Attachment_2_-_Specifications.pdf
PDF 637 KB Posted
- Attached to
- BLM-CO 18 ROAD REC AREA IMPROVEMENTS
- Solicitation number
- 140L1724Q0012
About this file
This document is the technical specifications and requirements related to a federal contract opportunity for improvements to the 18 Road Recreation Area in Colorado. The work includes site work, road and parking area construction, installation of a precast concrete toilet building and gazebo, and construction of campsites. The project is located approximately 12 miles north of the city of Fruita, Colorado. The contract will have a period of performance from July 15 to December 31, 2024, with work prohibited from April 15 to July 15 and September 19-22 and October 3-6 due to wildlife and scheduled events. This is a small business set-aside contract with a rough order of magnitude between $250,000 and $500,000. Key requirements include submitting a priced SF1442, bid bond, and technical response. Payments will be made via progress payments through IPP with a 14-day prompt pay policy.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Sol_140L1724Q0012_Amd_0002.pdf | ||
| Sol_140L1724Q0012_Amd_0001.pdf | ||
| Sol_140L1724Q0012.pdf | ||
| Attachment_4_-_Wage_Determination.pdf | ||
| Attachment_3_-_Bid_Schedule.pdf | ||
| Attachment_1_-_Drawings.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
United States Department of the Interior Bureau of Land Management
Grand Junction Field Office Colorado
18 Road Recreation Area Improvements
SPECIFICATIONS
PROJECT TABLE OF CONTENTS
DI VI SI ON 01 - GENERAL REQUI REMENTS
01 11 00 SUMMARY OF WORK
01 20 00 PRICE AND PAYMENT PROCEDURES
01 32 01 PROJECT SCHEDULE
01 33 00 SUBMITTAL PROCEDURES
01 46 00 QUALITY CONTROL
01 57 60 SUPPLEMENTAL ENVIRONMENTAL CONTROLS
01 80 00 PHOTOGRAPHIC DOCUMENTATION
DI VI SI ON 02 - EXI STI NG CONDI TI ONS
02 20 00 SURVEY AND PROJECT STAKEOUT
02 41 00 DEMOLITION
DI VI SI ON 03 - CONCRETE
03 30 00 CAST-IN-PLACE CONCRETE
DI VI SI ON 05 - METALS
05 50 20 GAZEBO
DI VI SI ON 12 - FURNI SHI NGS
12 60 00 PRECAST CONCRETE TOILET BUILDING
12 93 00 SITE FURNISHINGS
DI VI SI ON 31 - EARTHWORK
31 00 00 EARTHWORK
31 11 00 CLEARING AND GRUBBING
DI VI SI ON 32 - EXTERI OR I MPROVEMENTS
32 90 20 SEEDING
DI VI SI ON 33 - UTI LI TI ES
33 40 00 STORM DRAINAGE UTILITIES
-- End of Project Table of Contents --
PROJECT TABLE OF CONTENTS Page 1
SECTION 01 11 00
SUMMARY OF WORK
PART 1 GENERAL
1.1 PROJECT DESCRIPTION
The work includes, but is not limited to; site work, road and parking area construction, precast concrete toilet installation, gazebo installation, and campsite construction.
1.2 LOCATION
The project is located approximately 12 miles north of the city of Fruita, CO. From Fruita, Colorado, travel north on 18 Road until you get to the existing BLM North Fruita Desert trailhead. The project location can also be found by searching "North Fruita Desert" in google maps.
1.3 WORK SCHEDULE
Work is not allowed from April 15 to July 15 to protect wildlife.
Work is not allowed September 19-22 and October 3-6. There are large race events scheduled at the project site those dates.
Work shall occur Monday - Friday, excluding federal holidays.
Work shall be completed within 150 days of the Notice to Proceed.
1.4 PUBLIC SAFETY
The project site is a busy recreation area. The project site will remain open to the public during the work. Contractor shall take precautions, as necessary, to protect the public from construction hazards.
PART 2 PRODUCTS
Not used.
PART 3 EXECUTION
Not used.
-- End of Section --
SECTION 01 11 00 Page 2
SECTION 01 20 00
PRICE AND PAYMENT PROCEDURES
PART 1 GENERAL
Payment items for the work of this contract for which contract payments will be made are listed in the SCHEDULE and described below. All costs for items of work, which are not specifically mentioned to be included in a particular job are included in the listed job item most closely associated with the work involved. The price and payment made for each item listed constitutes full compensation for furnishing all labor, materials, and equipment, and performing any associated Contractor quality control, environmental protection, meeting safety requirements, tests and reports, and for performing all work required for which separate payment is not otherwise provided.
1.1 MOBILIZATION AND DEMOBILIZATION
1.1.1 Payment
Payment will be made for costs associated with mobilization and demobilization.
When 5% of the original Contract amount is earned from other bid items, 50% of the amount bid for mobilization or 5% of the original Contract amount, whichever is lesser, will be paid.
When 15% of the original Contract amount is earned from other bid items, 100% of the amount bid for mobilization or 8% of the original Contract amount, whichever is lesser, will be paid.
Upon completion of work for the project, payment of the amount bid for mobilization in excess of 8% of the original Contract amount, will be paid.
1.1.2 Unit of Measure
Unit of measure: job.
1.2 PROJECT STAKEOUT
1.2.1 Payment
Payment will be made for all costs associated with surveying and staking out the work.
1.2.2 Unit of Measure
Unit of measure: Job.
SECTION 01 20 00 Page 3
1.3 DEMOLITION
1.3.1 Payment
Payment will be made for all costs associated with demolition. Including transportation and disposal.
1.3.2 Unit of Measure
Unit of measure: job.
1.4 CLEARING AND GRUBBING
1.4.1 Payment
Payment will be made for all costs associated with clearing and grubbing.
Including transportation and disposal of materials.
1.4.2 Unit of Measure
Unit of measure: Job.
1.5 SITE GRADING
1.5.1 Payment
Payment will be made for all costs associated with site grading, including moisture conditioning, and compaction.
1.5.2 Unit of Measure
Unit of measure: Job.
1.6 PRECAST CONCRETE TOILET BUILDING
1.6.1 Payment
Payment will be made for all costs associated with providing a precast concrete toilet building. Including preparation, transportation, bedding material, installation, and backfill compaction.
1.6.2 Unit of Measure
Unit of measure: Each.
1.7 AGGREGATE BASE COURSE
1.7.1 Payment
Payment will be made for all costs associated with providing aggregate base course. Including preparation, transportation, placement, moisture
SECTION 01 20 00 Page 4 conditioning, and compaction. Submit weight tickets.
