Oil Water Separator Design/Install
Solicitation number
FA489726B0004
Issued by

About this file

This is a Statement of Work for the installation of an Oil Water Separator (OWS) system at Hush House No. 2, Mountain Home Air Force Base in Idaho. The project, identified as NEXGEN WT 14118044 and dated July 28, 2025, requires the contractor to design, fabricate, install, and commission a complete 300 GPM OWS system fully integrated into the existing facility infrastructure to handle wastewater from aircraft maintenance operations while ensuring compliance with EPA, DoD, and NPDES regulations.

The execution plan consists of four phases. Phase 1 (Pre-Construction Planning & Submittals) requires design drawings, product data, and specifications due within 20 calendar days of Notice to Proceed, including OWS components capable of 300 GPM flow rate with 99% removal of hydrocarbons larger than 20 microns using gravitational and coalescing plate separation, compliance with 40 CFR Parts 112 and 122, integrated sensors for oil accumulation detection beyond 15% tank volume threshold, smart maintenance alerts, scheduled solids extraction and dewatering systems, vapor-phase carbon adsorption units for VOC emissions, and explosion-proof venting systems. Tank construction must use corrosion-resistant 316L stainless steel or fiber reinforced polymer to withstand JP-8 and aviation-grade fuels, with epoxy-based interior coating. All submittals must meet FAR Buy American compliance. Phase 1 also requires a detailed work plan with timeline and major milestones, contractor employee roles and resumes, safety protocols, and disinfection/commissioning methodology including 72-hour hydrostatic testing, flow capacity validation, and EPA Method 1664 oil separation efficiency testing.

Phase 2 (Site Preparation) includes a geotechnical survey to verify subgrade strength and load-bearing capacity, excavation with a minimum 48-inch clearance below the 32-inch frost line per UFC 3-240-04A, and installation of compacted crushed stone base or reinforced slab. Phase 3 (System Installation) requires installation of the corrosion-resistant tank with internal epoxy coatings, integration of internal separation and retention systems, Schedule 80 PVC/stainless steel piping with 0.5–1% gravity grade, pre-filtration debris screens with mesh <100 microns, automatic inlet flow restrictors and emergency shutoff valves, Class I Division 2 explosion-proof electrical enclosures, remote monitoring and shutdown capability with redundant fail-safe mechanisms, and automatic level and hydrocarbon detection sensors with scheduled sludge removal and secondary vapor control measures. Phase 4 (Commissioning & Testing) requires 72-hour hydrostatic leak testing, 300 GPM flow capacity validation, controlled hydrocarbon injection testing per EPA Method 1664, NPDES compliance validation, state-level discharge permit acquisition, on-site operator training, submission of "As-Built" drawings and O&M manuals, and provision of a 1-year no-limit commercial warranty.

Technical standards include UFC 3-240-04A, 40 CFR Parts 112 and 122, NPDES Permit Requirements, FAR Buy American Compliance, NFPA and NEC standards for hazardous environment installation, Idaho State Environmental Codes, and MHAFB Environmental Specifications. Work authorization must be directed in writing by the Contracting Officer, with hours of operation Monday to Friday, 0700–1630 MST, excluding federal holidays. Key emergency contacts include Brad Newcomb (CES PM) at 208-828-2792, SSGT Samuel Donoso (WFSM R&O SME) at 208-828-4015, and WFSM Shop at 208-828-6538. Acceptance criteria require the system to achieve >99% hydrocarbon removal efficiency under load conditions, pass all hydrostatic, flow rate, and EPA discharge compliance tests, integrate fully into the facility without leaks or disruptions, and meet all safety, operational, and documentation requirements.

View the file

Other files

Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Page | 1 of 6

STATEMENT OF WORK CONSTRUCTION

PROJECT: Installation of Oil Water Separator System

LOCATION: Hush House No. 2, Mountain Home AFB

NEXGEN WT: 14118044

DATE: July 28, 2025

SCOPE OF WORK

General:

The contractor shall furnish all personnel, equipment, supervision, and materials necessary to design, fabricate, install, and commission a complete and functional Oil Water Separator (OWS) system that will be fully integrated into the existing facility infrastructure. This system must handle wastewater from aircraft maintenance operations, ensuring compliance with EPA, DoD, and NPDES regulations. Updating this facility to meet these standards will allow a more efficient and continuous way to test jets and their engines by reducing maintenance intervals between uses and reducing possible environmental hazards.

