Attachment 2 - SOW GAOA Escalante Ranger District Housing Upgrad.pdf
PDF 2 MB Posted
- Attached to
- GAOA Escalante Ranger District Housing Upgrade
- Solicitation number
- 1240LT24R0061
- Issued by
-
Department of Agriculture Forest Service
About this file
This document is a Statement of Work (SOW) for the GAOA Escalante Ranger District Housing Upgrade project on the Custer Gallantin National Forest. The project includes the remodel of an existing bunkhouse building, conversion of a storage building to a laundry facility, and window upgrades to two existing dwelling buildings. Optional bid items include the construction of four tiny homes. The work is to be completed while the buildings are unoccupied, and the contractor must coordinate staging and storage of materials with the government. The project has a start date of September 2024, with the base bid work to be completed in 120 calendar days and the optional tiny home work to be completed in 150 calendar days. The work is a 100% Small Business Set-Aside, with a site visit scheduled for August 27, 2024. The federal agency involved is the United States Forest Service.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SECTION C - DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK 000001-1
Section C - Description/Specifications/Statement of Work
GENERAL SPECIFICATIONS
GAOA-ESCALANTE RANGER DISTRICT HOUSING UPGRADES
100% Submittal – 5/29/2024
1.1 SCOPE OF CONTRACT
A. This project includes all work and materials necessary for the remodel of the existing Escalante bunkhouse building, conversion of an existing storage building to a laundry facility, and two window upgrades for two existing dwelling buildings.
B. BASE BID ITEM: Work is described in the following specifications and drawings and includes but is not limited to: demolition of walls, framing, carpet, vinyl flooring, siding, gypsum board, doors, hardware, plumbing fixtures, toilet accessories, plumbing, lighting, wiring, and appliances. Base Bid work includes wood wall framing, siding, gypsum board, doors and frames, windows and frames, minor window repairs, FRP, wall covering, carpeting, vinyl sheet flooring, concrete floor treatment, thermal and sound insulation, painting, toilets, faucets, lavatories, toilet and shower accessories, laundry room accessories, fans, new lighting, power, wiring, and all work for utilities at the lower housing site.
C. This project has the following possible Bid Options as shown in the drawings and specifications.
1. The schedule of Items for the bid options described in the drawings and specifications are as follows.
a. OPTIONAL BID ITEM (1)- All work for construction of one tiny home.
Work is described in the following specification and drawings and includes but is not limited to: foundation, wood wall framing, siding, gypsum board, doors and frames, windows and frames, FRP, wall covering, vinyl sheet flooring, thermal and sound insulation, roofing, painting, toilets, faucets, lavatories, toilet and shower accessories, lighting, power, plumbing, wiring, and all appliances as listed in drawings.
b. OPTIONAL BID ITEM (2)- All work for construction of one tiny home.
Work is described in the following specification and drawings and includes but is not limited to: foundation, wood wall framing, siding, gypsum board, doors and frames, windows and frames, FRP, wall covering, vinyl sheet flooring, thermal and sound insulation, roofing, painting, toilets, faucets, lavatories, toilet and shower accessories, lighting, power, plumbing, wiring, and all appliances as listed in drawings.
c. OPTIONAL BID ITEM (3)- All work for construction of one tiny home.
Work is described in the following specification and drawings and includes but is not limited to: foundation, wood wall framing, siding, gypsum board, doors and frames, windows and frames, FRP, wall covering, vinyl sheet flooring, thermal and sound insulation, roofing, painting, toilets, faucets, lavatories, toilet and shower accessories, lighting, power, plumbing, wiring, all appliances as listed in drawings, and all utility work at warehouse stie
SECTION C - DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK 000001-2
d. OPTIONAL BID ITEM (4)- All work for construction of one tiny home.
Work is described in the following specification and drawings and includes but is not limited to: foundation, wood wall framing, siding, gypsum board, doors and frames, windows and frames, FRP, wall covering, vinyl sheet flooring, thermal and sound insulation, roofing, painting, toilets, faucets, lavatories, toilet and shower accessories, lighting, power, plumbing, wiring, and all appliances as listed in drawings.
D. This project is to be completed while building is NOT occupied by the user. Coordination and phasing of work is required. Staging and storage of materials are to be coordinated with the government prior to the start of the project. Damages to any portion of the building(s) while this project is completed are to be repaired with matching finishes.
1.2 PROJECT LOCATION
A. The project is located in the Escalante Ranger District of the Dixie National Forest, Garfield County, UT. There are three different project locations.
B. Lower Housing: 60 W 100 N, Escalante, UT 84726
a. Bunkhouse remodel
b. Storage to laundry conversion
c. (1/2) Window upgrade
d. Optional Bid Items 1&2
C. Upper Housing: 87 E 200 N, Escalante, UT 84726
a. (2/2) Window upgrade
D. Warehouse (future contract): 165N 700 W, Escalante, UT 84726
a. Optional Bid Item 3&4
1.3 SITE INFORMATION AND LIMITATIONS
A. The following site conditions are considered incidental to the contract and the contractor will not be paid directly for any of the following items:
1. Construction site will not be closed to the public or Forest Service during construction. The contractor will be responsible for signing and limiting public and Forest Service access to the buildings.
2. There is existing electrical services for the site. Contractor shall have permission to use existing electrical service during construction. Contractor shall provide connections and extensions of services as required for construction operations.
3. Water is available at the site for construction purposes.
4. The Contractor shall provide temporary toilet facilities (porta-potty) at the site during all construction work.
5. Construction Hours- Hours of operation for the construction, demolition, excavation, and subsequent cleanup shall be only between the hours of 7:00 a.m.
and 7:00 p.m. Monday through Saturday.
SECTION C - DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK 000001-3
1.4 TEMPORARY ACCESS
A. Parking: Contractor may NOT use any stall of the surface parking during construction, but shall utilize street parking to minimize impact of Forest parking areas. Coordinate all other parking with the Contracting Officer’s Representative.