1.7.2 Unit of Measure
Unit of measure: ton.
1.8 CONCRETE PARKING STOP
1.8.1 Payment
Payment will be made for all costs associated with providing parking stops.
1.8.2 Unit of Measure
Unit of measure: Each.
1.9 FIRE RING
1.9.1 Payment
Payment will be made for all costs associated with providing fire rings.
Including foundation, gravel, and site preparation.
1.9.2 Unit of Measure
Unit of measure: Each.
1.10 ACCESSIBLE FIRE RING
1.10.1 Payment
Payment will be made for all costs associated with providing accessible fire rings. Including foundation, gravel, and site preparation.
1.10.2 Unit of Measure
Unit of measure: Each.
1.11 PICNIC TABLE
1.11.1 Payment
Payment will be made for all costs associated with providing picnic tables. Including grading and aggregate surfacing around picnic tables.
1.11.2 Unit of Measure
Unit of measure: Each.
SECTION 01 20 00 Page 5
1.12 SIGN POSTS - CAMPSITE IDENTIFICATION
1.12.1 Payment
Payment will be made for all costs associated with providing sign posts.
1.12.2 Unit of Measure
Unit of measure: Each.
1.13 GAZEBO
1.13.1 Payment
Payment will be made for all costs associated with providing a gazebo.
Including preparation, grading, foundation, erection, and aggregate.
1.13.2 Unit of Measure
Unit of measure: Each.
1.14 CORRUGATED METAL PIPE CULVERT
Payment will be made for all costs associated with providing corrugated metal pipe culverts, including bedding material, earthwork, and compaction.
1.14.1 Unit of Measure
Unit of measure: linear foot
1.15 SEEDING
1.15.1 Payment
Payment will be made for all costs associated with seeding.
1.15.2 Unit of Measure
Unit of measure: Job.
SECTION 01 20 00 Page 6
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
Not Used
SECTION 01 20 00 Page 7
SECTION 01 32 01
PROJECT SCHEDULE
PART 1 GENERAL
1.1 SUBMITTALS
Government approval is required for submittals with a "G" designation.
Submit the following in accordance with Section 01 33 00 SUBMITTAL
PROCEDURES:
SD-01 Preconstruction Submittals
Initial Project Schedule ; G
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
3.1 GENERAL REQUIREMENTS
Prepare for approval a Project Schedule, as specified herein, and pursuant to FAR Clause 52.236-15 Schedules for Construction Contracts. Show in the schedule the proposed sequence to perform the work and dates contemplated for starting and completing all schedule activities. The scheduling of the entire project is required.
3.2 PROJECT SCHEDULE DETAILED REQUIREMENTS
3.2.1 Level of Detail Required
Develop the Project Schedule to the appropriate level of detail to address major milestones and to allow for satisfactory project planning and execution.
3.2.2 Mandatory Tasks
Include the following activities/tasks in the initial project schedule and all updates.
a. Submission, review and acceptance of submittals.
b. Long procurement activities
c. Contractor's pre-final inspection.
d. Government's pre-final inspection.
e. Final inspection.
SECTION 01 32 01 Page 8
3.2.3 Government Activities
Include Government activities that could impact progress. These activities include, but are not limited to: Government inspections of work, Government approval of submittals.
3.3 WEEKLY PROGRESS MEETINGS
Conduct a weekly meeting with the Government for the purpose of jointly reviewing the actual progress of the project as compared to the as planned progress and to review planned activities.
3.4 FAILURE TO ACHIEVE PROGRESS
Should the progress fall behind the approved project schedule, the Contracting Officer may require provision of a written recovery plan for approval. The plan must detail how progress will be made-up to include which activities will be accelerated by adding additional crews, longer work hours, extra work days, etc.
3.4.1 Failure to Perform
Failure to perform work and maintain progress in accordance with the supplemental recovery plan may result in an interim and final unsatisfactory performance rating and may result in corrective action directed by the Contracting Officer pursuant to FAR 52.236-15 Schedules for Construction Contracts, FAR 52.249-10 Default (Fixed-Price Construction), and other contract provisions.
3.4.2 Recovery Schedule
Should the Contracting Officer find it necessary, submit a recovery schedule pursuant to FAR 52.236-15 Schedules for Construction Contracts.
SECTION 01 32 01 Page 9
SECTION 01 33 00
SUBMITTAL PROCEDURES
PART 1 GENERAL
1.1 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only.
1.2 INFORMATION ONLY SUBMITTALS
Normally submittals for information only will not be returned. Approval of the Contracting Officer's Representative is not required on information only submittals. The Government reserves the right to require the Contractor to resubmit any item found not to comply with the contract.
This does not relieve the Contractor from the obligation to furnish material conforming to the plans and specifications; will not prevent the Contracting Officer from requiring removal and replacement of nonconforming material incorporated in the work; and does not relieve the Contractor of the requirement to furnish samples for testing by the Government.
1.3 GOVERNMENT APPROVING AUTHORITY
The Contracting Officer's Representative will:
a. Note the date on which the submittal was received.
b. Review submittals for approval within 10 days of receipt.
c. Identify returned submittals with one of the actions defined in paragraph REVIEW NOTATIONS and with markings appropriate for action indicated.
Upon completion of review of submittals requiring Government approval, one copy of the submittal will be retained by the Contracting Officer's Representative and one copy of the submittal will be returned to the Contractor.
1.3.1 Review Notations
Submittals will be returned to the Contractor with the following notations:
a. Submittals marked "approved" or "accepted" authorize the Contractor to proceed with the work covered.
b. Submittals marked "approved as noted" or "approved, except as noted, resubmittal not required," authorize the Contractor to proceed with the work covered provided the Contractor takes no exception to the corrections.
c. Submittals marked "not approved" or "disapproved," or "revise and resubmit," indicate noncompliance with the contract requirements or design concept, or that submittal is incomplete. Resubmit with appropriate changes. No work shall proceed for this item until
SECTION 01 33 00 Page 10 resubmittal is approved.
d. Submittals marked "not reviewed" will indicate submittal has been previously reviewed and approved, is not required, does not have evidence of being reviewed and approved by Contractor, or is not complete. A submittal marked "not reviewed" will be returned with an explanation of the reason it is not reviewed. Resubmit submittals returned for lack of review by Contractor or for being incomplete, with appropriate action, coordination, or change.
e. Submittals marked "receipt acknowledged" indicate that submittals have been received by the Government. This applies only to "information-only submittals" as previously defined.
