the responsibility of all offerors to have compared the premises and the site with the Specifications and Drawings, and to have satisfied themselves as to all conditions of the premises, the existing obstructions, the actual elevations, and any other conditions affecting the execution and completion of the work prior to submission of the Proposal. Reference Contract Clause FAR 52.236-3, "Site Investigation and Conditions Affecting the Work."

C. No allowances or extra construction on behalf of any CONTRACTOR will be permitted subsequently by reason of error of oversight on the part of the subcontractor, or on account of interference by the activities of the CONTRACTING OFFICER or others. Reference Contract clause FAR 52,236-3. “Site Investigation and Conditions Affecting the Work.”

D. All dimensions shown on the Drawings are based on “as-built” record Drawings and, to the extent possible, accurately represent existing conditions: however, there may be some variance between existing conditions and Contract Drawings. The CONTRACTOR is responsible for verifying all dimensions and for reporting to the CONTRACTING OFFICER any discrepancies that may affect performance of the work represented by the Contract Drawings and Specifications. Reference Contract Clause DFARS 252.236-7001. “Contract Drawings and Specifications.”

1.5 CORRELATION OF DRAWINGS, SPECIFICATIONS AND CONTRACTS

A. The Specifications, Contract and the accompanying Drawings are intended to describe and provide for a complete, new and usable facility. They are intended to be cooperative and what is called for by one shall be as binding as if called for by all. The CONTRACTOR will understand that the work herein described shall be complete in every detail, notwithstanding every item necessarily involved is not particularly mentioned, and the CONTRACTOR shall be responsible to provide all labor and material for the entire completion of the work intended. Should any error or inconsistency appear in the Drawings or Specifications, the CONTRACTOR, before proceeding with the work, shall make mention of same to the CONTRACTING OFFICER for proper adjustment, and in no case shall the work proceed with uncertainty. Reference Contract Clause DFARS 252.236- 7001, "Contract Drawings and Specifications."

1.6 REPORT OF ERROR AND DISCREPANCIES

A. The CONTRACTOR shall be responsible for any and all discrepancies in work due to failure to obtain dimensions and investigate conditions at the building before fabrication and installation.

B. The CONTRACTOR shall bear all costs in replacing all materials and labor due to not observing the above paragraph and such replaced materials shall meet the approval of the CONTRACTING OFFICER.

GENERAL REQUIREMENTS 010000 - 4

OHIO ARMY NATIONAL GUARD

PN# 390321

C. The CONTRACTOR shall promptly notify the CONTRACTING OFFICER in writing of any discrepancies.

D. Reference Contract clauses FAR 52.236-21, "Specifications and Drawings for Construction." FAR 52.246-12 "Inspection of Construction," and DFARS 252.236-7001, "Contract Drawings and Specifications."

E. Any proposed changes to the specifications by the CONTRACTOR must be submitted in writing to the CONTRACTING OFFICER for approval prior to implementation.

1.7 DIVISION OF WORK

A. The various divisions of the specifications shall not be considered as negotiations of the material and labor involved. The arrangement and order of these divisions have been made for convenience only, and it is not the intent, nor shall it be so construed, a particular trade or subcontractor must perform that work included in any one division.

B. Any item mentioned under any division heading must be supplied even though it is not specified under the heading for the respective work but is shown on the Drawings.

No claims for extras arising out of real or alleged error in such arrangement or order of the various division will be given consideration.

C. The organization of the specifications into divisions, sections, and articles, and the arrangement of the Drawings shall not control the CONTRACTOR in dividing the work among subcontractors or in establishing the extent of the work to be performed by any trade.

D. Reference Contract clause FAR 52,236-21 “Specifications and Drawings for Construction.”

E. Any proposed changes to the specifications by the CONTRACTOR must be submitted in writing to the CONTRACTING OFFICER for approval prior to implementation.

1.8 METHOD OF CARRYING ON THE WORK

A. All work under the Contract shall be arranged and carried on in such a manner as to complete work in the least possible time. The CONTRACTOR shall consult with the CONTRACTING OFFICER as to methods or sequence of carrying on the work. A definite program of work shall be arranged before starting. Reference Contract Clause FAR 52.236-15, "Schedules for Construction Contracts."

B. Activities in the vicinity of this Project may be kept in full or partial operation during construction. The CONTRACTOR shall coordinate with the CONTRACTING OFFICER and schedule construction activities. Reference Contract Clause FAR 52.236-8, "Other Contracts."

