This document provides details on a federal solicitation to renovate and expand the emergency department at the Gallup Indian Medical Center. The solicitation number is 75H70124R00012 and is being issued by the Department of Health and Human Services Indian Health Service for architectural and engineering services. Interested parties are to provide technical qualifications and pricing information by April 15th, 2023. The selected contractor will be responsible for designing the renovated and expanded emergency department facility with the goal of improving patient care and outcomes. The project is to be completed within 24 months of award.
View the file
Other files
Show all 22
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
GIMC EMERGENCY DEPT.
EXPANSION & RENOVATION
Indian Health Service
516 East Nizhoni Boulevard Gallup, New Mexico 87301
SPECIFICATION MANUAL
FINAL CONSTRUCTION DOCUMENTS
October 11, 2022
ARCHITECT
JOHNSON SMITTHIPONG & ROSAMOND ASSOCIATES, INC.
TUCSON, ARIZONA
10/11/2022
Table of Contents - 1
TABLE OF CONTENTS
DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS
SECTION 003126 - EXISTING HAZARDOUS MATERIAL INFORMATION
SECTION 003132 - GEOTECHNICAL DATA
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 011100 - SUMMARY OF WORK
SECTION 011400 - WORK RESTRICTIONS
SECTION 012000.0020 - PRICE AND PAYMENT PROCEDURES
SECTION 013000 - ADMINISTRATIVE REQUIREMENTS
SECTION 013201.0010 - PROJECT SCHEDULE
SECTION 013300 - SUBMITTAL PROCEDURES
SECTION 013329 - SUSTAINABILITY REQUIREMENTS AND REPORTING
SECTION 013526 - GOVERNMENTAL SAFETY REQUIREMENTS
SECTION 014500.0010 - QUALITY CONTROL
SECTION 014535 - SPECIAL INSPECTIONS
SECTION 015000 - TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS
SECTION 015720.0010 - ENVIRONMENTAL PROTECTION
SECTION 015721 - INDOOR AIR QUALITY CONTROLS
SECTION 015723 - TEMPORARY STORM WATER POLLUTION CONTROL
SECTION 015800 - PROJECT IDENTIFICATION
SECTION 017419 - CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL
SECTION 017419.01 - FORM CWM-1: CONSTRUCTION WASTE IDENTIFICATION
SECTION 017419.02 - FORM CWM-2: DEMOLITION WASTE IDENTIFICATION
SECTION 017419.03 - FORM CWM-3: CONSTRUCTION WASTE REDUCTION WORK PLAN
SECTION 017419.04 - FORM CWM-4: DEMOLITION WASTE REDUCTION WORK PLAN
SECTION 017419.05 - FORM CWM-5: COST/REVENUE ANALYSIS OF CONSTRUCTION
WASTE REDUCTION WORK PLAN
SECTION 017419.06 - FORM CWM-6: COST/REVENUE ANALYSIS OF DEMOLITION WASTE
REDUCTION WORK PLAN
SECTION 017419.07 - FORM CWM-7: CONSTRUCTION WASTE REDUCTION PROGRESS
REPORT
SECTION 017419.08 - FORM CWM-8: DEMOLITION WASTE REDUCTION PROGRESS REPORT
SECTION 017800 - CLOSEOUT SUBMITTALS
SECTION 017823 - OPERATION AND MAINTENANCE DATA
SECTION 017900 - DEMONSTRATION AND TRAINING
DIVISION 02 - EXISTING CONDITIONS
SECTION 020100 - MAINTENANCE OF EXISTING CONDITIONS
SECTION 024000 - SITE DEMOLITION
SECTION 024119 - SELECTIVE DEMOLITION
SECTION 028216.00 20 - ENGINEERING CONTROL OF ASBESTOS CONTAINING MATERIALS
DIVISION 03 - CONCRETE
SECTION 031000 - CONCRETE FORMING AND ACCESSORIES
SECTION 032000 - CONCRETE REINFORCING
SECTION 033000 - CAST-IN-PLACE CONCRETE
Table of Contents - 2
DIVISION 04 - MASONRY
SECTION 042200 - CONCRETE UNIT MASONRY
DIVISION 05 - METALS
SECTION 051200 - STRUCTURAL STEEL FRAMING
SECTION 052100 - STEEL JOIST FRAMING
SECTION 053100 - STEEL DECK
SECTION 054000 - COLD-FORMED METAL FRAMING
SECTION 055000 - METAL FABRICATIONS
SECTION 055213 - PIPE AND TUBE RAILINGS
DIVISION 06 - WOOD, PLASTICS, AND COMPOSITES
SECTION 061600 - SHEATHING
SECTION 064116 - PLASTIC-LAMINATE-FACED ARCHITECTURAL CABINETS
SECTION 066400 - PLASTIC PANELING
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
SECTION 071416 - COLD FLUID-APPLIED WATERPROOFING
SECTION 072100 - THERMAL INSULATION
SECTION 072419 - WATER-DRAINAGE EXTERIOR INSULATION AND FINISH SYSTEM
(EIFS)
SECTION 075419 - POLYVINYL-CHLORIDE (PVC) ROOFING
SECTION 076200 - SHEET METAL FLASHING AND TRIM
SECTION 078100 - APPLIED FIREPROOFING
SECTION 078413 - PENETRATION FIRESTOPPING
SECTION 078443 - JOINT FIRESTOPPING
SECTION 079200 - JOINT SEALANTS
SECTION 079513.13 - INTERIOR EXPANSION JOINT COVER ASSEMBLIES
SECTION 079513.16 - EXTERIOR EXPANSION JOINT COVER ASSEMBLIES
DIVISION 08 - OPENINGS
SECTION 081113 - HOLLOW METAL DOORS AND FRAMES
SECTION 081416 - FLUSH WOOD DOORS
SECTION 083113 - ACCESS DOORS AND FRAMES
SECTION 083313 - COILING COUNTER DOORS
SECTION 083616.13 - ALUMINUM FRAMED SLIDING DOORS
