Attachment 2 Schedule of Items.xlsx
XLSX spreadsheet 38 KB Posted
- Attached to
- GAOA Facilities, Barracks Inyo NF
- Solicitation number
- 1240BH26Q0078
- Issued by
-
Department of Agriculture Forest Service
About this file
This is a Schedule of Items pricing template for the Forestwide Facilities Improvement Project at Inyo National Forest under solicitation 1240BH26Q0037. The document outlines a comprehensive facilities maintenance and repair program across multiple forest service locations including Mt. Whitney, Helitack, White Mountain, Rock Creek, Mammoth, Lee Vining, and Crestview compounds.
The base scope includes eight main work categories: exterior painting and staining (approximately 33,950 square feet across 16 buildings), interior painting (approximately 18,850 square feet across 13 buildings), roofing repair and replacement (approximately 11,100 square feet plus miscellaneous vent stack and awning work), pest exclusion measures (approximately 1,636 linear feet across 8 locations), window and door repair/replacement (11 lump sum items including realignment, weatherstripping, and sealing), siding replacement (360 square feet), building inspection and structural repairs (3 lump sum items), and trailer pad construction with associated utility installations at three compounds (Mammoth, Crestview, and Lee Vining). The solicitation also includes 19 optional line items (Options 1-19) covering targeted repairs at specific facilities such as updated electrical/water/sewer services, interior renovations, flooring replacement, and exterior improvements at individual barracks and houses. All pricing is to be submitted on a unit basis (per square foot, linear foot, or lump sum), with responses requiring complete pricing for each item and sub-item to be acceptable. Responses exceeding $35,000 require bonds, and those exceeding $150,000 require a bid bond equal to 20 percent of total price.
View the file
Other files
Show all 14
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sched B
| SCHEDULE OF ITEMS |
| SECTION B |
| PROJECT | Forestwide Facilities Improvement Project | ||||
| UNIT | Inyo National Forest | ||||
| SOL # | 1240BH26Q0037 | ||||
| ITEM NO. | DESCRIPTION | UNIT | QTY | UNIT PRICE | TOTAL PRICE |
| BASE - See Project Technical Specifications & Schedule of Work for specific site/building information | |||||
| 0001 | Exterior Painting/Staining | ||||
| Exterior Painting, Mt Whitney Barracks | SF | 2000 | $ - 0 | ||
| Exterior Painting, Mt Whitney House | SF | 1700 | $ - 0 | ||
| Exterior Painting, Helitack Barracks | SF | 2000 | $ - 0 | ||
| Exterior Painting, White Mtn. Fire Barracks | SF | 2000 | $ - 0 | ||
| Exterior Painting, White Mtn. Rec Barracks | SF | 2000 | $ - 0 | ||
| Exterior Painting, Smokey Club House | SF | 1700 | $ - 0 | ||
| Exterior Painting, Rock Creek House | SF | 1400 | $ - 0 | ||
| Exterior Painting, Rock Creek Exterior Bathroom | SF | 1000 | $ - 0 | ||
| Exterior Painting, Mammoth Rec Barracks | SF | 2000 | $ - 0 | ||
