This document is Attachment 2 to a federal contract solicitation, containing the clauses and provisions incorporated into a "Relocate MDF" contract. The attachment does not specify products or services, response dates, award dates, pricing terms, or set-asides, as it functions solely as a compilation of contract terms and conditions.
The document incorporates multiple FAR (Federal Acquisition Regulation) clauses by reference, including provisions related to System for Award Management registration, HUBZone small business price evaluation preferences, construction wage rate requirements, and labor standards compliance. Full text clauses address liquidated damages for construction delays, contract publication requirements specific to the Department of the Treasury with FOIA redaction procedures, mandatory IRS security training for contractor personnel with staff-like access to IRS information systems and facilities, electronic invoicing requirements through the Invoice Processing Platform (IPP) with provisions for short payment processing and waiver procedures, and Section 508 accessibility compliance for information and communication technology products and services. The document also includes a Treasury Acquisition Bulletin notice regarding potential discrepancies between System for Award Management requirements and agency solicitation provisions that contracting officers will not enforce.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Questions and Answers for RFQ 5000230038 Aug 25 2026.pdf | ||
| SOW - IT-RELOCATE MDF.pdf | ||
| relocation MDF RFQ.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Attachment 2 Relocate MDF Clauses
Provisions Incorporated by Reference:
52.204-7 System for Award Management—Registration (Oct 2025)
52.219-4 Notice of Price Evaluation preference for HUBZone Small Business Concerns (Oct 2025)
52.222-5 Construction Wage Rate Requirements-Secondary Site of the Work (Oct 2025)
Clauses Incorporated by Reference:
52.203-19 Prohibition on Requiring Certain Internal Confidentiality Agreements or Statements (Jan 2017)
52.204-10 Reporting Executive Compensation and First-Tier Subcontract Awards (Oct 2025)
52.204-13 System for Award Management—Maintenance (Oct 2025)
52.204-19 Incorporation by Reference of Representations and Certifications (Dec 2014)
52.209-10 Prohibition on Contracting with Inverted Domestic Corporations (Oct 2025)
52.212-4 Terms and Conditions—Commercial Products and Commercial Services (Oct 2025)
52.222-6 Construction Wage Rate Requirements (Oct 2025)
52.222-7 Withholding of Funds (Oct 2025)
52.222-8 Payrolls and Basic Records (Oct 2025)
52.222-9 Apprentices and Trainees (Oct 2025)
52.222-10 Compliance with Copeland Act Requirements (Oct 2025)
52.222-11 Subcontracts (Labor Standards) (Oct 2025)
52.222-12 Contract Termination-Debarment (May 2014)
52.222-13 Compliance with Construction Wage Rate Requirements and Related Regulations (May 2014)
52.222-14 Disputes Concerning Labor Standards (Oct 2025)
52.222-15 Certification of Eligibility (May 2014)
52.222-41 Service Contract Labor Standards (Oct 2025)
52.222-50 Combating Trafficking in Persons (Oct 2025)
52.222-90 Addressing DEI Discrimination by Federal Contractors (Oct 2025)
52.223-2 Reporting of Biobased Products Under Service and Construction Contracts (Oct 2025)
52.223-23 Sustainable Products (Oct 2025)
52.227-1 Authorization and Consent (Jun 2020)
52.227-2 Notice and Assistance Regarding Patent and Copyright Infringement (Jun 2020)
52.232-23 Assignment of Claims (May 2014)
52.232-39 Unenforceability of Unauthorized Obligations (Jun 2013)
52.232-40 Providing Accelerated Payments to Small Business Subcontractors (Mar 2023)
52.233-3 Protest after Award (Oct 2025)
52.233-4 Applicable Law for Breach of Contract Claim (Oct 2025)
52.243-1 Changes-Fixed Price (Oct 2025) Alternate I (Oct 2025)
1052.210-70 Contractor Publicity (Apr 2015)
Full Text Clauses:
52.211-12 Liquidated Damages-Construction (Sept 2000)
(a) If the Contractor fails to complete the work within the time specified in the contract, the Contractor shall pay liquidated damages to the Government in the amount of ____________ [Contracting Officer insert amount] for each calendar day of delay until the work is completed or accepted.
(b) If the Government terminates the Contractor’s right to proceed, liquidated damages will continue to accrue until the work is completed. These liquidated damages are in addition to excess costs of repurchase under the Termination clause.