1.4 DISAPPROVED SUBMITTALS
Make corrections required by the Contracting Officer's Representative. If the Contractor considers any correction or notation on the returned submittals to constitute a change to the contract drawings or specifications; notice as required under the FAR clause entitled CHANGES, is to be given to the Contracting Officer.
If changes are necessary to submittals, make such revisions and submission of the submittals in accordance with the procedures above. No item of work requiring a submittal change is to be accomplished until the changed submittals are approved.
1.5 APPROVED SUBMITTALS
The Contracting Officer's approval of submittals is not to be construed as a complete check.
Approval or acceptance will not relieve the Contractor of the responsibility for any error which may exist, as the Contractor under the Contractor Quality Control (CQC) requirements of this contract is responsible for.
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
Not Used
SECTION 01 33 00 Page 11
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 1 OF 2 PAGES
18 Road Recreation Area Improvements, Phase 3
01 32 01 SD-01 Preconstruction Submittals
GInitial Project Schedule
01 46 00 SD-01 Preconstruction Submittals
1.2 GQuality Control (QC) Manager
01 57 60 SD-01 Preconstruction Submittals
3.6 GSpill Prevention And Cleanup
Plan
3.1 GRainfall Erosivity Waiver
Exclusion Permit
3.2 GState Of Colorado Stormwater
Discharge Permit
SD-11 Closeout Submittals
3.5 GPhotographic Documentation
03 30 00 SD-03 Product Data
2.3 GStructural Macro Synthetic
Reinforcing Fibers
05 50 20 SD-01 Preconstruction Submittals
2.1 GGazebo
3.3 GInstallation Instructions
SD-11 Closeout Submittals
3.2 GPhotographic Documentation
12 60 00 SD-03 Product Data
2.1 GPrecast Toilet Building
3.1 GManufacturer's Product
Specifications and installation instructions
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P H
C L A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
AUTH REMARKS
(a) (b) (c) (d) (e) (f) (g) (h) (i) (j) (k) (l) (m) (n) (o) (p) (q) (r)
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 2 OF 2 PAGES
18 Road Recreation Area Improvements, Phase 3
12 93 00 SD-03 Product Data
2.2 GPicnic Tables
2.1 GFire Rings
2.4 GParking Stops
31 00 00 SD-03 Product Data
2.1 GAggregate Base Course
SD-07 Certificates
3.8Aggregate Weight Tickets
32 90 20 SD-03 Product Data
2.1 GSeed Mixture
SD-07 Certificates
3.1 GSeed Certification
33 40 00 SD-03 Product Data
2.1 GCorrugated Steel Pipe
2.2 GJoint
SD-11 Closeout Submittals
3.3 GPhotographic Documentation
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P H
C L A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
AUTH REMARKS
(a) (b) (c) (d) (e) (f) (g) (h) (i) (j) (k) (l) (m) (n) (o) (p) (q) (r)
SECTION 01 46 00
QUALITY CONTROL
PART 1 GENERAL
1.1 QUALITY CONTROL
Contractor shall establish and maintain an effective quality control (QC) system that complies with FAR 52.246-12 Inspection of Construction.
Quality control (QC) is comprised of plans, procedures, and organization necessary to produce an end product that complies with the contract requirements.
1.2 QUALITY CONTROL MANAGER
Provide a quality control (QC) manager at the work site to implement and manage the QC program. The QC Manager may also be the project superintendent.
1.3 SUBMITTALS
Government approval is required for submittals with a "G" designation;
Submit the following in accordance with Section 01 33 00 SUBMITTAL
PROCEDURES:
SD-01 Preconstruction Submittals
Quality Control (QC) Manager ; G
PART 2 PRODUCTS
Not Used.
PART 3 EXECUTION
3.1 QUALITY CONTROL
Contractor shall ensure that the construction complies with the requirements of the contract. At a minimum, perform the following prior to beginning work on each definable feature of work:
Review each paragraph of the applicable specification sections.
Review the contract drawings.
Verify that appropriate submittals have been approved.
Verify that the required preliminary work has been completed and complies with the contract.
Do not build upon nor conceal non-conforming work.
SECTION 01 46 00 Page 12
SECTION 01 57 60
SUPPLEMENTAL ENVIRONMENTAL CONTROLS
PART 1 GENERAL
1.1 DEFINITIONS
Equipment: for the purpose of this specification, equipment shall include, but isn't limited to; dozers, backhoes, trackhoes, trailers, graders, compactors, or any other construction equipment used to accomplish the work. Passenger vehicles are not considered equipment.
1.2 SUBMITTALS
Government approval is required for submittals with a "G" designation;
Submit the following in accordance with Section 01 33 00 SUBMITTAL
PROCEDURES:
SD-01 Preconstruction Submittals
Spill Prevention And Cleanup Plan ; G
Rainfall Erosivity Waiver Exclusion Permit ; G
State Of Colorado Stormwater Discharge Permit ; G
SD-11 Closeout Submittals
Photographic Documentation ; G
PART 2 PRODUCTS
Not Used.
PART 3 EXECUTION
3.1 STATE OF COLORADO STORMWATER DISCHARGE PERMIT - RAINFALL EROSIVITY
WAIVER EXCLUSION FROM STORMWATER PERMITTING
The contractor shall be responsible for all aspects of obtaining a State of Colorado rainfall erosivity waiver exclusion permit. The contractor shall submit the approved rainfall erosivity waiver exclusion permit prior to completing any work on site.
The contractor shall complete all ground disturbance work withing the timeline specified in the rainfall erosivity waiver exclusion permit. If the contractor exceeds the timeline specified in the permit, then all ground disturbance work shall stop and shall not restart until the contractor obtains an approved State of Colorado, stormwater discharge permit.
If the contractor can not obtain an approved rainfall erosivity waiver exclusion, then the contractor shall obtain a State of Colorado stormwater discharge permit.
SECTION 01 57 60 Page 13
3.1.1 GROUND DISTURBANCE AREA
The ground disturbance area for this project is 4.3 acres.
3.2 STATE OF COLORADO STORMWATER DISCHARGE PERMIT
A State of Colorado stormwater discharge permit is only required if the contractor can not obtain a rainfall erosivity waiver exclusion permit, or exceeds the time limitations of the rainfall erosivity waiver exclusion permit.
The contractor shall be responsible for all aspects of obtaining the stormwater discharge permit. The BLM will sign the application only after the contractor has fully completed the permit application.
The contractor shall be responsible for ensuring compliance with all terms and conditions of the permit including, and not limited to; completion and implementation of the Stormwater Management Plan (SWMP), providing a qualified stormwater manager, site inspections, inspection reports, monitoring and monitoring records.
The contractor shall submit the approved stormwater discharge permit, issued by the state of Colorado, prior to completing any work on site.