| Exterior Painting, Mammoth Fire Barracks | SF | 2000 | $ - 0 | ||
| Exterior Painting, 103 Ritter House | SF | 1700 | $ - 0 | ||
| Exterior Painting, 105 Ritter House | SF | 1700 | $ - 0 | ||
| Exterior Painting, 106 Ritter House | SF | 1700 | $ - 0 | ||
| Exterior Painting, 1 Ediza House | SF | 1700 | $ - 0 | ||
| Exterior Painting, 1 Murphy House | SF | 2000 | $ - 0 | ||
| Exterior Painting, 6 Ruby House | SF | 1700 | $ - 0 | ||
| Exterior Staining, Crestview Cabin 1120 | SF | 1000 | $ - 0 | ||
| Exterior Staining, Crestview Cabi 1119 | SF | 1000 | $ - 0 | ||
| Exterior Staining, Crestview Cabin 1122 | SF | 1000 | $ - 0 | ||
| Exterior Painting, Lee Vining Recreation Barracks | SF | 2000 | $ - 0 | ||
| Exterior Painting, Lee Vining Fire Barracks | SF | 2000 | $ - 0 | ||
| Exterior Painting, 1012 Lee Vining House | SF | 2500 | $ - 0 | ||
| Exterior Painting, 1006 Lee Vining Big House | SF | 2300 | $ - 0 | ||
| Exterior Painting, 1025 Lee Vining Small House | SF | 900 | $ - 0 | ||
| Exterior Painting, Lee Vining Bathhouse | SF | 450 | $ - 0 | ||
| 0002 | Interior Painting | ||||
| Interior Painting, Mt Whitney Barracks | SF | 2000 | $ - 0 | ||
| Interior Painting, Helitack Barracks | SF | 2000 | $ - 0 | ||
| Interior Painting, White Mtn. Fire Barracks | SF | 2000 | $ - 0 | ||
| Interior Painting, White Mtn. Rec Barracks | SF | 2000 | $ - 0 | ||
| Interior Painting, Rock Creek House | SF | 1400 | $ - 0 | ||
| Interior Painting, Rock Creek Exterior Bathroom | SF | 1000 | $ - 0 | ||
| Interior Painting, Mammoth Rec Barracks | SF | 2000 | $ - 0 | ||
| Interior Painting, Mammoth Fire Barracks | SF | 2000 | $ - 0 | ||
| Interior Painting, 1 Murphy House | SF | 2000 | $ - 0 | ||
| Interior Painting, Lee Vining Recreation Barracks | SF | 2000 | $ - 0 | ||
| Interior Painting, Lee Vining Fire Barracks | SF | 2000 | $ - 0 | ||
| Interior Painting, 1012 Lee Vining House | SF | 2500 | $ - 0 | ||
| Interior Painting, Lee Vining Bathhouse | SF | 450 | $ - 0 | ||
| Repair and Paint Front Porch, 1025 Lee Vining Small House | SF | 1 | $ - 0 | ||
| 0003 | Roofing Repair/Replacement | ||||
| Roof Replacement, Helitack Barracks | SF | 1800 | $ - 0 | ||
| Roof Replacement, White Mtn. Recreation Barracks | SF | 3400 | $ - 0 | ||
| Roof Replacement, Smokey Club House | SF | 1600 | $ - 0 | ||
| Roof Replacement, 1012 Lee Vining House | SF | 2500 | $ - 0 | ||
| Roof Replacement, 1025 Lee Vining Small House | SF | 900 | $ - 0 | ||
| Roof Replacement, Crestview Cabin 1120 | SF | 600 | $ - 0 | ||
| Roof Replacement, Helitack Fire Office, Storage Shed | SF | 600 | $ - 0 | ||
| Minor Roof Repair, 106 Ritter House | SF | 200 | $ - 0 | ||
| Minor Roof Repair, 1 Murphy House | SF | 200 | $ - 0 | ||
| Install New Vent Stacks, Rock Creek Barracks, East | LS | 5 | $ - 0 | ||
| Install New Vent Stacks, Rock Creek Barracks, West | LS | 5 | $ - 0 | ||
| Repair Front Porch Awning | LS | 1 | $ - 0 | ||
| Front Porch Roof Replacement, Mammoth Rec Barracks | SF | 200 | $ - 0 | ||
