Weldon Springs Recreational Trail and Bridge Improvements - Special Provisions
This document consists of Special Provisions for a construction contract issued by the Illinois Department of Natural Resources (IDNR) for the Weldon Springs Recreational Trail and Bridge Improvements Project in DeWitt County, Illinois (Contract 3-23-001). The project scope includes removal of an existing timber bridge structure, installation of a new timber bridge structure, installation of new timber stairs with shallow concrete caisson foundations and reinforcement steel, traffic control for hiking paths and parking lots, erosion control, and maintenance of affected trails and park roads. The work is located along hiking trails at Weldon Springs State Park between the dam and the Long Point Group Campsite. The construction start date is July 7, 2026, with a work completion date 90 calendar days thereafter (October 5, 2026). Close-out documents are due 75 calendar days after work completion (December 19, 2026), and the contract end date is May 14, 2027. Bids are accepted only through electronic submission on BidBuy. The contractor must be pre-approved on the Illinois Department of Transportation (IDOT) pre-approved list.
The project is funded with State funds and federal funds from the Recreational Trails Program (RTP) administered by IDNR. The contract incorporates by reference the Standard Specifications for Road and Bridge Construction (adopted January 1, 2022) and Supplemental Specifications adopted January 1, 2026. Liquidated damages are assessed at $300 per calendar day if close-out documents are not completed by the specified deadline. The contractor must comply with prevailing wage requirements under the Illinois Prevailing Wage Act and must employ at least 90 percent Illinois laborers during periods of excessive unemployment. For contracts valued at $500,000 or more, contractors must comply with the Illinois Works Apprenticeship Initiative, requiring apprentices to perform either 10 percent of total labor hours or 10 percent of estimated labor hours in each prevailing wage classification, whichever is less. All workers must have certified payroll submitted to the Illinois Department of Labor in IDOL format by the 15th of each month, and records must be maintained for five years. Mandatory meetings include pre-construction, weekly progress meetings, meetings prior to specific construction phases, and a final demobilization meeting. The contractor is responsible for all field engineering and surveying, site layout and staking, traffic control and protection, debris control, pollution control, and dust control. Any damage to existing facilities, utilities, roads, or parking areas must be repaired at the contractor's expense and to the satisfaction of the engineer.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| ipg-active-registered-vendor-disclosure-formerly-forms-b-v-26-1-8-26-2025-1~45.docx | DOCX document | |
| B52702contract-template-v-25-4.docx | DOCX document | |
| vendor-disclosure-formerly-forms-a-v26-2-7-22-2025~22.docx | DOCX document | |
| Attachment 1 - Project Plans~10.pdf | ||
| B52702invitation-for-bid-vendor-instructions-and-requirements-v26-1.docx | DOCX document | |
| B52702invitation-for-bid-offer-to-the-state-of-illinois.pdf | ||
| Attachment 3 - Bid Form~2.xlsx | XLSX spreadsheet |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Weldon Springs Recreational Trail and Bridge Improvements DeWitt County, Illinois
3-23-001 ii
SPECIAL PROVISIONS
For the construction of
Weldon Springs Recreational Trail and Bridge Improvements Project DeWitt County, Illinois
Contract 3-23-001
The "Standard Specifications for Road and Bridge Construction," adopted January 1, 2022, by the Illinois Department of Transportation and supplemented by the "Supplemental Specifications and Recurring Special Provisions," adopted January 1, 2026, are incorporated by reference and made a part of this Contract for the Weldon Springs Recreational Trail and Bridge Improvements Project, DeWitt County, Contract 3-23-001” project. The "Standard Specifications for Road and Bridge Construction," are hereinafter referred to as the “Standard Specifications”. The Standard Specifications and the Supplemental Specifications and Recurring Special Provisions can be purchased from the Illinois Department of Transportation (IDOT) or downloaded from the IDOT website.
The following Special Provisions supplement the Standard Specifications and the Supplemental Specifications and Recurring Special Provisions. In the event of a conflict, the hierarchy in Article 105.05 of the Standard Specifications shall govern.
In the application of the Standard Specifications to this Contract, references to the Department of Transportation shall be interpreted to mean the Department of Natural Resources hereinafter referred to as the Department. All references in the Standard Specifications to the Department’s qualified producer list refers to the IDOT prequalified list.
The Invitation for Bids, issuance of Contract, Proposal Guarantee, Schedule of Bid Items, Signature Sheet, Opening of Bids, Acceptance of Bids, other bidding or contract requirements shall be in accordance with the policies and procedures of the Illinois Department of Natural Resources - Office of Reality and Environmental Planning.
PREQUALIFICATIONS
The contractor shall be on the Illinois Department of Transportation (IDOT) pre-approved list, unless otherwise acceptable to the Department.
BIDDING
Bids will be accepted by electronic submission on BidBuy only.
CONSTRUCTION START DATE
The Contractor shall begin construction to be performed under the contract as stated in the Construction Start Date paragraph of these Special Provisions.
FUNDING
This project is being funded with State funds and federal funds from the Recreational Trails Program (RTP) administered by the Illinois Department of Natural Resources.
3-23-001 iii
INDEX
FOR
SUPPLEMENTAL SPECIFICATIONS AND RECURRING
SPECIAL PROVISIONS
Adopted January 1, 2026
This index contains a listing of SUPPLEMENTAL SPECIFICATIONS, frequently used RECURRING SPECIAL PROVISIONS, and LOCAL ROADS AND STREETS RECURRING
SPECIAL PROVISIONS.
ERRATA Standard Specifications for Road and Bridge Construction (Adopted 1-1-22) (Revised 1-1-26)
SUPPLEMENTAL SPECIFICATIONS
Std. Spec. Sec. Page No.