3.3 EROSION CONTROL
In addition to the requirements of the State of Colorado stormwater permits, contractor shall take measures, as necessary to control erosion. Contractor shall inspect site after rain (or melt) events and mitigate areas where erosion or sediment runoff is occurring. Erosion includes wind. Contractor shall water exposed soils, as necessary, to prevent wind erosion.
3.4 FIRE PREVENTION
All equipment shall have a spark arrester installed. The Contractor shall have a fire extinguisher and shovel readily available to contain and extinguish fires.
3.5 EQUIPMENT CLEANING AND MAINTENANCE
Equipment shall be cleaned prior to arriving on site. Equipment shall arrive on site free from dirt, debris, weeds, and seeds. All equipment shall be inspected by the Contracting Officer's Representative, on site, and prior to unloading. Notify the Contracting Officer's Representative at least 7 days prior to equipment delivery to coordinate inspection. If equipment leaves the jobsite, and returns at a later date, then equipment shall be re-inspected before reentering the work site.
Equipment maintenance will not be allowed on site. Equipment leaking fluids shall be removed from site.
Provide photographic documentation in accordance with section 01 80 00 .
Provide pictures demonstrating equipment is clean while the equipment is onsite, and prior to unloading.
SECTION 01 57 60 Page 14
3.6 SPILL PREVENTION
The Contractor shall submit a spill prevention and cleanup plan. The spill prevention and cleanup plan shall identify foreseeable accidents, including spills while adding fluids to equipment, and identify an action plan to rapidly clean all accidents. Cleanup materials and equipment shall be on site during work.
3.7 WASTE CONTROL
All waste generated by the work shall be contained and removed from the site and disposed of in a legal manor.
SECTION 01 57 60 Page 15
SECTION 01 80 00
PHOTOGRAPHIC DOCUMENTATION
PART 1 GENERAL
1.1 SUMMARY OF WORK
Document that the work is in compliance with contract requirements.
PART 2 PRODUCTS
Not Used.
PART 3 EXECUTION
3.1 PHOTOGRAPHS
Provide photographs in sufficient detail and quantity to demonstrate compliance with contract requirements. Submit electronic photographs via email. Photographs sent via text message will not be accepted.
Photographs do not negate requirements for Contracting Officer's Representative's inspections and approvals on specified items of work.
SECTION 01 80 00 Page 16
SECTION 02 20 00
SURVEY AND PROJECT STAKEOUT
PART 1 GENERAL
Not Used.
PART 2 PRODUCTS
Not Used.
PART 3 EXECUTION
3.1 PROJECT STAKEOUT
The contractor shall stake out the project as detailed on the drawings, and as required for construction.
3.2 STAKEOUT REVIEW
The Contracting Officer's Representative and the Contractor shall review the layout, as staked, together. The Contractor shall build 15 working days into the project schedule for coordination of a meeting date that works for both the Contractor and the Contracting Officer's Representative.
The Contracting Officer's Representative may make minor modifications to the layout in order to minimize the damage to existing vegetation, or for constructability. The contractor shall receive approval of the stakeout prior to clearing and grubbing, or other earth disturbing activities.
SECTION 02 20 00 Page 17
SECTION 02 41 00
DEMOLITION
PART 1 GENERAL
Remove approximately 70 feet of existing post and cable fencing. Exact fence removal extents will be flagged by the Contracting Officer's Representative during the survey stakeout review.
PART 2 PRODUCTS
Not Used.
PART 3 EXECUTION
3.1 POST AND CABLE FENCING
Cut the wire rope, relocate the end post, and reconnect the wire rope to the relocated end fence post in the same manor that it was connected before relocation.
3.2 DISPOSAL OF REMOVED MATERIALS
All materials removed, shall become the property of the Contractor and shall be removed from Government property and disposed of in a legal manor.
SECTION 02 41 00 Page 18
SECTION 03 30 00
CAST-IN-PLACE CONCRETE
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this section to the extent referenced. The publications are referred to within the text by the basic designation only.
AMERICAN CONCRETE INSTITUTE (ACI)
ACI 301 (2016) Specifications for Structural Concrete
ACI 305.1 (2014) Specification for Hot Weather Concreting
ACI 306.1 (1990; R 2002) Standard Specification for Cold Weather Concreting
ASTM INTERNATIONAL (ASTM)
ASTM A615/A615M (2020) Standard Specification for Deformed and Plain Carbon-Steel Bars for Concrete Reinforcement
ASTM C387/C387M (2017) Standard Specification for Packaged, Dry, Combined Materials for Concrete and High Strength Mortar
NATIONAL READY MIXED CONCRETE ASSOCIATION (NRMCA)
NRMCA QC 3 (2015) Quality Control Manual: Section 3, Plant Certifications Checklist:
Certification of Ready Mixed Concrete Production Facilities
1.2 SUBMITTALS
Government approval is required for submittals with a "G" designation;
Submit the following in accordance with Section 01 33 00 SUBMITTAL
PROCEDURES:
SD-03 Product Data
Structural Macro Synthetic Reinforcing Fibers ; G
PART 2 PRODUCTS
2.1 CONCRETE
Provide concrete composed of portland cement, aggregates, water, and admixtures as specified.
SECTION 03 30 00 Page 19
2.1.1 STRENGTH
Compressive strength (f'c) shall be 3500 psi at 28 days.
2.1.2 Air Entrainment
Attain air content at point of placement between 4 and 6 percent.
2.1.3 SLUMP
Slump of the concrete, at the point of placement, shall be 4 inches or less.
2.1.4 PORTLAND CEMENT
ASTM C150/C150M, Type II.
2.2 STEEL REINFORCEMENT BARS (REBAR)
Steel reinforcement shall comply with ACI 301 and ASTM A615/A615M , Grade60;
2.3 STRUCTURAL MACRO SYNTHETIC REINFORCING FIBERS
Structural macro synthetic reinforcing fibers shall be Sika Fibermesh 650, or approved equal. Structural macro synthetic reinforcing fibers shall have a diameter greater than 0.3 mm and a length between 1 inch and 3 inches.
2.4 PREPACKAGED CONCRETE MIXTURE
Prepackaged concrete mix shall be identified as conforming to
ASTM C387/C387M
2.5 READY MIXTURE
Ready-mix plant equipment and facilities must be certified in accordance with NRMCA QC 3.
PART 3 EXECUTION
3.1 STRUCTURAL MACRO SYNTHETIC REINFORCING FIBERS
Provide 4 pounds of reinforcing fibers per cubic yard of concrete.
Incorporate into concrete mix as recommended by the manufacturer.
