Attachment 2 Specifications 23.02.09.pdf

PDF 5 MB Posted

Attached to
Rosebud Heating Plant Replacement Federal contract opportunity
Solicitation number
75H70124R00024
Issued by
Department of Health and Human Services Indian Health Service

About this file

This document appears to be an attachment to a federal contract opportunity solicitation for a construction project to replace the heating plant at the Rosebud Comprehensive Health Care Facility in Rosebud, South Dakota.

The solicitation is being issued by the Department of Health and Human Services Indian Health Service as a 100% small business set-aside under NAICS code 236220 for commercial and institutional building construction. The construction project involves removing existing boilers and pumps and installing a new boiler system. The period of performance is 365 calendar days after issuance of the notice to proceed, and the estimated construction magnitude is between $1 million and $5 million. The contract type will be a firm-fixed-price construction contract awarded based on the lowest price technically acceptable proposal. A site visit is required, and all questions must be submitted in writing to the contract specialist. Offerors must be registered in the System for Award Management (SAM) database to be considered for award.

View the file

Other files for this federal contract opportunity

Other files attached to Rosebud Heating Plant Replacement, newest first.
File Type Posted
B05 Amendment 4.pdf PDF
B05 Amendment 3 Attachment 1 RFI Response 1-28.pdf PDF
B05 Amendment 3.pdf PDF
B05 Amendment 2.pdf PDF
B05 Amendment 1.pdf PDF
Attachment 3 Drawings 23.02.09.pdf PDF
Attachment 4 WH347 PAYROLL.pdf PDF
Attachment 5 Release of Claims.pdf PDF
Attachment 1 Wage Determination SD20240018.pdf PDF
Attachment 8 Past Performance Questionnaire.docx DOCX document
Attachment 6 Subcontracting Plan.pdf PDF
Attachment 7 Specialized Experience Construction Form.docx DOCX document
B01 24R00024 v3.pdf PDF
Show all 13

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ROSEBUD HEAT PLANT DESIGN

75H70122F30015

400 Soldier Creek Dr, Rosebud, SD 57570

SPECIFICATION MANUAL

FINAL CONSTRUCTION DOCUMENTS

February 09, 2023

ARCHITECT

JOHNSON SMITTHIPONG & ROSAMOND ASSOCIATES, INC.

