This is a Schedule of Items pricing attachment for a federal construction solicitation. The Sandia District Vehicle Gate Replacement project, solicitation number 127EAX26Q0090, is issued by the Department of Agriculture Forest Service for the installation of an exterior motorized vehicle gate on the south side of a building at a Forest Service facility. The contractor must provide all labor, equipment, tools, materials, supervision, and services necessary to complete the installation.
The pricing schedule is structured as a lump sum contract with seven line items: Labor, Mobilization/taxes, Vehicle Gate, Motor, Pressure Loops (quantity 2), Disposal of Materials, and the overall Base Item total. All mobilization costs must be included within the pricing proposal. The gate installation must match the appearance of existing fence sections and be sufficiently durable to withstand frequent daily opening and closing cycles while being integrated with existing card reader equipment located on the northwest side of the gate.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 127EAX26Q0090_Amd_0002.pdf | ||
| Amendment 2 Attachment 3 - Wage Determination Updated.pdf | ||
| Amendment 2 Attachment 1 - Statement of Work Updated.docx | DOCX document | |
| 127EAX26Q0090_Amd_0001.pdf | ||
| 127EAX26Q0090 Vehicle Gate Replacement.pdf | ||
| Attachment 1 - Statement of Work.docx | DOCX document | |
| Attachment 3 - Wage Determination.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
B1 – SCHEDULE OF ITEMS
| BASE ITEM # |
| DESCRIPTION OF PROJECT ITEMS |
| UNIT OF MEASURE |
| EST. QTY |
| UNIT PRICE |
| EXTENDED AMOUNT |
| B1 |
| Sandia Dist. Vehicle Gate Replacement |
| Lump Sum |
| 1 |
| B1.1 |
| Labor |
| Lump Sum |
| 1 |
| B1.2 |
| Mobilization/taxes |
| Lump Sum |
| 1 |
| B1.3 |
| Vehicle Gate |
| Lump Sum |
| 1 |
| B1.4 |
| Motor |
| Lump Sum |
| 1 |
B1.5
Pressure Loops
| Lump Sum |
| 2 |
| B1.6 |
| Disposal of Materials |
| Lump Sum |
| 1 |
Total of All Base Items
*All mobilization costs must be included in the pricing.