| 0004 | Pest Exclusion | ||||
| Install Exterior Pest Exclusion Measures, Mammoth Recreation Barracks | LF | 200 | $ - 0 | ||
| Install Exterior Pest Exclusion Measures, Mammoth Fire Barracks | LF | 200 | $ - 0 | ||
| Install Exterior Pest Exclusion Measures, Crestview Cabin 1120 | LF | 200 | $ - 0 | ||
| Install Exterior Pest Exclusion Measures, Crestview Cabin 1122 | LF | 200 | $ - 0 | ||
| Install Exterior Pest Exclusion Measures, Lee Vining Fire Barracks | LF | 200 | $ - 0 | ||
| Install Exterior Pest Exclusion Measures, Lee Vining Rec Barracks | LF | 200 | $ - 0 | ||
| Install Exterior Pest Exclusion Measures, Lee Vining Bathhouse | LF | 36 | $ - 0 | ||
| Install Exterior Pest Exclusion Measures, Crestview Cabin 1119 | LF | 200 | $ - 0 | ||
| 0005 | Window & Door Repair/Replacement | ||||
| Realign Door, Lee Vining Bathhouse | LS | 1 | $ - 0 | ||
| Replace Front Door, Crestview Cabin 1122 | LS | 1 | $ - 0 | ||
| Replace Back Door, Crestview Cabin 1122 | LS | 1 | $ - 0 | ||
| Replace Back Door, 1012 Lee Vining House | LS | 1 | $ - 0 | ||
| Install New Screen Door, 1025 Lee Vining Small House | LS | 1 | $ - 0 | ||
| Install Weather Stripping, Crestview Cabin 1120 | LS | 2 | $ - 0 | ||
| Install Weather Stripping, Crestview Cabin 1119 | LS | 2 | $ - 0 | ||
| Install Weather Stripping, Mammoth Fire Barracks | LS | 2 | $ - 0 | ||
| Install Weather Stripping, Lee Vining Fire Barracks | LS | 2 | $ - 0 | ||
| Install Weather Stripping, Lee Vining Bathhouse | LS | 1 | $ - 0 | ||
| Seal Windows, Mammoth Fire Barracks | LS | 2 | $ - 0 | ||
| 0006 | Siding Replacement | ||||
| Replace Siding, Mammoth Rec Barracks | SF | 320 | $ - 0 | ||
| Replace Siding, 1025 Lee Vining Small House | SF | 40 | $ - 0 | ||
| 0007 | Building Inspection/Structural Repair | ||||
| Building Inspection, Crestview Cabin 1121 | LS | 1 | $ - 0 | ||
| Wall and Structural Repairs, Crestview 1120 | LS | 1 | $ - 0 | ||
| Demolish & Remodel Bathrooms, Mammoth Rec Barracks | LS | 2 | $ - 0 | ||
| 0008 | Trailer Pads | ||||
| Construct New Concrete Trailer Pads, Mammoth RD Compound | LS | 3 | $ - 0 | ||
| Install New Water Service, Mammoth RD Compound | LS | 3 | $ - 0 | ||
| Install New Sewer Service, Mammoth RD Compound | LS | 3 | $ - 0 | ||
| Install New Electrical Service, Mammoth RD Compound | LS | 3 | $ - 0 | ||
| Construct New Concrete Trailer Pads, Crestview FS Compound | LS | 4 | $ - 0 | ||
| Install New Water Service, Crestview FS Compound | LS | 4 | $ - 0 | ||
| Install New Sewer Service, Crestview FS Compound | LS | 4 | $ - 0 | ||
| Install New Electrical Service, Crestview FS Compound | LS | 4 | $ - 0 | ||
| Construct New Concrete Trailer Pads, Lee Vining RS Compound | LS | 7 | $ - 0 | ||
| Base Subtotal | $ - 0 | ||||
| OPTIONAL ITEMS - See Project Technical Specifications & Schedule of Work for specific site/building information | |||||
| 0001A | Option 1, Lee Vining RS Compound Trailer Pads | ||||
| Update Electrical Service | LS | 7 | $ - 0 | ||