GENERAL REQUIREMENTS 010000 - 5

OHIO ARMY NATIONAL GUARD

PN# 390321

1.9 STANDARDS OF MANUFACTURER

A. All recognized regulatory/code standards shall be the latest published edition prior to the date of release for bid/proposal of the Contract Documents.

B. For purpose of establishing the standard of construction and the requirements to be met in the work of all divisions, the Drawings and these Specifications are based on the use of products hereinafter specified, adapted to the installation as required to meet the condition.

C. Where brand names are shown, these names are intended to describe a quality of product, and in no way are intended to limit products of equal quality. Therefore, products of other manufacturers may be employed for this work provided they are approved as equivalent materials and construction and equally adaptable to the conditions as approved by the CONTRACTING OFFICER. Reference Contract Clause FAR 52.236-5, "Materials and Workmanship."

1.10 MEANING OF APPROVED, DIRECTED, ETC.

A. Approved," "Directed," "Required," "Applicable," or words of like or similar effect, when used in the Specifications shall be interpreted to mean "Approved By," "Directed By," etc., the CONTRACTING OFFICER unless otherwise specifically stipulated.

1.11 MISPLACED MATERIALS

A. Any material that is deposited elsewhere than areas designated as approved by the CONTRACTING OFFICER shall be rehandled and deposited where directed. No payment will be made for rehandling such material. The CONTRACTING OFFICIER will notify CONTRACTOR of any noncompliance with the foregoing provisions.

1.12 COMPLIANCE WITH CODES AND REGULATIONS

A. All work shall be done in accordance with the applicable codes and/or ordinances in force at the time of construction. It is the CONTRACTOR’s responsibility to ensure that where EPA or other such regulations control the removal, handling, installation, or disposal of materials, they shall be strictly adhered to whether or not specifically referenced in the construction documents.

B. CONTRACTOR shall have data sheets available at the site on any materials used to comply with EPA. Reference Contract Clause FAR 52.223.3, "Hazardous Material Identification and Material Safety Data."

GENERAL REQUIREMENTS 010000 - 6

OHIO ARMY NATIONAL GUARD

PN# 390321

1.13 MATERIAL TESTING BY NATIONAL LABORATORIES

A. Electrical materials and equipment shall be new and bear the UL label or be listed in UL Electrical Construction Materials Directory or Electrical Appliance and Utilization Equipment Directory, wherever standards have been established by the agency.

B. The CONTRACTOR shall submit proof that the material or equipment, which the CONTRACTOR proposes to furnish under this Specification, conforms to the standards of Underwriters' Laboratories. The label of Underwriters Laboratories (UL) shall be accepted as conforming to this requirement.

C. In lieu of the label, the CONTRACTOR may submit a written certification from any recognized testing agency, adequately equipped and competent to perform such services, that the material or equipment has been tested and conforms to the standards, including the methods of testing used.

1.14 SUBMITTALS

A. Shop Drawings and Product Data: The CONTRACTOR shall furnish submittals in the form of manufacturer's brochures, pamphlets, or written specifications on all items to be installed unless specifically directed otherwise by these Specifications or by the CONTRACTING OFFICER. Reference Contract Clause FAR 52.236-5, "Material and Workmanship," FAR 52.225-5, "Buy American Act-Construction Materials," FAR 52.225-9, "Hazardous Material Identification and Material Safety Data," and DFAR 252.227-7033, "Rights in Shop Drawings."

Submittals shall clearly identify performance criteria requested.

B. Approval of Materials: Prior to the purchase of material, the CONTRACTOR shall submit to the CONTRACTING OFFICER, for material approval/ disapproval, brochures and technical literature covering, in detail, the materials the CONTRACTOR proposes to supply. This shall include the specific catalog and model specification number designations. Submittals shall demonstrate that the item conforms to all of the requirements. No unapproved or disapproved materials shall be used. Submittals shall be made for the items listed in the submittal checklist, or equivalent. Reference Contract Clause FAR 52.236-5, "Material and Workmanship."

1.15 CONSTRUCTION SCHEDULING, WORK PROGRESS AND PREPARATION

OF PROGRESS SCHEDULES AND REPORTS

A. The CONTRACTOR shall prepare a work progress schedule in Microsoft Project, latest version, or acceptable substitute format. These schedules are to be submitted to the CONTRACTING OFFICER for approval, in the number of copies are directed, prior to the start of construction. The Schedule will show the order in which the contractor proposes to perform the work, the date on which the CONTRACTOR contemplates starting and completing the various divisions and salient features of the work. Reference Contract Clause FAR 52.236-15.