SECTION 084113 - ALUMINUM-FRAMED ENTRANCES AND STOREFRONTS
SECTION 084229.23 - SLIDING AUTOMATIC ENTRANCES
SECTION 084243 - INTENSIVE CARE UNIT/CRITICAL CARE UNIT (ICU/CCU) ENTRANCES
SECTION 085659 - ALUMINUM SLIDING SERVICE WINDOW
SECTION 087100 - DOOR HARDWARE
SECTION 088000 - GLAZING
Table of Contents - 3
DIVISION 09 - FINISHES
SECTION 092116.23 - GYPSUM BOARD SHAFT WALL ASSEMBLIES
SECTION 092216 - NON-STRUCTURAL METAL FRAMING
SECTION 092900 - GYPSUM BOARD
SECTION 093013 - CERAMIC TILING
SECTION 095113 - ACOUSTICAL PANEL CEILINGS
SECTION 096513 - RESILIENT BASE AND ACCESSORIES
SECTION 096516 - RESILIENT SHEET FLOORING
SECTION 096519 - RESILIENT TILE FLOORING
SECTION 099000 - PAINTING
DIVISION 10 - SPECIALTIES
SECTION 101419 - DIMENSIONAL LETTER SIGNAGE
SECTION 101423 - SIGNS
SECTION 102123 - CUBICLE CURTAINS AND TRACK
SECTION 102600 - WALL AND DOOR PROTECTION
SECTION 102800 - TOILET, BATH, AND LAUNDRY ACCESSORIES
SECTION 104413 - FIRE EXTINGUISHER CABINETS
SECTION 104416 - FIRE EXTINGUISHERS
SECTION 105100 - SOLID PHENOLIC LOCKERS
DIVISION 11 - EQUIPMENT
SECTION 117000 - MEDICAL EQUIPMENT
DIVISION 12 - FURNISHINGS
SECTION 122413 - ROLLER WINDOW SHADES
SECTION 123623.13 - PLASTIC-LAMINATE-CLAD COUNTERTOPS
SECTION 123661.19 - QUARTZ AGGLOMERATE COUNTERTOPS
SECTION 124813 - ENTRANCE FLOOR MATS AND FRAMES
DIVISION 13 - SPECIAL CONSTRUCTION
SECTION 134900 - RADIATION PROTECTION
DIVISION 21 - FIRE SUPPRESSION
SECTION 210000 - SUPPLEMENTARY FIRE SUPPRESSION GENERAL CONDITION
SECTION 210517 - SLEEVES AND SLEEVE SEALS FOR FIRE-SUPPRESSION PIPING
SECTION 210518 - ESCUTCHEONS FOR FIRE-SUPPRESSION PIPING
SECTION 210553 - IDENTIFICATION FOR FIRE-SUPPRESSION PIPING AND EQUIPMENT
SECTION 211313 - WET-PIPE SPRINKLER SYSTEMS
SECTION 211316 - DRY-PIPE SPRINKLER SYSTEMS
Table of Contents - 4
DIVISION 22 - PLUMBING
SECTION 220000 - SUPPLEMENTARY PLUMBING GENERAL CONDITIONS
SECTION 220517 - SLEEVES AND SLEEVE SEALS FOR PLUMBING PIPING
SECTION 220518 - ESCUTCHEONS FOR PLUMBING PIPING
SECTION 220523 - GENERAL-DUTY VALVES FOR PLUMBING PIPING
SECTION 220529 - HANGERS AND SUPPORTS FOR PLUMBING PIPING AND EQUIPMENT
SECTION 220553 - IDENTIFICATION FOR PLUMBING PIPING AND EQUIPMENT
SECTION 220719 - PLUMBING PIPING INSULATION
SECTION 221116 - DOMESTIC WATER PIPING
SECTION 221119 - DOMESTIC WATER PIPING SPECIALTIES
SECTION 221316 - WASTE AND VENT PIPING
SECTION 221319 - SANITARY WASTE PIPING SPECIALTIES
SECTION 221423 - STORM DRAINAGE PIPING SPECIALTIES
SECTION 223100 - DOMESTIC WATER SOFTENERS
SECTION 224213.13 - COMMERCIAL WATER CLOSETS
SECTION 224216.13 - COMMERCIAL LAVATORIES
SECTION 224216.16 - COMMERCIAL SINKS
SECTION 224223 - COMMERCIAL SHOWERS, RECEPTORS, AND BASINS
SECTION 224300 - HEALTHCARE PLUMBING FIXTURES
SECTION 226113 - COMPRESSED-AIR PIPING FOR LABORATORY AND HEALTHCARE
FACILITIES
SECTION 226213 - VACUUM PIPING FOR LABORATORY AND HEALTHCARE FACILITIES
SECTION 226313 - GAS PIPING FOR LABORATORY AND HEALTHCARE FACILITIES
SECTION 226400 - MEDICAL GAS ALARMS
SECTION 226700 - PROCESSED WATER SYSTEMS FOR LABORATORY AND HEALTHCARE
FACILITIES
DIVISION 23 - HEATING, VENTILATING, AND AIR-CONDITIONING (HVAC)
SECTION 230000 - SUPPLEMENTARY HVAC GENERAL CONDITIONS
SECTION 230513 - COMMON MOTOR REQUIREMENTS FOR HVAC EQUIPMENT
SECTION 230516 - EXPANSION FITTINGS AND LOOPS FOR HVAC PIPING
SECTION 230517 - SLEEVES AND SLEEVE SEALS FOR HVAC PIPING
SECTION 230518 - ESCUTCHEONS FOR HVAC PIPING
SECTION 230519 - METERS AND GAUGES FOR HVAC PIPING
SECTION 230523 - GENERAL-DUTY VALVES FOR HVAC PIPING
SECTION 230529 - HANGERS AND SUPPORTS FOR HVAC PIPING AND EQUIPMENT
SECTION 230533 - HEAT TRACING FOR HVAC PIPING
SECTION 230553 - IDENTIFICATION FOR HVAC PIPING AND EQUIPMENT
SECTION 230593 - TESTING, ADJUSTING, AND BALANCING FOR HVAC
SECTION 230713 - DUCT INSULATION
SECTION 230719 - HVAC PIPING INSULATION
SECTION 230900 - INSTRUMENTATION AND CONTROL FOR HVAC
SECTION 232123 - HYDRONIC PUMPS
SECTION 233113 - METAL DUCTS
SECTION 233300 - AIR DUCT ACCESSORIES
SECTION 233423 - HVAC POWER VENTILATORS
SECTION 233600 - AIR TERMINAL UNITS
SECTION 233713 - DIFFUSERS, REGISTERS, AND GRILLES
SECTION 235100 - BREECHINGS, CHIMNEYS, AND STACKS
SECTION 235216 - CONDENSING BOILERS
SECTION 237313 - MODULAR INDOOR CENTRAL-STATION AIR-HANDLING UNITS
SECTION 237413 - PACKAGED, OUTDOOR, CENTRAL-STATION AIR-HANDLING UNITS
Table of Contents - 5
SECTION 238219 - FAN COIL UNITS
SECTION 238413 - HUMIDIFIERS
DIVISION 26 - ELECTRICAL