1.5 WASTE MANAGEMENT AND DISPOSAL
A. Waste Management Plan: Submit a copy of plan within 14 days of date established for the Notice to Proceed.
B. Processing waste material for salvage and recycling is encouraged.
C. The Contractor shall provide and maintain appropriate waste disposal containers or bins at the project site for the duration of the project construction. Verify with Contracting Officer for placement of disposal containers and bins on the project site.
D. Waste material and debris shall be picked up and deposited in the waste disposal bins on a daily basis. Containers must be emptied on a weekly basis unless more frequent emptying is needed.
E. Burning or burying of construction waste material on site will NOT be permitted.
Material shall be disposed of in accordance with the Waste Material Disposal specification.
1.6 TRAFFIC CONTROL AND CONSTRUCTION SIGNING
A. No work that endangers, interferes, or conflicts with traffic or access to work sites shall be performed until a plan for satisfactory warning and handling of traffic has been submitted by the contractor and approved by the COR and Local Transportation Authority. Construction signing for traffic control shall conform to the Manual of Uniform Traffic Control Devices (MUTCD). All traffic control signs will be placed in areas adequate for a truck pulling a fifth wheel trailer to be turned around. Contractor shall not be paid directly for this item, rather it will be considered incidental to other items of work listed in the Schedule of Items.
B. Provide project signs as indicated. Unauthorized signs are not permitted.
1. Identification Signs: Provide Project identification signs.
2. Temporary Signs: Provide other signs as indicated and as required informing public and individuals seeking entrance to Project.
3. Provide temporary, directional signs for construction personnel and visitors as required.
4. Maintain and touchup signs so they are legible at all times.
1.7 FIELD OFFICES, WORK CAMPS, STAGING AND STORAGE AREAS
A. Within 15 days of Notice to Proceed, Contractor shall submit a site plan showing proposed staging areas, access and parking locations, locations for field offices (if needed), and storage areas for review and approval by the CO.
SECTION C - DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK 000001-4
B. Areas for staging operations and storage of materials shall be approved by the CO. The Contractor must request in writing for approval from the CO to stage trailers (work) on site.
C. No overnight camping will be allowed on site.
1.8 INSPECTION OF WORKSITE
A. The contractor acknowledges they have taken the necessary steps to ascertain the nature and location of work, and have investigated and satisfied themselves as to the general and local conditions that can affect the work or its cost. Any failure of the contractor to take the actions described and acknowledged in this paragraph will not relieve the Contractor from the responsibility of estimating properly the difficulty and cost of successfully performing the work, or for proceeding to successfully perform the work without additional expenses to the government.
1.9 START DATE
A. September 2024
1.10 CONTRACT TIME
A. Base Bid: 120 Calendar Days
B. Option #1: 150 Calendar Days
C. Option #2: 150 Calendar Days
D. Option #3: 150 Calendar Days
E. Option #4: 150 Calendar Days
1.11 SPECIFICATIONS
A. The following specifications are attached. Some sections in the schedule of items refer to other sections not listed and are subsidiary to, or are included in payment for other pay items in this contract. These items are considered incidental and no additional compensation will be made.
SECTION 000501 - TINY HOMES
SECTION 011250 - MEASUREMENT AND PAYMENT
SECTION 011400 - WORK RESTRICTIONS
SECTION 011900 - MOBILIZATION
SECTION 012500 - UTILITY COMPANY COORDINATION
SECTION 013100 - PROJECT MANAGEMENT AND COORDINATION
SECTION 013300 - SUBMITTAL PROCEDURES
SECTION 014100 - QUALITY CONTROL
SECTION 017320 - SELECTIVE DEMOLITION
SECTION 017700 - CLOSEOUT PROCEDURES
SECTION C - DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK 000001-5
SECTION 022220 - STRUCTURAL EXCAVATION, BACKFILL AND
COMPACTION
SECTION 022450 - GRADING
SECTION 023701 - SEDIMENT AND EROSION CONTROL MEASURES
SECTION 024100 - WASTE MATERIAL DISPOSAL
SECTION 024134 - WORK INVOLVING LEAD-BASED PAINT (LBP)
SECTION 033000 - CAST-IN-PLACE CONCRETE
SECTION 033440 - CONCRETE STAIRS
SECTION 061000 - ROUGH CARPENTRY
SECTION 061533 - WOOD PATIO DECKING
SECTION 061600 - SHEATHING
SECTION 061753 - SHOP-FABRICATED WOOD TRUSSES
SECTION 062013 - EXTERIOR FINISH CARPENTRY
SECTION 062023 - INTERIOR FINISH CARPENTRY
SECTION 064023 - INTERIOR ARCHITECTURAL WOODWORK
SECTION 064116 - PLASTIC-LAMINATE-FACED ARCHITECTURAL
CABINETS
SECTION 064300 - WOOD STAIRS
SECTION 071113 - DAMPPROOFING SYSTEMS
SECTION 072100 - THERMAL INSULATION
SECTION 074113 - FORMED METAL ROOF PANELS
SECTION 076200 - SHEET METAL FLASHING AND TRIM
SECTION 079200 - JOINT SEALANTS
SECTION 081416 - FLUSH WOOD DOORS
SECTION 083513 - FOLDING ACCORDIAN DOORS
SECTION 085200 - ALUMINUM CLAD WOOD WINDOWS
SECTION 087100 - DOOR HARDWARE
SECTION 088000 - GLAZING
SECTION 089119 - FIXED LOUVERS
SECTION 090190 - MAINTENANCE REPAINTING
SECTION 092900 - GYPSUM BOARD
SECTION 096513 - RESILIENT BASE AND ACCESSORIES
SECTION 096516 - RESILIENT SHEET FLOORING
SECTION 096816 - SHEET CARPETING
SECTION 097700 - SPECIAL WALL FINISHES
SECTION 099113 - EXTERIOR PAINTING
SECTION 099123 - INTERIOR PAINTING
SECTION 099600 - HIGH-PERFORMANCE COATINGS
SECTION 102800 - TOILET AND BATH ACCESSORIES