(End of Clause)
1052.224-70 Contract Publication (Oct 2018)
(a) The Department of the Treasury (Treasury) may, at its sole discretion, publish this contract or portions thereof, including orders issued under the contract when deemed in the best interest of the Government.
(b) To afford the Contractor an opportunity to review and propose redactions for any information contained in the Treasury contract that may be subject to a FOIA exemption, the Contractor may submit, within ten business (10) days from the date of award of this contract or any order issued under the contract—
(1) A pdf file of the fully executed contract or order that is suitable for publication and which includes all Contractor proposed redactions (e.g, trade secrets or any commercial or financial information that the Contractor believes to be privileged or confidential business information) and.
(2) A written statement identifying the portions of each proposed redactions, including the applicable exemption under the Freedom of Information Act (FOIA), 5 U.S.C. 552, and, in the case of FOIA Exemption 4, 5 U.S.C. 552(b)(4), shall demonstrate why the information is considered to be a trade secret or commercial or financial information that is privileged or confidential.
(c) Treasury will consider the Contractor’s proposed redactions and associated grounds for nondisclosure prior to making a determination as to what information may be properly withheld for purposes of publishing this contract or portions thereof.
(d) The Contractor may submit a request to the CO for additional time to complete the action prescribed by paragraph (b) of this clause. The lack of action by the Contractor will be deemed by the Government as there being no information in the Treasury contract subject to a FOIA exemption.
(e) Information provided by the Contractor in response to this clause may itself be subject to disclosure under the FOIA.
Mandatory IRS Security Training for Information Systems, Information Protection and Facilities Physical Access (Apr 2024)
The Federal Information Security Modernization Act of 2014 (FISMA) requires each federal agency to provide periodic information security and privacy awareness training to all contractors/subcontractors involved in the management, use, or operation of Federal information and information systems. In addition, contractor/subcontractor personnel are subject to the Taxpayer Browsing Protection Act of 1997, which prohibits willful unauthorized inspection of returns and return information and details that any violation of the Act could result in civil and criminal penalties. Contractor/subcontractor personnel are bound by the Records Management by Federal Agencies (44 U.S.C. Chapter 31) regarding the care and retention of federal records.
1. The contractor must ensure all new contractor/subcontractor personnel complete all assigned briefings which are based on the responses provided on the Risk Assessment Checklist Form 14606. These responses pertaining to access to any IRS system, including basic LAN, email, and internet; access to any Sensitive but Unclassified (SBU) data; and access to any IRS facility. Since new contractor/subcontractor personnel will not have access to the IRS training system, the COR shall provide softcopy versions of each briefing.
i. Exception: Contractor personnel (including subcontractors) performing under IRS contracts with Nonprofit Agencies Employing People Who Are Blind or Severely Disabled (as described in FAR Subpart 8.7) are exempted from the aforementioned briefing requirements, unless the contractor requests access to the training, or there is a compelling justification for requiring the training that is approved by the Contracting Officer (CO). An example of this would be in an instance where visually impaired personnel is assigned to perform systems development and has potential staff-like access to IRS information.
ii. Contractor/subcontractor personnel working with IRS information at contractor-controlled facilities with no access to the IRS network will be subject to all mandatory briefing excepting the Facilities Management Physical Security briefing as outlined in Publication 4812.
iii. Service Personnel: Inadvertent Sensitive Information Access Training
Contractor personnel performing: (i) janitorial and cleaning services (daylight operations),
(ii) building maintenance, or (iii) other maintenance and repair and need staff-like access to
IRS facilities are required to complete Inadvertent Access to Sensitive Information (SBU) Access training.
iv. Service Personnel Security Awareness Training: Contractor personnel providing services in the following categories are required to complete FMSS Physical Security Training:
• Medical;
• Cafeteria;
• Landscaping;
• Janitorial and cleaning (daylight operations);
• Building maintenance; or
• Other maintenance and repair
2. In combination these mandatory briefings are known as IRS Security Awareness Training (SAT). The topics covered are: Cybersecurity Awareness, Privacy Information Protection and Disclosure, Unauthorized Access to Taxpayer Data, Records Management, Inadvertent Sensitive Information Access, and/or Facilities Physical Security. The completion of the assigned mandatory briefings constitutes the completion of the Security Orientation.