| Install New Water Service | LS | 7 | $ - 0 | ||
| Install New Sewer Service | LS | 7 | $ - 0 | ||
| Option 1 Subtotal | $ - 0 | ||||
| 0002A | Option 2, 1012 Lee Vining House Repairs | ||||
| Replace Ceiling Tiles | SF | 2500 | $ - 0 | ||
| Update Lighting | LS | 14 | $ - 0 | ||
| Install New Bathroom Fan/Light Combo | LS | 2 | $ - 0 | ||
| Update Toilets | LS | 1 | $ - 0 | ||
| Replace Faucets | LS | 4 | $ - 0 | ||
| Replace Kitchen Counter | LS | 1 | $ - 0 | ||
| Replace Double Sink | LS | 1 | $ - 0 | ||
| Replace Deck | LS | 1 | $ - 0 | ||
| Repair and Paint Front Steps | LS | 1 | $ - 0 | ||
| Replace Vent Stacks | LS | 5 | $ - 0 | ||
| Install Weather Stripping | LS | 3 | $ - 0 | ||
| Replace Windows | LS | 1 | $ - 0 | ||
| Flooring Replacement | SF | 1500 | $ - 0 | ||
| Flooring Replacement | SF | 1000 | $ - 0 | ||
| Replace Bathroom Ceiling Heater | LS | 1 | $ - 0 | ||
| Option 2 Subtotal | $ - 0 | ||||
| Option 3, Mt Whitney Barracks Repairs | |||||
| 0003A | Paint and Repair Main Entrance Ramp | LS | 1 | $ - 0 | |
| Replace Bathroom Sinks | LS | 2 | $ - 0 | ||
| Replace Back Stairs | LS | 2 | $ - 0 | ||
| Replace Kitchen Counter | LS | 1 | $ - 0 | ||
| Install New Bathroom Fan/Light Combo | LS | 2 | $ - 0 | ||
| Replace Ceiling Tiles | SF | 1600 | $ - 0 | ||
| Roof Replacement | SF | 1600 | $ - 0 | ||
| Option 3 Subtotal | $ - 0 | ||||
| 0004A | Option 4, Helitack Barracks Repairs | ||||
| Replace Sink (Westside) | LS | 1 | $ - 0 | ||
| Replace Kitchen Counter | LS | 1 | $ - 0 | ||
| Replace Double Sink | LS | 2 | $ - 0 | ||
| Replace Faucet | LS | 2 | $ - 0 | ||
| Replace Vent Hood | LS | 2 | $ - 0 | ||
| Install New Bathroom Fan/Light Combo | LS | 2 | $ - 0 | ||
| Paint Main Entrance Stairs and Backdoor Stairs | LS | 2 | $ - 0 | ||
| Paint Main Entrance Ramp and Railing | LS | 1 | $ - 0 | ||
| Option 4 Subtotal | $ - 0 | ||||
| 0005A | Option 5, White Mtn. Recreation Barracks Repairs | ||||
| Replace Kitchen Counter | LS | 1 | $ - 0 | ||
| Replace Double Sink | LS | 1 | $ - 0 | ||
| Replace Faucet | LS | 1 | $ - 0 | ||
| Flooring Replacement | SF | 1580 | $ - 0 | ||
| Flooring Replacement | SF | 500 | $ - 0 | ||
| Paint Bathroom Floors | SF | 200 | $ - 0 | ||
| Replace Ceiling Tiles | LS | 240 | $ - 0 | ||
| Replace Exterior Doors | LS | 3 | $ - 0 | ||
| Replace 90 degree Downspouts | LS | 3 | $ - 0 | ||
| Install New Bathroom Fan/Light Combo | LS | 2 | $ - 0 | ||
| Option 5 Subtotal | $ - 0 | ||||
| 0006A | Option 6, Mammoth Recreation Barracks Repairs | ||||
| Install New Bathroom Fan/Light Combo | LS | 2 | $ - 0 | ||
| Bedroom Expansion | LS | 1 | $ - 0 | ||
| Paint Back Entrance Railing | LS | 1 | $ - 0 | ||
| Flooring Replacement | SF | 1000 | $ - 0 | ||
| Flooring Replacement | SF | 800 | $ - 0 | ||
| Replace Ceiling Tiles | SF | 1800 | $ - 0 | ||
| Option 6 Subtotal | $ - 0 | ||||
| 0007A | Option 7, Lee Vining Recreation Barracks Repairs | ||||
| Replace Ceiling Tiles | SF | 1600 | $ - 0 | ||