“Schedule for Construction Contracts.” The work shall be scheduled so that upon

GENERAL REQUIREMENTS 010000 - 7

OHIO ARMY NATIONAL GUARD

PN# 390321

the start of construction, work progresses in a continuous and diligent manner. A schedule that does not reflect steady and reasonable progress throughout the construction period will be rejected. The schedule shall include a line item for rough inspections by GOVERNMENT personnel as outlined in the various sections of the Specifications or on the Drawings. A rough inspection is required on all installed systems prior to sealing off or closing in a wall, pipe chase, suspended ceiling system etc. These systems include by not limited to:

domestic and heating water lines, communication and electric runs, all insulation material to be covered by other material (GWB, wood panel etc.), duct runs, ceiling suspension systems, fire detection/protection/suppression systems etc. A second or finish inspection will be conducted after these systems are "hidden" to ensure the quality of the finished product. The finish inspection does not constitute the final Project inspection accomplished at Project completion. The CONTRACTOR shall request these inspections, through the CONTRACTING OFFICER at least 5 workdays prior to the desired inspection date.

B. A weekly meeting may be held between the CONTRACTOR and CONTRACTING OFFICER, to discuss work progress, problems, and potential change orders. The CONTRACTOR shall attend these meetings at no additional cost to the GOVERNMENT. Prior to specific work elements of a project, the CONTRACTOR shall confer with the COR and agree on a sequence of procedures and means of access to premise; space for storage of materials and equipment; delivery of materials and use of approaches, use of corridors, stairways, and similar means of passage. Bi- weekly progress reports are to be submitted to the CONTRACTING OFFICER covering the period from notice to proceed through final inspection. If there are possible deviations from the original plan, those are to be noted and approved by the CONTRACTING OFFICER before work changes are implemented.

Reference Contract Clause FAR 52.236-15, "Schedules for Construction Contracts."

C. The Contract Schedule will include the final 5 percent of the Contract for closeout and 5 percent for punch list. Closeout retainage will include O&M Data, manufacturer's services (i.e., training for equipment use), red line drawings, as built drawings, and warranties.

1.16 SAFETY ASSURANCE

A. Compliance with Regulations. All work including the handling of hazardous materials shall comply with the applicable requirements of 29 CPR 1910/1926. All work shall comply with applicable state and municipal safety and health requirements. Where there is a conflict between applicable regulations, the most stringent shall apply.

B. CONTRACTOR Responsibility. The CONTRACTOR shall assume full responsibility and liability for compliance with all applicable regulations pertaining to the health and safety of personnel during the execution of work.

The GOVERNMENT shall not be held liable for any action on the part of the

GENERAL REQUIREMENTS 010000 - 8

OHIO ARMY NATIONAL GUARD

PN# 390321

CONTRACTOR, the CONTRACTOR's employees, or subcontractor, which result in illness, injury, or death.

C. Where an employee can fall more than 6 feet, a fall protection system must be used; 29 CPR 1926.500 stipulates where this occurs and the different types of fall arrest systems.

D. All references to protection of the site and adjacent buildings when trenching, shall include protection of all employees also.

E. Inspections, Tests and Reports. The required inspections, tests and reports made by the CONTRACTOR, subcontractor, especially trained technicians, equipment manufacturers and other as required, shall be at the CONTRACTOR’s expense.

F. Materials and Equipment. Special facilities, devices, equipment, clothing, and similar items used by the CONTRACTOR in the execution of the work shall comply with applicable regulations.

G. Traffic Control Devices. The CONTRACTOR shall comply with the recommendations contained in Part 6 of the U. S. Department of Transportation, Federal Highway Administrations "Manual on Uniform Traffic Control Devices (D6. -1978) to ensure proper warnings to motorists and adequate traffic control.

The CONTRACTOR shall provide all warning lights, barricades and other traffic control devices and signs.

H. Health and Safety Plan: Prior to commencing on-site work, Contractor must submit an Occupational Safety and Health Administration (OSHA) Emergency Action Plan (EAP) to Contracting Officer to demonstrate compliance by Contractor and subcontractors with applicable OSHA regulations. Prior to commencing on-site work, Contractor must submit a project-specific Project Safety Plan to Contracting Officer. The plan must include, but is not limited to, hazard communications, labeling, emergency response and preparedness and training.

I. The CONTRACTOR shall adhere to Section 010000.1 for any suspected unexploded ordnance (UXO). The GOVERNMENT will provide UXO support to the CONTRACTOR during construction.

1.17 INSPECTIONS AND TESTS

A. Inspections and tests are for the sole benefit of the GOVERNMENT and shall not relieve the CONTRACTOR of the responsibility of providing quality control measures to ensure that the work strictly complies with the Contract requirements.