TUCSON, ARIZONA

02/09/2023

ROSEBUD, SD

75H70122F30015 Table of Contents 1

TABLE OF CONTENTS

DIVISION 02 - EXISTING CONDITIONS

SECTION 020100 - MAINTENANCE OF EXISTING CONDITIONS

SECTION 024119 - SELECTIVE DEMOLITION

DIVISION 03 - CONCRETE

SECTION 030130 - MAINTENANCE OF CAST-IN-PLACE CONCRETE

DIVISION 08 - OPENINGS

SECTION 083323 - OVERHEAD COILING DOORS

DIVISION 09 - FINISHES

SECTION 099000 - PAINTING

DIVISION 22 - PLUMBING

SECTION 220000 - SUPPLEMENTARY PLUMBING GENERAL CONDITION

SECTION 220513 - COMMON MOTOR REQUIREMENTS FOR PLUMBING EQUIPMENT

SECTION 220516 - EXPANSION FITTINGS AND LOOPS FOR PLUMBING PIPING

SECTION 220519 - METERS AND GAGES FOR PLUMBING PIPING

SECTION 220523 - GENERAL-DUTY VALVES FOR PLUMBING PIPING

SECTION 220529 - HANGERS AND SUPPORTS FOR PLUMBING PIPING AND EQUIPMENT

SECTION 220553 - IDENTIFICATION FOR PLUMBING PIPING AND EQUIPMENT

SECTION 220716 - PLUMBING EQUIPMENT INSULATION

SECTION 220719 - PLUMBING PIPING INSULATION

SECTION 221116 - DOMESTIC WATER PIPING

SECTION 221119 - DOMESTIC WATER PIPING SPECIALTIES

SECTION 221123 - DOMESTIC WATER PUMPS

SECTION 221316 - SANITARY WASTE AND VENT PIPING

SECTION 221319 - SANITARY WASTE PIPING SPECIALTIES

SECTION 223400 - FUEL-FIRED, DOMESTIC-WATER HEATERS

DIVISION 23 - HEATING VENTILATING AND AIR CONDITIONING

SECTION 230000 - SUPPLEMENTARY HVAC GENERAL CONDITIONS

SECTION 230513 - COMMON MOTOR REQUIREMENTS FOR HVAC EQUIPMENT

SECTION 230516 - EXPANSION FITTINGS AND LOOPS FOR HVAC PIPING

SECTION 230519 - METERS AND GAGES FOR HVAC PIPING

SECTION 230523 - GENERAL-DUTY VALVES FOR HVAC PIPING

SECTION 230529 - HANGERS AND SUPPORTS FOR HVAC PIPING AND EQUIPMENT

SECTION 230553 - IDENTIFICATION FOR HVAC PIPING AND EQUIPMENT

SECTION 230593 - TESTING, ADJUSTING, AND BALANCING FOR HVAC

SECTION 230719 - HVAC PIPING INSULATION

SECTION 230900 - INSTRUMENTATION AND CONTROL FOR HVAC

SECTION 231113 - FACILITY FUEL-OIL PIPING

SECTION 232113 - HYDRONIC PIPING

SECTION 232123 - HYDRONIC PUMPS

ROSEBUD, SD

75H70122F30015 Table of Contents 2

SECTION 232300 - REFRIGERANT PIPING

SECTION 235100 - BREECHINGS, CHIMNEYS, AND STACKS

SECTION 235216 - CONDENSING BOILERS

SECTION 235700 - HEAT EXCHANGERS FOR HVAC

SECTION 238126 - SPLIT-SYSTEM AIR-CONDITIONERS

SECTION 238239 - UNIT HEATERS

DIVISION 26 - ELECTRICAL

SECTION 260000 - SUPPLEMENTARY ELECTRICAL GENERAL CONDITIONS

SECTION 260519 - LOW-VOLTAGE ELECTRICAL POWER CONDUCTORS AND CABLES

SECTION 260526 - GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS

SECTION 260529 - HANGERS AND SUPPORTS FOR ELECTRICAL SYSTEMS

SECTION 260533 - RACEWAYS AND BOXES FOR ELECTRICAL SYSTEMS

SECTION 260544 - SLEEVES AND SLEEVE SEALS FOR ELECTRICAL RACEWAYS AND

CABLING

SECTION 260553 - IDENTIFICATION FOR ELECTRICAL SYSTEMS

SECTION 262200 - LOW-VOLTAGE TRANSFORMERS

SECTION 262416 - PANELBOARDS

SECTION 262813 - FUSES

SECTION 262816 - ENCLOSED SWITCHES AND CIRCUIT BREAKERS

SECTION 263600 - TRANSFER SWITCHES

ROSEBUD HEAT PLANT DESIGN

ROSEBUD, SD

SECTION 020100 MAINTENANCE OF EXISTING CONDITIONS

PART 1 - GENERAL

1.1 GENERAL

A. The Contractor shall protect all existing utilities and improvements not designated for removal and shall restore damaged or temporarily relocated utilities and improvements to a condition equal to or better than prior to such damage or temporary relocation, all in accordance with the Contract Documents.

B. The Contractor shall verify the exact locations and depths of all utilities shown and the Contractor shall make exploratory excavations of all utilities that may interfere with the Work.

All such exploratory excavations shall be performed as soon as practicable after award of the contract and, in any event, a sufficient time in advance of construction to avoid possible delays to the Contractor's work. When such exploratory excavations show the utility location as shown to be in error, the Contractor shall so notify the Architect.

C. The number of exploratory excavations required shall be that number which is sufficient to determine the alignment and grade of the utility.

1.2 RIGHTS-OF-WAY

A. The Contractor shall not do any Work that would affect any oil, gas, sewer, or water pipeline;

any telephone, telegraph, or electric transmission line; any fence; or any other structure, nor shall the Contractor enter upon the rights-of-way involved until notified that the Owner has secured authority therefor from the proper party.

B. After authority has been obtained, the Contractor shall give said party due notice of its intention to begin work, if required by said party, and shall remove, shore, support, or otherwise protect such pipeline, transmission line, ditch, fence, or structure, or replace the same.

1.3 PROTECTION OF SURVEY MARKERS

A. The Contractor shall not destroy, remove, or otherwise disturb any existing survey markers or other existing street or roadway markers without proper authorization. No pavement breaking or excavation shall be started until all survey or other permanent marker points that will be disturbed by the construction operations have been properly referenced. Survey markers or points disturbed by the Contractor shall be accurately restored after street or roadway resurfacing has been completed.

75H70122F30015 MAINTENANCE OF EXISTING

CONDITIONS

020100 - 1

ROSEBUD HEAT PLANT DESIGN

ROSEBUD, SD

1.4 RESTORATION OF PAVEMENT AND CONCRETE WORK

A. General: All paved areas including sidewalks, private driveways, curbs, gutters and asphaltic concrete berms cut or damaged during construction shall be replaced with similar materials of equal thickness to match the existing adjacent undisturbed areas, except where specific resurfacing requirements have been called for in the Contract Documents or in the requirements of the agency issuing the permit. The pavement restoration requirement to match existing sections shall apply to all components of existing sections, including sub-base, base, and pavement. Temporary and permanent pavement shall conform to the requirements of the affected pavement owner. Pavements which are subject to partial removal shall be neatly saw-cut in straight lines.

B. Temporary Resurfacing: Wherever required by the public authorities having jurisdiction, the Contractor shall place temporary surfacing promptly after backfilling and shall maintain such surfacing for the period of time fixed by said authorities before proceeding with the final restoration of improvements.

C. Permanent Resurfacing: In order to obtain a satisfactory junction with adjacent surfaces, the Contractor shall saw cut back and trim the edge so as to provide a clean, sound, vertical joint before permanent replacement of an excavated or damaged portion of pavement. Damaged edges of pavement along excavations and elsewhere shall be trimmed back by saw cutting in straight lines. All pavement restoration and other facilities restoration shall be constructed to finish grades compatible with adjacent undisturbed pavement.

D. Restoration of Sidewalks or Private Driveways: In order to obtain a satisfactory junction with adjacent surfaces, the Contractor shall saw cut back and trim the edge so as to provide a clean, sound, vertical joint before permanent replacement of an excavated or damaged portion of Sidewalk or Private Driveway. Wherever sidewalks or private roads have been removed for purposes of construction, the Contractor shall place suitable temporary sidewalks or roadways promptly after backfilling and shall maintain them in satisfactory condition for the period of time fixed by the authorities having jurisdiction over the affected portions. If no such period of time is so fixed, the Contractor shall maintain said temporary sidewalks or roadways until the final restoration thereof has been made.

E. Restoration of Curb and Gutter: In order to obtain a satisfactory junction with adjacent surfaces, the Contractor shall saw cut back and trim the edge so as to provide a clean, sound, vertical joint before permanent replacement of an excavated or damaged portion of curb, gutter or both. Wherever curb and gutter have been removed for purposes of construction, the Contractor shall place suitable temporary curb and gutter promptly after backfilling and shall maintain them in satisfactory condition for the period of time fixed by the authorities having jurisdiction over the affected portions. If no such period of time is so fixed, the Contractor shall maintain said temporary curb and gutter until the final restoration thereof has been made.

75H70122F30015 MAINTENANCE OF EXISTING

020100 - 2

ROSEBUD HEAT PLANT DESIGN

ROSEBUD, SD

1.5 EXISTING UTILITIES AND IMPROVEMENTS

A. General: The Contractor shall protect underground utilities and other improvements which may be impaired during construction operations, regardless of whether or not the Utilities are indicated on the Drawings. The Contractor shall take all possible precautions for the protection of unforeseen Utility lines to provide for uninterrupted service and to provide such special protection as may be necessary.

B. Except where the Drawings indicate Utilities have been field located during design or certain Utility locations shall be exposed as part of the Work, the Contractor shall be responsible for exploratory excavations as it deems necessary to determine the exact locations and depths of Utilities which may interfere with its work. All such exploratory excavations shall be performed as soon as practicable after Notice to Proceed and, in any event, a sufficient time in advance of construction to avoid possible delays to the Contractor's progress. When such exploratory excavations show the Utility location as shown on the Drawings to be in error, the Contractor shall so notify the Architect.

C. The number of exploratory excavations required shall be that number which is sufficient to determine the alignment and grade of the Utility.

