This document is a Specifications file for a Walk-In Growth-Chamber with Incidental Installation Services for the USDA-ARS NEA Foreign Disease-Weed Science Research Unit (FDWSRU) in Frederick, MD. The project requires a water-cooled, walk-in environmental plant growth chamber with specific technical requirements, including a minimum of 96 square feet of growth space, LED grow lighting with dimming and tunable spectrum capabilities, precise temperature and humidity controls (-5°C to 40°C), and a programmable controller for dynamic chamber controls.
The deliverables schedule includes material submittal within 7 days after award, chamber delivery 60 days after submittal approval, installation completed 14 days after delivery, and training and final inspection within 7 days of installation completion. The installation will be at 1301 Ditto Avenue, with specific delivery constraints including a 34.5" x 82.5" side door access and elevator limitations. The contract includes user training and a 2-year parts/1-year labor warranty, with the contractor required to meet specific governmental safety and work restriction requirements.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Specifications Project: Walk-In Growth-Chamber with Incidental Installation Services
GENERAL INFORMATION
1.0 Backround:
The Foreign Disease-Weed Science Research Unit (FDWSRU) conducts research on emerging plant pathogens in Biosafety Level (BSL)-3 and BSL-2 laboratories and requires an additional 4th walk-in fluid-cooled controlled environmental plant growth chamber to be procured and installed to support research capability needs at our locations. Currently, Bldg. 1301 contains 3 walk-in and 8 reach-in fluid-cooled controlled environment plant growth chambers that house research projects critical to the mission. Fluid-cooled heat exchange on the units ensures that excessive heat from chamber operations does not build up inside bldg. 1301. These plant growth chambers are serviced by two existing 56-ton York chiller units external to the building.
CONTRACTOR REQUIREMENTS
2.0 Technical Requirements/Tasks:
Water-cooled condenser (Walk-In Growth Chamber)
• Form Factor:
o Minimum of 96 Square Feet of Growth Space o Maximum external dimensions of 9’11” w x 11’10” d x 9’2” h o Capable of racking, multilevel plants
• LED Grow Lighting:
o Dimming 10-100% o Tunable light spectrum o Capable of at least 1500 micromoles at 1 meter from canopy
• Temperature and Humidity Controls:
o Temp range: minimum range -5°C to 40°C, o Lights on/off +/- 1 degree C (continuous operation without defrost spikes) o Temperature control: ± 0.5 degrees C around the temperature set point o Relative humidity range: 40 - 70%, lights off and 40 - 60%, lights on between a temperature range of 15°C to 30°C.
o Additive Dehumidification/Humidification: 2% to 95% RH with +5% control, (subject to dew point restrictions)
• Cooling: Water-cooled condensing unit to be in mechanical space one floor below room
• Dynamic Scheduling Control: Programmable Controller with touchscreen and scheduling capabilities for dynamic chamber controls and weather condition mimicking
• Capable of racking, multilevel plants Building Utilities:
• 120/208V – 3 phase – 60 Hz, 4-wire plus ground
• Water for humidification
• Chilled water supply/return
• Sanitary Sewer: floor drain Security Requirements:
• Meet “Section 01140 – Work Restrictions”
Assembly & Installation:
• Installation: Shipping, Onsite Assembly & Installation, Commissioning/Starup
• Meet “Section 01352 - Governmental Safety Requirements”
Training:
• User Training after Commissioning/Startup
Warranty:
• 2-year warranty parts; 1-year warranty labor
3.0 Deliverables / Schedule:
Item QTY Unit Place of Delivery
Delivery Date
Growth-Chamber (Material Submittal with Dimensions and cut-sheet)
1 Each See Below 7 Days After Award
Growth-Chamber Delivered 1 Each See Below 60 Days After Submittal Approval
Installation Completed 1 Each See Below 14 Days After Delivery
Training & Final Inspection 1 Each See Below Within 7 Days of Installation Completion
Place of Delivery USDA-ARS NEA Foreign Disease Weed Science Research Unit (FDWSRU) 1301 Ditto Avenue, Frederick, MD 21702
Delivery Details A loading dock is not available, there are multiple building access points. Closest to installation location is located at the side of the building, through a 34.5” x 82.5” door.
Elevator and stairs are available for delivery to the basement/lower floor.
The available elevator dimensions will not accommodate the size of the item if fully assembled when delivered.
Delivery Point of Contact TBD at time of award.
| CONTRACTOR REQUIREMENTS |
| 2.0 Technical Requirements/Tasks: |