No inspection or test by the GOVERNMENT shall be construed as constituting or implying acceptance. Reference Contract Clause FAR 52.246-12, "Inspection of Construction."

GENERAL REQUIREMENTS 010000 - 9

OHIO ARMY NATIONAL GUARD

PN# 390321

1.18 QUALITY CONTROL/TESTS

A. Where work is specified to be in conformity with Standard Specifications of the American Society for Testing Materials (ASTM), or with Federal Specifications or with specifications of well-known recognized technical and trade organizations, but no tests are specifically stipulated in connection herewith, the CONTRACTOR shall furnish and pay for any tests or certifications required by the CONTRACTING OFFICER to show that the proposed materials meet with the applicable requirements.

B. The CONTRACTOR shall submit a written certification from any recognized testing agency, adequately equipped and competent to perform such services, that the material or equipment has been tested and conforms to the standards, including the methods of testing used.

C. Wherever testing or analysis of material is required, such testing unless otherwise noted will be made at the CONTRACTOR’s expense.

D. Subsequent testing of those materials which fail to meet specifications will be accomplished by the CONTRACTOR at no cost to the GOVENRMENT.

E. CONTRACTOR Quality Control (CQC) Program: The CONTRACTOR shall provide and maintain an effective quality control program in accordance with the Contract. Within 10 days of the Award of the Contract, the CONTRACTOR shall provide three copies of the Project CQC plan to the CONTRACTING OFFICER.

This document, as a minimum, shall include name and address of the independent testing agency and the responsible principal with the firm; as summary of the QC tests required by the Specification and to be provided by the testing agency: and typical daily reports forms to be used for this Project. The plan shall also indicate organizational procedures to immediately notify the CONTRACTING OFFICER or COR of test results in noncompliance with the Specification and recommendations on correction. The testing agency must be an independent company and not owned or partially owned by the CONTRACTOR or any relation or employee of the CONTRACTOR and is subject to approval of the

CONTRACTING OFFICER.

F. Samples used for testing shall be selected as specified for the various tests elsewhere in the Specifications but in every case the method of selecting samples and the location for selection shall be as approved by the CONTRACTING

OFFICER.

G. Tests shall be made in accordance with the specified testing procedures and/or methods and otherwise as required to provide compliance with all Contract requirements. Tests shall be made by independent, commercial testing laboratories approved in writing by the CONTRACTING OFFICER.

H. Results of all tests shall be recorded on certified test reports of the commercial testing laboratories. Reports shall include a statement that the materials tested do or do not meet the requirements of the Contract Specifications. Six copies of all reports shall be forwarded directly to the CONTRACTING OFFICER for approval within 5 days of the actual performance of the test. The testing agency

GENERAL REQUIREMENTS 010000 - 10

OHIO ARMY NATIONAL GUARD

PN# 390321

shall immediately notify (verbally) the CONTRACTING OFFICER of any tests, which indicate failure to meet the Contract requirements.

I. Any item, for which test reports show failure to meet all Contract requirements shall be retested as often as required to show full compliance with Contract requirements, at the CONTRACTOR's expense.

J. CONTRACTOR will provide an emergencies plan, with names of personnel to accomplish the repairs in the event of utility and/or communications emergencies.

1.19 KEYS

A. The CONTRACTOR shall be responsible for any GOVERNMENT-owned keys that have been issued to the CONTRACTOR for access to facilities or areas pertinent to this Contract.

B. Upon completion of the work in an area, or upon request of the CONTRACTING OFFICER, the key or keys relevant to the area shall be returned immediately.

Keys shall be returned prior to final payment.

C. Should the CONTRACTOR lose a Key: The CONTRACTOR shall notify the CONTRACTING OFFICER, immediately and in writing, but not later than 1 working day after the CONTRACTOR is aware of the loss. Should the key not be found before final acceptance, the final Contract payment shall be reduced by the replacement cost for each key not returned and, if required by the CONTRACTING OFFICER, any re-keying costs and cost of any other damages suffered by the

GOVERNMENT.

1.20 WARRANTY

A. In addition to the specific guarantees required by the Specifications for certain portions of the work to be performed under this Contract, the CONTRACTOR shall furnish a written warranty for all of the work to be performed under this Contract, against defects in materials or workmanship for a period of 1 year from the date of final acceptance of the completed work by the GOVERNMENT.