D. Utilities to be Moved: In case it shall be necessary to move the property of any public utility or franchise holder, such utility company or franchise holder will, upon request of the Contractor, be notified by the Owner to move such property within a specified reasonable time. When utility lines that are to be removed are encountered within the area of operations, the Contractor shall notify the Architect a sufficient time in advance for the necessary measures to be taken to prevent interruption of service.

E. Utilities to be Removed: Where the proper completion of the Work requires the temporary or permanent removal and/or relocation of an existing Utility or other improvement which is indicated, the Contractor shall remove and, without unnecessary delay, temporarily replace or relocate such Utility or improvement in a manner satisfactory to the Architect and the owner of the facility. In all cases of such temporary removal or relocation, restoration to the former location shall be accomplished by the Contractor in a manner that will restore or replace the Utility or improvement as nearly as possible to its former locations and to as good or better condition than found prior to removal.

F. Owner's Right of Access: The right is reserved to the Owner and to the owners of public utilities and franchises to enter at any time upon any public street, alley, right-of-way, or easement for the purpose of making changes in their property made necessary by the Work of this Contract.

G. Underground Utilities Indicated: Existing Utility lines that are indicated or the locations of which are made known to the Contractor prior to excavation and that are to be retained, and all Utility lines that are constructed during excavation operations shall be protected from damage during excavation and backfilling and, if damaged, shall be immediately repaired or replaced by the Contractor, unless otherwise repaired by the owner of the damaged Utility. If the owner of the damaged facility performs its own repairs, the Contractor shall reimburse said owner for the costs of repair.

75H70122F30015 MAINTENANCE OF EXISTING

020100 - 3

ROSEBUD HEAT PLANT DESIGN

ROSEBUD, SD

H. Underground Utilities Not Indicated: In the event that the Contractor damages existing Utility lines that are not indicated or the locations of which are not made known to the Contractor prior to excavation, a verbal report of such damage shall be made immediately to the Architect and a written report thereof shall be made promptly thereafter. The Architect will immediately notify the owner of the damaged Utility. If the Architect is not immediately available, the Contractor shall notify the Utility owner of the damage. If directed by the Architect, repairs shall be made by the Contractor. Additional compensation for such work will be at the discretion of the Owner.

I. Costs of locating and repairing damage not due to failure of the Contractor to exercise reasonable care, and removing or relocating such Utility facilities not indicated in the Contract Documents with reasonable accuracy, and for equipment on the project which was actually working on that portion of the Work which was interrupted or idled by removal or relocation of such Utility facilities, and which was necessarily idled during such work may be paid for as extra work in accordance with the provisions of the General Conditions. Payment for such work shall be at the discretion of the Owner.

J. Approval of Repairs: All repairs to a damaged Utility or improvement are subject to inspection and approval by an authorized representative of the Utility or improvement owner before being concealed by backfill or other work.

K. Maintaining in Service: Unless indicated otherwise, oil and gasoline pipelines, power, and telephone or the communication cable ducts, gas and water mains, irrigation lines, sewer lines, storm drain lines, poles, and overhead power and communication wires and cables encountered along the line of the Work shall remain continuously in service during all the operations under the Contract, unless other arrangements satisfactory to the Architect are made with the owner of said pipelines, duct, main, irrigation line, sewer, storm drain, pole, or wire or cable. The Contractor shall be responsible for and shall repair all damage due to its operations, and the provisions of this Section shall not be abated even in the event such damage occurs after backfilling or is not discovered until after completion of the backfilling.

1.6 TREES OR SHRUBS WITHIN STREET RIGHTS-OF-WAY AND PROJECT LIMITS

A. General: Except where trees or shrubs or other plantings are indicated to be removed, the Contractor shall exercise all necessary precautions so as not to damage or destroy any trees or shrubs or other plantings, including those lying within street rights-of-way and project limits, and shall not trim or remove any trees unless such trees have been approved for trimming or removal by the jurisdictional agency or Owner. Existing trees and shrubs which are damaged during construction shall be trimmed or replaced by the Contractor or a certified tree company under permit from the jurisdictional agency and/or the Owner. Tree trimming and replacement shall be accomplished in accordance with the following paragraphs.

B. Trimming: Symmetry of the tree shall be preserved; no stubs or splits or torn branches left;

clean cuts shall be made close to the trunk or large branch. Spikes shall not be used for climbing live trees. Cuts over 1-1/2 inches in diameter shall be coated with a tree paint product that is waterproof, adhesive, and elastic, and free from kerosenes, coal tar, creosote, or other material injurious to the life of the tree.

75H70122F30015 MAINTENANCE OF EXISTING

020100 - 4

ROSEBUD HEAT PLANT DESIGN

ROSEBUD, SD

C. Replacement: The Contractor shall immediately notify the jurisdictional agency and/or the Owner if any tree or shrub is damaged by the Contractor's operations. If, in the opinion of said agency or the Owner, the damage is such that replacement is necessary, the Contractor shall replace the tree or shrub at its own expense. The tree or shrub shall be of a like size and variety as the one damaged, or, if of a smaller size, the Contractor shall pay to the owner of said tree a compensatory payment acceptable to the tree or shrub owner, subject to the approval of the jurisdictional agency or Owner. The size of the tree or shrub shall be not less than 1-inch diameter nor less than 6 feet in height. Planting of replacement trees and shrubs shall be in accordance with the recommendations of the nursery furnishing the plants. Unless otherwise indicated, the Contractor shall water and maintain the replacement trees and shrubs for 6 months after planting.

1.7 LAWN AREAS

A. Lawn or landscaped areas damaged during construction shall be repaired to match the pre-construction condition to the satisfaction of the land owner and the Owner.

1.8 NOTIFICATION BY THE CONTRACTOR

A. Prior to any excavation in the vicinity of any existing underground facilities, including all water, sewer, storm drain, gas, petroleum products, or other pipelines; all buried electric power, communications, or television cables; all traffic signal and street lighting facilities; and all roadway and state highway rights-of-way, the Contractor shall notify the respective authorities representing the Owner or agencies responsible for such facilities not less than 3 days nor more than 7 days prior to excavation so that a representative of said Owner or agencies can be present during such work if they so desire.