109 Measurement and Payment..……….…………………………….1 202 Earth and Rock Excavation 204 Borrow and Furnished Excavation 207 Porous Granular Embankment 211 Topsoil and Compost 214 Grading and Shaping Ditches 406 Hot-Mix Asphalt Binder and Surface Course 407 Hot-Mix Asphalt Pavement (Full-Depth) 420 Portland Cement Concrete Pavement 502 Excavation for Structures 504 Precast Concrete Structures 509 Metal Railings 522 Retaining Walls 540 Box Culverts 542 Pipe Culverts 550 Storm Sewers 586 Granular Backfill for Structures 601 Pipe Drains, Pipe Underdrains, and French Drains 630 Steel Plate Beam Guardrail 632 Guardrail and Cable Road Guard Removal 644 High Tension Cable Median Barrier 665 Woven Wire Fence 701 Work Zone Traffic Control and Protection 781 Raised Reflective Pavement Markers 782 Reflectors 801 Electrical Requirements 821 Roadway Luminaires
1003 Fine Aggregates 1004 Coarse Aggregates 1010 Finely Divided Minerals 1020 Portland Cement Concrete 1030 Hot-Mix Asphalt 1040 Drain Pipe, Tile, and Wall Drain
3-23-001 iv
1042 Precast Concrete Products 1061 Waterproofing Membrane System 1067 Luminaire 1097 Reflectors 1102 Hot-Mix Asphalt Equipment
3-23-001 v
RECURRING SPECIAL PROVISIONS
The following RECURRING SPECIAL PROVISIONS indicated by an “X” are applicable to this contract and are included by reference:
CHECK SHEET # PAGE NO.
1 Additional State Requirements for Federal-Aid Construction Contracts…………… 87 2 Subletting of Contracts (Federal-Aid Contracts)…………….……………….……….. 90
3 X EEO……………………………………………………………….………………………. 91
4 X Specific EEO Responsibilities Nonfederal-Aid Contracts .…………………………… 101 5 X Required Provisions - State Contracts …..………………………………………….… 106 6 Asbestos Bearing Pad Removal …………..………………………………………..… 112 7 Asbestos Waterproofing Membrane and Asbestos Hot-Mix Asphalt
Surface Removal ……………………..……………….………………………………
8 Temporary Stream Crossings and In-Stream Work Pads …....…………………….. 114 9 Construction Layout Stakes …………………………………….……………………… 115
10 Use of Geotextile Fabric for Railroad Crossing ………………..…………………….. 118 11 Subsealing of Concrete Pavements ……………………………..………………… 12 Hot-Mix Asphalt Surface Correction ………………………………………………..…. 124 13 Pavement and Shoulder Resurfacing ……..………………………………………..…. 126 14 Patching with Hot-Mix Asphalt Overlay Removal ……..…………………………..…. 127 15 Polymer Concrete ………………………………………….……………………...…….. 129 16 Reserved …………………………………………………….………………………… 17 Bicycle Racks ……………………………………………….………………………… 18 Temporary Portable Bridge Traffic Signals ……………….……………………..…… 134 19 Nighttime Inspection of Roadway Lighting ……………….………………… 20 English Substitution of Metric Bolts ………………………….……………………….…. 137 21 Calcium Chloride Accelerator for Portland Cement Concrete …………………...…. 138 22 Quality Control of Concrete Mixtures at the Plant ………………………………..…… 139 23 X Quality Control/Quality Assurance of Concrete Mixtures ………………………….…. 147 24 Reserved ………………………………………………………………………………….…. 163 25 Reserved ………………………………………………………………………………….…. 164 26 Temporary Raised Pavement Markers …………………………………………………. 165 27 Restoring Bridge Approach Pavements Using High-Density Foam ………………... 166 28 Portland Cement Concrete Inlay or Overlay ………………………………………… 29 Portland Cement Concrete Partial Depth Hot-Mix Asphalt Patching …… 30 Longitudinal Joint and Crack Patching ………………………………………………….. 176 31 Concrete Mix Design – Department Provided ……………………………………… 32 Station Numbers in Pavements or Overlays …………………………………
3-23-001 vi
LOCAL ROADS AND STREETS RECURRING SPECIAL PROVISIONS
Table of Contents
CHECK SHEET # PAGE NO.
LRS1 Reserved LRS2 Furnished Excavation LRS3 Work Zone Traffic Control Surveillance LRS4 Flaggers in Work Zones LRS5 Contract Claims LRS6 Bidding Requirements and Conditions for Contract Proposals ….. 186 LRS7 Bidding Requirements and Conditions for Material Proposals …... 192 LRS8 Reserved LRS9 Bituminous Surface Treatments LRS10 Reserved LRS11 Employment Practices LRS12 Wages of Employees on Public Works LRS13 Selection of Labor LRS14 Paving Brick and Concrete Paver Pavements and Sidewalks LRS15 X Partial Payments LRS16 Protests on Local Lettings LRS17 X Substance Abuse Prevention Program LRS18 Multigrade Cold Mix Asphalt LRS19 Reflective Crack Control Treatment
3-23-001 vii
SPECIAL PROVISIONS
TABLE OF CONTENTS
GENERAL 1
DESCRIPTION OF PROJECT 1
LOCATION OF THE PROJECT 1
ABILITY OF CONTRACTOR TO COMPLETE WORK 1
RESPONSIBILITY OF THE CONTRACTOR 1
CONSTRUCTION START DATE 2
WORK COMPLETION DATE 2
CLOSE-OUT DOCUMENTS DATE 2
CONTRACT END DATE 2
PROGRESS AND LIQUIDATED DAMAGES 2
CERTIFIED PAYROLL 3
CONSTRUCTION MANDATORY MEETINGS 3
CONTRACT CLAIM 3
EMPLOYMENT OF PUBLIC WORKERS ON PUBLIC WORKS 4
EXISTING PAVEMENTS 4
FIELD ENGINEERING AND SURVEYING 4
MAINTENANCE OF EXISTING UTILITIES 5
OWNER OCCUPANCY 5
PREVAILING WAGE RATES 5
TEMPORARY CONTROLS 6
TRAFFIC CONTROL AND PROTECTION 6
STANDARD SPECIFICATIONS:
SECTION 101 - Definition of Terms 7 SECTION 107 - Legal Relations and Responsibility to the Public 8 SECTION 108 - Prosecution and Progress 9 SECTION 201 - Clearing, Tree Removal and Protection, Care and 9
Repair of Existing Plant Material
STEEL AND IRON MATERIALS 9
WEEKLY BEP TRUCKING REPORTS 10
PERIMETER EROSION BARRIER 10
PERMANENT SEEDING 10
HARDWARE 10
PIPE HANDRAIL, SPECIAL 11
OTHER SPECIAL PROVISIONS
COMPENSABLE DELAY COSTS 13
EROSION CONTROL BLANKET 17
ILLINOIS WORKS APPRENTICESHIP INITIATIVE-
STATE FUNDED CONTRACTS 20
SEEDING 21
SUBCONTRACTOR MOBILIZATION PAYMENTS 27
WORK ZONE TRAFFIC CONTROL DEVICES 28
COMPREHENSIVE ENVIRONMENTAL REVIEW PROCESS 31
3-23-001
GENERAL
The following Special Provisions supplement the "Standard Specifications for Road and Bridge Construction," adopted January 1, 2022, the latest edition of the "Manual on Uniform Traffic Control Devices for Streets and Highways", and the "Manual of Test Procedures for Materials" in effect on the date of Invitation for Bids, and the Supplemental Specifications and Recurring Special Provisions indicated on the Check Sheet included herein which apply to and govern the construction of the “Weldon Springs Recreational Trail and Bridge Improvements Project.” In the event of a conflict with any part or parts of said Specifications, the hierarchy of contract documents in Article 105.05 in the Standard Specifications shall govern.