SECTION 260000 - SUPPLEMENTARY ELECTRICAL GENERAL CONDITIONS
SECTION 260519 - LOW-VOLTAGE ELECTRICAL POWER CONDUCTORS AND CABLES
SECTION 260526 - GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS
SECTION 260529 - HANGERS AND SUPPORTS FOR ELECTRICAL SYSTEMS
SECTION 260533 - RACEWAYS AND BOXES FOR ELECTRICAL SYSTEMS
SECTION 260543 - UNDERGROUND DUCTS AND RACEWAYS FOR ELECTRICAL SYSTEMS
SECTION 260544 - SLEEVES AND SLEEVE SEALS FOR ELECTRICAL RACEWAYS AND
CABLING
SECTION 260553 - IDENTIFICATION FOR ELECTRICAL SYSTEMS
SECTION 260575 - SHORT CIRCUIT AND ARC FLASH STUDIES
SECTION 260923 - LIGHTING CONTROL DEVICES
SECTION 262416 - PANELBOARDS
SECTION 262726 - WIRING DEVICES
SECTION 262813 - FUSES
SECTION 262816 - ENCLOSED SWITCHES AND CIRCUIT BREAKERS
SECTION 263600 - TRANSFER SWITCHES
SECTION 264113 - LIGHTNING PROTECTION FOR STRUCTURES
SECTION 265100 - INTERIOR LIGHTING
SECTION 265600 - EXTERIOR LIGHTING
DIVISION 27 - COMMUNICATIONS
SECTION 270536 - CABLE TRAYS FOR COMMUNICATIONS SYSTEMS
SECTION 271100 - COMMUNICATIONS EQUIPMENT ROOM FITTINGS
SECTION 271500 - COMMUNICATIONS HORIZONTAL CABLING
SECTION 271510 - STRUCTURED CABLING
SECTION 275116 - PUBLIC ADDRESS AND MASS NOTIFICATION SYSTEM
SECTION 275223 - NURSE CALL CODE BLUE SYSTEM
DIVISION 28 - ELECTRONIC SAFETY AND SECURITY
SECTION 280513 - CONDUCTORS AND CABLES FOR ELECTRONIC SAFETY AND SECURITY
SECTION 281300 - ACCESS CONTROL
SECTION 282300 - VIDEO SURVEILLANCE
SECTION 283100 - FIRE ALARM
DIVISION 31 - EARTHWORK
SECTION 311000 - SITE CLEARING AND GRADING
SECTION 312000 - EARTH MOVING
SECTION 313116 - TERMITE CONTROL
DIVISION 32 - EXTERIOR IMPROVEMENTS
SECTION 321200 - PAVING AND AGGREGATE BASE
SECTION 321313 - CONCRETE PAVING
003126 - 1 EXISTING HAZARDOUS
MATERIAL INFORMATION
003126 - 1
DOCUMENT 003126 - EXISTING HAZARDOUS MATERIAL INFORMATION
PART 1 -
1.1 EXISTING HAZARDOUS MATERIAL INFORMATION
A. This Document with its referenced attachments is part of the Procurement and
Contracting Requirements for Project. They provide Owner's information for Bidders' convenience and are intended to supplement rather than serve in lieu of Bidders' own investigations. They are made available for Bidders' convenience and information, but are not a warranty of existing conditions. This Document and its attachments are not part of the Contract Documents.
B. An existing asbestos report for Project, prepared by iiná bá, Inc. Project No.
IHS0000-00010, dated February 3, 2012, is available for viewing by request, contact
Contracting Officer.
C. An existing lead report for Project, prepared by iiná bá, Inc. Project No.
IHS0000-00019, dated February 22, 2012, is available for viewing by request, contact
Contracting Officer.
D. Related Requirements:
1. Document 003132 "Geotechnical Data" for reports and soil-boring data from geotechnical investigations that are made available to bidders.
2. Section 024119 "Selective Demolition" for notification requirements if materials suspected of containing hazardous materials are encountered.
3. Section 013000 “Administrative requirements” for notification requirements if materials suspected of containing hazardous materials are encountered
4. Section 015721 “Indoor Air Quality Control” for submittal of Indoor Air Quality
Management Plan.
5. Section 024000 “Site Demolition” for notification requirements if materials suspected of containing hazardous materials are encountered.
6. Section 028216.0020 “Engineering Control of Asbestos Containing Materials” for notification requirements if materials suspected of containing hazardous materials are encountered.
END OF DOCUMENT 003126
003132 - 1 GEOTECHNICAL DATA 003132 - 1
DOCUMENT 003132 - GEOTECHNICAL DATA
PART 1 - GENERAL
1.1 GEOTECHNICAL DATA
A. This Document with its referenced attachments is part of the Procurement and
Contracting Requirements for Project. They provide Owner's information for Bidders' convenience and are intended to supplement rather than serve in lieu of Bidders' own investigations. They are made available for Bidders' convenience and information, but are not a warranty of existing conditions. This Document and its attachments are not part of the Contract Documents.
B. Soil-boring data for Project, obtained by Ninyo & Moore, dated January 8, 2016, is available for viewing as appended to this Document.
C. A geotechnical investigation report for Project, prepared by Ninyo & Moore, dated
January 8, 2016, is available for viewing as appended to this Document.