PART 2 - PRODUCTS (NOT USED)

PART 3 - EXECUTION (NOT USED)

END OF SECTION

75H70122F30015 MAINTENANCE OF EXISTING

020100 - 5

ROSEBUD HEAT PLANT DESIGN

ROSEBUD, SD

SECTION 024119 - SELECTIVE DEMOLITION

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. Section Includes:

1. Demolition and removal of selected portions of building or structure.

2. Demolition and removal of selected site elements.

3. Salvage of existing items to be reused or recycled.

1.3 DEFINITIONS

A. Remove: Detach items from existing construction and legally dispose of them off-site unless indicated to be removed and salvaged or removed and reinstalled.

B. Remove and Salvage: Carefully detach from existing construction, in a manner to prevent damage, and deliver to location indicated by Contracting Officer.

C. Remove and Reinstall: Detach items from existing construction, prepare for reuse, and reinstall where indicated.

D. Existing to Remain: Existing items of construction that are not to be permanently removed and that are not otherwise indicated to be removed, removed and salvaged, or removed and reinstalled.

1.4 MATERIALS OWNERSHIP

A. Unless otherwise indicated, demolition waste becomes property of Contractor.

B. Historic items, relics, antiques, and similar objects including, but not limited to, cornerstones and their contents, commemorative plaques and tablets, and other items of interest or value to Government that may be uncovered during demolition remain the property of the Government.

1. Carefully salvage in a manner to prevent damage and promptly return to Government.

75H70122F30015 SELECTIVE DEMOLITION 024119 - 1

ROSEBUD HEAT PLANT DESIGN

ROSEBUD, SD

1.5 PREINSTALLATION MEETINGS

A. Predemolition Conference: Conduct conference at Project site.

1. Inspect and discuss condition of construction to be selectively demolished.

2. Review structural load limitations of existing structure.

3. Review and finalize selective demolition schedule and verify availability of materials, demolition personnel, equipment, and facilities needed to make progress and avoid delays.

4. Review requirements of work performed by other trades that rely on substrates exposed by selective demolition operations.

5. Review areas where existing construction is to remain and requires protection.

1.6 INFORMATIONAL SUBMITTALS

A. Proposed Protection Measures: Submit report, including drawings, that indicates the measures proposed for protecting individuals and property , for environmental protection , for dust control and , for noise control. Indicate proposed locations and construction of barriers.

B. Schedule of Selective Demolition Activities: Indicate the following:

1. Detailed sequence of selective demolition and removal work, with starting and ending dates for each activity. Ensure the Government's on-site operations are uninterrupted.

2. Interruption of utility services. Indicate how long utility services will be interrupted.

3. Coordination for shutoff, capping, and continuation of utility services.

4. Use of elevator and stairs.

5. Coordination of Government's continuing occupancy of portions of existing building and of Government's partial occupancy of completed Work.

C. Inventory: Submit a list of items to be removed and salvaged and deliver to Contracting Officer's proposed location prior to start of demolition.

D. Predemolition Photographs or Video: Submit before Work begins.

1.7 CLOSEOUT SUBMITTALS

A. Inventory: Submit a list of items that have been removed and salvaged.

B. Landfill Records: Indicate receipt and acceptance of hazardous wastes by a landfill facility licensed to accept hazardous wastes.

1.8 FIELD CONDITIONS

A. Government will occupy portions of building immediately adjacent to selective demolition area. Conduct selective demolition so Government's operations will not be disrupted.

75H70122F30015 SELECTIVE DEMOLITION 024119 - 2

ROSEBUD HEAT PLANT DESIGN

ROSEBUD, SD

B. Conditions existing at time of inspection for bidding purpose will be maintained by Government as far as practical.

C. Notify Contracting Officer of discrepancies between existing conditions and Drawings before proceeding with selective demolition.

D. Hazardous Materials: It is not expected that hazardous materials will be encountered in the Work.

Retain subparagraph below to cover instances where hazardous materials are unexpectedly found and must be remediated. See the General Conditions for additional requirements on hazardous materials.

1. If suspected hazardous materials are encountered, do not disturb; immediately notify Contracting Officer. Hazardous materials will be removed by Goverment under a separate contract.

E. Storage or sale of removed items or materials on-site is not permitted.

F. Utility Service: Maintain existing utilities indicated to remain in service and protect them against damage during selective demolition operations.

1. Maintain fire-protection facilities in service during selective demolition operations.

PART 2 - PRODUCTS

2.1 PEFORMANCE REQUIREMENTS

A. Regulatory Requirements: Comply with governing EPA notification regulations before beginning selective demolition. Comply with hauling and disposal regulations of authorities having jurisdiction.

B. Standards: Comply with ANSI/ASSE A10.6 and NFPA 241.

PART 3 - EXECUTION

3.1 EXAMINATION

A. Verify that utilities have been disconnected and capped before starting selective demolition operations.

B. Review record documents of existing construction provided by Contracting Officer.

Government does not guarantee that existing conditions are same as those indicated in record documents.

C. Survey existing conditions and correlate with requirements indicated to determine extent of selective demolition required.

75H70122F30015 SELECTIVE DEMOLITION 024119 - 3

ROSEBUD HEAT PLANT DESIGN

ROSEBUD, SD

D. When unanticipated mechanical, electrical, or structural elements that conflict with intended function or design are encountered, investigate and measure the nature and extent of conflict.

Promptly submit a written report to Contracting Officer and Architect.

E. Survey of Existing Conditions: Record existing conditions by use of preconstruction photographs .

1. Inventory and record the condition of items to be removed and salvaged. Provide photographs of conditions that might be misconstrued as damage caused by salvage operations.

3.2 UTILITY SERVICES AND MECHANICAL/ELECTRICAL SYSTEMS

A. Existing Services/Systems to Remain: Maintain services/systems indicated to remain and protect them against damage.

B. Existing Services/Systems to Be Removed, Relocated, or Abandoned: Locate, identify, disconnect, and seal or cap off indicated utility services and mechanical/electrical systems serving areas to be selectively demolished.

1. Contracting Officer will arrange to shut off indicated services/systems when requested by Contractor.

2. If services/systems are required to be removed, relocated, or abandoned, provide temporary services/systems that bypass area of selective demolition and that maintain continuity of services/systems to other parts of building.