DESCRIPTION OF THE PROJECT
The Weldon Springs Recreational Trail and Bridge Improvements Project consists of furnishing all labor, materials, tools and equipment for the removal of an existing timber bridge structure, installing a new timber bridge structure, installing new timber stairs, shallow concrete caisson foundations and associated reinforcement steel, traffic control for hiking paths, parking lots, and roadways as necessary to complete the project, erosion control as outlined in the plans, and maintenance and clean-up of affected trails, parking areas, and park roads used for the project.
LOCATION OF THE PROJECT
The proposed Weldon Springs Recreational Trail and Bridge Improvements Project is located on the south half of Weldon Springs State Park, along the hiking trails between the dam and the Long Point Group Campsite in DeWitt County of central Illinois.
ABILITY OF CONTRACTOR TO COMPLETE WORK
The Contractor shall furnish the necessary labor, materials, tools, equipment and supervision to successfully complete all phases of the contract as described herein.
The Contractor shall perform all work indicated or implied in the Contract Documents. All work not specified but required to complete the project in a satisfactory manner, shall be performed by the Contractor. All items of work not listed in the Bid Items shall be considered as incidental work to the Contract and no additional compensation will be allowed. The project includes all incidental and collateral work required for the completion of the project in accordance with the requirements of the Contract Documents.
RESPONSIBILITY OF THE CONTRACTOR
It shall be the responsibility of the Contractor to visit the site in order to become fully acquainted with all the surrounding conditions pertaining to the project.
3-23-001
CONSTRUCTION START DATE
In Article 108.03 of the Standard Specifications, add the following:
The Construction Start date is July 7, 2026, unless otherwise acceptable to the Engineer. After execution of the contract, the Contractor shall prepare and transmit submittals. Materials may be ordered after acceptance of the submittal. After the projected delivery date of long lead items are known, an earlier Construction Start date may be acceptable to the Engineer. No construction will be allowed prior to the Construction Start date, unless otherwise acceptable to the Engineer. The Construction Start date shall be shown on the construction schedule.
WORK COMPLETION DATE
In addition to Article 108.05(a) of the Standard Specifications, the following shall apply:
The Contractor shall complete all work on or before the Work Completion Date. The Work Completion Date will be determined by adding 90 calendar days to the Construction Start Date. The Work Completion Date shall be shown on the construction schedule.
Add to Article 101.55: "Additionally, the work shall include punch list, site cleaning and removal of equipment and excess materials."
CLOSE-OUT DOCUMENTS DATE
The Close-out Documents Date shall be 75 calendar days added to the Work Completion Date. All project close-out documents shall be completed by the Close-out Documents Date. The Close-out Documents Date shall be shown on the construction schedule.
CONTRACT END DATE
The Contract End Date shall be May 14, 2027. The Contract End Date shall be shown on the construction schedule.
PROGRESS AND LIQUIDATED DAMAGES
If the work is not completed by the Work Completion Date, then the Department may assess liquidated damages in accordance with Article 108.09 of the Standard Specifications.
The final payment to the Contractor will be processed after all Close-out Documents have been reviewed and accepted. If the project close-out documents are not completed by the Close-out Documents Date, then the Contractor may be liable to pay the Department $300.00 per calendar day as liquidated damages for failure to provide the close-out documents. The liquidated damages amount specified will accrue and be assessed until the close-out documents are complete.
3-23-001
CERTIFIED PAYROLL
The Contractor and all sub-contractors shall submit certified payroll records to the Illinois Department of Labor (IDOL) and to the Project Manager. The payroll records shall include all workers employed by the contractors on the project. Payroll records shall be submitted to the IDOL in IDOL format. The Contractor shall transmit a copy of the certified payroll in IDOL format with the IDOL transcript to the Engineer no later than the 15th day of each calendar month for the preceding month. See Submission of Payroll Records Special Provision.
In accordance with 820 ILCS 130/5, the Contractor and sub-contractor(s) shall make and keep, for a period of 5 years from the date of the last payment made on or after January 1, 2014, (the effective date of Public Act 98-328) on a contract or subcontract for public works, records of all laborers, mechanics, and other workers employed by them on the project.