END OF DOCUMENT 003132
003132 - 2 GEOTECHNICAL DATA 003132 - 2
011100 - 1 SUMMARY OF WORK 011100 - 1
SECTION 01 11 00 - SUMMARY OF WORK
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
ASTM INTERNATIONAL (ASTM)
ASTM E2114 (2008) Standard Terminology for Sustainability Relative to the Performance of Buildings
U.S. ENVIRONMENTAL PROTECTION AGENCY (EPA)
Energy Star (1992; R 2006) Energy Star Energy Efficiency Labeling System
1.2 DEFINITIONS
Definitions pertaining to sustainable development are as defined in ASTM E2114 and as specified.
a. "Environmentally preferable products" have a lesser or reduced effect on the environment in comparison to conventional products and services. This comparison may consider raw materials acquisition, production, manufacturing, packaging, distribution, reuse, operation, maintenance, or disposal of the product.
b. "Indoor environmental quality" is the physical characteristics of the building interior that impact occupants, including air quality, illumination, acoustics, occupant control, thermal comfort, daylighting, and views.
c. "Operational performance" is the functional behavior of the building as a whole or of the building components.
d. "Sustainability" is the balance of environmental, economic, and societal considerations.
1.3 SUBMITTALS
Government approval is required for submittals with a "G" designation; submittals not having a "G" designation are for information only. The following shall be submitted in accordance with Section 01
33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Submit the following items to the Contracting Officer:
Utility Outage Requests Utility Connection Requests
Excavation Permits
Welding Permits
011100 - 2 SUMMARY OF WORK 011100 - 2
1.4 WORK COVERED BY CONTRACT DOCUMENTS
1.4.1 Project Description
The Work of Project is defined by the Contract Documents and consists of the following:
Demolition, Renovation & Expansion of the east wing first floor of the Gallup Indian Medical Center.
Renovation work will be 7,048 sq.ft. and the new construction expansion work will be 2,623 sq.ft. The building has been classified as construction type II-A per IBC 2021 and Occupancy type I-2 per IBC
2021. The major building assemblies consist of: existing cast in place concrete structural floors, beams and column, new structural steel, new slab on grade basement floor, composite deck first floor and metal roof deck, PVC flat roofs, EIFS on existing wall structure and new metal frame, Hollow metal
Window and Door frames, Aluminum storefront system, reconfigured existing HVAC systems and new HVAC systems, new electrical and plumbing. Hospital functions will remain active during construction period; construction will be phased. Dust, sound and air quality controls shall be provided.
1.4.2 Location
A. The work shall be located at the main building of the Gallup Indian Medical Center campus in the existing Emergency Department and existing eye care wing as indicated in the construction documents.
1. Project address:
a. 516 East Nizhoni Boulevard
b. Gallup, NM 87301
c. Lat/Long: 35.507680, -108.729589
1.5 NOT USED.
1.6 WORK SCHEDULING
Refer to 01 14 00 Work Restrictions.
1.7 PROJECT ENVIRONMENTAL GOALS
Contractor shall distribute copies of the Environmental Goals to each subcontractor and the Contracting Officer. The overall goal for design, construction, and operation is to produce a building that meets the functional program needs and incorporates the principles of sustainability.
a. Preserve and restore the site ecosystem and biodiversity; avoid site degradation and erosion.
Minimize offsite environmental impact. Refer to Section 01 57 20.00 10.
b. Use the minimum amount of energy, water, and materials feasible to meet the design intent.
Select energy and water efficient equipment and strategies. Refer to Section 01 33 29. 00 20
c. Use environmentally preferable products and decrease toxicity level of materials used. Refer to individual technical specification requirements.
d. Use renewable material resources. Refer to individual technical specification requirements.
011100 - 3 SUMMARY OF WORK 011100 - 3
e. Optimize operational performance (through commissioning efforts) in order to ensure energy efficient equipment operates as intended. Consider the durability, maintainability, and flexibility of building systems.
f. Manage construction site and storage of materials to ensure no negative impact on the indoor environmental quality of the building. Refer to Section 01 57 21.
g. Reduce construction waste through reuse, recycling, and supplier take-back. Refer to Section 01 74 19.
1.8 OCCUPANCY OF PREMISES
Building(s) will be occupied during performance of work under this Contract. Occupancy notifications will be posted in a prominent location in the work area.
Before work is started, the Contractor shall arrange with the Contracting Officer a sequence of procedure, means of access, space for storage of materials and equipment, and use of approaches, corridors, and stairways.
1.9 EXISTING WORK
In addition to "FAR 52.236-9, Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements":
a. Remove or alter existing work in such a manner as to prevent injury or damage to any portions of the existing work which remain.
b. Repair or replace portions of existing work which have been altered during construction operations to match existing or adjoining work, as approved by the Contracting Officer. At the completion of operations, existing work shall be in a condition equal to or better than that which existed before new work started.
1.10 ON-SITE PERMITS
1.10.1 Utility Outage Requests and Utility Connection Requests
Notify the Contracting Officer at least 72 hours prior to starting excavation work. Contractor is responsible for marking and verifying all utilities not marked.
The Contractor shall verify the elevations of existing piping, utilities, and any type of underground obstruction not indicated or specified to be removed. But indicated in locations to be transversed by piping, ducts, and other work to be installed.
Work shall be scheduled to hold outages to a minimum.
Utility outages and connections required during the prosecution of work that affect existing systems shall be arranged for at the convenience of the Government and shall be scheduled outside the regular working hours or on weekends.
Contracting Officer may permit utility outages at his discretion. Contractor shall not be entitled to additional payment for utility outages and connections required to be performed outside the regular work hours.
Requests for utility outages and connections shall be made in writing to the Contracting Officer at
011100 - 4 SUMMARY OF WORK 011100 - 4
least 15 calendar days in advance of the time required. Each request shall state the system involved, area involved, approximate duration of outage, and the nature of work involved.
1.10.2 Excavation and Welding Permits
ACTIVITY SUBMISSION DATE SUBMISSION FORM
Excavation Permits 7 calendar days prior to work Electronic Notification (email)
Welding Permits 3 calendar days prior to work Electronic Notification (email)
Permits shall be posted at a conspicuous location in the construction area.
1.11 LOCATION OF UNDERGROUND UTILITIES
Verify the elevations of existing piping, utilities, and any type of underground obstruction not indicated to be specified or removed but indicated or discovered during scanning in locations to be traversed by piping, ducts, and other work to be conducted or installed.
1.11.1 Notification Prior to Excavation
Notify the Contracting Officer at least 48 hours prior to starting excavation work.