3.2 STEEL REINFORCEMENT BARS (REBAR)
Provide as shown on the drawings.
3.3 PREPACKAGED CONCRETE MIXTURE
Use the minimum amount of water to make the mixture. Adding too much water to the mixture will greatly reduce the overall compressive strength. Average slump shall be between 2" to 4".
3.4 FOOTINGS
Concrete for footings may be placed in excavations without forms.
SECTION 03 30 00 Page 20
Excavation width must be a minimum of 2 inches greater than indicated if forms are not used.
3.5 CONCRETE CONSOLIDATION
Concrete shall be adequately vibrated, rodded, or spaded into place to fill voids. The gazebo footings shall be vibrated.
3.6 COLD WEATHER REQUIREMENTS
Perform cold weather concreting in accordance with ACI 306.1 . Use special protection measures if freezing temperatures are anticipated before the expiration of the specified curing period. The ambient temperature of the air where concrete is to be placed and the temperature of surfaces to receive concrete must be not less than 40 degrees F. The temperature of the concrete when placed must be not less than 50 degrees F nor more than 75 degrees F. Heat the mixing water or aggregates to regulate the concrete placing temperature. Materials entering the mixer must be free from ice, snow, or frozen lumps. Do not incorporate salt, chemicals or other materials in the concrete to prevent freezing.
3.7 HOT WEATHER REQUIREMENTS
When job-site conditions are present or anticipated that accelerate the rate of moisture loss or rate of cement hydration of freshly mixed concrete, including an ambient temperature of 80 degrees F or higher, and an evaporation rate that exceeds 0.2 lb/ft2/h, conform concrete work to all requirements of ACI 305.1 .
SECTION 03 30 00 Page 21
SECTION 05 50 20
GAZEBO
PART 1 GENERAL
1.1 SUBMITTALS
Government approval is required for submittals with a "G" designation;
Submit the following in accordance with Section 01 33 00 SUBMITTAL
PROCEDURES:
SD-01 Preconstruction Submittals
Gazebo; G
Installation Instructions ; G
SD-11 Closeout Submittals
Photographic Documentation ; G
PART 2 PRODUCTS
2.1 GAZEBO
Gazebo shall be, 20' x 20' Mesa, HR-36, as manufactured by Classic Recreation Systems Inc.
Roofing shall be 24 gauge, HR-36 panels, factory coated with Kynar500 finish. Steel shall be factory powder coated. Submit gazebo details and color samples for approval.
http://shadesun.com/
(928) 775-3307 11875 E. Berry Drive Dewey AZ 86327
PART 3 EXECUTION
3.1 LOCATION
Gazebo location shown on the drawings is approximate. Exact location will be staked by the Contracting Officer's Representative.
3.2 FOUNDATION
Verify the exact dimensions of the gazebo prior to constructing the foundation. The gazebo columns shall align with the center of the foundations. Secure the columns to the foundation. Provide anchor bolt, washer, and nuts.
Provide photographic documentation in accordance with section 01 80 00 PHOTOGRAPHIC DOCUMENTATION. Provide pictures demonstrating the foundation and rebar comply with requirements.
SECTION 05 50 20 Page 22
3.3 ERECTION
Erect the gazebo in accordance with the manufacturer's installation instructions. Submit the manufacturer's installation instructions .
SECTION 05 50 20 Page 23
SECTION 12 60 00
PRECAST CONCRETE TOILET BUILDING
PART 1 GENERAL
1.1 SCOPE
This specification covers the installation of a precast toilet building as produced by CXT Incorporated.
1.2 SUBMITTALS
Government approval is required for submittals with a "G" designation.
Submit the following in accordance with Section 01 33 00 SUBMITTAL
PROCEDURES:
SD-03 Product Data
Precast Toilet Building ; G
Manufacturer's Product Specifications and installation instructions ; G
PART 2 PRODUCTS
2.1 PRECAST TOILET BUILDING
The precast toilet building shall be manufactured by CXT Incorporated.
CXT Incorporated Spokane Industrial Park 3808 North Sullivan Road, Building 7 Spokane, WA 99216 Phone 800-696-5766
2.1.1 MODEL
Tioga Special, double vault.
2.1.2 TEXTURES AND COLORS
Ext er i or Locat i on Texture Color
Walls Barnwood Sand Beige
Roof Cedar Shake Granite Rock
2.1.3 WALL VENT LOCATION
The wall vents shall be on the back wall, upon entering the door.
SECTION 12 60 00 Page 24
2.1.4 ADDITIONAL BUILDING REQUIREMENTS
Supply (2) 3 roll paper holders, for a total of 6 rolls. Note: (1) 3 roll holder is standard, (2) 3 roll paper holders will require additional coordination with the manufacturer.
Install solar vent fan for each vent.
Install unisex signage.
2.2 PRODUCT REQUIREMENTS
The precast toilet building shall meet the following criteria.
2.2.1 Manufacturer Criteria
The manufacturer supplying the precast concrete vault toilet must meet the following:
A. Manufacturer must be ISO 9001 certified.
B. Manufacturing plant must be PCI certified.
C. Manufacturer must provide stamped, engineered drawings prior to acceptance.
D. Manufacturer must show four (4) examples of Sweet Smelling Technology designed precast concrete vault toilet facilities produced, installed, and in use as an example of their ability to perform.
E. Manufacture shall provide a twenty (20) year warranty.
F. UL 752 Bullet Resistance on 4" thick concrete samples.
2.2.2 Design Criteria
2.2.2.1 Roof Snow Load
Vault buildings are designed to withstand a 350 pounds per square foot snow load.
2.2.2.2 Floor Load
Vault buildings are designed to withstand 400 pounds per square foot floor load.
2.2.2.3 Wind Load
Vault buildings shall withstand the effects of 150 miles per hour (3-second gust) wind exposure C.
2.2.2.4 Earthquake
Vault buildings will withstand the effects of a seismic design category E earthquake.
2.2.2.5 Sweet Smelling Technology (SST)
Vault buildings shall incorporate design aspects of SST as outlined by Briar Cook for the U.S. Forest Service. All wall to floor interior surface seams shall have a minimum 1" radius coving made of high strength grout. The vault shall have a bottom slope of 1" per foot from under the toilet riser out to the outside cleanout area. The vault shall have a 24"
SECTION 12 60 00 Page 25 diameter (minimum) lightweight manhole cover installed to the rear or side of the building. The manhole cover should be raised, with the surrounding concrete sloped away using a minimum slope of ½" per foot. The depth of the vault shall be no deeper than 4½' to 5'. A 12" diameter round pipe will be installed to vent the vault and the pipe shall be raised a minimum of 3' above the highest point of the roof. Vent pipe shall be straight up from the vault. There shall be only one vent opening in the building.