CONSTRUCTION MANDATORY MEETINGS
For project coordination, satisfactory Contractor performance, and clarification of the requirements of the Contract Documents inclusive of the Special Provisions, the following mandatory meetings shall be scheduled by the Engineer and shall include mandatory representation by the Engineer and Contractor:
1. Pre-construction meeting: Overall review of Project. Contractor shall submit a construction schedule during or prior to the pre-construction meeting.
2. Weekly progress meetings.
3. Prior to construction of shallow concrete caisson foundations
4. Prior to placement of superstructures of both structures
5. Prior to placement of stairs of stairway structure
6. Prior to demobilization by the Contractor
CONTRACT CLAIM
In Article 109.09 (e) of the Standard Specifications:
1. Delete "Engineer of Construction" and insert "Project Manager".
2. Delete "Chief Engineer/Director of Highways or Designee" and insert "Kyle Schweizer, PE or other licensed Professional Engineer designated by the Director of Office of Reality and Environmental Planning (Director)".
Add to Article 109.09(e): "Each Level of the claim shall be submitted to the Project Manager. Two paper copies and one electronic copy shall be transmitted to the Project Manager. Department or Contractor may request an opportunity to present the claim verbally at each level if the claim has not been satisfactorily resolved at the previous level."
In Article 109.09(e)(1): Delete in the third line, "simultaneously to the District and the Engineer of Construction" and insert "to the Project Manager".
In Article 109.09(e)(1): Delete in the fourth line, "in consultation with the District".
3-23-001
EMPLOYMENT OF PUBLIC WORKERS ON PUBLIC WORKS
In a period of excessive unemployment rates, State contractors (1) constructing or building any public works or (2) cleaning-up and disposing on-site of hazardous waste, and that clean-up or on-site disposal is funded or financed in whole or in part with State funds or funds administered by the State, are required to employ at least 90% Illinois laborers on such project. For projects involving clean-up and on-site disposal of hazardous waste, emergency response or immediate removal activities are excluded. This requirement applies to all labor whether skilled, semi-skilled or unskilled, whether manual or non-manual.
A period of excessive unemployment rates is defined as any month immediately following two consecutive calendar months during which the level of unemployment in the State of Illinois has exceeded 5% as measured by the United States Bureau of Labor Statistics in its monthly publication of employment and unemployment figures.
Any public works project financed in whole or in part by federal funds administered by the State of Illinois is covered under the provisions of this requirement, to the extent permitted by any applicable federal law or regulation. (30 ILCS 570)
Contractors may receive an exception from this requirement by submitting a request and supporting documents certifying that Illinois laborers are either not available or are incapable of performing the particular type of work involved. The certification must: (a) be submitted to the agency within the first quarter of the Contract Term; (b) provide sufficient support that demonstrates the exception is met; (c) be signed by an authorized signatory of the contractor;
and (d) be approved by the agency.
EXISTING PAVEMENTS
Existing on-site trails may be used for construction traffic. The Contractor shall provide additional temporary access when needed with the route acceptable to the Engineer. The Contractor shall maintain and clean existing roads throughout construction and restore roads, parking lots, and trails to original or better condition at completion of work.
FIELD ENGINEERING AND SURVEYING
Requirements Included:
The Contractor shall furnish all field engineering and surveying services required for the project, including:
1. Lay-out and field stake the construction limits, unless otherwise specified on the plans, to the satisfaction of the Engineer.
2. Survey work required in execution of the construction.
3. Civil, structural or other professional engineering services specified, or required to execute the Contractor's construction methods.
3-23-001
Survey Reference Points:
Existing basic horizontal and vertical control points for the project are identified in the plans for the Contractor's use. The Contractor shall locate and protect control points prior to starting site work and preserve all permanent reference points during construction.
Project Survey Requirement:
The Contractor shall use established benchmarks on-site as identified in the plans. The Contractor shall establish construction limits, lines and levels, locate and lay-out by instrumentation and similar appropriate means, all site improvements. The Engineer may verify the layouts.
Records:
The Contractor shall maintain complete, accurate records, computations and field books of all control and survey work as it progresses. These shall be kept on-site for use of and reference by the Engineer.
All records shall be submitted to the Engineer as the records shall become the property of the Department.
Measurement and Payment:
This work will be paid at the contract lump sum price for CONSTRUCTION STAKING.
MAINTENANCE OF EXISTING UTILITIES
The Contractor shall be responsible for interference with or damage to any existing utilities, such as water mains, sewers, gas mains, cable, conduit, etc., and shall repair or replace same at the Contractor's expense and with the least possible delay. The Contractor shall give prior notification to the utility companies of his intention to begin work. The Contractor shall call J.U.L.I.E. at 1-800-892-0123 to mark the location of underground utilities (48 hours prior to commencing the work). The Contractor shall host a joint meeting that includes the Landowner and the Engineer. The requirements to satisfy the conditions stated herein shall be included in all other pay items.
OWNER OCCUPANCY
Owners will occupy premises during entire construction period for conduction of their normal operations. The Contractor shall cooperate with Owners in scheduling operations to minimize conflict and to facilitate Owner's usage.
PREVAILING WAGE RATES
The Contractor and subcontractors shall comply with State prevailing wage rates.
This contract or agreement calls for the construction of a public works within the meaning of the Illinois Prevailing Wage Act, 820 ILCS 130/0.01 et. seq. ("the Act"). The Act requires contractors and subcontractors to pay laborers, workers and mechanics performing services on public works projects no less than the current "prevailing rate of wages" (hourly cash wages plus amount for fringe benefits) in the county where the work is performed. The Illinois Department of Labor (IDOL) publishes the prevailing wage rates on its website at https:// www2.illinois.gov/idol/laws/rules-
3-23-001 conmed/pages/rates.aspx. IDOL revises the prevailing wage rates and the Contractor and subcontractors have an obligation to check the IDOL's web site for revisions to prevailing wage rates. For information regarding current prevailing wage rates, please refer to IDOL's website. All contractors and subcontractors rendering services under this contract shall comply with all requirements of the Act, including but not limited to, all wage requirements and notice and record keeping duties.