1.12 GOVERNMENT-FURNISHED MATERIAL AND EQUIPMENT
The Government will furnish the following materials and equipment for installation by the Contractor:
Refer to Section 102800 Refer to Section 117000
1.13 NOT USED.
1.14 NOT USED.
1.15 SALVAGE MATERIAL AND EQUIPMENT
Items designated by the Contracting Officer to be salvaged shall remain the property of the Government.
The salvaged property shall be segregated, itemized, delivered, and off-loaded at the Government designated storage area located within 15 miles of the construction site.
Contractor shall maintain property control records for material or equipment designated as salvage.
Contractor's system of property control may be used if approved by the Contracting Officer. Contractor shall be responsible for storage and protection of salvaged materials and equipment until disposition by the Contracting Officer.
PART 2 PRODUCTS
011100 - 5 SUMMARY OF WORK 011100 - 5
NOT USED.
PART 3 EXECUTION
NOT USED.
-- End of Section --
011400 - 1 WORK RESTRICTIONS 011400 - 1
SECTION 01 14 00 - WORK RESTRICTIONS
1.1 SPECIAL SCHEDULING REQUIREMENTS
a. Have materials, equipment, and personnel required to perform the work at the site prior to the commencement of the work.
b. The existing ambulance entry and drive will remain in operation during the entire construction period. The Contractor must conduct his operations so as to cause the least possible interference with normal operations of the activity.
c. Permission to interrupt any Activity roads, railroads, and/or utility service must be requested in writing a minimum of 15 calendar days prior to the desired date of interruption.
1.2 CONTRACTOR ACCESS AND USE OF PREMISES
1.2.1 Activity Regulations
Ensure that Contractor personnel employed on the Activity become familiar with and obey Activity regulations including safety, fire, traffic and security regulations. Keep within the limits of the work and avenues of ingress and egress. Wear hard hats in designated areas. Do not enter any restricted areas unless required to do so and until cleared for such entry. Mark Contractor equipment for identification.
1.2.1.1 Subcontractors and Personnel Contacts
Provide a list of contact personnel of the Contractor and subcontractors including addresses and telephone numbers for use in the event of an emergency. As changes occur and additional information becomes available, correct and change the information contained in previous lists.
1.2.1.2 No Smoking Policy
Smoking is prohibited within and outside of all buildings on installations except in designated smoking areas. This applies to existing buildings, buildings under construction and buildings under renovation. Discarding tobacco materials other than into designated tobacco receptacles is considered littering and is subject to fines. The Contracting Officer will identify designated smoking areas.
1.5.2 Working Hours
Regular working hours must consist of a minimum 10 hour period between 7 a.m. and 6 p.m., Monday through Friday, and 7 a.m. to 6 p.m. on Saturday, excluding Government holidays.
1.5.3 Work Outside Regular Hours
Work outside regular working hours requires Contracting Officer approval. Submit request in writing to the Contracting Officer for approval 72 hours prior to starting revised work schedule.
1.5.4 Occupied and Existing Building
The Contractor shall be working in an existing building which is occupied.
011400 - 2 WORK RESTRICTIONS 011400 - 2
The existing buildings and their contents must be kept secure at all times. Provide temporary closures as required to maintain security as directed by the Contracting Officer.
Provide dust covers or protective enclosures to protect existing work that remains and Government material located in the facility during the construction period.
The Government will remove and relocate other Government property in the areas of the building scheduled to receive work.
1.5.5 Utility Cutovers and Interruptions
a. Make utility cutovers and interruptions after normal working hours or on Saturdays, Sundays, and Government holidays. Conform to procedures required in the paragraph "Work Outside Regular Hours."
b. Ensure that new utility lines are complete, except for the connection, before interrupting existing service.
c. Interruption to water, sanitary sewer, storm sewer, telephone service, electric service, air conditioning, heating, fire alarm, compressed air, and Medical gas and vacuum are considered utility cutovers pursuant to the paragraph entitled "Work Outside Regular Hours." Such interruption are further limited to 1 hour. This time limit includes time for deactivation and reactivation.
Not Used
012000.0020 - 1 PRICE AND PAYMENT
PROCEDURES
012000.0020 - 1
SECTION 01 20 00.00 20 - PRICE AND PAYMENT PROCEDURES
1.1 SUBMITTALS
designation are for information only. The following shall be submitted in accordance with Section 01
Earned Value Report [G]
1.2 EARNED VALUE REPORT
1.2.1 Data Required
This contract requires the use of a cost-loaded Network Analysis Schedule (NAS). The information required for the Schedule of Prices will be entered as an integral part of the Network Analysis
Schedule. Within 15 calendar days of notice of award, prepare and deliver to the Contracting Officer an Earned Value Report as directed by the Contracting Officer. Provide a detailed breakdown of the contract price, giving quantities for each of the various kinds of work, unit prices, and extended prices. Costs shall be summarized and totals provided for each construction category.
1.2.2 Schedule Instructions
Payments will not be made until the Earned Value Report from the cost-loaded NAS has been submitted to and accepted by the Contracting Officer.
1.2.3 Real Property Assets
The Government will provide the Real Property Report. The Contractor shall complete the Draft Real
Property Report to represent the final constructed facility and include all associated cost.
1.3 CONTRACTOR'S INVOICE AND CONTRACT PERFORMANCE STATEMENT
1.3.1 Content of Invoice
Requests for payment will be processed in accordance with the Contract Clause FAR 52.232-27, Prompt Payment Construction Contracts and FAR 52.232-5, Payments Under Fixed-Price
Construction Contracts. The requests for payment shall include the documents listed below.
a. The Contractor's invoice, showing in summary form, the basis for arriving at the amount of the invoice. Invoice shall include certification by Quality Control (QC) Manager as required by the contract.
b. The Earned Value Report from the cost-loaded NAS, showing in detail: the estimated cost,
012000.0020 - 2 PRICE AND PAYMENT
012000.0020 - 2 percentage of completion, and value of completed performance.
c. Updated Project Schedule and reports required by the contract.
d. Contractor Safety Self Evaluation Checklist.
e. Other supporting documents as requested.
f. Updated copy of submittal register.
g. Invoices not completed in accordance with contract requirements will be returned to the Contractor for correction of the deficiencies.
h. Materials on Site.
i. Solid Waste Disposal Report.
1.3.2 Final Invoice
Final invoices not accompanied by the Contractor's Final Release will be considered incomplete and will be returned to the Contractor.