B. All work including workmanship, material, and equipment (other than GOVERNMENT furnished equipment) shall be warranted for the full period of standard manufacturer's warranty, but in no case shall be warranted for a period of less than 1 year. Upon notice from the CONTRACTING OFFICER of any failure during this warranty period, the part or parts shall be replaced promptly with new parts by and at the expense of the CONTRACTOR. Whenever the manufacturer of a piece of equipment supplied by the CONTRACTOR customarily provides a warranty covering the equipment, the CONTRACTOR shall promptly turn over such to the CONTRACTING OFFICER.

C. Upon completion, the CONTRACTOR shall provide the CONTRACTING OFFICER with five bound sets and two CD's containing maintenance, repair and operating instructions and parts lists for each piece of installed equipment.

GENERAL REQUIREMENTS 010000 - 11

OHIO ARMY NATIONAL GUARD

PN# 390321

D. Reference Contract Clause FAR 52.246-12, "Inspection of Construction" and FAR 52.246-21, "Warranty of Construction."

1.21 CUTTING AND REPAIRING

A. Unless otherwise specified hereinafter, the CONTRACTOR shall do all necessary cutting, drilling, fitting and patching of work and corresponding work that may be required to make several parts come together and fit it to receive, or be received, by work of other trades shown upon, or reasonably implied, by the Drawings and Specifications for the completed Project. Reference Contract Clause FAR 52.246- 12, "Inspection of Construction."

B. The CONTRACTOR shall be held responsible for all cutting, replacement, and repairing of work that is due to faulty workmanship and which is not specifically covered by Specifications for trades which are affected. The CONTRACTOR will also be held responsible for providing, without extra cost to the GOVERNMENT, any small incidental items which are not specifically mentioned in trade specifications, but which are necessary to complete the work in accordance with the Drawings, and under the general understanding that the work when completed, shall be a finished and workmanlike job. Reference Contract Clause FAR 52.236- 5, "Material and Workmanship," and FAR 52.246-12, "Inspection of Construction."

1.22 SITE CLEANUP

A. The CONTRACTOR shall maintain the construction site in as clean and orderly condition as possible. All refuse and/or salvage material shall be gathered and disposed of periodically to maintain the site in this condition. Refer to Section 017419. CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL. For requirements on material disposal. All roadways, and roadway areas within the work area, or used by the CONTRACOTR shall be kept free of construction debris, and associated mud, dirt, sand or gravel that may be tracked from the construction work area by cleaning daily to assure safe operation of vehicles. The method of cleaning and equipment employed shall be subject to the approval of the CONTRACTING OFFICER, Reference contract clause FAR 52.236-12.

“Cleaning Up.”

B. Dewatering shall be done in compliance with OHARNG Environmental Procedures Section 01 22 00.

C. Following completion of the work, the CONTRACTOR shall clean the entire area from any debris and/or excess of misplaced material due to the CONTRACTOR' s operation and obtain CONTRACTING OFFICER's approval of this finished work. (Reference Contract Clause FAR 52.246-12, entitled "Inspection of Construction," and FAR 52.236-12, "Cleaning Up.")

GENERAL REQUIREMENTS 010000 - 12

OHIO ARMY NATIONAL GUARD

PN# 390321

1.23 LAYOUT AND GRADES

A. All lines and grade work not presently established at the site shall be laid out by the CONTRACTOR in accordance with the Drawings and Specifications. The CONTRACTOR shall maintain all established boundaries and benchmarks and replace as directed any which are destroyed or disturbed. Reference Contract Clause FAR 52.236-17, "Layout of Work."

B. The CONTRACTOR shall engage a Professional Engineer or Registered Land Surveyor, licensed to practice in the state where the project is to be located, to properly establish all locations, grades, elevations, dimensions, joints, etc., necessary to the proper location of all items of work included in this Contract. All such items shall be established in relation to the benchmark and control points noted on the Drawings.

C. Prior to acceptance of the facility and at such times as directed by the CONTRACTING OFFICER, the CONTRACTOR shall thoroughly clean all exposed surfaces of the building where work under this Contract was completed.

D. All protective coatings, except lacquers, shall be removed from finish surfaces and the finish surfaces shall be washed and cleaned. CONTRACTOR shall be held responsible for all damaged materials, and at completion, shall replace, at the CONTRACTOR's own expense, all such damaged materials.

E. Reference Contract Clause FAR 52.236-12, "Cleaning Up," and FAR 52.246-12, "Inspection of Construction."

F. The CONTRACTOR shall only impact wetlands and streams that have been identified in the Contract Drawings and indicated in the OHARNG provided wetland permits. Impacts to include grading, filling, and culverts.