The Contractor and each subcontractor shall permit the Contractor’s employees to be interviewed on the job, during work hours, by compliance investigators of the Department or the Department of Labor.
TEMPORARY CONTROLS
A. Debris Control:
The Contractor shall initiate and maintain a specific program to prevent accumulation of debris at the construction site, storage and parking areas, or along access roads and haul roads.
B. Pollution Control:
The Contractor shall provide methods, means and facilities required to prevent contamination of soil, water or atmosphere by the discharge of noxious substances and sediments from construction operations.
The Contractor shall prevent harmful substances from entering public or private waters. If treatment of acid water is determined necessary by the Engineer and it is not specified within these special provisions, any water treated will be paid for in accordance with Article 109.04 of the Standard Specifications. The Contractor is liable for restoration of water quality and aquatic life if adversely affected by his/her actions. The Contractor shall maintain all such systems throughout the duration of the project.
The Contractor shall provide systems for control of atmospheric pollutants to prevent toxic concentrations of chemicals; to prevent harmful dispersal of pollutants into the atmosphere; and to comply with all permit requirements that may apply.
The Contractor must notify the Engineer immediately if buried wastes, liquid waste vessels or other potentially harmful materials are encountered. Necessary precautions should be taken to safeguard the area and to protect workers and the public until further directions are provided by the Engineer.
TRAFFIC CONTROL AND PROTECTION, SPECIAL
Description:
This work shall consist of the furnishing, installation, maintenance, relocation, and removal of work zone traffic control and protection in accordance with Section 701 of the Standard Specifications, as specified herein and in the plans, and as directed by the Engineer.
Access and Staging Area:
Access to the work areas i s provided by internal park trails shown in the plans. Construction traffic shall enter and exit the work areas at the locations shown in the plans. Any damage to sidewalks or the parking areas shall be repaired at no additional cost to the Department.
3-23-001
Contractor vehicles, equipment and materials shall be stored at the staging area identified in the plans or at locations acceptable to the Engineer. Any damage shall be restored to a condition equal to or better than the existing condition and to the satisfaction of the Engineer at no additional cost to the Department.
The Contractor shall not park any vehicles or block traffic on the public roadway. The Contractor shall provide appropriate Illinois Department of Transportation (IDOT) signage for vehicles leaving and entering the access locations. All public roadways shall be kept clean of all debris from site work, and all posted weight limits shall be respected.
Damage to existing roadways, parking lots and detour areas as a result of Contractor activity shall be repaired at no additional cost to the Department in accordance with standards set by the applicable roadway authority and as directed by the Engineer.
Public Convenience and Safety:
In addition to the requirements of Article 107.09 of the Standard Specifications, the Contractor shall place the Type III barricades at the entrance of the access when not being used by construction traffic.
Interference with traffic movements and inconvenience to owners of abutting property and public shall be kept to a minimum. Any delays or inconveniences to the Contractor by complying with these requirements shall be considered as incidental to the contract, and no additional compensation shall be allowed. During all construction operations, the Contractor shall be required to provide, erect, and maintain proper signage and barricades as necessary for safe traffic control.
The Contractor shall not be allowed to close any street to local traffic without the prior approval of the Engineer. The Contractor shall be required to provide all warning signs, barricades, traffic cones, flagmen and other appurtenances as the Engineer deems necessary to guarantee the safety of motorists and pedestrians for the duration of the project.
The Contractor shall restore the access and staging area to their original condition and grade to the satisfaction of the Engineer, and the Contractor shall remove all temporary traffic control devices at the completion of construction.
Method of Measurement:
This item of work will be measured on a lump sum basis.
Basis of Payment:
This work will be paid for at the contract lump sum price for TRAFFIC CONTROL AND
PROTECTION, SPECIAL.
STANDARD SPECIFICATIONS SECTION 101: DEFINITION OF TERMS - (revise and add the following articles as indicated)
Whenever in the contract documents the following terms are used, the intent of meaning shall be interpreted as follows:
Article 101.14 Department - (revise as indicated)
The Department of Natural Resources of the State of Illinois with its principal offices of business in Springfield.
3-23-001
Article 101.16 Engineer - (revise as indicated)
Kyle Schweizer, PE or other licensed Professional Engineer designated by The Director of the Office of Reality and Capital Planning of the Illinois Department of Natural Resources.
Article 101.35 Right of Way - (revise as indicated)
Right of way shall be replaced by construction limits, except when used in conjunction with right of way markers or highways.
Article 101.39 Roadway - (revise as indicated)
Roadway shall be replaced with Site. Slope limits of embankments will be replaced by proposed lines and grades.
STANDARD SPECIFICATIONS SECTION 107: LEGAL RELATIONS AND RESPONSIBILITY TO THE
PUBLIC - (revise and add the following articles as indicated)
Article 107.20 Protection and Restoration of Property - (add the following)
If any damages are incurred from the Contractor's operations to any properties outside of the construction limits, the Contractor shall be responsible for all repairs required to restore the damaged areas to their original condition regardless of the property involved. Any deviations from the limits of the construction area or requirements specified herein shall only be done with written approval of the Engineer pursuant to the following:
1. Written request from the Contractor, due to the limitations of the construction area as it affects his efficiency to complete the contract.
2. If the Engineer deems it necessary to deviate from the construction limits, as provided herein, to improve the work area for construction. The Engineer will not grant permission to enter the property owned by others.
Article 107.27 Insurance - (add the following)
All references to Sections or Articles in this specification shall be construed to mean specific Section or Article of the Standard Specifications for Road and Bridge Construction, adopted by the Department of Transportation.
The Contractor shall name the following entities as additional insured under the Contractor’s general liability insurance policy in accordance with Article 107.27:
1. Illinois Department of Natural Resources and its officers and employees, and agents.
The entities listed above and their officers, employees, and agents shall be indemnified and held harmless in accordance with Article 107.26 of the Standard Specifications.