3. The SAT must be completed by contractor/subcontractor personnel within 10 business days of successful resolution of the suitability and eligibility for staff-like access as outlined in IR1052.204-9000 Submission of Security Forms and Related Materials and before being granted access to SBU data. The date listed on the memo provided by IRS Personnel Security shall be used as the commencement date.
4. Training completion process:
The contractor must submit confirmation of completed SAT mandatory briefings for each contractor/subcontractor personnel by either:
i. Using Form 14616 signed and dated by the individual and authorized contractor management entity and returned to the COR. This option is used for new contractor/subcontractor personnel and any that do not have an IRS network account.
ii. Using the IRS training system which is available to all contractors with IRS network accounts
5. Annual Training. For contracts/orders/agreement exceeding one year in length, either on a multiyear or multiple year basis, the contractor must ensure that personnel complete assigned SAT mandatory briefings annually no later than October 31st of the current calendar year. The contractor must submit confirmation of completed annual SAT on all personnel unable to complete the briefings in the IRS training systems by submitting completed Form 14616 assigned to this contract/order/agreement, via email, to the COR, upon completion.
6. Contractor’s failure to comply with IRS security policy (to include completion and certification of SAT requirements within the timeframe specified) may be subject to suspension, revocation, or termination (temporarily or permanently) of staff-like access to IRS IT systems and facilities.
7. Flow down of clauses. The contractor shall include and flow down, in its subcontracts (or arrangements or outsourced service agreements) that entails staff-like access to SBU information by a subcontractor, at any tier, the substantially same Federal Acquisition Regulation (FAR) and local security or safeguard clauses or provisions for protecting SBU information or information systems that apply to and are incorporated in its prime contract with IRS.
Electronic Invoicing and Payment Requirements for the Invoice Processing Platform (IPP) (Jul 2019)
(a) Definitions:
"Short payment" as used in this clause means the partial payment of an invoice for goods/services actually rendered at the time of payment when the invoice includes additional goods/services that have not yet been provided/rendered.
"Short payment" example: The contract requires the delivery of a set number of items, with the price, delivery location, and delivery due date also specified. The vendor delivers 50% of the items as specified but invoices for 100% of the items. Before implementation of the IPP, the IRS would have paid the vendor for the items delivered and instructed the vendor to re-invoice the IRS when the balances of the items were delivered. In other words, the IRS would "short pay" the invoice since the IRS did not remit payment for the full invoice amount. With implementation of the IPP, the IRS can no longer do this because the IRS cannot accept an electronic invoice that includes items not yet received. The IRS will reject the invoice. The vendor needs to submit an invoice for only the items received by the IRS (in this case, 50%), and, if these items meet all other contract terms and conditions, the IRS will pay the invoiced amount. The vendor submits subsequent invoice(s) for items as they are delivered and accepted.
(b) The Invoice Processing Platform (IPP) is a secure Web-based electronic invoicing and payment information service available to all Federal agencies and their suppliers. Effective October 1, 2012, invoicing for payment through the IPP will be mandatory for all new contract awards. Additional information regarding the IPP may be found at the IPP website address https://www.ipp.gov. Contractors must complete the contractor point of contact information below and submit it with their proposal submissions. Contractors may contact the IPP Helpdesk for assistance via e-mail at ippgroup@stls.frb.org or via phone at (866) 973-3131. Once a contract award has been made, the contractor will be contacted by the IPP via e-mail to set-up an account. It will be necessary for contractors to login to their IPP accounts every 90 days to keep their IPP accounts active.
(c) Contractor Point of Contact Information
Contractor Name: ______________________________________________________ Contractor IPP Point of Contact Name:
Contractor Phone Number: ______________________________________________________ Contractor E-mail Address: ______________________________________________________
(d) Electronic Invoicing and Payment Requirements
Vendor invoices submitted electronically through the IPP should be in the proper format and contain the information required for payment processing. To be approved for payment, a "proper invoice" must list the items specified in FAR 52.232-25 (a)(3)(i) through (a)(3)(x), or in the case of a Commercial Item Contract, the items included in 52.212-4(g)(1)(i) through (g)(1)(x).