2.2.2.6 Additional Design Standards
Single vault buildings shall be an all concrete design with a minimum 7/12 roof pitch. Vault buildings shall have a minimum 4" wall, 4½" roof, and 5" floor thickness. Vault buildings shall have a one-piece floor unit to prevent panels that migrate in different directions during periods of freeze/thaw stress. Vault buildings shall have a one-piece full length and width vault unit to support the building, screen area, and snow loads evenly.
2.2.2.7 Concrete - Colored
The roof panels, building walls, and screen panels shall be colored concrete. Color shall match the existing concrete toilet building on site.
2.2.2.8 Doors - Steel
Doors are flush panel type 1¾" thick, minimum 16-gauge galvanized steel, top painted with DTM ALKYD.
Door frames are knockdown or welded type, single rabbet, minimum 16-gauge prime coated steel top painted with DTM ALKYD, width to suit wall thickness. Three (3) rubber door silencers are provided on latch side of frame. Three hinges (3) per door with dull chrome plating 4½" x 4½", adjustable tension, and automatic closing for each door. Dome style doorstop stop meeting ANSI 156.16. Provide door sweep at the bottom of door with an adjustable brush.
2.2.2.9 Grab Bars
Grab ars shall be 18-gauge, type 304 stainless steel with 1½" clearance.
Able to withstand 300-pound top loading.
2.2.2.10 Riser
Riser shall meet ADA standards, be constructed of molded one-piece HDPE polyethylene, and have a smooth surface and have high impact resistance at extremely cold temperatures.
2.2.2.11 Toilet Paper Dispenser
Toilet Paper Dispenser shall be constructed of ¼" thick, type 304 stainless steel, hold three (3) standard rolls of toilet paper.
Fastening system able to withstand 300-pound top loading.
2.2.2.12 Polyethylene Vault Liner
Polyethylene Vault Liner shall be made of a Roto molded 8460 polyethylene. Hold up to 1,000 gallons of waste. Minimum thickness .100.
SECTION 12 60 00 Page 26
2.3 CONTRACTOR PROPOSED SUBSITUTIONS
Contractor proposed substitutions to the precast toilet building specified shall be submitted with the bid. If proposed substitution doesn't meet the specifications, the bid will not be considered. If a bid is submitted without a proposed substitution, then the contractor shall install the precast toilet building specified.
PART 3 EXECUTION
3.1 INSTALLATION
Install the precast toilet building in accordance with the manufacturer's product specifications. The entire manufacturer's specification will be incorporated, including the excavation, elevation, backfill, compaction, and material requirements. A sand or aggregate bedding material shall be installed. Submit the manufacturer's product specifications and installation instructions , which will supplement this specification section.
3.1.1 Finish Floor Elevation and Slope
The finish floor elevation will be provided by the BLM. The contractor shall install the precast toilet building within 0.05 feet of the elevation provided. The precast toilet building shall be sloped between 1% and 1.5% to allow water to drain out of the interior of the building, through the door.
3.1.2 Backfill and Compaction
Backfill and compact in accordance with the manufacturer's product specifications. In addition to the compaction specified in the manufacturer's product specifications:
Backfill adjacent to the precast toilet building shall be placed in 8 inch, maximum, lifts and compacted with a whacker-type mechanical tamper or equivalent.
SECTION 12 60 00 Page 27
SECTION 12 93 00
SITE FURNISHINGS
PART 1 GENERAL
1.1 SUBMITTALS
Government approval is required for submittals with a "G" designation.
Submit the following in accordance with Section 01 33 00 SUBMITTAL
PROCEDURES:
SD-03 Product Data
Picnic Tables ; G
Fire Rings ; G
Parking Stops ; G
PART 2 PRODUCTS
2.1 FIRE RINGS
2.1.1 Accessible Fire Rings
Accessible fire rings shall be compliant with the American with Disability Act (ADA). Accessible fire rings shall be as manufactured by Pilot Rock or approved equal. Note: Jamestown Advanced Products will NOT be approved as an "or equal".
Pilot Rock Fire Ring Model: M-32/17/PA
2.1.2 Fire Rings
Fire rings shall be as manufactured by Pilot Rock or approved equal.
Note: Jamestown Advanced Products will NOT be approved as an "or equal".
Pilot Rock Fire Ring Model: FSW-30/9/PA
2.1.3 Anchors
Fire rings shall be anchored with three steel pins and encased in concrete as shown on the drawings.
2.2 PICNIC TABLES
Picnic tables shall be "one piece" reinforced concrete as manufactured by Outdoor Creations Inc. or approved equal, with the Bureau of Land Management (BLM) logo cast into both sides of the table.
Outdoor Creations Inc. Model 100S.
2.3 SIGN POSTS - CAMPSITE IDENTIFICATION
U-Channel sign posts shall be steel, 6 foot total length, have a 1-3/8"
SECTION 12 93 00 Page 28 channel depth, 3/8" holes on 1" centers, and be painted brown.
2.4 CONCRETE PARKING STOPS
Parking stops shall be reinforced concrete. With minimum dimensions of;
six foot length, eight inch width, and 5 inch height.
PART 3 EXECUTION
3.1 SIGN POSTS - CAMPSITE IDENTIFICATION
Install sign posts plumb. Drive the posts 2 feet into the ground. When rock prevents driving, excavate or drill a hole, place post in hole, and grout post securely in position with cement grout or mortar. Install at locations staked by the Contracting Officer.
The contractor is not required to obtain signs for the sign posts.
3.2 PICNIC TABLES
Grade the ground surface level prior to placing picnic tables. Place aggregate under the picnic tables as shown on the drawings. Picnic tables shall be placed in locations staked by the Contracting Officer. Location shown on the drawings is approximate.
3.3 FIRE RINGS
Grade the ground surface level prior to placing fire rings. Fire rings shall be placed in locations staked by the Contracting Officer. Location shown on the drawings is approximate.
3.4 CONCRETE PARKING STOPS
Each parking stop shall be held in place with two (2) #4 rebars, 24 inches long.
SECTION 12 93 00 Page 29
SECTION 31 00 00
EARTHWORK
PART 1 GENERAL
1.1 SUBMITTALS
Government approval is required for submittals with a "G" designation.