SECTION 113100 - RESIDENTIAL APPLIANCES
SECTION 220517 - SLEEVES AND SLEEVE SEALS FOR PLUMBING PIPING
SECTION 220518 - ESCUTCHEONS FOR PLUMBING PIPING
SECTION 220523 - GENERAL-DUTY VALVES FOR PLUMBING PIPING
SECTION 220523.12 - BALL VALVES FOR PLUMBING PIPING
SECTION 220529 - HANGERS AND SUPPORTS FOR PLUMBING PIPING AND
EQUIPMENT
SECTION C - DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK 000001-6
SECTION 220553 - IDENTIFICATION FOR PLUMBING PIPING AND
EQUIPMENT
SECTION 221116 - DOMESTIC WATER PIPING
SECTION 221316 - SANITARY WASTE AND VENT PIPING
SECTION 221319 - SANITARY WASTE PIPING SPECIALTIES
SECTION 224100 - RESIDENTIAL PLUMBING FIXTURES
SECTION 224213.13 - WATER CLOSETS
SECTION 224216.13 - COMMERCIAL LAVATORIES
SECTION 233423 - HVAC POWER VENTILATORS
SECTION 238126.13 - MINI SPLIT-SYSTEM HEAT PUMPS
SECTION 260000 - COMMON WORK RESULTS FOR ELECTRICAL
SECTION 260519 - LOW-VOLTAGE ELECTRICAL POWER CONDUCTORS AND
CABLES
SECTION 260526 - GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS
SECTION 260533.13 - CONDUITS FOR ELECTRICAL SYSTEMS
SECTION 260923 - LIGHTING CONTROL DEVICES
SECTION 262726 - WIRING DEVICES
SECTION 262816 - ENCLOSED SWITCHES AND CIRCUIT BREAKERS
SECTION 312000 - EARTHWORK
SECTION 312100 - PROJECT SITE PREPARATION AND GRADING
SECTION 312225 - EXCAVATION & EMBANKMENT
SECTION 321204 - CRUSHED AGGREGATE BASE OR SURFACE COURSE
END OF SECTION C
August 2024
TINY HOMES 000501-1
USDA FOREST SERVICE, R4
GAOA-ESCALANTE RANGER DISTRICT HOUSING UPGRADES
SECTION 000501 - TINY HOMES
PART 1 - GENERAL
1.1 SUMMARY
A. This project includes all work and materials necessary for the remodel of the existing Escalante bunkhouse building, conversion of an existing storage building to a laundry facility, and two window upgrades for two existing dwelling buildings. Option items include all work necessary in the construction of tiny homes in Escalante.
1.2 MEASUREMENT AND PAYMENT
A. Bunkhouse- Measurement and Payment shall be as shown in the Schedule of Items.
B. Laundry Building- Measurement and Payment shall be as shown in the Schedule of Items.
C. Tiny Home - Measurement and Payment shall be Lump Sum Quantity (LSQ) as shown in the Schedule of Items for the tiny home constructed and completed ready for use.
Measurement shall include all work items within 5 feet of the roof line (including utilities within those limits). Payment will also include the work as described in the following specification and drawings and includes but is not limited to: earthwork, foundation, wood wall framing, siding, gypsum board, doors and frames, windows and frames, FRP, wall covering, vinyl sheet flooring, thermal and sound insulation, roofing, painting, toilets, faucets, lavatories, toilet and shower accessories, lighting, power, plumbing, interior electrical, mini split system, and all appliances as listed in drawings.
D. The project includes the following base bid items and bid option items as shown in the Schedule of Items:
1. Base Bid:
a. Bunkhouse, Laundry, Windows, and Lower Housing Site Work
2. Optional Bid -1
a. Tiny Home
3. Optional Bid -2
a. Tiny Home
4. Optional Bid -3
a. Tiny Home and Warehouse Site Work
5. Optional Bid -4
a. Tiny Home
TINY HOMES 000501-2
E. LSQ measurement for the building does not include landscaping (plants, irrigation, cobble, boulders and mulch), impact or city connection fees, or other utility connections.
F. Schedule of Values. The Contractor shall submit to the Government with the bid an initial Schedule of Values for the Work, allocating values as the contractor understands the work among all categories or portions of the Work to provide a complete and functional facility. The contractor shall include all work within 5’ of the building roof perimeter and concrete as described above. The Schedule of Values shall be prepared in such form and supported by data to substantiate its accuracy to the extent as the Government may require, and shall be based upon the latest cost information available to Contractor.
1.3 RELATED WORK
A. The work shall be in accordance with the contract documents.
B. The work shall be in accordance with the following specifications. The subsidiary specifications are referred to in the text by the Section designation only.
PART 2 - PRODUCTS - Not Applicable
PART 3 - EXECUTION
3.1 GENERAL
A. Work shall be completed in accordance with the contract drawings and specifications.
END OF SECTION 000501
MEASUREMENT AND PAYMENT 011250-1
GAOA-ESCALANTE RANGER DISTRICT HOUSING UPGRADES
SECTION 011250 - MEASUREMENT AND PAYMENT
PART 1 - GENERAL
1.1 SUMMARY
A. Measurement and payment for contract work will be made only for and under those pay items included in the Schedule of Items. All other work, labor, materials, equipment, and incidentals necessary to successfully complete the project will be considered as included in the payment for items shown. This section defines the method of measurements and basis of payment for work items listed in the Schedule of Items.
B. When more than one class, size, type, thickness, etc. is specified in the Schedule of Items for any pay item, suffixes will be added to the item number to differentiate between the pay items.
1.2 DETERMINATION OF QUANTITIES
A. The following measurements and calculations shall be used to determine contract quantities for payment.
1. For individual construction items, longitudinal and lateral measurements for area computations shall be made horizontally or corrected to horizontal measurement unless otherwise specified. Measurements for geotextiles, netting and erosion control blankets shall be along slope lines.
2. For excavation or embankment volumes, the average end area method shall be used to compute volumes. However, if in the judgment of the Contracting Officer (CO), the average end area method is impractical, measurement shall be made by volume in hauling vehicles or by other three-dimensional methods.
3. For Structures, they shall be measured according to neat lines shown on the drawings or as altered by the CO, in writing, to fit field conditions.
4. For items that are measured by the linear foot, such as pipe culverts, fencing, guardrail, piping, utilities, and underdrains, measurements shall be made parallel to the base or foundation upon which the structures are placed.
5. For aggregates weighed for payment, the tonnage shall not be adjusted for moisture content, unless otherwise provided for.
6. For standard manufactured items (such as fence, wire, plates, rolled shapes, pipe conduits) identified by gauge, weight, section dimensions, and so forth, such identifications shall be considered the nominal weights or dimensions. Unless controlled by tolerances in cited specifications, manufacturer's tolerances shall be accepted.
B. Earthwork Tolerances - Adjustments of horizontal or vertical alignment, within the tolerances specified in this contract, or shifts of balance points up to 100 feet shall be made by the contractor as necessary to produce the designed sections and to balance earthwork. Such adjustments shall not be considered as "Changes."
MEASUREMENT AND PAYMENT 011250-2
1.3 UNITS OF MEASUREMENT
A. Payment shall be by units defined and determined according to U.S. Standard measure and by the following:
1. Acre: Make longitudinal and transverse measurements for area computations horizontally.
2. 50lb Bag: Measurement will be for the actual number of 50lb bags of standard bentonite grout.
3. 94lb Bag: Measurement will be for the actual number of 94lb bags of standard cement or grout.
4. Cubic Yard (CY): A measurement computed by one of the following methods:
a. Excavation, Embankment, or Borrow. The measurement computed by the average end area method from measurements made longitudinally along a centerline or reference line.
b. Material in Place or Stockpile. The measurement computed using the dimensions of the in-place material.
c. Material in the Delivery Vehicle. The measurement computed using measurements of material in the hauling vehicles at the point of delivery.
Vehicles shall be loaded to at least their water level capacity. Leveling of the loads may be required when vehicles arrive at the delivery point.
5. Each (EA): One complete unit, which may consist of one or more parts.
6. Gallons (GAL): The quantity shall be measured by any of the following methods:
a. Measured volume in container.
b. Metered volume by approved metering system.
c. Commercially package volume.
7. Hour (HR): Measurement will be for the actual number of hours (or fraction thereof) ordered by the Contracting Officer and performed by the contractor.
8. Linear Foot (LF): Measurement of work along its length from point-to-point;
parallel to the base or foundation. Do not measure overlaps.
9. Lump Sum (LS): One complete unit.
10. Mile: Measured horizontally along the centerline of each roadway, approach, or ramp.
11. Pound (LB): For sacked or packaged material, measurement will be the net weight as packed by the manufacturer.
12. Square Foot (SF): Measured on a plane parallel to the surface being measured.
13. Square Yard (SY): Measured on a plane parallel to the surface being measured.
14. Ton: Measured as a short ton consisting of 2,000 pounds.
1.4 METHOD OF MEASUREMENT
A. One of the following methods of measurement for determining final payment is designated on the Schedule of Items for each pay item:
1. ACTUAL QUANTITIES (AQ) - These quantities are determined from actual measurements of completed work.
MEASUREMENT AND PAYMENT 011250-3
2. DESIGNED QUANTITIES (DQ) - These quantities denote the final number or units to be paid for under the terms of the contract. They are based upon the original design data available prior to advertising the project. Original design data include the preliminary survey information, design assumptions, calculations, drawings, and the presentation in the contract. Changes in the number of units shown in the Schedule of Items may be authorized under any of the following conditions:
a. As a result of changes in the work authorized by the CO.
b. As a result of the CO determining that errors exist in the original design that cause a pay item quantity to change by 15 percent or more.
c. As a result of the Contractor submitting to the CO a written request showing evidence of errors in the original design that cause a pay item quantity to change by 15 percent or more. The evidence must be verifiable and consist of calculations, drawings, or other data that show how the designed quantity is believed to be in error.
3. LUMP SUM QUANTITIES (LSQ) - These quantities denote one complete unit of work as required by or described in the contract, including necessary materials, equipment, and labor to complete the job. They shall not be measured.
4. STAKED QUANTITIES (SQ) - These quantities are determined from staked measurements prior to construction.
5. VEHICLE QUANTITIES (VQ) - These quantities are measured or weighed in hauling vehicles.
PART 2 - PRODUCTS (NOT APPLICABLE)
PART 3 - EXECUTION (NOT APPLICABLE)
END OF SECTION 011250
WORK RESTRICTIONS 011400-1
GAOA-ESCALANTE RANGER DISTRICT HOUSING UPGRADES
SECTION 011400 - WORK RESTRICTIONS
PART 1 - GENERAL
1.1 USE OF PREMISES
A. Use of Site: Limit use of premises to work in areas indicated. Do not disturb portions of site beyond areas in which the Work is indicated.
1. Government Occupancy: Allow for Government occupancy of site
2. Driveways and Entrances: Keep driveways and entrances serving premises clear and available to Occupants, Government employees, and emergency vehicles at all times. Do not use these areas for parking or storage of materials.
a. Schedule deliveries to minimize use of driveways and entrances.
b. Schedule deliveries to minimize space and time requirements for storage of materials and equipment on-site.
B. Use of Existing Building: Maintain existing building in a weathertight condition throughout construction period. Repair damage caused by construction operations.
Protect building and its occupants during construction period.
1.2 OCCUPANCY REQUIREMENTS
A. Full Government Occupancy: Government will occupy site and existing building during entire construction period. Cooperate with Government during construction operations to minimize conflicts and facilitate Government usage. Perform the Work so as not to interfere with Government operations.
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION (Not Used)
END OF SECTION 011400
MOBILIZATION 011900-1
GAOA-ESCALANTE RANGER DISTRICT HOUSING UPGRADES
SECTION 011900 - MOBILIZATION
PART 1 - GENERAL
1.1 SUMMARY
A. This item is intended to compensate the Contractor for operations including, but not limited to, those necessary for the movement of personnel, equipment, supplies, and incidentals to the project site; for payment of premiums for bonds and insurance for the project; and for any other work and operations which must be performed or costs that must be incurred incident to the initiation of meaningful work at the site and for which payment is not otherwise provided for under the contract.
1.2 MEASUREMENT AND PAYMENT
A. The measurement shall be lump sum for mobilization. Payment shall be as follows:
1. Bond premiums will be reimbursed after receipt of the evidence of payment.
2. 50% of the lump sum, not to exceed 5% of the original contract amount, will be paid following completion of 5% of the original contract amount not including mobilization and bond premiums.
3. Payment of the remaining portion of the lump sum, up to 10% of the original contract amount, will be paid following completion of 10% of the original contract amount not including mobilization and bond premiums.
4. Any portion of the lump sum in excess of 10% of the original contract amount will be paid after final acceptance.
5. Progress payments for mobilization and preparatory work shall be subject to retainage.
PART 2 - PRODUCTS (NOT USED)
PART 3 - EXECUTION (NOT USED)
END OF SECTION 011900
UTILITY COMPANY COORDINATION 012500-1
GAOA-ESCALANTE RANGER DISTRICT HOUSING UPGRADES
SECTION 012500 - UTILITY COMPANY COORDINATION
PART 1 - GENERAL
1.1 SUMMARY
A. The work of this section consists of coordination with utility companies for connection to their systems.
1.2 RELATED WORK SPECIFIED ELSEWHERE
A. Section 017700 – Closeout Procedures
1.3 COORDINATION
A. EDIT AS NEEDED.
B. Electrical: Garkane Energy Cooperative: 435-676-3023
C. Communications telephone: South Central Utah Telephone 435-676-0509 (not required)
D. Water (culinary and sewer): Escalante City: 435-826-4644
1.4 FEES FOR UTILITY COMPANIES
A. T.ap and connection fees: Tap and connection fees are to be paid by the contractor.
1.5 PAYMENT TO UTILITY COMPANIES
A. Payment to Utility Companies:
1. Where work is to be performed by the utility company that requires payment to the utility company, payment will be made by the Government.
2. Where the Contractor identifies the need for work by the utility company that requires payment and no known contractual arrangement by Government and utility company has been made in advance, the Contractor shall immediately notify the Contracting Officer.
B. Payment to Utility Companies:
1. Any costs associated with utility installation as a component of construction, including, but not limited to, distribution lines, distribution equipment, and meter assemblies, will be the responsibility of the contractor. This does not include tap fees. All utility use charges associated with permanent utility installation shall be the responsibility of the Contractor until Substantial Completion.
2. At least two weeks prior to the anticipated date of Substantial Completion, prepare a written request to the Contracting Officer for all desired pertinent Government
UTILITY COMPANY COORDINATION 012500-2
information for each utility, such as the billing name, billing address, and contact information. Once this information is furnished by the Government to the Contractor, the Contractor shall be responsible for contacting each utility company and changing the billing information to the name of the Government, with pertinent information as described above, on or after the date of Substantial Completion.
1.6 INSPECTION
A. Permits are not anticipated at this time.
B. If needed, comply with utility company requirements for inspections before final connection is made.
1.7 PERMITS
A. Permits are not anticipated at this time.
B. Any needed applications for utility connection permits will be completed by the Government. Copies will be provided to the Contractor.
1.8 MEASUREMENT AND PAYMENT
A. No separate payment will be made for the work included under this section; rather payment shall be considered to be included in the items of work listed in the Schedule of Items.
PART 2 – PRODUCTS – not used
PART 3 – EXECUTION – not used
END OF SECTION 012500
PROJECT MANAGEMENT AND COORDINATION 013100-1
GAOA-ESCALANTE RANGER DISTRICT HOUSING UPGRADES
SECTION 013100 - PROJECT MANAGEMENT AND COORDINATION
PART 1 - GENERAL
1.1 SUMMARY
A. This section includes certain administrative provisions for managing and coordinating construction operations, including but not limited to the following:
1. General project coordination.
2. Coordination drawings.
3. Conservation.
4. Administrative and supervisory personnel.
5. Conferences and meetings.
6. Cleaning and protection.
1.2 GENERAL PROJECT COORDINATION
A. Coordination of Trades: Coordinate construction operations included in the various sections of the Specifications to provide an efficient and orderly installation of each part of the Work. Coordinate construction operations included under different sections of the Specifications that depend on each other for proper installation, connection or operation.
1. Schedule construction operations in the sequence required to obtain the best results where the installation of one part of the Work depends on installation of other components before or after that part.
2. Coordinate installation of different components to provide maximum accessibility for required maintenance, service, testing and repair.
3. Accommodate items scheduled for later installation.
B. Notification: Where necessary, prepare and distribute memoranda to each party involved, outlining special procedures required for coordination. When applicable, include notices, reports and meeting minutes as part of the memoranda.
C. Administrative Procedures: Coordinate scheduling and timing of administrative procedures with other construction activities to avoid conflicts and promote orderly progress of the Work. Administrative procedures include but are not limited to the following:
1. Preparation of schedules.
2. Installation and removal of temporary facilities.
3. Delivery and processing of submittals.
4. Progress meetings.
5. Project closeout activities.
1.3 COORDINATION DRAWINGS
PROJECT MANAGEMENT AND COORDINATION 013100-2
A. Prepare coordination drawings where careful coordination is needed for installation of products and materials fabricated by separate entities, and prepare coordination drawings where limited space availability necessitates maximum utilization of the space for efficient installation of different components.
1. Show the relationship of components shown on separate shop drawings.
2. Indicate required installation sequences.
3. Provide vertical and horizontal dimensions necessary to locate each component and avoid conflicts within the space.
4. Comply with requirement specified in Division 1 Section "Submittal Procedures."
B. Refer to Division 23 and Division 26 for specific coordination drawing requirements for mechanical and electrical installations.
1.4 CONSERVATION
A. Coordinate construction activities to ensure that operations are carried out with consideration given to conservation of energy, water and materials.
1. Salvage materials and equipment involved in performance of, but not actually incorporated in the Work
1.5 CONFERENCES AND MEETINGS
A. Preconstruction Conference: The Contracting Officer shall schedule a preconstruction conference before starting construction at a time and place convenient to the Contractor.
Conference shall review responsibilities and personnel assignments.
1. Attendees: Participants at the conference shall be familiar with the project, shall be authorized to conclude matters relating to the Work, and shall minimally include representatives of the following parties:
a. Contracting Officer.
b. Contracting Officer’s Representative
c. Contractor.
d. Major subcontractors.
e. Major suppliers.
f. Other concerned parties.
2. Agenda: Subjects for discussion shall include items of significance that could effect progress, including but not limited to the following:
a. Tentative construction schedule.
b. Critical work sequencing.
c. Designation of responsible personnel.
d. Procedures for processing field decisions and Change Orders.
e. Procedures for processing Applications for Payment.
f. Distribution of Contract Documents.
g. Submittal of Shop Drawings, Product Data, and Samples.
h. Preparation of Record Documents.
PROJECT MANAGEMENT AND COORDINATION 013100-3
i. Use of the premises.
j. Parking availability.
k. Office, work, and storage areas.
l. Equipment deliveries and priorities.
m. Safety procedures.
n. First aid.
o. Security.
p. Housekeeping and progress cleaning.
q. Working hours.
3. Reporting: No later than five (5) calendar days after the conference, the Contractor shall distribute minutes of the conference to each party present and to other concerned parties, including the Contracting Officer.
B. Progress Meetings: The Contracting Officer's Representative shall conduct progress meetings at the Project Site at regular intervals, but no more than 2 week intervals, unless approved by the COR. Dates of meetings shall be coordinated with preparation of the payment request.
1. Attendees: In addition to the Contractor's and Contracting Officer's representatives, each subcontractor, supplier, or other entity concerned with current progress or involved in planning, coordination, or performance of future activities shall be represented. All participants at the conference shall be familiar with the Project and authorized to conclude matters relating to the Work.
2. Agenda: Review and correct or approve minutes of the previous progress meeting.
Review other items of significance that could affect progress. Include topics for discussion as appropriate to the status of the Project.
a. Contractor's Construction Schedule: Review progress since the last meeting.
Determine where each activity is in relation to the Contractor's Construction Schedule, whether on time or ahead or behind schedule. Determine how construction behind schedule will be expedited; secure commitments from parties involved to do so. Discuss whether schedule revisions are required to insure that current and subsequent activities will be completed within the Contract Time.
b. Review the present and future needs of each entity present, including but not limited to the following:
1) Interface requirements.
2) Time.
3) Sequences of operations.
4) Status of submittals.
5) Deliveries.
6) Off-site fabrication.
7) Access.
8) Site utilization.
9) Temporary facilities and controls.
10) Hours of work.
11) Hazards and risks.
PROJECT MANAGEMENT AND COORDINATION 013100-4
12) Housekeeping and progress cleaning.
13) Quality and work standards.
14) Change Orders.
15) Documentation of information for payment requests.
16) Updating of Record Documents.
3. Reporting: No later than five (5) calendar days after each meeting, the Contractor shall distribute minutes of the meeting to each party present and to other concerned parties, including the Contracting Officer. Include a brief summary, in narrative form, of progress since the previous meeting and report.
4. Schedule Updating: The Contractor shall revise the Contractor's Construction Schedule after each progress meeting where revisions to the schedule have been made or recognized. The revised schedule shall be issued concurrently with the report of each meeting.
1.6 MEASUREMENT AND PAYMENT
A. No separate payment will be made for the work included under this section; rather payment shall be considered to be included in the items of work listed in the Schedule of Items.
PART 2 - PRODUCTS (Not applicable)
PART 3 - EXECUTION
3.1 GENERAL COORDINATION PROVISIONS
A. Inspection of Conditions: Prior to installations, require the installer of each major component to inspect both the substrate and conditions under which work is to be performed.
1. Do not proceed until unsatisfactory conditions have been corrected in an acceptable manner.
2. Coordinate temporary enclosures with required inspections and tests to minimize the necessity of uncovering completed construction for that purpose.
B. Construction in Progress: Keep construction in progress, and adjoining materials in place, clean during handling and installation. Apply protective coverings where required for protection from damage or deterioration.
C. Completed Construction: Clean completed construction, and provide maintenance, as frequently as necessary to prevent damage or soiling or other deterioration through the remainder of the construction period. Adjust and lubricate operable components as necessary to assure operability without damage.
D. Limiting Exposures: Supervise construction operations to prevent exposure of any part of construction, completed or in progress, to harmful, dangerous, damaging or otherwise deleterious conditions during the construction period. Such conditions include but are not limited to the following:
PROJECT MANAGEMENT AND COORDINATION 013100-5
1. Excessive static or dynamic loading.
2. Excessive internal or external pressures.
3. Excessively high or low temperatures.
4. Thermal shock.
5. Excessively high or low humidity.
6. Pollution and air contamination.
7. Water or ice.
8. Chemicals and solvents.
9. Light.
10. Radiation.
11. Puncture.
12. Abrasion.
13. Heavy traffic.
14. Soiling, staining, and corrosion.
15. Bacteria.
16. Rodent and inset infestation.
17. Combustion.
18. Electrical current.
19. High-speed operation.
20. Improper lubrication.
21. Unusual wear or other misuse.
22. Contact between incompatible materials.
23. Destructive testing.
24. Misalignment.
25. Excessive weathering.
26. Unprotected storage.
27. Improper shipping or handling.
28. Theft or vandalism.
END OF SECTION 013100
SUBMITTAL PROCEDURES 013300-1
GAOA-ESCALANTE RANGER DISTRICT HOUSING UPGRADES
SECTION 013300 - SUBMITTAL PROCEDURES
PART 1 - GENERAL
1.1 SUMMARY
A. This Section includes administrative and procedural requirements for submitting Shop Drawings, Product Data, Samples, and other miscellaneous submittals. See Table 013300-1 for a summary of required submittals.
B. See other specification section within this package for additional requirements on submittal.
1.2 SUBMITTAL PROCEDURES
A. Coordination: Coordinate preparation and processing of submittals with performance of construction activities.
1. Coordinate transmittal of different types of submittals for related parts of the Work so processing will not be delayed because of need to review submittals concurrently for coordination.
a. The Contracting Officer (CO) reserves the right to withhold action on a submittal requiring coordination with other submittals until related submittals are received.
B. Processing Time: Allow enough time for submittal review, including time for re-submittals, as follows. Time for review shall commence on CO's receipt of submittal.
1. Initial Review: Allow 14 days for initial review of each submittal. Allow additional time if processing must be delayed to permit coordination with subsequent submittals. CO will advise Contractor when a submittal being processed must be delayed for coordination.
2. If intermediate submittal is necessary, process it in same manner as initial submittal.
3. Allow 14 days for processing each re-submittal.
4. No extension of the Contract Time will be authorized because of failure to transmit submittals enough in advance of the Work to permit processing.
C. Identification: Place a permanent label or title block on each submittal for identification.
1. Indicate name of firm or entity that prepared each submittal on label or title block.
2. Provide a space on label or beside title block to record Contractor's review and approval markings and action taken by CO.
3. Include the following information on label for processing and recording action taken:
a. Project name.
b. Date.
SUBMITTAL PROCEDURES 013300-2
c. Name and address of Contractor.
d. Name of manufacturer.
e. Unique identifier, including revision number.
f. Number and title of appropriate Specification Section.
g. Drawing number and detail references, as appropriate.
h. If more than one item is shown on submittal sheet, identify item.
D. Deviations: Highlight, encircle, or otherwise identify deviations from the Contract Documents on submittals.
E. Additional Copies: Unless additional copies are required for final submittal, and unless CO observes noncompliance with provisions of the Contract Documents, initial submittal may serve as final submittal.
F. Use for Construction: Use only final submittals with mark indicating action taken by CO in connection with construction.
1.3 MEASUREMENT AND PAYMENT
A. No separate measurement and/or payment will be made for this section. Payment shall be included with work shown in the schedule of items.
PART 2 - PRODUCTS
2.1 ACTION SUBMITTALS – (Submittals requiring CO approval)
A. General: Prepare and submit Action Submittals required by individual Specification Sections.
1. Number of Copies: Submit three copies of each submittal, unless otherwise indicated. CO will return two copies. Mark up and retain one returned copy as a Project Record Document.
B. Product Data: Collect information into a single submittal for each element of construction and type of product or equipment.
1. If information must be specially prepared for submittal because standard printed data are not suitable for use, submit as Shop Drawings, not as Product Data.
2. Mark each copy of each submittal to show which products and options are applicable.
3. Include the following information, as applicable:
a. Manufacturer's written recommendations.
b. Manufacturer's product specifications.
c. Manufacturer's installation instructions.
d. Manufacturer's catalog cuts.
e. Wiring diagrams showing factory-installed wiring.
f. Compliance with recognized trade association standards.
g. Compliance with recognized testing agency standards.
SUBMITTAL PROCEDURES 013300-3
C. Shop Drawings: Prepare Project-specific information, drawn accurately to scale. Do not base Shop Drawings on reproductions of the Contract Documents or standard printed data.
1. Preparation: Include the following information, as applicable:
a. Dimensions.
b. Identification of products.
c. Fabrication and installation drawings.
d. Roughing-in and setting diagrams.
e. Wiring diagrams showing field-installed wiring, including power, signal, and control wiring.
f. Notation of dimensions established by field measurement.
2. Wiring Diagrams: Differentiate between manufacturer-installed and field-installed wiring.
D. Contractor's Construction Schedule: The contractor shall submit a Construction Schedule, for approval by CO, in accordance with the contract provisions within 5 day of commencement of work.
E. Samples: Prepare physical units of materials or products, including the following:
1. Samples for Initial Selection: Submit manufacturer's color charts consisting of units or sections of units showing the full range of colors, textures, and patterns available.
2.2 INFORMATIONAL SUBMITTALS – (Submittals NOT requiring CO approval)
A. General: Prepare and submit Informational Submittals required by other Specification Sections.
1. Number of Copies: Submit three copies of each submittal, unless otherwise indicated. CO will not return copies.
2. Certificates and Certifications: Certificates and certifications shall be signed by an officer or other individual authorized to sign documents on behalf of that entity.
3. Test and Inspection Reports: Comply with requirements in Section 014100 "Quality Control."
B. Material Test Reports: Prepare reports written by a qualified testing agency, on testing agency's standard form, indicating and interpreting test results of material for compliance with requirements.
C. Field Test Reports: Prepare reports written by a qualified testing agency, on testing agency's standard form, indicating and interpreting results of field tests performed either during installation of product or after product is installed in its final location, for compliance with requirements.
D. Maintenance Data: Prepare written and graphic instructions and procedures for operation and normal maintenance of products and equipment.
SUBMITTAL PROCEDURES 013300-4
E. Manufacturer's Instructions: Prepare written or published information that documents manufacturer's recommendations, guidelines, and procedures for installing or operating a product or equipment. Include name of product and name, address, and telephone number of manufacturer.
PART 3 - EXECUTION
3.1 GENERAL
A. Review each submittal and check for compliance with the Contract Documents. Note corrections and field dimensions. Mark with approval stamp before submitting to CO.
B. Approval Stamp: Stamp each submittal with a uniform, approval stamp. Include Project name and location, submittal number, Specification Section title and number, name of reviewer, date of Contractor's approval, and statement certifying that submittal has been reviewed, checked, and approved for compliance with the Contract Documents.
C. CO will not review submittals that do not bear Contractor's approval stamp and will return them without action.
D. Submittals not required by the Contract Documents will not be reviewed and may be discarded.
E. Substitutions – Whenever materials, products, and equipment are listed by name or brand in the specifications and/or on the drawings, it is used as a measure of quality, utility, or standard. If the Contractor prefers to use any other brand or manufacturer of same quality, appearance and utility to that specified, he shall request substitution as provided below, not less than 30 days before the planned installation of the item. The Contracting Officer will approve or disapprove the request for substitution.
F. Requests for substitutions will only be considered if contractor submits the following:
1. Complete technical data including drawings, complete performance specifications, test data, samples and performance tests of the article proposed for substitution.
Submit additional information if required by Contracting Officer. All items in the above information shall be circled, tagged, or marked in some way to indicate all deviations or differences which the proposed item differs from the originally specified item.
2. Similar data as above for item originally specified. All items shall be marked to identify where/how the proposed substitution will differ.
3. A statement by the Contractor that the proposed substitution is in full compliance with the contract documents, applicable codes, and laws.
4. The Contractor shall be responsible for any effect upon related work in the project for any substitution and shall pay any additional costs generated by any substitutions.
3.2 SUBMITTAL SCHEDULE – Submittals shall be made as required by and called for in the drawings and specifications. The following table is a summary of the required
SUBMITTAL PROCEDURES 013300-5
submittals for the project - the table is to assist the Contractor and may not be all inclusive
– additional submittals may be required by specific specifications:
TABLE 013000-1
Spec.
Section Section Title Subse ction Required Submittal
C General Specifications 1.6A Traffic Control Plan 013300 Submittal Procedures 2.1D Construction Schedule 014100 Quality Control 1.3 A Contractor quality control plan 014100 Quality Control 1.3 B Permits, Licenses, and Certificates 014100 Quality Control 1.3 C Test and inspection reports 014100 Quality Control 1.3 D As-Built drawings 017320 Selective Demolition 1.4A Schedule of Selective Demolition 017320 Selective Demolition 1.4B Hazardous Waste Manifests 017700 Closeout Procedures 1.2A Product Data 017700 Closeout Procedures 1.2B Contractor’s list of Incomplete
Items 017700 Closeout Procedures 1.2C Certified List of Incomplete Items 023701 Sediment & Erosion Control
Measures 1.2A Sediment & Erosion Control Plan
024134 Work Involving Lead Based Paint 1.3A Health and Safety Plan 024134 Work Involving Lead Based Paint 1.3B BRP Records 033000 Cast-in-Place Concrete 1.3A Product Data 033000 Cast-in-Place Concrete 1.3B Design Mix 033000 Cast-in-Place Concrete 1.3C Shop Drawings 033000 Cast-in-Place Concrete 1.3D Material Test Reports 061000 Rough Carpentry 1.3.A Product Data 061533 Wood Patio Decking 1.2A Product Data 061533 Wood Patio Decking 1.3A Material Certificates 061533 Wood Patio Decking 1.3B Evaluation Reports 061600 Sheathing 1.2.A Product Data 061753 Shop Fabricated Wood Trusses 1.4.A Shop Drawings, Qualification 061753 Shop Fabricated Wood Trusses 1.4.B Product and Material Certificates 062013 Exterior Finish Carpentry 1.2A Product Data 062023 Interior Finish Carpentry 1.2A Product Data 064023 Interior Architectural Woodwork 1.2A Product Data 064116 Cabinets 1.2A-
C Product Data, Shop Drawings, and Samples 064300 Wood Stairs 1.2A Shop Drawings 071113 Dampproofing Systems 1.2A Product Data 072100 Thermal Insulation 1.2A Product Data 074113 Metal Roof Panels 1.3A Product Data 074113 Metal Roof Panels 1.3B Shop Drawings 074113 Metal Roof Panels 1.3D Mtnc Data for O&M Manuals 076200 Sheet Metal Flashing and Trim 1.3A Product Data and Shop Drawings 079200 Joint Sealants 1.2.A Product Data
SUBMITTAL PROCEDURES 013300-6
Spec.
Section Section Title Subse ction Required Submittal
081416 Flush Wood Doors 1.2A Product Data 083513 Folding Accordion Doors 1.2A Product Data 085200 Aluminum Clad Wood Windows 1.4.A-
B Product Data- Warranty
087110 Door Hardware 1.2A- C
Product Data, Hardware Schedule, Keying Schedule
088000 Glazing 1.3A Product Data 089119 Fixed Louvers 1.2A Product Data 090190 Maintenance Repainting 1.4A Product Data 092900 Gypsum board 1.2.A Product Data 096513 Resilient Base and Accessories 1.2A Product Data 096516 Flooring 1.2A Product Data 096516 Flooring 1.2B Samples 096516 Flooring 1.2C Maintenance Data 097700 Special Wall Finishes 1.2A Product Data 097700 Special Wall Finishes 1.2B O&M Manuels 099113 Exterior Paints and Coatings 1.3A-
B Product Data, Samples
099123 Interior Paints and Coatings 1.3A- B
Product Data, Samples
099600 High Performance Coatings 1.3A- B
Product Data, Samples
102800 Toilet and Bath Accessories 1.2A Product Data 113100 Residential Appliances 1.2A Product Data 113100 Residential Appliances 1.4A Warranty 220517 Sleaves and Seals for Plumbing 1.2A Product Data 220518 Escutcheons for Plumbing 1.2A Product Data 220523 Ball Valves for Plumbing 1.2A Product Data 220529 Hangers and Supports for Plumbing 1.2A Product Data 220529 Hangers and Supports for Plumbing 1.2B Welding Certificates 220553 Identification for Plumbing 1.2A Product Data 221116 Domestic Water Piping 1.2A Product Data 221316 Sanitary Waste…