1.24 REFUSE AND SALVAGE MATERIALS:

A. The CONTRACTOR must manage, recycle, and dispose of waste in accordance with guidance in the OHARNG Environmental Procedures, Section 01 22 00.

B. All salvage property removed and not reinstalled under the Contract shall be returned to the GOVERNMENT at a place on base designated by the CONTRACTING OFFICER, or properly disposed of when directed by the

GOVERNMENT.

C. Nonhazardous solid waste must be diverted to recycling, through appropriate means available to the CONTRACTOR.

D. All trees, treetops, and stumps cleared from the site shall be diverted by the CONTRACTOR from a landfill to a mulch yard or wood burning power plant.

This diversion is reported as recycling of organic waste. The GOVERNMENT will salvage and remove all merchantable saw timber which is not considered an organic waste.

E. Prior to Contract closeout the CONTRACTOR must supply a report, including the following:

GENERAL REQUIREMENTS 010000 - 13

OHIO ARMY NATIONAL GUARD

PN# 390321

1. Amount (in tons) of nonhazardous solid waste, including construction and demolition debris, that is composted, mulched, recycled, reused, donated or otherwise diverted from a disposal facility.

2. Amount (in tons) of solid waste (including construction and demolition debris) transferred to a disposal facility (landfill).

1.25 STORAGE

A. No secure storage space will be provided by the GOVERNMENT. The GOVERNMENT will not be responsible for property belonging to, or under the present control of the CONTRACTOR. The CONTRACTING OFFICER, or COR, will designate an unsecured, open area for storage of construction equipment and materials during the period covered by this Contract. Reference Contract Clause FAR 52.236-10, "Operations and Storage Areas." The CONTRACTOR shall protect CONTRACTOR's materials.

B. The CONTRACTOR shall construct such temporary sheds, as may be required, for the use of workmen and as required for tool cribs and storage of all work under this Contract. Temporary sheds shall be confined to the space assigned by the CONTRACTING OFFICER, or COR. Sheds shall be of approved construction and wood floors, lighting and heat shall be provided in all parts used by workmen. Exterior of sheds shall be painted, all parts maintained in good condition throughout the life of the Contract, and at completion, all parts shall be removed and the premises cleaned up. Reference Contract Clauses FAR 52.236- 10, "Operations and Storage Areas," and FAR 52.236-12, "Cleaning Up."

1.26 TEMPORARY FIELD OFFICES

A. As soon as practicable after award of Contract, and until final completion of the work, CONTRACTOR shall provide, maintain and later remove suitable temporary office(s). All field offices shall be in good repair, painted on the exterior, provided with adequate heating, lighting and maintained in a clean and sanitary condition at all times. Reference Contract Clause FAR 52.236-10, "Operations and Storage Areas."

B. The CONTRACTOR shall provide temporary office space for the exclusive use of the GOVERNMENT inspectors, to include contracted inspectors. This office shall include, as a minimum, two desks, two suitable chairs, access to a phone line and separate high speed internet connection at no additional cost to the

GOVERNMENT.

C. The CONTRACTOR is reminded that smoking in buildings on a GOVERNMENT facility is prohibited. A smoking area for employees, away from the main entrance of a building, must be provided.

GENERAL REQUIREMENTS 010000 - 14

OHIO ARMY NATIONAL GUARD

PN# 390321

1.27 TEMPORARY TOILET FACILITIES

A. The CONTRACTOR must provide all temporary toilet facilities. The temporary toilet facilities shall meet the requirements of health authorities having jurisdiction and shall be kept clean and in a sanitary condition at all times.

1.28 TELEPHONE AND COMMUNICATIONS SECURITY MONITORING

A. The CONTRACTOR shall provide telephone service at the field office for personal and subcontractor use. Arrangements with the telephone company will be the responsibility of the CONTRACTOR, as well as all charges for installation, services, and removal.

B. All communications with DOD organizations are subject to communications security (COMSEC) review. CONTRACTOR personnel will be aware telephone communications networks are continually subject to intercept by unfriendly intelligence organizations. The DOD has authorized the military departments to conduct COMSEC monitoring and recording of telephone calls originating from, or terminating at, DOD organizations. Therefore, civilian CONTRACTOR personnel are advised any time they place a call to, or receive a call from, a DOD organization, they are subject to COMSEC procedures. The CONTRACTOR will assume the responsibility for ensuring wide and frequent dissemination of the above information to all employees dealing with DOD information.