Article 107.15 Dirt on Pavement or Structures – (add the following)
3-23-001 If the Contractor fails to clean the surface of State Park Road, Campground Lane, Lookout Point Lane, Meadowview Lane, or any other local street, highway, or parking lot area to the satisfaction of the Engineer at any time during the contract, the Engineer will notify the Contractor at which time the Contractor shall have 24 hours to begin cleaning the pavement to the satisfaction of the Engineer. If the Contractor fails to begin cleaning the pavement within 24 hours, an amount of $1,000.00 per day will be deducted from any monies due the Contractor. The requirements to satisfy the conditions stated herein shall be included in all other pay items.
Article 107.36 Dust Control – (add the following)
The Contractor shall provide positive methods and apply dust control materials to minimize raising dust from construction operations and provide positive means to prevent air-borne dust from dispersing into the atmosphere.
STANDARD SPECIFICATIONS SECTION 108: PROSECUTION AND PROGRESS - (revise the following articles as indicated)
Article 108.07 Suspension of Work - (add the following)
The Department hereby makes express provision for any suspensions which may result from disputes with property owners. The Engineer may suspend work for up to ten working days during the contract period without additional compensation to the Contractor, when such suspension is necessary to resolve disputes or problems with property owners. Multiple suspensions, less than ten working days each, shall not exceed ten working days total, without additional compensation.
The appropriation for the State's current fiscal year, from which the cost of this contract will be paid, will lapse at the end of the fiscal year, which is June 30. Continuation of this contract into the State's next fiscal year will be contingent upon the Illinois General Assembly re-appropriating funds for this contract.
If funds are not re-appropriated, this contract will be suspended or terminated on or before the appropriation lapse date.
STANDARD SPECIFICATIONS SECTION 201: CLEARING, TREE REMOVAL AND PROTECTION,
CARE AND REPAIR OF EXISTING PLANT MATERIAL - (revise or add the following as indicated)
Article 201.01 Description - (add the following)
(f) Trash and Debris Removal -- Trash and debris removal shall consist of the removal and disposal of all trash and debris that is within the work area to an approved landfill off-site. The area shall be graded, seeded, and mulched. No burning shall be allowed on the project site.
STEEL AND IRON MATERIALS
Buy America requirements apply to all steel and iron permanently incorporated into this project, unless an exception is permitted by the Department. The Contractor shall submit the mill analysis and certification as required in Article 106.01 of the Standard Specifications. The use of nondomestic steel and iron materials shall be approved by the Department prior to delivery of the material to the project. The cost and reasons for the use of nondomestic steel and iron shall be submitted with the request to use the nondomestic material. The cost of the nondomestic material is the value of the nondomestic steel and iron at the material is delivered to the site. The total cost of nondomestic iron and steel material shall not exceed 0.1% of the total contract cost or $2,500, whichever is greater.
3-23-001
WEEKLY BEP TRUCKING REPORTS
The Contractor shall submit a weekly report of Business Enterprise Program (BEP) trucks hired by the Contractor or subcontractors (i.e. not owned by the Contractor or subcontractors) that are used for BEP goal credit.
The report shall be submitted to the Engineer on a form provided by the Department within ten business days following the reporting period. The reporting period shall be Sunday through Saturday for each week reportable trucking activities occur.
Any costs associated with providing weekly BEP trucking reports shall be considered as included in the contract unit prices bid for the various items of work involved and no additional compensation will be allowed.
PERIMETER EROSION CONTROL BARRIER
Remove paragraph (b) of Article 280.04 and replace with the following:
"(b) Perimeter Erosion Barrier. The system consists of a continuous barrier placed adjacent to an area of construction and as shown in the plans to intercept a sheet flow of water borne silt and sediment and prevent it from leaving the construction area. The barrier shall be Sedimax-FR or equivalent filtration roll. Perimeter Erosion Barrier shall be free of PVC plastic netting."
PERMANENT SEEDING
Permanent Seeding, Mulching, and Fertilizing shall not be measured separately for payment and the cost shall be included in the cost of other pay items. Seeding shall be Class 4A as per Section 250 and mulch shall be Method 1 per Section 251. Fertilizer application shall be as described in Article 250.04.
Remove Article 250.09 and insert the following:
“Seeding, fertilizer nutrients, and agricultural limestone will not be measured for payment.”
Remove Article 250.10.
Remove Article 251.06 and insert the following:
“Mulch Methods 1,2,3,3A, and 4 will not be measured for payment.”
Remove Article 251.07.
HARDWARE
Hardware will not be paid separately. The cost shall be included in the cost of TREATED TIMBER.
Remove second paragraph of Article 507.17 (b).
Add the following to Article 507.17 “ (c) Hardware will not be measured for payment.”
3-23-001 Remove the following sentence from Article 507.18:
“All items classified as hardware will be paid for at the contract unit price per pound (kilogram) for
HARDWARE.”
Add the following sentence to Article 507.18:
“Costs of hardware required for the construction of Timber Structures shall be included in the cost of TREATED
TIMBER.”
PIPE HANDRAIL, SPECIAL
Description: This work shall consist of furnishing, powder coating, and erecting metal pipe handrails as shown in the plans and described herein.
Materials:
a. Pipe Handrail........................................................ASTM A 53 (A53) 1 1/4” Type S, Standard Pipe
b. Bent Rods.....................................................................................ASTM A 36 (A36) 3/8” Diameter
c. Plates and Other Structural Steel...................ASTM A 36 (A36) of dimensions shown in the plans
d. Lag Screws.....................ASTM A 307 (A307) 1/2” Diameter with length as indicated in the plans
e. Washers..........................................................................................................ANSI/ASME B18.22.1
f. Powder Coating.......................................................................................................Per Manufacturer
CONSTRUCTION REQUIREMETNS
General. Work shall be according to the details shown on the planes, and lines and grades shall not follow any defects in the structure. All welds facing pedestrian areas shall be ground smooth in the shop. The rails shall be straight and true to line, without kinks, bends, or warps, and straightened as necessary before shipment.
Submittals. Before beginning fabrication, the Contractor shall submit shop drawings to the Engineer according to Article 505.03 of the Standard Specifications. The Contractor shall also submit a color chart for selection of the railing color (fir green family) and powder coat manufacturer material specification, and cleaning and powder coating recommended procedures to the Engineer.
Pipe Handrail. The railings shall be standard (Schedule 40) seamless pipe and shall be continuous within each run of handrail indicated in the plans. In general landings do not have handrail.
Connection of railing to plates shall be welded as shown in the plans. Welded joints shall be continuous and weld surfaces shall be ground smooth.
Cleaning and powder coating of the railing shall be done according to the manufacturer’s recommended procedures.
Vent holes shall be drilled into the bottom of the handrail to prevent the accumulation of moisture. The holes shall be 1/4” in diameter.
Ends of pipe handrail shall return to the timber side rail. The returned handrail ends shall be capped with a 1/4” plate. The cap plate shall be welded to the pipe handrail.
Method of Measurement. This work will be measured for payment in place in feet. The length measured will be the along the pipe centerline from the end to end of pipe.
3-23-001
Powder Coating will not be measured for payment and shall be included in the cost of the pipe handrail.
Structural Steel, lag screws, washers, and other hardware required to mount the pipe handrail to the timber structures will not be measured for payment and shall included in the cost of the pipe handrail.
Drilling of vent holes, grinding of welds, and other fabrication work, either done in the shop or field required to mount the pipe handrail to the timber structure will not be measured for payment and shall be included in the cost of the pipe handrail.
Cap plate for pipe handrail returns and welding, painting, and installation of the cap plate onto the pipe handrail will not be measured for payment and shall be included in the cost of the pipe handrail.
Basis of Payment. This work will be paid for at the contract unit price per foot for PIPE HANDRAIL, SPECIAL.
COMPENSABLE DELAY COSTS (BDE)
Effective: June 2, 2017 Revised: April 1, 2019
Revise Article 107.40(b) of the Standard Specifications to read:
“ (b) Compensation. Compensation will not be allowed for delays, inconveniences, or damages sustained by the Contractor from conflicts with facilities not meeting the above definition; or if a conflict with a utility in an unanticipated location does not cause a shutdown of the work or a documentable reduction in the rate of progress exceeding the limits set herein. The provisions of Article 104.03 notwithstanding, compensation for delays caused by a utility in an unanticipated location will be paid according to the provisions of this Article governing minor and major delays or reduced rate of production which are defined as follows.
(1) Minor Delay. A minor delay occurs when the work in conflict with the utility in an unanticipated location is completely stopped for more than two hours, but not to exceed two weeks.
(2) Major Delay. A major delay occurs when the work in conflict with the utility in an unanticipated location is completely stopped for more than two weeks.
(3) Reduced Rate of Production Delay. A reduced rate of production delay occurs when the rate of production on the work in conflict with the utility in an unanticipated location decreases by more than 25 percent and lasts longer than seven calendar days.”
Revise Article 107.40(c) of the Standard Specifications to read:
“ (c) Payment. Payment for Minor, Major, and Reduced Rate of Production Delays will be made as follows.
(1) Minor Delay. Labor idled which cannot be used on other work will be paid for according to Article 109.04(b)(1) and (2) for the time between start of the delay and the minimum remaining hours in the work shift required by the prevailing practice in the area.
Equipment idled which cannot be used on other work, and which is authorized to standby on the project site by the Engineer, will be paid for according to Article 109.04(b)(4).
(2) Major Delay. Labor will be the same as for a minor delay.
Equipment will be the same as for a minor delay, except Contractor-owned equipment will be limited to two weeks plus the cost of move-out to either the
Weldon Springs Recreational Trail and Bridge Improvements DeWitt County, Illinois
3-23-001
Contractor’s yard or another job and the cost to re-mobilize, whichever is less.
Rental equipment may be paid for longer than two weeks provided the Contractor presents adequate support to the Department (including lease agreement) to show retaining equipment on the job is the most economical course to follow and in the public interest.
(3) Reduced Rate of Production Delay. The Contractor will be compensated for the reduced productivity for labor and equipment time in excess of the 25 percent threshold for that portion of the delay in excess of seven calendar days.
Determination of compensation will be in accordance with Article 104.02, except labor and material additives will not be permitted.
Payment for escalated material costs, escalated labor costs, extended project overhead, and extended traffic control will be determined according to Article 109.13.”
Revise Article 108.04(b) of the Standard Specifications to read:
“ (b) No working day will be charged under the following conditions.
(1) When adverse weather prevents work on the controlling item.
(2) When job conditions due to recent weather prevent work on the controlling item.
(3) When conduct or lack of conduct by the Department or its consultants, representatives, officers, agents, or employees; delay by the Department in making the site available; or delay in furnishing any items required to be furnished to the Contractor by the Department prevents work on the controlling item.
(4) When delays caused by utility or railroad adjustments prevent work on the controlling item.
(5) When strikes, lock-outs, extraordinary delays in transportation, or inability to procure critical materials prevent work on the controlling item, as long as these delays are not due to any fault of the Contractor.
(6) When any condition over which the Contractor has no control prevents work on the controlling item.”
Revise Article 109.09(f) of the Standard Specifications to read:
“ (f) Basis of Payment. After resolution of a claim in favor of the Contractor, any adjustment in time required for the work will be made according to Section 108. Any adjustment in the costs to be paid will be made for direct labor, direct materials, direct equipment, direct jobsite overhead, direct offsite overhead, and other direct costs allowed by the resolution. Adjustments in costs will not be made for interest charges, loss of anticipated profit, undocumented loss of efficiency, home office overhead and unabsorbed overhead
Weldon Springs Recreational Trail and Bridge Improvements DeWitt County, Illinois other than as allowed by Article 109.13, lost opportunity, preparation of claim expenses and other consequential indirect costs regardless of method of calculation.
