This federal contract opportunity solicitation is for the Melvin Price Flood Control Project - Reach 1. The solicitation requests bids for furnishing all equipment, labor, services, supplies and materials necessary to satisfactorily construct Wood River Levee District's relief wells. The contract duration is 420 days with an estimated value between $5,000,000 and $10,000,000. This is a best value procurement using subjective trade-off source selection by the Department of the Army Corps of Engineers Engineering District St Louis. Davis Bacon Wage Determination No. IL 17, Revision 9, dated 6/19/2020 applies. All work must be completed in coordination with other ongoing Federal projects onsite and without disruption to site operations.