1.29 UTILITIES

A. The CONTRACTING OFFICER has determined that GOVERNMENT-operated utilities are not adequate and will not be furnished to the CONTRACTOR without charge where existing outlets are available. The CONTRACTOR is responsible for installing temporary service outlets, as necessary. Any expense incurred to gain access to these utilities (temporary tap-ins, etc.,) shall be the responsibility of the CONTRACTOR and all utilities shall be returned to their original configurations at the end of the contracts. No alterations to existing utilities shall be accomplished without the written permission of the CONTRACTING

OFFICER.

1.30 UTILITY INTERRUPTIONS

A. All utility shutdowns require the prior approval of the CONTRACTING OFFICER. Request for utility shutdown shall be made in writing at least 4 weeks prior to the expected date of implementation. As soon as actual shutdown date is known, the CONTRACTOR shall notify the CONTRACTING OFFICER, in writing, requesting approval at least 8 workdays prior to requested shutdown.

B. The CONTRACTOR’s progress schedule shall include preliminary listing of all proposed shutdown dates. Every effort shall be made to make all shutdowns as brief as possible and as limited in extent as possible

GENERAL REQUIREMENTS 010000 - 15

OHIO ARMY NATIONAL GUARD

PN# 390321

1.31 PERMITS

A. CONTRACTOR is required to secure all permit required for the project before proceeding with any work.

1.32 COMPRESSED AIR

A. CONTRACTOR shall provide all compressed air used for work under this Contract, including temporary lines and connections. All temporary lines, etc. shall be removed at the completion of the work.

1.33 WEATHER PROTECTION AND TEMPORARY HEATING

A. The CONTRACTOR shall provide and maintain weather protection as may be required to properly protect all parts of the structure from damage during construction.

B. The CONTRACTOR shall be responsible for repairs and maintenance to the heating system or units during the period during progress of building construction and shall deliver same to the GOVERNMENT, at termination of such use, in perfect condition, cleaning out all air ducts and replacing all filters. Any temporary heating shall be at the expense of the CONTRACTOR.

1.34 ARCHEOLOGICAL, PALEONTOLOGICAL AND ENDANGERED SPECIES

FINDS

A. Any archeological finds (evidence of human occupation) or paleontological finds (evidence of prehistoric plant or animal life) are to be reported to the CONTRACTING OFFICER immediately and continue work in other areas without interruption. Protect native endangered flora and fauna and notify the CONTRACTING OFFICER of any construction activities that might threaten endangered species or their habitats.

B. The CONTRACTOR shall comply with the OHARNG Environmental Procedures, Section 01 22 00.

1.35 REAL PROPERTY/EQUIPMENT REPORT

A. The CONTRACTOR shall furnish, upon completion of the Project, "Real Property Installed Cost," form in triplicate, and on two CD's of all equipment installed in the facility, and the installed cost of each item. Furthermore, the listing shall include the location of each item and nameplate data.

B. Typically, the listing shall include: air conditioners, air handling units, condensers, fans, pumps, air compressors, transformers, unit heaters, regulators, direct current power supplies, latrine fixtures, motors, engines, motor or engine-driven equipment, drinking fountains, sinks, water coolers, generators, space heaters, water heaters, refrigerators, freezers, coolers, meters, gas detectors, humidifiers

GENERAL REQUIREMENTS 010000 - 16

OHIO ARMY NATIONAL GUARD

PN# 390321

dehumidifier, air purifier, ovens, power units, fuel tanks, water tanks, elevators, welders, recorders, reels, scales, hydrants, intrusion detection equipment, fire detection and alarm equipment, emergency light sets, emergency eye wash, deluge showers, washers, dryers dishwashers, bridge cranes and like items of equipment.

C. Final payment will not be made to the CONTRACTOR until the GOVERNMENT has received and approved the listing. The CONTRACTOR shall use the DD 1354 form.

1.36 DAMAGES REPAIRS

A. All damages by the CONTRACTOR’s operations shall be repaired, or replaced, at the CONTRACTOR’s expense, as directed by the CONTRACTING OFFICER. Any GOVERNMENT property damaged as a result of the work, materials, or operations of the CONTRACTOR shall be restored at no additional expense to the

GOVERNMENT.

B. All existing sidewalks, curbs, fencing, and pavement disturbed, broken or removed or otherwise damaged by the CONTRACTOR during performance of the work under this contract shall be replaced by the CONTRACTOR at the CONTRACTOR's own expense. Replaced sidewalks, curbs, and pavements shall be smooth, shall blend into the existing work, and shall not present depressions or humps.

C. Reference Contract Clause FAR 52.236-9, "Protection of Existing Vegetation, Structures, Equipment, Utilities and Improvements."