EXECUTION PLAN

Assess suitable area, excavate and install into existing facility infrastructure a 300 GPM OWS, that meets or exceeds any applicable regulations.

Phase 1:

Pre-Construction Planning & Submittals

1. Material and Design Submittals

a. Submit design drawings, product data, and specifications for but not limited to:

i. OWS system components

1. Capable of a flow rate of 300 GPM (Gallons per minute)

2. 99% Removal of free and dispersed hydrocarbons larger than 20 microns

3. Designed to allow gravitational and coalescing plate separation for optimal hydrocarbon phase separation.

4. Must meet or exceed 40 CFR Part 112 (Oil Pollution Prevention)

a. Must meet or exceed 40 CFR 122 (NPDES Permit

Regulations)

ii. Sensors and automation systems

Page | 2 of 6

1. Integrated sensors for real-time detection of oil accumulation beyond 15% tank volume threshold.

2. Smart alert for maintenance personnel when hydrocarbon level exceed environmental discharge limits.

3. Scheduled solids extractions and dewatering system to prevent sludge overloading.

4. Vapor-phase carbon adsorption units mitigate volatile organic compound (VOC) emissions.

5. Explosion-proof venting system for flammable vapor control.

iii. Coatings and structural materials

1. OWS tank will be made from corrosion-resistant steel, stainless steel (316L), or fiber reinforced polymer (FRP) tank construction to withstand exposure to JP-8, MIL-PRF-7808, MIL-PRF-83282, and MIL-PRF-23699 aviation-grade fuel and lubricants.

2. OWS interior will be epoxy-based, high-resistance coating for hydrocarbon and chemical exposure mitigation.

iv. Control system schematics

1. Will design, produce and implement working schematic of operating control system for OWS.

b. All products must meet FAR Buy American compliance.

c. All submittals are due within 20 calendar days of NTP.

2. Work Plan

a. Timeline with major milestones (mobilization, construction, commissioning)

b. Roles and responsibilities of project administration

i. During performance under contract, the contractor shall participate in administrative tasks inherent to the administration, surveillance, and oversight

c. Role and Resume of Contract Employees

i. All contract personnel must be able to read, write, speak, and understand

English fluently. Contract personnel shall present a neat appearance and be easily identified as a contract employee. The contractor shall obtain base identification, and vehicle passes for all employees who make frequent visits to or perform work on Mountain Home AFB in accordance with the current installation access/entry requirements. Contractor personnel are required to wear or prominently display installation identification while visiting or performing work on the installation. The contractor shall not employ persons for work on this contract, identified to the contractor by the CO as a potential threat to the health, safety, security, general well-being, or operational mission of the installation and its population. Each employee will be easily identified by wearing distinctive clothing bearing the name of the company or by wearing appropriate badges that contain

Page | 3 of 6 the company name and employee name(s). The contractor shall not employ any person who is an employee of the Government, if employing that person would create a conflict of interest. The contractor is cautioned that off-duty active military personnel hired under this contract may be subject to permanent change of station, change in duty hours, or deployment. Military Reservists and National Guard members may be subject to recall to active duty. The abrupt absence of these personnel could adversely affect the service provider’s ability to perform; however, their absence at any time shall not constitute an excuse for non-performance under this contract.

d. Safety protocols and training certificates (OSHA 30, HAZMAT, etc.)

3. Disinfection and Commissioning Plan

a. Methodology for system flush-out

b. Hydrostatic and operational testing strategy

i. Hydrostatic Testing: Verify tank integrity with 72-hour static water load test.

ii. Flow Capacity Testing: Confirm compliance with designed flow rates.

iii. Oil Separation Efficiency Testing: Conduct controlled hydrocarbon injection test and measure separation performance against EPA Method

1664 (IF APPLICABLE)

Phase 2:

Site Preparation

1. Geotechnical Survey

a. Verify subgrade strength and drainage profile

b. Determine suitability for OWS weight and excavation impact

i. Conduct geotechnical soil analysis to determine subsurface stability and load-bearing capacity.