3. Disconnect, demolish, and remove fire-suppression systems, plumbing, and HVAC systems, equipment, and components indicated to be removed.

a. Piping to Be Removed: Remove portion of piping indicated to be removed and cap or plug remaining piping with same or compatible piping material.

b. Piping to Be Abandoned in Place: Drain piping and cap or plug piping with same or compatible piping material.

c. Equipment to Be Removed: Disconnect and cap services and remove equipment.

d. Equipment to Be Removed and Reinstalled: Disconnect and cap services and remove, clean, and store equipment; when appropriate, reinstall, reconnect, and make equipment operational.

e. Equipment to Be Removed and Salvaged: Disconnect and cap services and remove equipment and deliver to location indicated by Contracting Officer.

f. Ducts to Be Removed: Remove portion of ducts indicated to be removed and plug remaining ducts with same or compatible ductwork material.

g. Ducts to Be Abandoned in Place: Cap or plug ducts with same or compatible ductwork material.

3.3 PREPARATION

A. Site Access and Temporary Controls: Conduct selective demolition and debris-removal operations to ensure minimum interference with roads, streets, walks, walkways, and other adjacent occupied and used facilities.

75H70122F30015 SELECTIVE DEMOLITION 024119 - 4

ROSEBUD HEAT PLANT DESIGN

ROSEBUD, SD

1. Comply with requirements for access and protection specified in Section 015000 "Temporary Facilities and Controls."

B. Temporary Facilities: Provide temporary barricades and other protection required to prevent injury to people and damage to adjacent buildings and facilities to remain.

1. Provide protection to ensure safe passage of people around selective demolition area and to and from occupied portions of building.

2. Provide temporary weather protection, during interval between selective demolition of existing construction on exterior surfaces and new construction, to prevent water leakage and damage to structure and interior areas.

3. Protect walls, ceilings, floors, and other existing finish work that are to remain or that are exposed during selective demolition operations.

4. Cover and protect furniture, furnishings, and equipment that have not been removed.

5. Comply with requirements for temporary enclosures, dust control, heating, and cooling specified in Section 015000 "Temporary Facilities and Controls."

C. Temporary Shoring: Provide and maintain shoring, bracing, and structural supports as required to preserve stability and prevent movement, settlement, or collapse of construction and finishes to remain, and to prevent unexpected or uncontrolled movement or collapse of construction being demolished.

1. Strengthen or add new supports when required during progress of selective demolition.

3.4 SELECTIVE DEMOLITION, GENERAL

A. General: Demolish and remove existing construction only to the extent required by new construction and as indicated. Use methods required to complete the Work within limitations of governing regulations and as follows:

1. Proceed with selective demolition systematically, from higher to lower level. Complete selective demolition operations above each floor or tier before disturbing supporting members on the next lower level.

2. Neatly cut openings and holes plumb, square, and true to dimensions required. Use cutting methods least likely to damage construction to remain or adjoining construction.

Use hand tools or small power tools designed for sawing or grinding, not hammering and chopping, to minimize disturbance of adjacent surfaces. Temporarily cover openings to remain.

3. Cut or drill from the exposed or finished side into concealed surfaces to avoid marring existing finished surfaces.

4. Do not use cutting torches until work area is cleared of flammable materials. At concealed spaces, such as duct and pipe interiors, verify condition and contents of hidden space before starting flame-cutting operations. Maintain fire watch and portable fire-suppression devices during flame-cutting operations.

5. Maintain adequate ventilation when using cutting torches.

6. Remove decayed, vermin-infested, or otherwise dangerous or unsuitable materials and promptly dispose of off-site.

7. Remove structural framing members and lower to ground by method suitable to avoid free fall and to prevent ground impact or dust generation.

75H70122F30015 SELECTIVE DEMOLITION 024119 - 5

ROSEBUD HEAT PLANT DESIGN

ROSEBUD, SD

8. Locate selective demolition equipment and remove debris and materials so as not to impose excessive loads on supporting walls, floors, or framing.

9. Dispose of demolished items and materials promptly. Comply with requirements in Section 017419 "Construction Waste Management and Disposal."

B. Removed and Salvaged Items:

1. Clean salvaged items.

2. Pack or crate items after cleaning. Identify contents of containers.

3. Store items in a secure area until delivery to Government.

4. Transport items to Government's storage area designated by Contracting Officer.

5. Protect items from damage during transport and storage.

C. Removed and Reinstalled Items:

1. Clean and repair items to functional condition adequate for intended reuse.

2. Pack or crate items after cleaning and repairing. Identify contents of containers.

3. Protect items from damage during transport and storage.

4. Reinstall items in locations indicated. Comply with installation requirements for new materials and equipment. Provide connections, supports, and miscellaneous materials necessary to make item functional for use indicated.

D. Existing Items to Remain: Protect construction indicated to remain against damage and soiling during selective demolition. When permitted by Contracting Officer, items may be removed to a suitable, protected storage location during selective demolition and reinstalled in their original locations after selective demolition operations are complete.

3.5 SELECTIVE DEMOLITION PROCEDURES FOR SPECIFIC MATERIALS

A. Concrete: Demolish in small sections. Using power-driven saw, cut concrete to a depth of at least 3/4 inch at junctures with construction to remain. Dislodge concrete from reinforcement at perimeter of areas being demolished, cut reinforcement, and then remove remainder of concrete. Neatly trim openings to dimensions indicated.

B. Concrete Slabs-on-Grade: Saw-cut perimeter of area to be demolished, then break up and remove.

3.6 DISPOSAL OF DEMOLISHED MATERIALS

A. General: Except for items or materials indicated to be recycled, reused, salvaged, reinstalled, or otherwise indicated to remain Government's property, remove demolished materials from Project site and legally dispose of them in an EPA-approved landfill.

1. Do not allow demolished materials to accumulate on-site.

2. Remove and transport debris in a manner that will prevent spillage on adjacent surfaces and areas.

3. Remove debris from elevated portions of building by chute, hoist, or other device that will convey debris to grade level in a controlled descent.

75H70122F30015 SELECTIVE DEMOLITION 024119 - 6

ROSEBUD HEAT PLANT DESIGN

ROSEBUD, SD

4. Comply with requirements specified in Section 017419 "Construction Waste Management and Disposal."

B. Burning: Do not burn demolished materials.

C. Disposal: Transport demolished materials off Government's property and legally dispose of them.

3.7 CLEANING

A. Clean adjacent structures and improvements of dust, dirt, and debris caused by selective demolition operations. Return adjacent areas to condition existing before selective demolition operations began.