1.4 PAYMENTS TO THE CONTRACTOR
Payments will be made on submission of itemized requests by the Contractor which comply with the requirements of this section, and will be subject to reduction for overpayments or increase for underpayments made on previous payments to the Contractor.
1.4.1 Obligation of Government Payments
The obligation of the Government to make payments required under the provisions of this contract will, at the discretion of the Contracting Officer, be subject to reductions and/or suspensions permitted under the FAR and agency regulations including the following in accordance with "FAR
32.503-6:
a. Reasonable deductions due to defects in material or workmanship;
b. Claims which the Government may have against the Contractor under or in connection with this contract;
c. Unless otherwise adjusted, repayment to the Government upon demand for overpayments made to the Contractor; and
d. Failure to provide up to date record drawings not current as stated in Contract Clause "FAR
52.236-21."
1.4.2 Payment for Onsite and Offsite Materials
Progress payments may be made to the contractor for materials delivered on the site, for materials stored off construction sites, or materials that are in transit to the construction sites under the
012000.0020 - 3 PRICE AND PAYMENT
012000.0020 - 3 following conditions:
a. FAR 52.232-5(b) Payments Under Fixed Price Construction Contracts.
b. Materials to be considered for progress payments prior to installation are limited to major high cost, long lead, special order or specialty items, not susceptible to deterioration or physical damage in storage or in transit to the construction site. Materials to be considered for progress payments prior to installation shall be separately identified by the contractor in the contractor’s FAR
52.232-5 proposal. The contractor is responsible for creating a detailed tracking list that includes all prepaid inventory identified in the contractor’s FAR 52.232-5 proposal. The contractor shall provide an updated copy of its prepaid inventory tracking list with each pay application and upon request of the Contracting Officer or the Contracting Officer’s Representative.
c. Materials to be considered for progress payment prior to installation shall be specifically and separately identified in the Contractor's estimates of work submitted for the Contracting Officer's approval in accordance with Earned Value Report requirement of this contract. Requests for progress payment consideration for such items shall be supported by documents establishing their value and that the title requirements of the clause at FAR 52.232-5 have been met.
d. Materials are adequately insured and protected from theft and exposure.
e. Provide a written consent from the surety company with each payment request for offsite materials.
GIMC EMERGENCY DEPT.
EXPANSION & RENOVATION
013000 - 1 ADMINISTRATIVE
REQUIREMENTS
013000 - 1
SECTION 01 30 00 - ADMINISTRATIVE REQUIREMENTS
1.1 REFERENCES
1.2 SUBMITTALS
designation are for information only. The following shall be submitted in accordance with Section 01
View location map [G]
Progress and completion pictures [G]
1.3 NOT USED.
1.4 VIEW LOCATION MAP
Submit to the Contracting Officer, prior to or with the first digital photograph submittals, a sketch or drawing indicating the required photographic locations. Update as required if the locations are moved.
1.5 PROGRESS AND COMPLETION PICTURES
Photographically document site conditions prior to start of construction operations. Provide monthly, and within one month of the completion of work, digital photographs, 1600 x 1200 x 24 bit true color minimum resolution in JPEG file format showing the sequence and progress of work. Take a minimum of 20 digital photographs each week throughout the entire project from a minimum of ten views from points located by the Contracting Officer. Submit a view location sketch indicating points of view. Submit with the monthly invoice two sets of digital photographs each set on a separate CD- R, cumulative of all photos to date. Photographs for each month shall be in a separate monthly directory and each file shall be named to indicate its location on the view location sketch. The view location sketch shall also be provided on the CD as digital file. All file names shall include a date designator. Cross reference submittals in the appropriate daily report. Photographs shall be provided for unrestricted use by the Government.
1.6 MINIMUM INSURANCE REQUIREMENTS
Procure and maintain during the entire period of performance under this contract the minimum insurance coverage required.
1.7 CONTRACTOR SPECIAL REQUIREMENTS
1.7.1 Asbestos Containing Material
All contract requirements of Section 02 82 16.00 20, "Engineering Control of Asbestos Containing Materials" assigned to the Private Qualified Person (PQP) shall be accomplished directly by a first tier subcontractor.
GIMC EMERGENCY DEPT.
EXPANSION & RENOVATION
013000 - 2 ADMINISTRATIVE
REQUIREMENTS
013000 - 2
1.8 SUPERVISION
In addition to the requirements at FAR 52.236-6 Superintendence by the Contractor, the Contractor shall have at least one qualified supervisor capable of reading, writing, and conversing fluently in the English language on the job site during working hours. In addition, if a Quality Control (QC) representative is required on the contract, then that individual shall also have fluent English communication skills.
1.9 NOT USED.
1.10 PRECONSTRUCTION CONFERENCE
After award of the contract but prior to commencement of any work at the site, meet with the Contracting Officer to discuss and develop a mutual understanding relative to the administration of the value engineering and safety program, preparation of the schedule of prices or earned value report, shop drawings, and other submittals, scheduling programming, prosecution of the work, and clear expectations of the "Draft Real Property Report" Submittal. Major subcontractors who will engage in the work shall also attend.
1.11 thru 1.14 NOT USED.
1.15 AVAILABILITY OF CADD DRAWING FILES
After award and upon request, the electronic "Computer-Aided Drafting and Design (CADD)" drawing files will only be made available to the Contractor for use in preparation of construction data related to the referenced contract subject to the following terms and conditions.
CADD files will be transmitted in AutoCad version 2013 DWG format, no earlier version shall be made available.
Data contained on these electronic files shall not be used for any purpose other than as a convenience in the preparation of construction data for the referenced project. Any other use or reuse shall be at the sole risk of the Contractor and without liability or legal exposure to the Government. The Contractor shall make no claim and waives to the fullest extent permitted by law, any claim or cause of action of any nature against the Government, its agents or sub consultants that may arise out of or in connection with the use of these electronic files. The Contractor shall, to the fullest extent permitted by law, indemnify and hold the Government harmless against all damages, liabilities or costs, including reasonable attorney's fees and defense costs, arising out of or resulting from the use of these electronic files.
