This document is a Specifications file for a Walk-In Growth-Chamber with Incidental Installation Services for the USDA-ARS NEA Foreign Disease-Weed Science Research Unit (FDWSRU) in Frederick, MD. The project requires a water-cooled, walk-in environmental plant growth chamber with specific technical requirements, including a minimum of 96 square feet of growth space, LED grow lighting with dimming and tunable spectrum capabilities, precise temperature and humidity controls (-5°C to 40°C), and a programmable controller for dynamic chamber controls.

The deliverables schedule includes material submittal within 7 days after award, chamber delivery 60 days after submittal approval, installation completed 14 days after delivery, and training and final inspection within 7 days of installation completion. The installation will be at 1301 Ditto Avenue, with specific delivery constraints including a 34.5" x 82.5" side door access and elevator limitations. The contract includes user training and a 2-year parts/1-year labor warranty, with the contractor required to meet specific governmental safety and work restriction requirements.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Specifications Project: Walk-In Growth-Chamber with Incidental Installation Services

GENERAL INFORMATION

1.0 Backround:

The Foreign Disease-Weed Science Research Unit (FDWSRU) conducts research on emerging plant pathogens in Biosafety Level (BSL)-3 and BSL-2 laboratories and requires an additional 4th walk-in fluid-cooled controlled environmental plant growth chamber to be procured and installed to support research capability needs at our locations. Currently, Bldg. 1301 contains 3 walk-in and 8 reach-in fluid-cooled controlled environment plant growth chambers that house research projects critical to the mission. Fluid-cooled heat exchange on the units ensures that excessive heat from chamber operations does not build up inside bldg. 1301. These plant growth chambers are serviced by two existing 56-ton York chiller units external to the building.

CONTRACTOR REQUIREMENTS

2.0 Technical Requirements/Tasks:

Water-cooled condenser (Walk-In Growth Chamber)

• Form Factor:

o Minimum of 96 Square Feet of Growth Space o Maximum external dimensions of 9’11” w x 11’10” d x 9’2” h o Capable of racking, multilevel plants

• LED Grow Lighting:

o Dimming 10-100% o Tunable light spectrum o Capable of at least 1500 micromoles at 1 meter from canopy

• Temperature and Humidity Controls:

o Temp range: minimum range -5°C to 40°C, o Lights on/off +/- 1 degree C (continuous operation without defrost spikes) o Temperature control: ± 0.5 degrees C around the temperature set point o Relative humidity range: 40 - 70%, lights off and 40 - 60%, lights on between a temperature range of 15°C to 30°C.

o Additive Dehumidification/Humidification: 2% to 95% RH with +5% control, (subject to dew point restrictions)

• Cooling: Water-cooled condensing unit to be in mechanical space one floor below room

• Dynamic Scheduling Control: Programmable Controller with touchscreen and scheduling capabilities for dynamic chamber controls and weather condition mimicking

• Capable of racking, multilevel plants Building Utilities:

• 120/208V – 3 phase – 60 Hz, 4-wire plus ground

• Water for humidification

• Chilled water supply/return

• Sanitary Sewer: floor drain Security Requirements:

• Meet “Section 01140 – Work Restrictions”

Assembly & Installation:

• Installation: Shipping, Onsite Assembly & Installation, Commissioning/Starup

• Meet “Section 01352 - Governmental Safety Requirements”

Training:

• User Training after Commissioning/Startup

Warranty:

• 2-year warranty parts; 1-year warranty labor

3.0 Deliverables / Schedule:

Item QTY Unit Place of Delivery

Delivery Date

Growth-Chamber (Material Submittal with Dimensions and cut-sheet)

1 Each See Below 7 Days After Award

Growth-Chamber Delivered 1 Each See Below 60 Days After Submittal Approval

Installation Completed 1 Each See Below 14 Days After Delivery

Training & Final Inspection 1 Each See Below Within 7 Days of Installation Completion

Place of Delivery USDA-ARS NEA Foreign Disease Weed Science Research Unit (FDWSRU) 1301 Ditto Avenue, Frederick, MD 21702

Delivery Details A loading dock is not available, there are multiple building access points. Closest to installation location is located at the side of the building, through a 34.5” x 82.5” door.

Elevator and stairs are available for delivery to the basement/lower floor.

The available elevator dimensions will not accommodate the size of the item if fully assembled when delivered.

Delivery Point of Contact TBD at time of award.

CONTRACTOR REQUIREMENTS
2.0 Technical Requirements/Tasks:

File details come from the government source that posted it. Updated .