| Update Lighting | LS | 16 | $ - 0 | ||
| Install Door Trim | LS | 1 | $ - 0 | ||
| Install Screen Door | LS | 1 | $ - 0 | ||
| Option 7 Subtotal | $ - 0 | ||||
| 0008A | Option 8, Mammoth Fire Barracks Repairs | ||||
| Replace Kitchen Counter | LS | 1 | $ - 0 | ||
| Replace Cabinet Door | LS | 1 | $ - 0 | ||
| Repair Cabinet Door | LS | 1 | $ - 0 | ||
| Replace Window Trim | LS | 2 | $ - 0 | ||
| Replace Kitchen Drawer | LS | 1 | $ - 0 | ||
| Replace Double Sink | LS | 2 | $ - 0 | ||
| Replace Faucet | LS | 2 | $ - 0 | ||
| Replace Front and Rear Stairs | LS | 2 | $ - 0 | ||
| Install Roof Enclosure Over Stairs | LS | 2 | $ - 0 | ||
| Roof Replacement | SF | 1800 | $ - 0 | ||
| Repair Bathroom Walls | SF | 512 | $ - 0 | ||
| Flooring Replacement | SF | 1200 | $ - 0 | ||
| Flooring Replacement | SF | 300 | $ - 0 | ||
| Install New Bathroom Fan/Light Combo | LS | 2 | $ - 0 | ||
| Option 8 Subtotal | $ - 0 | ||||
| 0009A | Option 9, Rock Creek House Repairs | ||||
| Flooring Replacement | SF | 200 | $ - 0 | ||
| Roof Replacement | SF | 800 | $ - 0 | ||
| Replace Ceiling Tiles | SF | 800 | $ - 0 | ||
| Update Lighting Fixtures | LS | 4 | $ - 0 | ||
| Replace Bedroom Wall Heater | LS | 1 | $ - 0 | ||
| Replace Bathroom Ceiling Heater | LS | 1 | $ - 0 | ||
| Replace Back Steps | LS | 1 | $ - 0 | ||
| Install Weatherstripping on Front Door | LS | 1 | $ - 0 | ||
| Install Door Sweep on Front Door | LS | 1 | $ - 0 | ||
| Replace Windows | LS | 1 | $ - 0 | ||
| Option 9 Subtotal | $ - 0 | ||||
| 0010A | Option 10, Smokey Club House Repairs | ||||
| Interior Painting | SF | 1700 | $ - 0 | ||
| Install Metal Grate in Door | LS | 1 | $ - 0 | ||
| Update Bathroom Lighting | LS | 1 | $ - 0 | ||
| Paint Back Entrance Railing | LS | 1 | $ - 0 | ||
| Paint Main Entrance Railing | LS | 1 | $ - 0 | ||
| Replace Windows | LS | 1 | $ - 0 | ||
| Bathroom Flooring Replacement | SF | 50 | $ - 0 | ||
| Replace Fencing, East Side | LF | 75 | $ - 0 | ||
| Option 10 Subtotal | $ - 0 | ||||
| 0011A | Option 11, Crestview Cabins Repairs | ||||
| Crestview Cabin 1120 | |||||
| Interior Painting | SF | 1000 | $ - 0 | ||
| Replace Vent Stacks | LS | 2 | $ - 0 | ||
| Replace Windows | LS | 1 | $ - 0 | ||
| Replace Bathroom Door | LS | 1 | $ - 0 | ||
| Install New Vanity | LS | 1 | $ - 0 | ||
| Install New Faucet | LS | 1 | $ - 0 | ||
| Flooring Replacement | SF | 24 | $ - 0 | ||
| Replace Bathroom Ceiling Heater | LS | 1 | $ - 0 | ||
| Install heat tape and Insulation | LS | 1 | $ - 0 | ||
| Insulate Water Heater and Pipe | LS | 1 | $ - 0 | ||
| Install Snow Bar | LF | 25 | $ - 0 | ||
| Crestview Cabin 1119 | |||||
| Interior Painting | SF | 1000 | $ - 0 | ||
| Replace Windows | LS | 1 | $ - 0 | ||
| Flooring Replacement | SF | 24 | $ - 0 | ||
| Install heat tape and Insulation | LS | 1 | $ - 0 | ||
| Insulate Water Heater and Pipe | LS | 1 | $ - 0 | ||
| Replace Shower Head | LS | 1 | $ - 0 | ||
| Install Front Porch Light Fixture | LS | 1 | $ - 0 | ||
| Install Bathroom Door Trim | LS | 1 | $ - 0 | ||
| Install Snow Bar | LF | 25 | $ - 0 | ||
| Crestview Cabin 1122 | |||||
| Interior Painting | SF | 1000 | $ - 0 | ||
| Replace Windows | LS | 1 | $ - 0 | ||
| Replace Deck | LS | 1 | $ - 0 | ||
| Install heat tape and Insulation | LS | 1 | $ - 0 | ||
| Insulate Water Heater and Pipe | LS | 1 | $ - 0 | ||
| Install New Vent Fan | LS | 1 | $ - 0 | ||
| Install Snow Bar | LF | 25 | $ - 0 | ||
| Option 11 Subtotal | $ - 0 | ||||
| 0012A | Option 12, Lee Vining Fire Barracks Repairs | ||||
| Replace Front and Rear Stairs | LS | 2 | $ - 0 | ||
| Install Roof Enclosure Over Stairs | LS | 2 | $ - 0 | ||
| Install New Bathroom Fan/Light Combo | LS | 2 | $ - 0 | ||
| Replace Storm Doors | LS | 2 | $ - 0 | ||
| Replace Vent Stacks | LS | 10 | $ - 0 | ||
| Replace Window Trim | LS | 1 | $ - 0 | ||
| Paint Main Entrance Ramp and Railing | LS | 1 | $ - 0 | ||
| Paint Back Entrance Stairs and Railing | LS | 1 | $ - 0 | ||
| Repair Bathroom Walls | SF | 512 | $ - 0 | ||
| Replace Kitchen Counter | LS | 1 | $ - 0 | ||
| Replace Double Sink | LS | 2 | $ - 0 | ||
| Replace Faucet | LS | 2 | $ - 0 | ||
| Install Door Sweeps | LS | 2 | $ - 0 | ||
| Flooring Replacement | SF | 1200 | $ - 0 | ||
| Flooring Replacement | SF | 300 | $ - 0 | ||
| Option 12 Subtotal | $ - 0 | ||||
| 0013A | Option 13, Mt. Whitney House Repairs | ||||
| Interior Painting | SF | 1700 | $ - 0 | ||
| Remove Wood Stove | LS | 1 | $ - 0 | ||
| Replace Kitchen Counter | LS | 1 | $ - 0 | ||
| Replace Double Sink | LS | 1 | $ - 0 | ||
| Replace Faucet | LS | 1 | $ - 0 | ||
| Install New Bathroom Fan/Light Combo | LS | 2 | $ - 0 | ||
| Option 13 Subtotal | $ - 0 | ||||
| 0014A | Option 14, White Mt Fire Barracks Repairs | ||||
| Replace Kitchen Counter | LS | 1 | $ - 0 | ||
| Repair Kitchen Drawer | LS | 1 | $ - 0 | ||
| Repair Kitchen Window Trim | LS | 1 | $ - 0 | ||
| Paint Main Entrance Stairs and Backdoor Stairs | LS | 2 | $ - 0 | ||
| Paint Main Entrance Ramp and Railing | LS | 1 | $ - 0 | ||
| Replace Fencing, East Side | LF | 100 | $ - 0 | ||
| Repair Flooring Transitions | LF | 10 | $ - 0 | ||
| Repair Bathroom Walls | SF | 512 | $ - 0 | ||
| Install New Bathroom Fan/Light Combo | LS | 2 | $ - 0 | ||
| Install New Shower Installs | LS | 2 | $ - 0 | ||
| Option 14 Subtotal | $ - 0 | ||||
| 0015A | Option 15, Rock Creek Exterior Bathroom Repairs | ||||
| Replace Door Casing | LS | 1 | $ - 0 | ||
| Option 15 Subtotal | $ - 0 | ||||
| 0016A | Option 16, Rock Creek Barracks Repairs | ||||
| East | |||||
| Exterior Painting | SF | 1600 | $ - 0 | ||
| Interior Painting | SF | 1600 | $ - 0 | ||
| Sidewalk Replacement | SF | 100 | $ - 0 | ||
| West | |||||
| Exterior Painting | SF | 1600 | $ - 0 | ||
| Interior Painting | SF | 1600 | $ - 0 | ||
| Option 16 Subtotal | $ - 0 | ||||
| 0017A | Option 17, Mammoth Houses Repairs | ||||
| 103 Ritter House | |||||
| Interior Painting | SF | 1700 | $ - 0 | ||
| Minor Roof Repair | SF | 200 | $ - 0 | ||