Submit the following in accordance with Section 01 33 00 SUBMITTAL
PROCEDURES:
SD-03 Product Data
Aggregate Base Course ; G
SD-07 Certificates
Aggregate Weight Tickets
PART 2 PRODUCTS
2.1 AGGREGATE BASE COURSE
Aggregate base course shall meet the requirements of Colorado Department of Transportation Standard Specifications for Road and Bridge Construction 2022, section 703 AGGREGATES. Aggregate base course gradation shall meet the gradation shown in Table 703-2, Class 6.
PART 3 EXECUTION
3.1 UNDERGROUND UTILITIES
The Contractor is responsible for locating underground utilities prior to construction. The Government is not aware of any underground utilities, however the Contractor shall verify the presence or absence prior to construction.
3.2 GENERAL EXCAVATION
Perform excavation of every type of material encountered to the lines, grades, and elevations indicated and as specified. Perform excavation and fill in a manner and sequence that will provide proper drainage at all times, including during construction.
3.3 GROUND SURFACE PREPARATION
Clear and grub in accordance with section 31 11 00 . Do not perform construction when surfaces are frozen or muddy. Prepare the subgrade to a smooth and compact surface in accordance with the lines, grades, and cross sections or elevations shown. Shape subgrade to drain.
SECTION 31 00 00 Page 30
3.4 EARTHWORK QUANTITIES
Location Cut (Cubic Yards) Fill (Cubic Yards) Net (Cubic Yards)
Grading Area #1 640 60 580
Grading Area #2 480 10 470
Grading Area #3 110 10 100
Grading Area #4 130 10 120
Grading Area #5 1080 1910 -830
Net 440
3.5 CAMPSITE GRADING AREAS
Grade camping areas relatively flat, with slopes not exceeding 2 percent.
3.6 VIBRATORY COMPACTION EQUIPMENT
Vibratory compaction equipment shall have a minimum of 10,000 pounds impact per vibration and a minimum frequency of 1,000 vibrations per minute.
3.7 AGGREGATE PLACEMENT LOCATIONS
3.7.1 Subgrade
Contractor shall prepare the subgrade to the lines and grades shown on the plans.
3.7.2 Subgrade Compaction
Moisten material as necessary to achieve compaction. Compact the subgrade by operating vibratory compaction equipment over the full width. Continue compaction until a firm surface is achieved, without any soft areas, and a minimum of 3 passes over the entire width.
3.7.3 Aggregate Base Course
Contractor shall receive approval of the subgrade prior to placing aggregate base course. Place base course aggregate to the lines and grades shown on the plans.
3.7.4 Aggregate Base Course Compaction
Moisten material as necessary to achieve compaction. Compact the base course aggregate by operating vibratory compaction equipment over the full width. Continue compaction until a firm surface is achieved, without any soft areas, and a minimum of 3 passes over the entire width.
3.8 AGGREGATE WEIGHT TICKETS
Submit aggregate weight tickets . Weight tickets are required prior to
SECTION 31 00 00 Page 31 payment.
3.9 EXCESS MATERIAL DISPOSAL
Move excess material from grading areas 1 through 4 to grading area 5.
Excess cut material shall be placed uniformly on site, at designated locations. Excess cut material shall not be removed from the work site.
Excess material disposed within 20 feet of the gazebo foundations, in all directions, shall be moisture conditioned and compacted in accordance with the subgrade requirements.
3.10 FINISHING
Finish the surfaces to a smooth and compact surface in accordance with the lines, grades, and cross sections or elevations shown. Provide the degree of finish for graded areas within 0.5 foot of the elevations indicated.
Finish surfaces in a manner that will result in effective drainage, regardless of tolerance.
3.10.1 STAKEOUT POINTS - SUBGRADE ELEVATIONS
There is a 0.5 foot tolerance on the subgrade elevations provided. The finish elevations may be altered to aid the earthwork. However, finish slopes shall generally match the slopes shown and never exceed the slopes shown.
3.11 TOILET AREA GRADING
The finish grade slopes from the toilet to the 4 parking spaces adjacent to the toilet shall be less than 2 percent.
SECTION 31 00 00 Page 32
SECTION 31 11 00
CLEARING AND GRUBBING
PART 1 GENERAL
Not Used.
PART 2 PRODUCTS
Not Used.
PART 3 EXECUTION
3.1 SURVEY STAKE OUT
Prior to clearing and grubbing, the contractor shall stake out the project stakeout points, as detailed on the drawings, in accordance with 02 20 00 SURVEY AND PROJECT STAKEOUT. The Contracting Officer's Representative will review the layout as staked and may make minor modifications to the layout in order to minimize the damage to existing vegetation. The contractor shall receive approval of the stakeout prior to clearing and grubbing.
3.2 CLEARING AND GRUBBING LIMITS
Clearing and grubbing limits shall be within the proposed; camping areas, road, parking areas, and ditches.
3.3 PROTECTION
Protect trees and vegetation from damage incident to clearing, grubbing, and construction operations.
3.4 CLEARING
Clearing shall consist of the felling, trimming, and cutting of trees into sections and the satisfactory disposal of the trees and other vegetation designated for removal, including downed timber, snags, brush, and rubbish occurring within the areas to be cleared. Trees, stumps, roots, brush, and other vegetation in areas to be cleared shall be cut off flush with or below the original ground surface.
3.5 GRUBBING
Grubbing consists of the removal and disposal of stumps, roots larger than 3 inches in diameter, and matted roots from the designated grubbing areas.
Remove material to be grubbed, together with logs and other organic or metallic debris not suitable for foundation purposes, to a depth of not less than 12 inches below the original surface level of the ground in the area of new road construction. Fill depressions made by grubbing with suitable material and compact to make the surface conform with the original adjacent surface of the ground.
SECTION 31 11 00 Page 33
3.6 DISPOSAL OF CLEARING AND GRUBBING VEGETATION
Dispose of clearing and grubbing material in locations designated. Logs, stumps, roots, brush, rotten wood, and other organic material resulting from the clearing and grubbing operations, shall be uniformly scattered on site in piles less than 18 inches off the ground. Process, mulch, cut, or limb material as necessary to comply with disposal pile requirements.
SECTION 31 11 00 Page 34
SECTION 32 90 20
SEEDING
PART 1 GENERAL
1.1 SUBMITTALS
Government approval is required for submittals with a "G" designation.
Submit the following in accordance with Section 01 33 00 SUBMITTAL
PROCEDURES:
SD-03 Product Data
Seed Mixture ; G
SD-07 Certificates
Seed Certification ; G
PART 2 PRODUCTS
2.1 SEED MIXTURE
Common Name Scientific Name
Variety Form Pounds per Acre
Total pounds required
Lewis/Blue flax
Linum lewisii Maple Grove Forb 0.5 1.0
Western yarrow Achillea millefolium
UP, Dry Fork Forb 0.3 0.6
Annual sunflower
Helianthus annuus
UP Forb 0.5 1.0
Western Wheatgrass
Pascopyrum [Agropyron] smithii
Uncompahgre Project* (UP), Native Colorado or Utah variety, if available.