END OF SECTION

75H70122F30015 SELECTIVE DEMOLITION 024119 - 7

ROSEBUD HEAT PLANT DESIGN

ROSEBUD, SD

SECTION 030130 - MAINTENANCE OF CAST-IN-PLACE CONCRETE

PART 1 - GENERAL

1.1 SUMMARY

A. Section Includes:

1. Removal of deteriorated concrete and subsequent patching.

1.2 ACTION SUBMITTALS

A. Product Data: For each type of product.

PART 2 - PRODUCTS

2.1 MANUFACTURERS

A. Source Limitations: For repair products, obtain each color, grade, finish, type, and variety of product from single source and from single manufacturer with resources to provide products of consistent quality in appearance and physical properties.

2.2 BONDING AGENTS

A. Epoxy Bonding Agent: ASTM C881/C881M, bonding system Type II and free of VOCs.

1. Manufacturers: Subject to compliance with requirements, available manufacturers offering products that may be incorporated into the Work include, but are not limited to, the following:

a. BASF Corp. - Construction Chemicals.

b. ChemCo Systems.

c. Dayton Superior.

d. Euclid Chemical Company (The); an RPM company.

e. Kaufman Products, Inc.

f. MAPEI Corporation.

g. Sika Corporation.

h. Sto Corp.

i. US SPEC, Division of US MIX Company.

2.3 PATCHING MORTAR

A. Patching Mortar Requirements:

75H70122F30015 MAINTENANCE OF

CAST-IN-PLACE CONCRETE

030130 - 1 http://www.specagent.com/LookUp/?ulid=11907&mf=04&src=wd http://www.specagent.com/LookUp/?uid=123457128339&mf=04&src=wd http://www.specagent.com/LookUp/?uid=123457128340&mf=04&src=wd http://www.specagent.com/LookUp/?uid=123457128341&mf=04&src=wd http://www.specagent.com/LookUp/?uid=123457128342&mf=04&src=wd http://www.specagent.com/LookUp/?uid=123457128343&mf=04&src=wd http://www.specagent.com/LookUp/?uid=123457128347&mf=04&src=wd http://www.specagent.com/LookUp/?uid=123457128344&mf=04&src=wd http://www.specagent.com/LookUp/?uid=123457128345&mf=04&src=wd http://www.specagent.com/LookUp/?uid=123457128346&mf=04&src=wd

ROSEBUD HEAT PLANT DESIGN

ROSEBUD, SD

1. Only use patching mortars that are recommended by manufacturer for each applicable horizontal, vertical, or overhead use orientation.

2. Coarse Aggregate for Patching Mortar: ASTM C33/C33M, washed aggregate, Size No. 8, Class 5S. Add to patching-mortar mix only as permitted by patching-mortar manufacturer.

B. Cementitious Patching Mortar : Packaged, dry mix for repair of concrete.

1. Manufacturers: Subject to compliance with requirements, available manufacturers offering products that may be incorporated into the Work include, but are not limited to, the following:

a. AWRC Corporation.

b. BASF Corp. - Construction Chemicals.

c. CGM, Incorporated.

d. ChemMasters, Inc.

e. Dayton Superior.

f. Euclid Chemical Company (The); an RPM company.

g. Kaufman Products, Inc.

h. KOSTER American Corporation.

i. MAPEI Corporation.

j. Sika Corporation.

k. Simpson Strong-Tie Co., Inc.

l. Sto Corp.

m. Tnemec Inc.

n. US SPEC, Division of US MIX Company.

o. W.R. Meadows, Inc.

2.4 MISCELLANEOUS MATERIALS

A. Portland Cement: ASTM C150/C150M, Type I, II, or III unless otherwise indicated.

B. Water: Potable.

2.5 MIXES

A. General: Mix products, in clean containers, according to manufacturer's written instructions.

B. Dry-Pack Mortar: Mix required type(s) of patching-mortar dry ingredients with just enough liquid to form damp cohesive mixture that can be squeezed by hand into a ball but is not plastic.

PART 3 - EXECUTION

3.1 CONCRETE MAINTENANCE

A. Have concrete-maintenance work performed only by qualified concrete-maintenance specialist.

75H70122F30015 MAINTENANCE OF

CAST-IN-PLACE CONCRETE

030130 - 2 http://www.specagent.com/LookUp/?ulid=11910&mf=04&src=wd http://www.specagent.com/LookUp/?uid=123457128376&mf=04&src=wd http://www.specagent.com/LookUp/?uid=123457128364&mf=04&src=wd http://www.specagent.com/LookUp/?uid=123457128365&mf=04&src=wd http://www.specagent.com/LookUp/?uid=123457128366&mf=04&src=wd http://www.specagent.com/LookUp/?uid=123457128367&mf=04&src=wd http://www.specagent.com/LookUp/?uid=123457128368&mf=04&src=wd http://www.specagent.com/LookUp/?uid=123457128369&mf=04&src=wd http://www.specagent.com/LookUp/?uid=123457128377&mf=04&src=wd http://www.specagent.com/LookUp/?uid=123457128375&mf=04&src=wd http://www.specagent.com/LookUp/?uid=123457128370&mf=04&src=wd http://www.specagent.com/LookUp/?uid=123457128374&mf=04&src=wd http://www.specagent.com/LookUp/?uid=123457128371&mf=04&src=wd http://www.specagent.com/LookUp/?uid=123457128378&mf=04&src=wd http://www.specagent.com/LookUp/?uid=123457128372&mf=04&src=wd http://www.specagent.com/LookUp/?uid=123457128373&mf=04&src=wd

ROSEBUD HEAT PLANT DESIGN

ROSEBUD, SD

B. Comply with manufacturers' written instructions for surface preparation and product application.

3.2 EXAMINATION

A. Notify Architect seven days in advance of dates when areas of deteriorated or delaminated concrete and deteriorated reinforcing bars will be located.

B. Locate areas of deteriorated or delaminated concrete using hammer or chain-drag sounding and mark boundaries. Mark areas for removal by simplifying and squaring off boundaries. At columns and walls make boundaries level and plumb unless otherwise indicated.

C. Perform surveys as the Work progresses to detect hazards resulting from concrete-maintenance work.

3.3 PREPARATION

A. Ensure that supervisory personnel are on-site and on duty when concrete maintenance work begins and during its progress.

B. Protect persons, motor vehicles, surrounding surfaces of building being repaired, building site, plants, and surrounding buildings from harm resulting from concrete maintenance work.

1. Comply with each product manufacturer's written instructions for protections and precautions.

2. Contain dust and debris generated by concrete maintenance work and prevent it from reaching the public or adjacent surfaces.

3. Protect floors and other surfaces along haul routes from damage, wear, and staining.

C. Existing Drains: Prior to the start of work in an area, test drainage system to ensure that it is functioning properly. Notify Architect immediately of inadequate drainage or blockage. Do not begin work in an area until the drainage system is in working order.

1. Prevent solids such as aggregate or mortar residue from entering the drainage system.

Clean out drains and drain lines that become sluggish or blocked by sand or other materials resulting from concrete maintenance work.

2. Protect drains from pollutants. Block drains or filter out sediments, allowing only clean water to pass.

D. Preparation for Concrete Removal: Make explorations, probes, and inquiries as necessary to determine condition of construction to be removed in the course of repair.

1. Verify that affected utilities have been disconnected and capped.

2. Provide and maintain shoring, bracing, and temporary structural supports as required to preserve stability and prevent unexpected or uncontrolled movement, settlement, or collapse of construction being demolished and construction and finishes to remain.

Strengthen or add new supports when required during progress of removal work.

75H70122F30015 MAINTENANCE OF

CAST-IN-PLACE CONCRETE

030130 - 3

ROSEBUD HEAT PLANT DESIGN

ROSEBUD, SD

3.4 REMOVAL OF CONCRETE

A. Do not overload structural elements with debris.

B. Saw-cut perimeter of areas indicated for removal to a depth of at least 1/2 inch. Make cuts perpendicular to concrete surfaces and no deeper than cover on reinforcement.

C. Remove deteriorated and delaminated concrete by breaking up and dislodging from reinforcement.

D. Remove additional concrete if necessary to provide a depth of removal of at least 1/2 inch over entire removal area.

E. Where half or more of the perimeter of reinforcing bar is exposed, bond between reinforcing bar and surrounding concrete is broken, or reinforcing bar is corroded, remove concrete from entire perimeter of bar and to provide at least 3/4-inch clearance around bar.

F. Test areas where concrete has been removed by tapping with hammer, and remove additional concrete until unsound and disbonded concrete is completely removed.

G. Provide surfaces with a fractured profile of at least 1/8 inch that are approximately perpendicular or parallel to original concrete surfaces. At columns and walls, make top and bottom surfaces level unless otherwise directed.

H. Thoroughly clean removal areas of loose concrete, dust, and debris.

3.5 APPLICATION OF BONDING AGENT

A. Epoxy Bonding Agent: Apply to reinforcing bars and concrete, leaving no pinholes or other uncoated areas. Apply to reinforcing bars in at least two coats, allowing first coat to dry before applying second coat. Place patching mortar while epoxy is still tacky. If epoxy dries, recoat before placing patching mortar.

3.6 INSTALLATION OF PATCHING MORTAR

A. Place patching mortar as specified in this article unless otherwise recommended in writing by manufacturer or where dry-pack mortar is indicated.

1. Provide forms where necessary to confine patch to required shape.

2. Wet substrate and forms thoroughly and then remove standing water.

B. Pretreatment: Apply specified bonding agent .

C. General Placement: Place patching mortar by troweling toward edges of patch to force intimate contact with edge surfaces. For large patches, fill edges first and then work toward center, always troweling toward edges of patch. At fully exposed reinforcing bars, force patching mortar to fill space behind bars by compacting with trowel from sides of bars.

75H70122F30015 MAINTENANCE OF

030130 - 4

ROSEBUD HEAT PLANT DESIGN

ROSEBUD, SD

D. Consolidation: After each lift is placed, consolidate material and screed surface.

E. Multiple Lifts: Where multiple lifts are used, score surface of lifts to provide a rough surface for placing subsequent lifts. Allow each lift to reach final set before placing subsequent lifts.

F. Finishing: Allow surfaces of lifts that are to remain exposed to become firm and then finish to a surface matching adjacent concrete.

G. Curing: Wet-cure cementitious patching materials, including polymer-modified cementitious patching materials, for not less than seven days by water-fog spray or water-saturated absorptive cover.

3.7 INSTALLATION OF DRY-PACK-MORTAR

A. Use dry-pack mortar for deep cavities and where indicated. Place as specified in this article unless otherwise recommended in writing by manufacturer.

1. Provide forms where necessary to confine patch to required shape.

2. Wet substrate and forms thoroughly and then remove standing water.

B. Pretreatment: Apply specified bonding agent.

C. Place dry-pack mortar into cavity by hand, and compact tightly into place. Do not place more material at a time than can be properly compacted. Continue placing and compacting until patch is approximately level with surrounding surface.

D. After cavity is filled and patch is compacted, trowel surface to match profile and finish of surrounding concrete.

E. Wet-cure patch for not less than seven days by water-fog spray or water-saturated absorptive cover.

END OF SECTION

75H70122F30015 MAINTENANCE OF

030130 - 5

ROSEBUD HEAT PLANT DESIGN

ROSEBUD, SD

SECTION 083323 - OVERHEAD COILING DOORS

PART 1 - GENERAL

1.1 SUMMARY

A. Section Includes:

1. Service doors.

1.2 ACTION SUBMITTALS

A. Product Data: For each type and size of overhead coiling door and accessory.

B. Shop Drawings: For each installation and for special components not dimensioned or detailed in manufacturer's product data.

1. Include points of attachment and their corresponding static and dynamic loads imposed on structure.

2. Show locations of controls, locking devices, detectors or replaceable fusible links, and other accessories.

1.3 INFORMATIONAL SUBMITTALS

A. Sample warranty.

1.4 CLOSEOUT SUBMITTALS

A. Maintenance data.

1.5 WARRANTY

A. Special Warranty: Manufacturer agrees to repair or replace components of doors that fail in materials or workmanship within specified warranty period.

1. Warranty Period: Two years from date of Substantial Completion.

75H70122F30015 OVERHEAD COILING DOORS 083323 - 1

ROSEBUD HEAT PLANT DESIGN

ROSEBUD, SD

PART 2 - PRODUCTS

2.1 PERFORMANCE REQUIREMENTS

A. Accessibility Standard: Comply with applicable provisions in the ABA standards of the Federal agency having jurisdiction.

