Attachment 2 SOW_Parque Cr 20240318.pdf

PDF 471 KB Posted

Attached to
GAOA Parque Creek Road Repair
Solicitation number
1240LT24R0058
Issued by

About this file

This document is a Statement of Work (SOW) for the GAOA Parque Creek Road Repair project located on the Shoshone National Forest in the Wind River Ranger District.

The SOW outlines the scope of work, which includes repairing a slumped road segment, excavating and stockpiling or hauling material, placing special rock embankment and unclassified burrow material, and adding a 6-inch layer of roadway aggregate to provide the finished driving surface. The project also includes roadway reconditioning work on two additional road segments. The contractor must submit a traffic control plan, comply with Construction Contract Act Wage Determinations, and provide a work plan and schedule for approval prior to start of work. Quality control measures are required, including material gradation testing. The project is set aside for 100% Small Business Concerns, with a performance period ending September 30, 2025. The solicitation number is 1240LT24R0058, and the contracting agency is the USDA Forest Service, Region 2 - Rocky Mountain Region.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

GAOA Parque Creek Road Repair Statement of Work

C.1 Scope of Work:

Work will consist of repairing a road segment that has slumped down the embankment at ~MP

4.2 of NFSR 504. Material from the failed road prism will be excavated, sorted, and stockpiled for future use, or hauled to a designated waste area.

Two waste areas are anticipated for the project. The first waste area is located adjacent to the slide location and the second is approximately 1.15 miles from the slide location.

Special rock embankment will be placed in the excavation area followed by unclassified burrow material sourced from the excavated material, a 6” layer of roadway aggregate will be placed on top to provide the finished driving surface. See Sheet A2 of plans for detailed typical section.

Work will require hauling large quantities of material from commercial pit source(s), sorting and hauling excavated material, placing, and compacting special rock embankment, unclassified burrow material and aggregate under moisture-controlled conditions, and improving/maintaining haul route(s) and access roads on the National Forest Service Road System.

Minor clearing, grubbing, seeding, and erosion control work will be performed.

Finish grading, installation of culverts, slope grading, and misc. work will be included in the project.

The aggregate material must meet FS Gradation U or WYDOT Grade W ‘Gravel Road’ gradation (See Exhibit A: Gradation requirements for WYDOT Grade W ‘Gravel Road’ and FS Gradation U aggregate) at the end of this section. Arrangements must be made with local commercial sources to supply the quantity of material requested, and that the material can meet gradation requirements of this contract.

NFSR 285 – Wiggins Fork Work shall consist of roadway reconditioning for ~3.0 miles, see plan set and FSSS for detailed specifications.

NFSR 504 – Parque Cr Work shall consist of roadway reconditioning for ~4.2 miles. One cattle guard cleaning is anticipated and will be flagged by CO prior to work. Work shall also address slide repair at ~ MP 4.2, see plan set and FSSS for detailed specifications.

C1.1 Traffic Control:

Traffic control will be required on this task order (for Base items and Option Items). A traffic control plan that complies with the 2009 MUTCD will need to be submitted for approval by the CO at the preconstruction meeting. The traffic control plan will need to be approved before work can start. Traffic Control is a subsidiary obligation of the Contractor and is indirectly paid by line item ‘151.01 Mobilization.’

Post construction signs and traffic control devices in conformance with MUTCD and Forest Service EM 7100-15.

All required signs must be in place and approved prior to beginning work on project.

C.1.2 The work for this contract is considered construction and current Construction Contract Act Wage Determinations for Fremont County apply to the task order.

C.2 Project Location:

All work occurs on the South Zone of the Shoshone National Forest in the Wind River Ranger District. See location maps in plan set and below for detailed location information.

C.4 Pre-Work Meeting:

A pre-work meeting will be held prior to start of work.

C.5 Contract Time:

Work shall be completed by September 30th 2025, subject to such extensions as may be authorized.

C.5 Government Furnished Material:

There are no Government furnished materials.

C.6 Work Plan and Schedule:

The Contractor shall provide a work plan and schedule that demonstrates how the work will be completed and in what time frame at the pre work meeting. No work shall start until the work plan and schedule is approved by the CO.

E.1 Quality Control

Government inspections are for the sole benefit of the Government and does not relieve the contractor of responsibility for providing adequate quality control measures. The contractor shall develop and maintain an effective quality control program to ensure services are performed in accordance with specifications. The contractor shall develop and implement procedures to identify, prevent, and ensure non-recurrence of defective services or materials. A quality control plan will be required for all task orders.

Testing:

The government is requesting a minimum of 1 gradation verification test (including Plasticity Index (P.I.)) per material source used on this project to ensure that materials are within conformance of the contract specifications.

Material must be tested as per Section 301 and 703.05 of the FP-14 (AASHTO T-11, T-27, and AASHTO T-89) and have test results submitted to and approved by either the CO or the Zone Engineer before any material will be accepted onto the project.

If any subsequent gradation tests identify deficiencies in materials, the materials will NOT BE ACCEPTED onto the project until the contractor can ensure that all services and materials conform with contract specifications.

Contractor Testing is a subsidiary obligation of the Contractor and is indirectly paid by line item ‘302.01 Roadway Aggregate.’

J.1 Location Maps

Location Maps:

Wind River Ranger District Area Map NFSR 504 and NFSR 285: Parque Creek Road and Wiggins Fork (Horse Creek) Road Location Map

Wind River Ranger District Area Map:

NFSR 504 and NFSR 285: Parque Creek Road and Wiggins Fork (Horse Creek) Road Location Map: