ATTACHMENT 2 - SOW Thomasville Exit Gate Replacement.pdf
PDF 578 KB Posted
- Attached to
- Thomasville Exit Gate Replacement Federal contract opportunity
- Solicitation number
- 70FBR422R00000008
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Questions-Responses.pdf | ||
| SOLICITATION - 70FBR422R00000008.pdf | ||
| ATTACHMENT 3 - Project Experience Questionnaire.pdf | ||
| ATTACHMENT 1 - General Decision No. GA20210166.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Statement of Work Region IV Thomasville FRC Exit Gate Demo/Replacement
Purpose: Demo existing B&B 25E Cable Beam Gate Arm and replace with a new HySecurity Strong Arm M30 P1 Operator
I. Project Objectives: Remove existing exit crash gate, replace with new HySecurity
Strong Arm M30 P1 gate and operator controls.
II. Scope of Work:
• Disconnect power and demolish and remove one B&B 25E Cable Gate Arm
Remove gate components;
Remove EM cabinet;
Remove traffic lights;
Cut/torch concrete foundations to needed depth
• Sawcut concrete curb/sidewalk and excavate to new foundation depth:
Run conduit to pivot foundation;
Trench across roadway for LV conduit to catch post foundation;
Install HySecurity StrongArm M30 P1 operator;
Run LV wire from guard house to new operator;
Sawcut and seal new vehicle loops;
Reconnect power to the new HySecurity StrongArm M30 P1 operator.
Program the controller to FEMA’s desired functionality
III. Specific Requirements/Task:
• Removal and disposal of (1) existing B&B 25E Cable Gate Arm
• Installation of (1) HySecurity StrongArm M30 P1 operator.
• Removal of existing power to the existing B&B 25E Cable Gate Arm.
and reconnect of power to the new HySecurity StrongArm M30 P1 operator.
• Programming operator to desired Functionality.
• Warrant parts and labor for a period of not less than 1 year from acceptance of the completed statement of work.
Existing gate to be removed
Gate Controls Open/Close for manual operation with in grounds loop detector for automatic egress.
Example of expectation of acceptable installation of new HySecurity M30 P1 Operator. This is the existing entrance gate.
Project Notes:
• Vendor shall be responsible for utility location services (Call-before-you-dig Free utility locate.
• Project shall be completed within specified contract Period of Performance.
Vendor shall provide ETA for procurement of new HySecurity StrongArm M30 P1 operator, ETA for removal of existing B&B 25E Cable Beam Gate Arm for the purpose of establishing a period of performance to complete the stated Scope of Work.
IV. Timeline and Period of Performance: This SOW’s period of performance shall be determined in the Solicitation and Award documents based on the lead time of the vendors ability to procure the HySecurity StrongArm M30 P1 gate.
Project shall be completed within specified contract Period of Performance.