These electronic CADD drawing files are not construction documents. Differences may exist between the CADD files and the corresponding construction documents. The Government makes no representation regarding the accuracy or completeness of the electronic CADD files, nor does it make representation to the compatibility of these files with the Contractors hardware or software. In the event that a conflict arises between the signed and sealed construction documents prepared by the Government and the furnished CADD files, the signed and sealed construction documents shall govern. The Contractor is responsible for determining if any conflict exists. Use of these CADD files does not relieve the Contractor of duty to fully comply with the contract documents, including and without limitation, the need to check, confirm and coordinate the work of all contractors for the project.
If the Contractor uses, duplicates and/or modifies these electronic CADD files for use in producing construction data related to this contract, all previous indicia of ownership (seals, logos, signatures, initials and dates) shall be removed.
GIMC EMERGENCY DEPT.
EXPANSION & RENOVATION
013000 - 3 ADMINISTRATIVE
REQUIREMENTS
013000 - 3
1.16 ELECTRONIC MAIL (E-MAIL) ADDRESS
The Contractor shall establish and maintain electronic mail (e-mail) capability along with the capability to open various electronic attachments in Microsoft, Adobe Acrobat, and other similar formats. Within 10 days after contract award, the Contractor shall provide the Contracting Officer a single (only one) e-mail address for electronic communications from the Contracting Officer related to this contract including, but not limited to contract documents, invoice information, request for proposals, and other correspondence.
It is the Contractor's responsibility to make timely distribution of all Contracting Officer initiated e-mail with its own organization including field office(s). The Contractor shall promptly notify the Contracting Officer, in writing, of any changes to this email address.
1.17 PROJECT WEB SITE
A. Provide the following Project Web site software packages under their current published licensing agreements:
1. Submittal Exchange.
2. Or approved equal.
B. Use Contractor's Project Web site for purposes of hosting and managing project communication and documentation until Final Completion. Project Web site shall include the following functions:
1. Project directory.
2. Project correspondence.
3. Meeting minutes.
4. Quality control reports.
5. Daily reports.
6. A/E site observations reports.
7. Contract modifications forms and logs.
8. Change order requests.
9. RFI, forms and logs.
10. Substitution requests.
11. Task and issue management.
12. Photo documentation.
13. Schedule and calendar management.
a. Overall project schedule and look ahead schedule
14. Submittals, forms and logs.
15. Payment application forms.
16. Drawing and specification document hosting, viewing, and updating.
17. Testing & inspection reports.
18. Equipment start up reports.
19. Punch list.
20. All close out documents including O&M’s and warranties.
21. Online document collaboration.
22. Reminder and tracking functions.
23. Archiving functions.
GIMC EMERGENCY DEPT.
EXPANSION & RENOVATION
013000 - 4 ADMINISTRATIVE
REQUIREMENTS
013000 - 4
C. Submittal components shall not be broken out as individual sub components within a section number. Submittals shall be registered and posted to Submittal Exchange as a single item under the related specification section number.
D. Provide up to seven Project Web site user licenses for use of the Owner, Architect, and
Architect's consultants. Provide up to four hours of online software training for Project Web site users upon request.
E. On completion of Project, provide one complete archive copy(ies) of Project Web site files to
Owner and to Architect in a digital storage format acceptable to Architect.
F. Contractor, subcontractors, and other parties granted access by Contractor to Project Web site shall execute a data licensing agreement in the form of AIA Document C106.
PART 3 EXECUTION
013201.0010 - 1 PROJECT SCHEDULE 013201.0010 - 1
SECTION 01 32 01.00 10 - PROJECT SCHEDULE
1.1 SUBMITTALS
designation are for Contractor Quality Control approval. Submit the following in accordance with
Section 01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals:
Project Schedule [G]
Qualifications of Scheduler [G]
1.2 SCHEDULE PREPARER
Designate an authorized representative to be responsible for the preparation of the schedule and all required updating (activity status) and preparation of reports. The authorized representative shall have previously developed, created, and maintained at least two (2) electronic schedules for projects similar in nature and complexity to this project and shall be experienced in the use of the scheduling software that meets the requirements of this specification.
PART 2 PRODUCTS
Not Used
3.1 GENERAL REQUIREMENTS
Prepare for approval a Project Schedule, as specified herein, pursuant to FAR 52.236-15 SCHEDULES FOR CONSTRUCTION CONTRACTS. Show in the schedule the sequence in which the Contractor proposes to perform the work and dates on which the Contractor contemplates starting and completing all schedule activities. The scheduling of the entire project is required. The scheduling of construction is the responsibility of the Contractor. Contractor management personnel shall actively participate in its development. Subcontractors and suppliers working on the project shall also contribute in developing and maintaining an accurate Project Schedule. Provide a schedule that is a forward planning as well as a project monitoring tool.
3.1.1 Approved Project Schedule
Use the approved Project Schedule to measure the progress of the work and to aid in evaluating time extensions. Make the schedule cost loaded and activity coded. The schedule will provide the basis for all progress payments. If the Contractor fails to submit any schedule within the time prescribed, the Contracting Officer may withhold approval of progress payments until the Contractor submits the required schedule.
3.1.2 Schedule Status Reports
Provide a Schedule Status Report on at least a monthly basis. If, in the opinion of the Contracting Officer, the Contractor falls behind the approved schedule, take steps necessary to improve its
013201.0010 - 2 PROJECT SCHEDULE 013201.0010 - 2
progress including those that may be required by the Contracting Officer, without additional cost to the Government. In this circumstance, the Contracting Officer may require the Contractor to increase the number of shifts, overtime operations, days of work, and/or the amount of construction plant, and to submit for approval any supplementary schedule or schedules as the Contracting Officer deems necessary to demonstrate how the approved rate of progress will be regained.
3.2 BASIS FOR PAYMENT AND COST LOADING
Use the schedule as the basis for determining contract earnings during each update period and therefore the amount of each progress payment. Lack of an approved schedule update, or qualified scheduling personnel, will result in the inability of the Contracting Officer to evaluate contract earned value for the purposes of payment. Failure of the Contractor to provide all required information will result in the disapproval of the preliminary, initial and subsequent schedule updates. In the event schedule revisions are directed by the Contracting Officer and those revisions have not been included in subsequent revisions or updates, the Contracting Officer may hold retainage up to the maximum allowed by contract, each payment period, until such revisions to the Project Schedule have been made. Activity cost loading shall be reasonable, as determined by the Contracting Officer. The aggregate value of all activities shall equal the value of the Contract.