If not, then: Rosana, Recovery, Rodan (not Arriba)
Sod-forming 2.5 5
SECTION 32 90 20 Page 35
Thickspike Wheatgrass
Elymus lanceolatus ssp.lanceolatus, Agropyron dasystachyum
Critana, Bannock,Schwendimar
Sod-forming 3.0 6.0
Indian Ricegrass
Oryzopsis] hymenoides
White River, Paloma, Rimrock
Bunch 2.5 5.0
Slender Wheat Elymus trachycaulus, Agropyron trachycaulum
White River, San Luis
Bunch 2.5 5.0
Squirrel tail Elymus elymoides, Sitanion hystrix
Fish Creek, Toe Jam, Wapiti
Bunch 0.5 1.0
Four wing Atriplex canescens
Shrub 1.0 2.0
Submit seed mixture for approval.
Two acres of seeding is required.
PART 3 EXECUTION
3.1 SEED CERTIFICATION
Seed shall be tested by an official state seed analysis laboratory. Seed shall meet the following requirements. Submit seed certification.
Germination Rate 80% minimum
Purity 90% minimum
Noxious Weed Seeds 0.0%
Weed Seeds 0.5% maximum
3.2 SEEDING
Uniformly broadcast seed on disturbed ground after all grading and earthwork is complete.
3.3 SEEDING TIMING RESTRICTIONS
Seed between November and February. If the project is completed outside of the specified time period, then provide the seed to the BLM, and the BLM will seed the ground at the appropriate time.
SECTION 32 90 20 Page 36
SECTION 33 40 00
STORM DRAINAGE UTILITIES
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this section to the extent referenced. The publications are referred to within the text by the basic designation only.
ASTM INTERNATIONAL (ASTM)
ASTM A760/A760M (2015) Standard Specification for Corrugated Steel Pipe, Metallic-Coated for Sewers and Drains
ASTM A929/A929M (2018) Standard Specification for Steel Sheet, Metallic-Coated by the Hot-Dip Process for Corrugated Steel Pipe
1.2 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-03 Product Data
Corrugated Steel Pipe ; G
Joint ; G
SD-11 Closeout Submittals
Photographic Documentation ; G
PART 2 PRODUCTS
2.1 CORRUGATED STEEL PIPE CULVERT
ASTM A929/A929M Aluminum-coated, type 2 (Aluminized Type 2) coated pipe:
a. ASTM A760/A760M Type I (circular) pipe with helical 2-2/3 by 1/2 inch corrugations.
b. 14 gage (0.079 inches).
c. 24 inch diameter.
2.1.1 CULVERT QUANTITIES
Six culverts are required.
SECTION 33 40 00 Page 37
Quantity Each Culvert Length (feet)
4 40
2 50
2.2 JOINT
ASTM A929/A929M Aluminum-coated, type 2 (Aluminized Type 2) coated joint.
ASTM A760/A760M , soil tight joint.
2.3 BEDDING MATERIAL
Bedding material shall meet the following gradation:
Sieve Size Percent passing
1 inch 100%
Number 4 20% - 65%
Number 200 0% - 10%
PART 3 EXECUTION
3.1 TRENCHING
The width of trenches at any point below the top of the pipe shall not be less than the outside diameter of the pipe plus 24 inches to permit thorough tamping of the bedding material under and around the pipe.
3.2 BEDDING
Provide bedding material. The bedding surface for the pipe shall provide a firm foundation of uniform density throughout the entire length of the pipe.
3.3 JOINTING
Install joint in accordance with manufacturer's recommendations. Provide a soil tight joint.
Provide photographic documentation in accordance with section 01 80 00 PHOTOGRAPHIC DOCUMENTATION. Provide pictures demonstrating the joint is properly installed and bedded.
3.4 BACKFILLING
After the pipe has been properly bedded, selected material from excavation or borrow, at a moisture content that will facilitate compaction, shall be placed along both sides of pipe in layers not exceeding 6 inches in compacted depth. The backfill shall be brought up evenly on both sides of
SECTION 33 40 00 Page 38 pipe for the full length of pipe. The fill shall be thoroughly compacted under the haunches of the pipe. Each layer shall be thoroughly compacted with mechanical tampers or rammers.
3.4.1 Backfill Material
Backfill material, within 12 inches of the culvert, shall be free of rocks or particles larger than 2 inches in diameter.
SECTION 33 40 00 Page 39
| PROJECT TABLE OF CONTENTS |
| DIVISION 01 - GENERAL REQUIREMENTS |
| 01 11 00 - SUMMARY OF WORK |
| PART 1 GENERAL |
| 1.1 PROJECT DESCRIPTION |
| 1.2 LOCATION |
| 1.3 WORK SCHEDULE |
| 1.4 PUBLIC SAFETY |
| PART 2 PRODUCTS |
| PART 3 EXECUTION |
| 01 20 00 - PRICE AND PAYMENT PROCEDURES |
| PART 1 GENERAL |
| 1.1 MOBILIZATION AND DEMOBILIZATION |
| 1.1.1 Payment |
| 1.1.2 Unit of Measure |
| 1.2 PROJECT STAKEOUT |
| 1.2.1 Payment |
| 1.2.2 Unit of Measure |
| 1.3 DEMOLITION |
| 1.3.1 Payment |
| 1.3.2 Unit of Measure |
| 1.4 CLEARING AND GRUBBING |
| 1.4.1 Payment |
| 1.4.2 Unit of Measure |
| 1.5 SITE GRADING |
| 1.5.1 Payment |
| 1.5.2 Unit of Measure |
| 1.6 PRECAST CONCRETE TOILET BUILDING |
| 1.6.1 Payment |
| 1.6.2 Unit of Measure |
| 1.7 AGGREGATE BASE COURSE |
| 1.7.1 Payment |
| 1.7.2 Unit of Measure |
| 1.8 CONCRETE PARKING STOP |
| 1.8.1 Payment |
| 1.8.2 Unit of Measure |
| 1.9 FIRE RING |
| 1.9.1 Payment |
| 1.9.2 Unit of Measure |
| 1.10 ACCESSIBLE FIRE RING |
| 1.10.1 Payment |
| 1.10.2 Unit of Measure |
| 1.11 PICNIC TABLE |
| 1.11.1 Payment |
| 1.11.2 Unit of Measure |
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .