Attachment 2 - Schedule of Supplies (CLIN stucture).xlsx

XLSX spreadsheet 22 KB Posted

Attached to
Camp Bullis Containerized Showers Federal contract opportunity
Solicitation number
FA301625Q6003
Issued by
Department of the Air Force Air Education and Training Command

About this file

This document is an attachment containing a Schedule of Supplies and Contract Line Item Numbers (CLINs) for a federal contract opportunity. The key details are:

The contract is for three (3) containerized shower units at Joint Base San Antonio (JBSA) Camp Bullis, Texas. The contract has a base year with four one-year option periods. The CLINs cover the lease, maintenance, and additional cleaning days for the shower units. If the government decides to purchase the units, the contract provides the formula for determining the remaining purchase price after lease payments. The total estimated value for the base year and option years is not provided. The related federal contract opportunity is a Request for Quote (RFQ) with a submission deadline of November 12, 2024 and a question/information request deadline of November 7, 2024. The contracting agency is the Department of the Air Force, Air Education and Training Command.

View the file

Other files for this federal contract opportunity

Other files attached to Camp Bullis Containerized Showers, newest first.
File Type Posted
24Q6003 amend 0002 CO Signed.pdf PDF
24Q6003 amend 0001 CO signed.pdf PDF
Attachment 1 - Statement of Work (SOW) dated 18 Oct 24.docx DOCX document
Combo Solicitation BOLC Showers.docx DOCX document
Attachment 3 - Clauses and Provisions.pdf PDF
Attachment 4 Containerized Shower Projected Timeline.xlsx XLSX spreadsheet

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1

ProductQTYUnitUnit PriceTotal Amount
CLIN 0001 – Base year POP IAW with SOW

Three (3) Each Containerized Shower Units

Total Purchase/60 months = Monthly Unit Lease Price

12Months$ - 0
CLIN 0002 – Containerized Shower Units Maintenance IAW SoW (Atch1)64days$ - 0
CLIN 0003 – Additional days (estimated); estimated additional cleaning needed outside of BOLC classes schedule; these days are infrequent and are on a as needed basis.
The number of estimated days is based on historical usage during the last period of performance and a predictable number of future events. Funded Upon Use Not to Exceed 30 days1day
CLIN 0004 - Delivery and Installation

Generic Name Description: Containerized Shower Unit

Delivery/Install1each$ - 0
$ - 0
Total Value for Current POP$ - 0
*INFO CLIN 0001 – If the Government decides to purchase during this POP, Container Purchase Price at is determined by subtracting the purchase price for each container minus the lease paid during this period of performance.

Container purchase price: $XXX,XXX Total Amount Paid Towards Lease: ($XX,XXX) Remaining purchase price: $XXX,XXX

1ea
Option Year 1QTYUnitUnit PriceTotal Amount
CLIN 1001 – Option Year 1 POP IAW with SOW

Three (3) Each Containerized Shower Units

Total Purchase/60 months = Monthly Unit Lease Price12Months$ - 0
CLIN 1002 – Containerized Shower Units Maintenance IAW SoW (Atch1)64days$ - 0
CLIN 1003 – Additional days (estimated); estimated additional cleaning needed outside of BOLC classes schedule; these days are infrequent and are on a as needed basis.
The number of estimated days is based on historical usage during the last period of performance and a predictable number of future events. Funded Upon Use Not to Exceed 30 days30days$ - 0
$ - 0
Total Value for Current POP$ - 0
*INFO CLIN 1001 – If the Government decides to purchase during this POP, Container Purchase Price at is determined by subtracting the purchase price for each container minus the lease paid during this period of performance.

Container purchase price: $XXX,XXX Total Amount Paid Towards Lease: ($XX,XXX)

Remaining purchase price: $XXX,XXX1ea
Option Year 2QTYUnitUnit PriceTotal Amount
CLIN 2001 – Option Year 2 POP IAW with SOW

Three (3) Each Containerized Shower Units

Total Purchase/60 months = Monthly Unit Lease Price

12Months$ - 0
CLIN 2002 – Containerized Shower Units Maintenance IAW SoW (Atch1)64days$ - 0
CLIN 2003 – Additional days (estimated); estimated additional cleaning needed outside of BOLC classes schedule; these days are infrequent and are on a as needed basis.
The number of estimated days is based on historical usage during the last period of performance and a predictable number of future events. Funded Upon Use Not to Exceed 30 days30days$ - 0
$ - 0
Total Value for Current POP$ - 0
*INFO CLIN 2001 – If the Government decides to purchase during this POP, Container Purchase Price at is determined by subtracting the purchase price for each container minus the lease paid during this period of performance.

Container purchase price: $XXX,XXX Total Amount Paid Towards Lease: ($XX,XXX)

Remaining purchase price: $XXX,XXX1ea
Option Year 3QTYUnitUnit PriceTotal Amount
CLIN 3001 – Option Year 3 POP IAW with SOW

Three (3) Each Containerized Shower Units

Total Purchase/60 months = Monthly Unit Lease Price

12Months$ - 0
CLIN 3002 – Containerized Shower Units Maintenance IAW SoW (Atch1)64days$ - 0
CLIN 3003 – Additional days (estimated); estimated additional cleaning needed outside of BOLC classes schedule; these days are infrequent and are on a as needed basis.
The number of estimated days is based on historical usage during the last period of performance and a predictable number of future events. Funded Upon Use Not to Exceed 30 days30days$ - 0
$ - 0
Total Value for Current POP$ - 0
*INFO CLIN 3001 – If the Government decides to purchase during this POP, Container Purchase Price at is determined by subtracting the purchase price for each container minus the lease paid during this period of performance.

Container purchase price: $XXX,XXX Total Amount Paid Towards Lease: ($XX,XXX)

Remaining purchase price: $XXX,XXX1ea
Option Year 4QTYUnitUnit PriceTotal Amount
CLIN 4001 – Option Year 4 POP IAW with SOW

Three (3) Each Containerized Shower Units

Total Purchase/60 months = Monthly Unit Lease Price

12Months$ - 0
CLIN 4002 – Containerized Shower Units Maintenance IAW SoW (Atch1)64days$ - 0
CLIN 4003 – Additional days (estimated); estimated additional cleaning needed outside of BOLC classes schedule; these days are infrequent and are on a as needed basis.
The number of estimated days is based on historical usage during the last period of performance and a predictable number of future events. Funded Upon Use Not to Exceed 30 days30days$ - 0
$ - 0
Total Value for Current POP$ - 0
* INFOCLIN 4001 – If the Government decides to purchase during this POP, Container Purchase Price at is determined by subtracting the purchase price for each container minus the lease paid during this period of performance.

Container purchase price: $XXX,XXX Total Amount Paid Towards Lease: ($XX,XXX)

Remaining purchase price: $01ea
$ - 0

File details come from the government source that posted it. Updated .