If the vendor is offering a discount via the IPP, the discount must be reflected on the invoice. The vendor will select 'Create Invoice'. The IPP system will default to 'Net 30 Prompt Pay' under the Payment Terms dropdown box. The vendor will select from 54 different discount options for the invoice that is being created. If the vendor chooses to offer a discount on the invoice screen, the information will interface to the payment system for processing. Discounts that are offered on attachments rather than the invoice itself cannot be accepted.
Under this contract, the following documents are required to be submitted as an attachment to the invoice (Contracting Officer fills in additional documentation that must be furnished by the contractor (e.g. timesheet)). Please do not submit into IPP any documentation/attachments that conflict with what is stated on the invoice:
Payment and Invoice Questions
For payment and invoice questions, contact the Ancillary Systems at (304) 254-3372 or via e-mail at cfo.fm.ipp.customer.support@irs.gov.
(e) Waiver
If the Contractor is unable to use the IPP for submitting payment requests starting on October 1, 2012, then a waiver form must be completed and submitted with the contractor's proposal submission for review and approval by the Contracting Officer based on one of the conditions listed in the waiver. The vendor will be notified prior to award as to whether their request for waiver has been approved or denied. If the waiver is granted, then a copy of the waiver must be submitted with each paper invoice that the vendor submits to the payment office or the invoice will be returned.
(f) Short Payment
Short payment on vendor submitted invoices will no longer be processed or paid. If any portion of the invoice does not meet the requirements for a proper invoice, the entire invoice shall be rejected and returned to the vendor unpaid.
IRS Invoice Processing Platform (IPP) Waiver Form
The IRS invoicing and payment requirements clause (IR1052.232-9000) requires that all invoices under awards made (or effective) on or after October 1, 2012, be submitted electronically via the IPP unless a waiver is requested and granted. If the Contractor is unable to submit its invoice through the IPP, the Contractor shall complete this waiver form indicating the reason for the waiver request by selecting the appropriate box below and providing a narrative summarizing in detail the circumstances requiring a waiver. For a solicitation, submit the waiver form with the proposal submission. For a modification that incorporates the IPP clause into an existing contract, submit the waiver form with the modification. The CO will notify the vendor via e-mail or another appropriate means of communication prior to award as to whether their waiver has been approved or denied. If the waiver is granted, then a copy of the approved waiver must be submitted with each invoice that the vendor submits to the payment office or the invoice will be returned.
Reason for requesting a waiver of the requirement to submit an electronic invoice via the
IPP:
[ ] 1. Submission of invoices through IPP would impose a hardship on an individual (includes employees and sole proprietors) due to: either a physical or mental disability; a geographic, language, or literacy barrier; or an undue financial burden. The requirement to submit invoices through the IPP is automatically waived for all individuals who do not have payment capability using ACH with a U.S. financial institution.
[ ] 2. The political, financial or communications infrastructure where the place of business is located does not support access to the IPP for submitting invoices electronically.
[ ] 3. The contractor is located within an area designated by the President of the United States or an authorized agency administration as a disaster area. (Please identify area/location.)
[ ] 4. The submission of invoices electronically may pose a threat to national security, the life or physical safety of an individual may be endangered, or a law enforcement action may be compromised.
[ ] 5. The agency does not expect to receive more than one invoice from the same contractor within a one-year period. i.e., the invoice submission is non-recurring.
[ ] 6. The contractor customarily submits a high volume of invoices on a regular basis via file format, not currently supported by the IPP (i.e., uses a file format other than XML or CSV) and the high volume of invoices would cause a significant burden to the contractor if submitted through the IPP individually. If utilizing this exception, please identify the file formats supported by your invoicing system so that the IPP may consider implementing the requested file format at a later date. File format(s) used: ___________ [ ] 7. Other - Please explain: ______________________________________________________
Attach a separate sheet of paper with a summary narrative substantiating the circumstances for the waiver exception selected from above (1 through 7).
Waiver Submitted By:
Contractor Name
Name of Person Submitting Request for Waiver Title
Signature of Person Submitting Request for Waiver
E-mail Address Phone No.