The above Basis of Payment is an essential element of the contract and the claim cost recovery of the Contractor shall be so limited.”
Add the following to Section 109 of the Standard Specifications.
“ 109.13 Payment for Contract Delay. Compensation for escalated material costs, escalated labor costs, extended project overhead, and extended traffic control will be allowed when such costs result from a delay meeting the criteria in the following table.
Contract Type Cause of Delay Length of Delay
Working Days Article 108.04(b)(3) or Article 108.04(b)(4)
No working days have been charged for two consecutive weeks.
Completion Date
Article 108.08(b)(1) or Article 108.08(b)(7)
The Contractor has been granted a minimum two week extension of contract time, according to Article 108.08.
Payment for each of the various costs will be according to the following.
(a) Escalated Material and/or Labor Costs. When the delay causes work, which would have otherwise been completed, to be done after material and/or labor costs have increased, such increases will be paid. Payment for escalated material costs will be limited to the increased costs substantiated by documentation furnished by the Contractor. Payment for escalated labor costs will be limited to those items in Article 109.04(b)(1) and (2), except the 35 percent and 10 percent additives will not be permitted.
(b) Extended Project Overhead. For the duration of the delay, payment for extended project overhead will be paid as follows.
(1) Direct Jobsite and Offsite Overhead. Payment for documented direct jobsite overhead and documented direct offsite overhead, including onsite supervisory and administrative personnel, will be allowed according to the following table.
Original Contract Amount
Supervisory and Administrative Personnel
Up to $5,000,000 One Project Superintendent
Over $ 5,000,000 -up to $25,000,000
One Project Manager, One Project Superintendent or Engineer, and One Clerk
Over $25,000,000 -up to $50,000,000
One Project Manager, One Project Superintendent, One Engineer, and
Weldon Springs Recreational Trail and Bridge Improvements DeWitt County, Illinois
One Clerk
Over $50,000,000
One Project Manager, Two Project Superintendents, One Engineer, and One Clerk
(2) Home Office and Unabsorbed Overhead. Payment for home office and unabsorbed overhead will be calculated as 8 percent of the total delay cost.
(c) Extended Traffic Control. Traffic control required for an extended period of time due to the delay will be paid for according to Article 109.04.
When an extended traffic control adjustment is paid under this provision, an adjusted unit price as provided for in Article 701.20(a) for increase or decrease in the value of work by more than ten percent will not be paid.
Upon payment for a contract delay under this provision, the Contractor shall assign subrogation rights to the Department for the Department’s efforts of recovery from any other party for monies paid by the Department as a result of any claim under this provision. The Contractor shall fully cooperate with the Department in its efforts to recover from another party any money paid to the Contractor for delay damages under this provision.”
80384
Weldon Springs Recreational Trail and Bridge Improvements DeWitt County, Illinois
EROSION CONTROL BLANKET (BDE)
Effective: August 1, 2025
Revise Article 251.02 of the Standard Specifications to read:
“ 251.02 Materials. Materials shall be according to the following.
Item Article/Section
(a) Compost ............................................................................................................ 1081.05(b)
(b) Mulch ................................................................................................................. 1081.06(a)
(c) Chemical Mulch Binder ................................................................................ 1081.06(a)(3)
(d) Chemical Compost Binder ........................................................................... 1081.06(a)(4)
(e) Erosion Control Blanket .................................................................................... 1081.10(a)
(f) Wildlife Friendly Erosion Control Blanket .......................................................... 1081.10(b)
(g) Wire Staples ....................................................................................................... 1081.10(c)
(h) Wood Stakes ..................................................................................................... 1081.10(d)
(i) Turf Reinforcement Mat .................................................................................. 1081.10(e)”
Revise the first and second sentences of Article 251.04 of the Standard Specifications to read:
“ 251.04 Erosion Control Blanket. All erosion control blanket materials shall be placed on the areas specified within 24 hours of seed placement.”
Revise the second paragraph of Article 251.04 of the Standard Specifications to read:
“ After the area has been properly shaped, fertilized (when applicable), and seeded, the blanket shall be laid out flat, evenly, and smoothly, without stretching the material. The erosion control blanket shall be placed according to the manufacture’s recommendations.”
Revise the second sentence of Article 251.06(b) of the Standard Specifications to read:
“ Erosion control blanket, wildlife friendly erosion control blanket, and turf reinforcement mat will be measured for payment in square yards (square meters).”
Revise Article 251.07 of the Standard Specifications to read:
“ 251.07 Basis of Payment. This work will be paid for at the contract unit price per acre (hectare) for MULCH, of the method specified; and at the contract unit price per square yard (square meter) for EROSION CONTROL BLANKET, WILDLIFE FRIENDLY EROSION CONTROL BLANKET, or TURF REINFORCEMENT MAT.”
Revise first sentence of Article 280.04(h) of the Standard Specifications to read:
Weldon Springs Recreational Trail and Bridge Improvements DeWitt County, Illinois
“ This system consists of temporarily installing erosion control blanket or wildlife friendly erosion control blanket over areas that are to be reworked during a later construction phase.”
Revise Article 280.08(g) of the Standard Specifications to read:
“ (g) Temporary Erosion Control Blanket. Temporary erosion control blanket will be paid for at the contract unit price per square yard (square meter) for TEMPORARY EROSION CONTROL BLANKET or TEMPORARY WILDLIFE FRIENDLY EROSION CONTROL
BLANKET.
The work of removing, storing, and reinstalling the blanket over areas to be reworked more than once will not be paid for separately but shall be included in the cost of the temporary erosion control blanket or temporary wildlife friendly erosion control blanket.”
Revise Article 1081.10 of the Standard Specifications to read:
“ 1081.10 Erosion Control Blankets.