1.37 AS-BUILT DRAWINGS

A. The CONTRACTOR shall keep an accurate record of all deviations from the approved design Drawings and Specifications which may occur in the work as actually constructed, and shall submit to the CONTRACTING OFFICER, at completion of the work, complete information including descriptions, Drawings, dimensions, marked prints, etc., as required for correction of the tracings to the as-built conditions. It is not sufficient to simply reference an addendum or change order. Contractor may tape graphics of such documents into as built and red line as built information on these graphics. The information is to be color coded for easy decoding as follows:

1. Red when showing information added to the Drawings.

2. Green when showing information deleted from the Drawings.

3. Blue and circled in blue to show notes.

B. The redlined Drawings shall be complete with any deviation in actual construction.

GENERAL REQUIREMENTS 010000 - 17

OHIO ARMY NATIONAL GUARD

PN# 390321

1.38 MAINTENANCE OF TRAFFIC AND SAFETY

A. Where possible, construction work shall not interfere with the normal operations of traffic, particularly emergency vehicles and equipment. CONTRACTOR is responsible for safety on the Project site.

B. The CONTRACTOR shall use only established haul routes. When materials are transported in prosecution of the work, vehicles shall not be loaded beyond the loading limit established by Federal, State or Local Law or regulation. When it is necessary to cross curbing or sidewalks, protection against damage shall be provided by the CONTRACTOR.

C. The CONTRACTOR shall provide for the free and unobstructed movement of Military vehicles with respect to all operations and the operations of subcontractors.

D. With respect to the CONTRACTOR’s own operations, and those of all the CONTRACTOR’s subcontractors, the CONTRACTOR shall provide marking, lighting and other acceptable means of identifying personal, equipment, vehicles, storage areas, and any work or condition that may be hazardous to the operation of military vehicles, fire-rescue equipment, or maintenance vehicles at the Post.

E. The CONTRACTOR shall furnish, erect, and maintain weighted barricades, warning signs, and other traffic control devices as required to maintain traffic and ensure that safety of military vehicles in the area and the CONTRACTOR’s equipment. The Contractor shall make an estimate of all labor, materials, equipment, and coincidental necessary for providing the maintenance of vehicular traffic

1.39 SPECIAL CONDITIONS

A. Any CONTRACTOR's equipment that causes or generates electro-magnetic disturbances or interference shall be removed from service until properly repaired.

The CONTRACTING OFFICER may also require repositioning or removal of the equipment from the Post.

1.40 HAZARDOUS MATERIAL USAGE

A. The CONTRACTOR shall establish a hazardous material (HM) storage and distribution system when HM is to be used. The CONTRACTOR HM Inventory Form will be provided to the CONTRACTING OFFICER at or prior to the Preconstruction meeting.

B. The CONTRACTOR shall maintain CONTRACTOR HM Inventory Form for HM on the jobsite for inspection/verification.

C. The CONTRACTOR shall establish a HM storage and issue location that complies with Federal, state and local environmental regulations. Materials issued shall be tracked for quantities used. Unused materials shall be inventoried and removed from the installation prior to closeout of the Contract or expiration date of the HM . Reports of material delivered, used and removed from the installation

GENERAL REQUIREMENTS 010000 - 18

OHIO ARMY NATIONAL GUARD

PN# 390321

shall be submitted to the CONTRACTING OFFICER monthly and prior to Contract closeout.

D. The CONTRACTOR shall comply with all Federal, state and local environmental standards, including OSHA HazCom and COE 385-1-1.

E. The CONTRACTOR shall accompany the COR and the installation Environmental Manager (EM) on Project closeout inspection to ensure all used and unused HM has been removed from the installation. This requirement shall not be a punchlist item and must be accomplished prior to the GOVERNMENT accepting beneficial occupancy of the facility or construction item.

F. Any material suspected of being hazardous that is encountered during performance of a project shall immediately be brought to the attention of the CONTRACTING OFFICER, at which time a determination will be made as to whether hazardous material testing shall be performed. If the CONTRACTING OFFICER directs the CONTRACTOR to perform tests, and/or the material is found to be of a hazardous nature requiring additional protective measures, a modifications may be required subject to equitable adjustment under the terms of the Contract.

1.41 ENERGY AND WATER EFFICIENY AND RENEWABLE ENERGY

A. The GOVERNMENT’s policy is to acquire supplies and services that promote energy and water efficiency, advance the use of renewable energy products, and help foster markets for emerging technologies.

B. The CONTRACTOR shall include the provisions of energy-using products for construction, renovations or maintenance of a public building by acquiring energy-using products designated by the Department of Energy’s Federal Energy…