Contract/Order No. Date Submitted
Waiver Approved By:
Contracting Officer's Name Printed
Contracting Officer's Signature Date
Section 508 Information, Documentation and Support (Dec 2019)
In accordance with 36 CFR, Appendix C to Part 1194, the information and communication technology (ICT) products and product support services documentation furnished in performance of this contract shall be provided at no additional cost. The contractor shall provide information, documentation, and support relative to the supplies and services as described in the statement of work, performance work statement or statement of objectives (select one). The following technical standards and provisions have been determined to be applicable to this contract:
___ Chapter 6: Support Documentation and Services ___ 601 General ___ 601.1 ___ 602 Support Documentation ___ 602.1 ___ 602.2 ___ 602.3 ___ 602.4 ___ 603 Support Services ___ 603.1 ___ 603.2 ___ 603.3
Section 508 Accessibility of Information and Communication Technology (100% Compliance) (Apr 2024)
Each information and communication technology (ICT) product or service furnished under this contract shall comply with the Information and Communication Technology Accessibility Standards (36 CFR, Appendix C to Part 1194). If the Contracting Officer determines any furnished products or services are not in compliance with the contract, the Contracting Officer will apply the remedies described under FAR 52.246-2, Inspection of Supplies – Fixed Price or FAR 52.246-4, Inspection of Services – Fixed Price.
The following technical standards and provisions have been determined to be applicable to this contract:
___ Chapter 4: Hardware ___ 401 General ___ 401.1 ___ 402 Closed Functionality ___ 402.1 ___ 402.2(1-6) ___ 402.3 ___ 402.4 ___ 402.5 https://www.section508.gov/manage/accessibility-faq/ https://www.section508.gov/manage/accessibility-faq/
___ 403 Biometrics ___ 403.1 ___ 404 Preservation of Information Provided for Accessibility ___ 404.1 ___ 405 Privacy ___ 405.1 ___ 406 Standard Connections ___ 406.1 ___ 407 Operable Parts ___ 407.1 ___ 407.2 ___ 407.3 ___ 407.4 ___ 407.5 ___ 407.6 ___ 407.7 ___ 407.8 ___ 408 Display Screens ___ 408.1 ___ 408.2 ___ 408.3 ___ 409 Status Indictors ___ 409.1 ___ 410 Color Coding ___ 410.1 ___ 411 Audible Signals ___ 411.1 ___ 412 ICT with Two-Way Communication ___ 412.1 ___ 412.2 ___ 412.3 ___ 412.4 ___ 412.5 ___ 412.6 ___ 412.7 ___ 412.8 ___ 413 Closed Caption Processing Technologies ___ 413.1 ___ 414 Audio Description Processing Technologies ___ 414.1 ___ 415 User Controls for Captions and Audio Descriptions ___ 415.1 ___ Chapter 5: Software ___ 501 General ___ 501.1 ___ 502 Interoperability with Assistive Technology ___ 502.1 ___ 502.2 ___ 502.3 ___ 502.4(A-G) ___ 503 Applications ___ 503.1 ___ 503.2 ___ 503.3 ___ 503.4 ___ 504 Authoring Tools ___ 504.1 ___ 504.2 ___ 504.3 ___ 504.4 ___ Chapter 7: Referenced Standards ___ 701 General ___ 701.1
___ 702 Incorporation by Reference ___ 702.1 ___ 702.2 ___ 702.3 ___ 702.4 ___ 702.5 ___ 702.6 ___ 702.7 ___ 702.8 ___ 702.9 ___ 702.10
The standards do not require the installation of specific accessibility-related software or the attachment of an assistive technology device, but merely require that the ICT be compatible with such software and devices so that it can be made accessible if so required by the agency in the future.
The following functional performance criteria (36 CFR Chapter 3) apply to this contract.
___ Chapter 3: Functional Performance Criteria ___ 301 General ___ 301.1 ___ 302 Functional Performance Criteria ___ 302.1 ___ 302.2 ___ 302.3 ___ 302.4 ___ 302.5 ___ 302.6 ___ 302.7 ___ 302.8 ___ 302.9
Treasury Acquisition Bulletin 25-01 Notice
System updates may lag policy updates. The System for Award Management (SAM) may continue to require entities to complete representations based on provisions that are not included in agency solicitations. Examples include 52.222-25, Affirmative Action Compliance, and paragraph (d) of 52.212-3, Offeror Representations and Certifications— Commercial Products and Commercial Services. Contracting officers will not consider these representations when making award decisions or enforce requirements. Entities are not required to, nor are they able to, update their entity registration to remove these representations in SAM.
(End of Language)
File details come from the government source that posted it. Updated .