2. Excavation & Ground Stabilization

a. Ensure maximum water level is below required frost depth per UFC 3-240-04A

i. MHAFB frost depth is 32”

b. Ensuring a minimum of 48-inches of clearance below the frost line. Install compacted crushed stone base or reinforced slab based on Geotech results

Phase 3:

System Installation

1. Tank and Mechanical Components

a. Install corrosion-resistant tank system (316L SS or FRP)

b. Internal epoxy coatings per hydrocarbon exposure spec

Page | 4 of 6

c. Integrate internal separation and retention system

2. Hydraulic & Piping Network

a. Schedule 80 PVC/stainless piping with 0.5–1% gravity grade

i. Prevent degradation due to petroleum-based products and wastewater, to include hydraulic fluids, jet fuel (JP-8, JP-10, etc.), grease, oils, soaps, and detergents.

b. Install pre-filtration debris screen and auto shut-off valves

i. Screen mesh to be <100 microns in filtration, to capture foreign object debris (FOD), jet blast residues, and metallic particulates.

ii. Automatic inlet flow restrictors and emergency shutoff valves to regulate surge flow conditions during fuel spill events. Install double-wall piping in critical zones to mitigate potential leaks.

3. Electrical & Automation Controls

a. Class I, Div 2 electrical enclosures

i. Provide explosion-proof electrical enclosure in hazardous locations.

b. Remote monitoring and shutdown capability

i. Implement redundant fail-safe mechanism throughout the system, with the ability to pause, shut down and de-energize the entire system as needed.

c. Level sensors, VOC monitoring, and maintenance alerts.

i. Automatic Level & Hydrocarbon Detection Sensors:

1. Integrated sensors for real-time detection of oil accumulation beyond 15% tank volume threshold.

2. Smart alerts for maintenance personnel when hydrocarbon levels exceed environmental discharge limits.

ii. Automatic Sludge Removal System:

1. Scheduled solids extraction & dewatering system to prevent sludge overloading.

iii. Secondary Vapor Control Measures:

1. Vapor-phase carbon adsorption units to mitigate volatile organic compound (VOC) emissions.

2. Explosion-proof venting system for flammable vapor control.

Phase 4:

Commissioning & Testing

1. System Testing

a. 72-hour hydrostatic leak testing

i. Verify tank integrity with a static water load test.

b. Flow capacity validation (300 GPM)

i. Confirm designed flow capacity of 300 GPM

c. Oil separation test per Method 1664 (if applicable)

Page | 5 of 6

i. Conduct controlled hydrocarbon injection test and measure separation against stablished standards.

2. Environmental Compliance

a. Conduct NPDES compliance validation for effluent discharge quality.

b. Obtain final discharge permits and agency signoffs.

i. Secure necessary State-level discharge permits if applicable.

c. Submit compliance certificate to base CE and contracting office

3. Training & Documentation

a. On-site training for operator teams

i. Provide comprehensive operator training on system operation, emergency shutdown, and routine maintenance.

b. Submit “As-Built” drawings and O&M manuals

c. Provide 1-year no-limit commercial warranty

TECHNICAL CRITERIA

1. All work shall conform to the latest editions of the following standards:

a. UFC 3-240-04A (Oil Water Separator Design)

b. 40 CFR Part 112 and 122 (EPA Regulations)

c. NPDES Permit Requirements

d. Federal Acquisition Regulation (FAR) Buy American Compliance

e. NFPA and NEC standards for hazardous environment installation

f. Idaho State Environmental Codes

g. 01 57 19 Temporary Environmental Controls_MHAFB Env Spec 20220614

(Attachment 1)

GENERAL PROVISIONS

1. Work Authorization: All work must be directed in writing by the Contracting Officer.

Hours of Operation: Monday to Friday, 0700–1630 MST. Federal holidays excluded.

2. Emergency Contact Numbers:

a. Fire Department: 911

b. CES PM: Brad Newcomb – 208-828-2792

c. WFSM R&O SME: Donoso, Samuel SSGT – 208-828-4015

d. WFSM Shop: 208-828-6538

Page | 6 of 6

ACCEPTANCE CRITERIA

1. The OWS system will be deemed successfully installed and operational when it meets the following criteria:

a. Achieves >99% hydrocarbon removal efficiency under load conditions.

b. Passes all hydrostatic, flow rate, and EPA discharge compliance tests

c. It is fully integrated into the facility without leaks or disruptions

d. Meets all safety, operational, and documentation requirements