B. Structural Performance, Exterior Doors: Capable of withstanding the following design wind loads:

1. Design Wind Load: Uniform pressure (velocity pressure) of 20 lbf/sq. ft., acting inward and outward.

2.2 DOOR ASSEMBLY

A. Service Door: Overhead coiling door formed with curtain of interlocking metal slats.

1. Manufacturers: Subject to compliance with requirements, available manufacturers offering products that may be incorporated into the Work include, but are not limited to, the following:

a. ACME Rolling Doors.

b. Advanced Door Technologies.

c. Alpine Overhead Doors, Inc.

d. Alumatec Pacific Products.

e. ASTA Door Corporation.

f. C.H.I. Overhead Doors, Inc.

g. City-Gates.

h. Clopay Building Products.

i. Cookson; a CornellCookson company.

j. Cornell; a CornellCookson company.

k. Dynamic Closures Corporation.

l. ENTREMATIC.

m. Hormann High Performance Doors.

n. Lawrence Roll-Up Doors, Inc.

o. McKeon Rolling Steel Door Company, Inc.

p. Metro Door LLC.

q. Overhead Door Corporation.

r. Raynor Garage Doors.

s. Southwestern Rolling Steel Door Co.

t. Wayne-Dalton Corp.

u. Windsor Door.

B. Operation Cycles: Door components and operators capable of operating for not less than 20,000.

C. Door Curtain Material: Galvanized steel.

75H70122F30015 OVERHEAD COILING DOORS 083323 - 2

http://www.specagent.com/LookUp/?ulid=7627&mf=&src=wd http://www.specagent.com/LookUp/?uid=123457222187&mf=04&src=wd http://www.specagent.com/LookUp/?uid=123457222211&mf=04&src=wd http://www.specagent.com/LookUp/?uid=123457222188&mf=04&src=wd http://www.specagent.com/LookUp/?uid=123457222189&mf=04&src=wd http://www.specagent.com/LookUp/?uid=123457222203&mf=04&src=wd http://www.specagent.com/LookUp/?uid=123457222191&mf=04&src=wd http://www.specagent.com/LookUp/?uid=123457222192&mf=04&src=wd http://www.specagent.com/LookUp/?uid=123457222193&mf=04&src=wd http://www.specagent.com/LookUp/?uid=123457222194&mf=04&src=wd http://www.specagent.com/LookUp/?uid=123457222195&mf=04&src=wd http://www.specagent.com/LookUp/?uid=123457222206&mf=04&src=wd http://www.specagent.com/LookUp/?uid=123457222190&mf=04&src=wd http://www.specagent.com/LookUp/?uid=123457222210&mf=04&src=wd http://www.specagent.com/LookUp/?uid=123457222196&mf=04&src=wd http://www.specagent.com/LookUp/?uid=123457222197&mf=04&src=wd http://www.specagent.com/LookUp/?uid=123457222198&mf=04&src=wd http://www.specagent.com/LookUp/?uid=123457222199&mf=04&src=wd http://www.specagent.com/LookUp/?uid=123457222201&mf=04&src=wd http://www.specagent.com/LookUp/?uid=123457222205&mf=04&src=wd http://www.specagent.com/LookUp/?uid=123457222202&mf=04&src=wd http://www.specagent.com/LookUp/?uid=123457222208&mf=04&src=wd

ROSEBUD HEAT PLANT DESIGN

ROSEBUD, SD

D. Door Curtain Slats: Flat profile slats of 1-7/8-inch center-to-center height.

E. Bottom Bar: Two angles, each not less than 1-1/2 by 1-1/2 by 1/8 inch thick; fabricated from hot-dip galvanized steel and finished to match door.

F. Curtain Jamb Guides: Galvanized steel with exposed finish matching curtain slats.

G. Hood: Match curtain material and finish.

1. Mounting: Face of wall.

H. Locking Devices: Equip door with locking device assembly.

1. Locking Device Assembly: Single-jamb side locking bars, operable from inside and outside with cylinders.

I. Manual Door Operator: Chain-hoist operator.

J. Curtain Accessories: Equip door with weatherseals.

K. Door Finish:

1. Factory Prime Finish: Manufacturer's standard color.

2.3 HOODS

A. General: Form sheet metal hood to entirely enclose coiled curtain and operating mechanism at opening head. Contour to fit end brackets to which hood is attached. Roll and reinforce top and bottom edges for stiffness. Form closed ends for surface-mounted hoods and fascia for any portion of between-jamb mounting that projects beyond wall face. Equip hood with intermediate support brackets as required to prevent sagging.

1. Exterior-Mounted Doors: Fabricate hood to act as weather protection and with a perimeter sealant-joint-bead profile for applying joint sealant.

2.4 LOCKING DEVICES

A. Locking Device Assembly: Fabricate with cylinder lock, spring-loaded dead bolt, operating handle, cam plate, and adjustable locking bars to engage through slots in tracks.

1. Lock Cylinders: As standard with manufacturerand keyed to building keying system.

2. Keys: Three for each cylinder.

75H70122F30015 OVERHEAD COILING DOORS 083323 - 3

ROSEBUD HEAT PLANT DESIGN

ROSEBUD, SD

2.5 CURTAIN ACCESSORIES

A. Weatherseals for Exterior Doors: Equip each exterior door with weather-stripping gaskets fitted to entire exterior perimeter of door for a weather-resistant installation unless otherwise indicated.

2.6 COUNTERBALANCE MECHANISM

A. General: Counterbalance doors by means of manufacturer's standard mechanism with an adjustable-tension, steel helical torsion spring mounted around a steel shaft and contained in a spring barrel connected to top of curtain with barrel rings. Use grease-sealed bearings or self-lubricating graphite bearings for rotating members.

B. Brackets: Manufacturer's standard mounting brackets of either cast iron or cold-rolled steel plate.

2.7 MANUAL DOOR OPERATORS

A. General: Equip door with manual door operator by door manufacturer.

B. Chain-Hoist Operator: Consisting of endless steel hand chain, chain-pocket wheel and guard, and gear-reduction unit with a maximum 25-lbf force for door operation. Provide alloy-steel hand chain with chain holder secured to operator guide.

PART 3 - EXECUTION

3.1 INSTALLATION, GENERAL

A. Install overhead coiling doors and operating equipment complete with necessary hardware, anchors, inserts, hangers, and equipment supports; according to manufacturer's written instructions and as specified.

3.2 DEMONSTRATION

A. Engage a factory-authorized service representative to train Owner's maintenance personnel to adjust, operate, and maintain overhead coiling…