| Install New Bathroom Fan/Light Combo | LS | 2 | $ - 0 | ||
| Update Bathroom Lighting | LS | 1 | $ - 0 | ||
| Replace Bathroom Ceiling Heater | LS | 1 | $ - 0 | ||
| Replace Interior Ceiling Vents | LS | 6 | $ - 0 | ||
| Replace Kitchen Light Fixture | LS | 1 | $ - 0 | ||
| Update Bedroom Lighting | LS | 3 | $ - 0 | ||
| 105 Ritter House | |||||
| Interior Painting | SF | 1700 | $ - 0 | ||
| Minor Roof Repair | SF | 200 | $ - 0 | ||
| Install New Bathroom Fan/Light Combo | LS | 2 | $ - 0 | ||
| Update Bathroom Lighting | LS | 1 | $ - 0 | ||
| Replace Bathroom Ceiling Heater | LS | 1 | $ - 0 | ||
| Replace Interior Ceiling Vents | LS | 6 | $ - 0 | ||
| Update Bedroom Lighting | LS | 3 | $ - 0 | ||
| Paint Kitchen Cabinets | SF | 300 | $ - 0 | ||
| Flooring Replacement | SF | 1000 | $ - 0 | ||
| Flooring Replacement | SF | 200 | $ - 0 | ||
| 1 Ediza House | |||||
| Minor Roof Repair | SF | 200 | $ - 0 | ||
| Replace Window Trim | LS | 7 | $ - 0 | ||
| Replace Front Sidewalk and Steps | LS | 1 | $ - 0 | ||
| 1 Murphy House | |||||
| Update Bathroom Lighting | LS | 2 | $ - 0 | ||
| Install New Bathroom Fan/Light Combo | LS | 2 | $ - 0 | ||
| Remove Wall Heater | LS | 1 | $ - 0 | ||
| 6 Ruby House | |||||
| Replace Siding | SF | 160 | $ - 0 | ||
| Replace Window Trim | LS | 7 | $ - 0 | ||
| Replace Front Steps | LS | 1 | $ - 0 | ||
| Option 17 Subtotal | $ - 0 | ||||
| 0018A | Option 18, 1006 Lee Vining Big House Repairs | ||||
| Replace Windows | LS | 1 | $ - 0 | ||
| Replace North Side Door | LS | 1 | $ - 0 | ||
| Option 18 Subtotal | $ - 0 | ||||
| 0019A | Option 19, Lee Vining Ranger Station Repairs | ||||
| Exterior Painting | SF | 8000 | $ - 0 | ||
| Interior Painting | SF | 8000 | $ - 0 | ||
| Replace Windows | LS | 1 | $ - 0 | ||
| Replace Siding | SF | 3350 | $ - 0 | ||
| Install Exterior Pest Exclusion Measures | LF | 400 | $ - 0 | ||
| Walkway Repair | SF | 300 | $ - 0 | ||
| Option 19 Subtotal | $ - 0 | ||||
| TOTAL | $ - 0 | ||||
| NOTES | 1. Responses for quantities less than those listed in the numbered items may be rejected | ||||
| 2. Responses without prices for each item and sub-item may be rejected. | |||||
| 3. If award response is made in excess of $35,000, bonds will be required (Section I) | |||||
| 4. If response is greater than $150,000, include bid bond = 20% of the total price | |||||
| 5. Following are abbreviation definitions from FP-03, Section 109 that may appear in the "Unit" column of the Schedule of Items; AC=Acre, CQ=Contract Quantity, CY= Cubic Yard, EA=Each, GAL=Gallon, HR=Hour, LF=Linear Foot, LS=Lump Sum, MI=Mile, LB=Pound, SF=Square Foot, SY=Square yard, ST=Station, TON=Ton. CQ and LS will be measured and paid as stated in FP-03, Section 109-02. All other Units will be paid according to FAR clause 52.211-18, Variation in Estimated Quantity. |
| PRICE SUBMITTED BY | |
| Signature | Phone: |
| Vendor | Fax: |
| Address | Email: |
| UEI | POC: |
File details come from the government source that posted it. Updated .