3.3 PROJECT SCHEDULE DETAILED REQUIREMENTS
The computer software system utilized to produce and update the Project Schedule shall be capable of meeting all requirements of this specification and shall be compatible with Oracle’s PRIMAVERA Contractor software (Version 6.1). Failure of the Contractor to meet the requirements of this specification will result in the disapproval of the schedule.
3.3.1 Critical Path Method
Use the Critical Path Method (CPM) of network calculation to generate the Project Schedule. Prepare the Project Schedule using the Precedence Diagram Method (PDM).
3.3.2 Level of Detail Required
Develop the Project Schedule to an appropriate level of detail. Failure to develop the Project Schedule to an appropriate level of detail, as determined by the Contracting Officer, will result in its disapproval. The Contracting Officer will consider, but is not limited to, the following characteristics and requirements to determine appropriate level of detail:
3.3.2.1 Activity Durations
Reasonable activity durations are those that allow the progress of ongoing activities to be accurately determined between update periods. Less than 2 percent of all non-procurement activities shall have Original Durations (OD) greater than 20 work days or 30 calendar days. Procurement activities are defined herein.
3.3.2.2 Procurement Activities
The schedule must include activities associated with the submittal, approval, procurement, fabrication and delivery of long lead materials, equipment, fabricated assemblies and supplies. Long lead procurement activities are those with an anticipated procurement sequence of over 90 calendar days.
A typical procurement sequence includes the string of activities: submit, approve, procure, fabricate, and deliver.
3.3.2.3 Mandatory Tasks
013201.0010 - 3 PROJECT SCHEDULE 013201.0010 - 3
The following tasks must be included and properly scheduled:
a. NOT USED.
b. Submission of mechanical/electrical/information systems layout drawings.
c. Submission and approval of O & M manuals.
d. Submission and approval of as-built drawings.
e. Submission and approval of installed equipment lists.
f. Submission and approval of testing and air balance (TAB).
g. Submission of TAB specialist design review report.
h. Submission and approval of fire protection specialist.
i. Submission and approval of HVAC testing and balancing, test data and reports: Prepare a schedule with integrated logic associated for testing and commissioning of building systems. The schedule shall be at a level of detail which identifies activities and integrates specific activity durations and interdependencies of tasks related to all building testing and commissioning of systems. The logic shall be tied to the overall project schedule and it shall be shown that all tasks associated with all building testing and commissioning will be completed prior to submission of building commissioning report and subsequent contract completion.
j. Air and water balancing.
k. HVAC commissioning.
l. Controls testing plan submission.
m. Controls testing.
n. Performance Verification testing.
o. Other systems testing, if required.
p. Contractor's pre-final inspection.
q. Correction of punchlist from Contractor's pre-final inspection.
r. Government's pre-final inspection.
s. Correction of punch list from Government's pre-final inspection.
t. Final inspection.
3.3.2.4 Government Activities
Show Government and other agency activities that could impact progress. These activities include, but are not limited to: submittal approvals, environmental permit approvals by Tribal or State regulators, inspections, utility tie-in, Government Furnished Equipment (GFE) and Notice to Proceed (NTP) for
013201.0010 - 4 PROJECT SCHEDULE 013201.0010 - 4
phasing requirements.
3.3.2.5 Activity Responsibility Coding
Assign responsibility Code for all activities to the Prime Contractor, Subcontractor or Government agency responsible for performing the activity. Activities coded with a Government Responsibility code include, but are not limited to: Government approvals, Government design reviews, environmental permit approvals by Tribal or State regulators, Government Furnished Equipment (GFE) and Notice to Proceed (NTP) for phasing requirements. Code all activities not coded with a Government Responsibility Code to the Prime Contractor or Subcontractor responsible to perform the work. Activities shall not have more than one Responsibility Code. Examples of acceptable activity code values are: DOR (for the designer of record); ELEC (for the electrical subcontractor); MECH (for the mechanical subcontractor); and IHS (for Indian Health Service). Unacceptable code values are abbreviations of the names of subcontractors.
3.3.2.6 Activity Work Area Coding
Assign Work Area code to activities based upon the work area in which the activity occurs. Define work areas based on resource constraints or space constraints that would preclude a resource, such as a particular trade or craft work crew, from working in more than one work area at a time due to restraints on resources or space. Examples of Work Area Coding include different areas within a floor of a building, different floors within a building, and different buildings within a complex of buildings.
Activities shall not have more than one Work Area Code. Not all activities are required to be Work
Area coded. A lack of Work Area coding will indicate the activity is not resource or space constrained.
3.3.2.7 Contract Changes/Requests for Equitable Adjustment (REA) Coding
Assign Activity code to any activity or sequence of activities added to the schedule as a result of a Contract Modification, when approved by the Contracting Officer, with a Contract Changes/REA Code. Key all Code values to the Government's modification numbering system. Any activity or sequence of activities added to the schedule as a result of alleged constructive changes made by the Government may be added to a copy of the current schedule, subject to the approval of the Contracting Officer. Assign Activity codes for these activities with a Contract Changes/REA Code.
Key the code values to the Contractor's numbering system. Approval to add these activities does not necessarily mean the Government accepts responsibility and, therefore, liability for such activities and any associated impacts to the schedule, but rather the Government recognizes such activities are appropriately added to the schedule for the purposes of maintaining a realistic and meaningful schedule. Such activities shall not be Responsibility Coded to the Government unless approved. An activity shall not have more than one Contract Changes/REA Code.
3.3.2.8 Contract Line Item (CLIN) Coding
Code all activities to the CLIN on the Contract Line Item Schedule to which the activity belongs. An activity shall not contain more than one CLIN Item Code. CLIN Item code all activities, even when an activity is not cost loaded.
3.3.2.9 Phase of Work Coding
Assign Phase of Work Code to all activities based upon the phase of work in which the activity occurs. Code activities to a Construction Phase. Code fast track construction phases proposed by the Contractor to allow filtering and organizing the schedule by fast track design and construction packages. If the contract specifies construction phasing with separately defined performance periods, identify a Construction Phase Code to allow filtering and organizing the schedule accordingly. Each
013201.0010 - 5 PROJECT SCHEDULE 013201.0010 - 5
activity shall be identified with a single project phase and have only one Phase of Work code.
3.3.2.10 Category of Work Coding
Assign Category of Work Code to all Activities based upon the category of work to which the activity…